Projectstausproblem.rtf
Please see the attachment
You are the sponsor for project XY. The project manager has provided you the following three status reports. The project started on
2
/1
and it is now the end of the 4th week. For this assignment, complete this packet in its entirety to include all tables, blanks, and questions. Complete the file and submit as your completed assignment.
Percent: Completion Report
Activity
Date Started
Percent completed
Time to Complete (weeks)
AB
2/1
100
Completed
AC
2/1
60
2
AD
2/1
100
Completed
DE
Not started—delayed
n/a
3
BF
2/14
40
3
Project Planning Budget: Dollars Budgeted Per Week for Each Activity, Project Starting 2/1
Activity
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Week 7
Week 8
Total
$
AB
2,000
2,000
2,000
6,000
AC
3,000
4,000
4,000
4,000
5,000
20,000
AD
2,000
3,000
2,500
7,500
BF
2,000
3,000
4,000
3,000
3,000
15,000
CE
2,500
2,500
DE
3,500
3,500
3,500
10,500
EF
3,000
3,000
Total:
7,000
9,000
8,500
9,500
11,500
10,000
6,000
3,000
6
4,500
Cost Summary
Week Ending
Cumulative to Date
Activity
Budget Cost
Actual
(Over) / Under
Budget Cost
Actual
(Over) / Under
AB
—
—
—
6,000
6,200
(200)
AC
4,000
4,500
(500)
15,000
12,500
2,500
AD
—
2,400
(2,400)
7,500
7,400
100
BF
2,000
2,800
(800)
2,000
4,500
(2,500)
DE
3,500
—
3,500
3,500
—
3,500
Total
9,500
9,700
(200)
34,000
30,600
3,400
It is now the end of Week 4 and you want to determine the status of the project using earned value management. Complete the table and earned value metrics below. Some of the information has already been entered for you.
Activity
% Complete
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
Cost Variance
Schedule Variance
Total Budget
AB
6200
6000
AC
60
12000
20000
AD
7500
BF
6000
15000
CE
0
0
2500
DE*
0
0
10500
EF
0
0
3000
TOTAL
64500
* Note that activity DE has been delayed and does not impact the calculations.
Calculate each of the following:
Cost Variance ($) = EV – AC
Schedule Variance ($) = EV – PV
Schedule Variance (weeks) = Schedule Variance ($) / Average Weekly PV
Cost-at-Completion = (Rate of Spending x Total Budget) = ([AC / EV] * Total Budget)
CPI = EV / AC
SPI = EV / PV
Add your written analysis below by answering three questions:
1. What is the state of the project?
2. Which activity has had the most positive impact on the project?
Which activity has had th