1
MGSC-303 EXAM III SUM II-2013
NAME:______________________________________________
1.
The quarterly demand for a product(in units) is given below:
Quarters: Q1 Q2 Q3 Q4
Demand: 1300 1400 1600 1700
Each unit of product requires 5 hours of labor. A worker works for 500 hours per
quarter.
a) Compute the number of workers required each quarter to meet demand?
No. of Workers, Q1 =
No. of Workers, Q2 =
No. of Workers, Q3 =
No. of workers, Q4 =
b) Perform a rough-cut capacity planning analysis. Does the plant have the capacity to meet the total demand for the 4 quarters? Assume 7500 labor hours of capacity is available each quarter.
Qtr. 1
Qtr. 2
Qtr. 3
Qtr. 4
Total
Demand
(units)
Load
Labor hrs
Capacity
Labor Hrs.
Over/Under
Note: Over/Under = Capacity – Load .
What is your recommendation?
2. In problem 1, assume the cost of carrying an item in inventory is $50 per unit per year.
a) If level production, based on average quarterly demand is planned, compute the annual inventory carrying costs. Assume initial inventory of the product is zero. Use the following table to perform your calculations.
Quarters
Aggregate
Demand
Planned
Production
Beginning
Inventory
Ending
Inventory
Avg. Qtrly
Inventory
Q1
Q2
Q3
Q4
Total =
Total =
Average Qtrly demand =
Average Annual Inventory =
Annual Inventory carrying cost =
b) If the production capacity is limited to 1300 units per quarter and excess demand is met through subcontracting at $60 per unit in the above problem, find the annual
subcontracting cost?
Quarter 1
Quarter 2
Quarter 3
Quarter 4
Actual Demand
Production
Subcontracted
Total subcontracted =
Annual cost =
3. Complete the MRP schedule for the product below.
Product A Lot Size = 100 Safety Stock = 75
Lead Time = 1 week Allocated = 250 In hand =600
WEEKS
1
2
3
4
5
Gross requirement
550
700
400
Scheduled receipt
200
Available
Net requirements
Planned order receipts
Planned order releases
Note: Net requirement = Gross requirement – Available
For week 1, Available = In hand + Scheduled receipt – Allocated – Safety stock.
If net requirement for current period is zero, then for next period
Available = Available for current period – Gross reqmnts for current period.
If net requirement for current period is greater than zero, then for next period
Available = Planned order receipt for current period – Net requirement for
current period.
Planned order receipt will depend on net requirements and lot size rule.
4. Product X has the structure given below.
X
P3 R2 S3
Q2 T4 V2
a) If 60 units 0f product X has to be produced, compute the bill of materials.
ITEM
QUANTITY
X
P
R
S
Q
T
V
b) Given the following lead times draw the time phased product structure for X.
If delivery is desired in week 10 from now.
ITEM
LEAD TIME
IN WEEKS
X
2
P
2
Q
2
R
2
S
3
T
2
V
3
1 2 3 4 5 6 7 8 9 10
We have to start production from week 5 to deliver the finished product by week 10.
Total lead time is 5 weeks.