Project status problem

Projectstausproblem.rtf

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Please see the attachment

You are the sponsor for project XY. The project manager has provided you the following three status reports. The project started on

2

/1

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

and it is now the end of the 4th week. For this assignment, complete this packet in its entirety to include all tables, blanks, and questions. Complete the file and submit as your completed assignment.
Percent: Completion Report
Activity

Date Started

Percent completed

Time to Complete (weeks)

AB

2/1

100

Completed

AC

2/1

60

2

AD

2/1
100
Completed

DE

Not started—delayed

n/a

3

BF

2/14

40

3

Project Planning Budget: Dollars Budgeted Per Week for Each Activity, Project Starting 2/1
Activity

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

Total

$

AB

2,000

2,000
2,000

6,000

AC

3,000

4,000

4,000
4,000

5,000

20,000

AD
2,000
3,000

2,500

7,500

BF

2,000
3,000
4,000
3,000
3,000

15,000

CE

2,500

2,500
DE

3,500

3,500
3,500

10,500

EF

3,000
3,000

Total:

7,000

9,000

8,500

9,500

11,500

10,000

6,000
3,000

6

4,500

Cost Summary

Week Ending

Cumulative to Date

Activity

Budget Cost

Actual

(Over) / Under

Budget Cost
Actual
(Over) / Under
AB



6,000

6,200

(200)

AC
4,000
4,500

(500)

15,000

12,500

2,500
AD

2,400

(2,400)

7,500

7,400

100
BF
2,000

2,800

(800)

2,000
4,500

(2,500)

DE
3,500

3,500
3,500

3,500
Total
9,500

9,700

(200)

34,000

30,600

3,400

It is now the end of Week 4 and you want to determine the status of the project using earned value management. Complete the table and earned value metrics below. Some of the information has already been entered for you.
Activity

% Complete

Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
Cost Variance
Schedule Variance
Total Budget
AB
 
 
 
 6200
 
 
6000
AC
60
 
12000
 
 
 
20000
AD
 
 
 
 
 
 
7500
BF
 
 
 6000
 
 
 
15000
CE
0
 
0
 
 
 
2500
DE*
0
 
0
 
 
 
10500
EF
0
 
0
 
 
 
3000
TOTAL
 
 
 
 
 
 
64500
* Note that activity DE has been delayed and does not impact the calculations.

Calculate each of the following:

 
Cost Variance ($) = EV – AC

 
Schedule Variance ($) = EV – PV

 
Schedule Variance (weeks) = Schedule Variance ($) / Average Weekly PV

 
Cost-at-Completion = (Rate of Spending x Total Budget) = ([AC / EV] * Total Budget)

 
CPI = EV / AC

 
SPI = EV / PV

Add your written analysis below by answering three questions:
1. What is the state of the project?
2. Which activity has had the most positive impact on the project?
Which activity has had th

Still stressed from student homework?
Get quality assistance from academic writers!

Order your essay today and save 25% with the discount code LAVENDER