Assignment 1: Given the information provided for your assigned rocket assembly project (See Course Resources as per attached): • Develop the cost management plan for your assigned rocket assembly project. • Develop the human resource management plan your assigned rocket assembly project. As limited to the rubric below: Ensure that your project documents address the criteria of the rubric below and follows the stated requirements. Cost Management Plan 1.1 Units of Measure 1.2 Level of Precision 1.3 Level of Accuracy 1.4 Process for Formal Acceptances 1.5 Process to Control Requests for Changes 1.6 Organizational Procedural Links 1.7 Control Thresholds 1.8 Rules of Performance Measurement 1.9 Reporting Formats 1.10 Process Descriptions Human Resource Management Plan 2.1 Roles and Responsibilities 2.2 Project Organization Charts 2.3 Staffing Management Plan GM592 Unit 3 Team Assignment: 50 Points Content (0-30 points) 1. Tool Development (Cost Management Plan) a) Units of measure. Each unit used in measurements (such as staff hours, staff days, weeks for time measures; or meters, liters, tons, kilometers, or cubic yards for quantity measures; or lump sum in currency form) is defined for each of the resources. 10 b) Level of precision. The degree to which activity cost estimates will be rounded up or down (e.g., US $100.49 to US $100, or US $995.59 to US $1,000), based on the scope of the activities and magnitude of the project c) Level of accuracy. The acceptable range (e.g., :10%) used in determining realistic activity cost estimates is specified, and may include an amount for contingencies d) Process that specifies how formal acceptances of the completed project deliverables will be obtained? e) Process to control how requests for changes to the detailed scope statement will be processed as defined in the Integrated Change Control process (PMBOK section 4.5)? f) Organizational procedures links. The WBS component used for the project cost accounting is called the control account. Each control account is assigned a unique code or account number(s) that links directly to the performing organizations accounting system. g) Control thresholds. Variance thresholds for monitoring cost performance may be specified to indicate an agreed—upon amount of variation to be allowed before some action needs to be taken. Thresholds are typically expressed as percentage deviations from the baseline plan. h) Rules of performance measurement. Earned value management (EVM) rules of performance measurement are set. i) Reporting formats. The formats and frequency for the various cost reports are defined. j) Process descriptions. Descriptions of each of the other cost management processes are documented. 2. Tool Development (Human Resource Management Plan) a) Roles and responsibilities of assigned skill sets? 10 i) Role? ii) Authority? iii) Responsibility? iv) Competency? b) Project organization charts? c) Staffing management plan? i) Staff acquisition? ii) Resource calendars? iii) Staff release plan? iv) Training needs? v) Recognition and rewards? vi) Compliance? vii) Safety? Analysis (0-11 points) Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 3 Analysis includes proper classifications, explanations, comparisons and inferences. 4 Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. Writing (0-9 points) Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 3 Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 3 Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions.
Assignment 2:
This Assignment is designed to evaluate your ability to research, organize, and demonstrate project data and financial information pertaining to the development of the feasibility study within the project planning phase.
In this Assignment, you will be assessed on the following outcome: Plan cost management with associated resources. Planning is moving right along. You are in the process of pulling together the Cost Management Plan, your definitive cost estimate, the project spend plan and baseline, your human resource management plan, and your procurement management plan.
Given the information provided you for your assigned rocket assembly project (See Course Resources):
• Construct a definitive cost estimate based on your definitive duration estimate for your assigned rocket assembly project.
• Build a project spend plan with a graph of your cost baseline (Cumulative or S-Curve) with your EAC identified for your assigned rocket assembly project.
• Ensure that your project documents address the criteria of the rubric below and follows the stated requirements. •
GM592 Unit 3 Individual Assignment: 40 Points
(0-24 points)
1. Tool Development (Definitive Cost Estimate)
a) Durations reflect task totals that match with deliverables? 12
b) Sub-task totals properly calculated and rolled up?
c) Work packages are accurate and controllable?
d) Work packages total to sub-tasks correctly?
e) Levels of effort reflect activity effort correctly?
f) Skill-sets totaled correctly?
g) Skill-set costs reflect rates and hour totals?
h) Duration total matches the total of all skill-sets?
2. Tool Development (Spend Plan with Baseline)
a) Reflects schedule planning increments (day/week/month)? 12
b) Incremental costs reflect labor/equipment/material costs (not counting indirect costs) and totaled incrementally as well as cumulatively?
c) Cumulative costs are depiction of total project costs?
d) Cumulative cost curve graph (S-curve graph)?
e) Cost baseline (S-Curve) based on total project cost?
f) Estimate at Completion (EAC) depicted on cost baseline graph?
Analysis (9 points) Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 3
Analysis includes proper classifications, explanations, comparisons and inferences. 3
Critical thinking includes appropriate judgments, conclusions and assessment based on 3
evaluation and synthesis of information.
Writing (7 points)
Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 3
Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 2
Project is in 12-point font.
Narrative sections are double-spaced with a double space between.
Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. 2
>Hi Lvl . & Dry
.0
.0
Measure body tube Apply glue .0
Assembly
.0
.0
Engine Mount Assembly Marking mount mm
mm
Cutting mount Inserting hook Testing adapter ring Shock Cord Mount Assembly Cut cord mount Crease assembly Glue mount assembly Fold mount assembly Clamp mount assembly Allow to dry Select fin pattern Trace fin patterns Trace fin #2 Save scrap Course sand fins Fine sand fins Engine Mount Installation Measure body tube mm
Spread glue Insert engine mount Tube Marking Detail Wrap guide Mark tube Draw fin markings mm
Draw straight line Draw straight line mm
Fin Attachment Apply second layer glue Set aside to dry Launch Lug Attachment mm
Glue lug attachment Dry lug attachment Allow to dry Stand rocket on drying table Allow to dry Apply glue Set mount Set glue Allow to dry Cut out parachute Tape removal Tape attachment Shroud line assembly Parachute & Shock Cord Attachment to Nose Cone Parachute pass throough Line tightening Shock cord tie down Finishing Rocket Prime rocket Paint rocket Allow to dry Decal #1 Decal #1 Decal #1 WBS Engine Mount Assembly Locate light blue engine mount tube Locate engine hook Locate green adapter ring Move tube to ruler Align with zero mark Take pencil Mark tube Cut 3mm slit Inserting hook Insert hook Extend hook Testing adapter ring Slide ring into front of engine tube Slide ring over engine hook to 25mm mark Glue & Dry Apply glue Apply glue to one side Apply glue to other side Dry glue Set assembly aside Allow to dry Locate cord mount on pattern sheet Cut cord mount along outline Fold on dotted lines Crease on dotted lines Spread glue Lay end of shock cord in glue Fold section 1 Apply glue section 3 Fold again Clamp assembly Allow to dry 3.1 Select fin pattern Select fin pattern Cut fin pattern from sheet Trace fin #2 Match fin #2 Trace fin #2 Match fin #2 Cut fin #1 Chect fin #1 Cut fin #2 Chect fin #2 Cut fin #3 Chect fin #3 Set aside piece scrap basa wood Lay sandpaper Stack fins Sand fins Fine sand fin #1 Round leading edge fin #1 Round trailing edge fin #1 Streamline training edge fin #1 Fine sand fin #2 Round leading edge fin #2 Round trailing edge fin #2 Streamline training edge fin #2 Fine sand fin #3 Round leading edge fin #3 Round trailing edge fin #3 Streamline training edge fin #3 Locate body tube Spread glue around body tube Insert engine mount assembly into body tube Locate tube marking guide on pattern sheet Cut guide alone outline Wrap guide around body tube Tape guide to body tube Mark tube for fins Mark tube for fin #1 Mark tube for fin #2 Mark tube for fin #3 Write LL on body tube Remove guide Fin #1 Draw straight line Extend line 76mm Fin #2 Draw straight line Extend line 76mm Fin #3 Draw straight line Extend line 76mm Draw launch lug line Allow fin #2 to dry Apply to fin #3 Allow fin #3 to dry Apply more glue to Fin #2 Set fin #2 Press fin #2 Apply more glue to Fin #3 Set fin #3 Press fin #3 Attach fin #2 Adjust fin #3 Attach fin #3 Stand rocket on drying table Allow fins to dry Ensure launch lug alignment Allow to dry Glue Reinforcement Reinforce fin fin #1 Reinforce fin fin #2 Reinforce fin fin #3 Reinforch side 1 Reinforce side 2 Allow to dry Shock Cord Mount Attachment 9.1 Measure body tube Measure 25mm 9.2 Apply glue Apply glue to shock cord Insert cord into tube Set mount 25mm Press mount into glue Hold mount attachment Allow to dry Parachute Assembly Cut parachute along line Remove tape Fold shroud lines Cut shroud lines Attach tape rings Attach tape ring #1 Attach tape ring #2 Attach tape ring #3 Attach tape ring #4 Attach tape ring #5 Attach tape ring #6 Press tape tape rings into place Press tape tape rings into place #1 Press tape tape rings into place #2 Press tape tape rings into place #3 Press tape tape rings into place #4 Press tape tape rings into place #5 Press tape tape rings into place #6 Punch tape ring holes Punch tape ring holes #1 Punch tape ring holes #2 Punch tape ring holes #3 Punch tape ring holes #4 Punch tape ring holes #5 Punch tape ring holes #6 Pass shroud line through hole Tie lines together Parachute & Shock Cord Attachment to Nose Cone Thread shroud lines Pass parachute through loop Line tightening Pull lines tight Shock cord tie down Tie down shock cord free end Finishing Rocket Check to ensure glue joint are dry Apply primer coat #1 Sand rocket body #1 Apply primer coat #2 Sand rocket body #2 Insert paint handle Apply paint to rocket Allow to dry Cut decals Decal #1 Decal #2 Decal #3 Decal #4 Decal #5 Decal #6 Decal #7 Decal #8 Decal #9 Decal #10 Decal #11 Decal #12 Decal #13 Dip in water Decal #1 Decal #2 Decal #3 Decal #4 Decal #5 Decal #6 Decal #7 Decal #8 Decal #9 Decal #10 Decal #11 Decal #12 Decal #13 Slip decals Decal #1 Decal #2 Decal #3 Decal #4 Decal #5 Decal #6 Decal #7 Decal #8 Decal #9 Decal #10 Decal #11 Decal #12 Decal #13 Blot decals Decal #1 Decal #2 Decal #3 Decal #4 Decal #5 Decal #6 Decal #7 Decal #8 Decal #9 Decal #10 Decal #11 Decal #12 Decal #13 Dry decals Allow to dry overnight Apply clear spray to decals Cut away backing Align decal Peel off backing Smooth decal Parachute Assembly 25 38 41 64 76 102 1.0 Engine Mount Assembly Est
Mark 25mm Mark 64 mm Apply glue to one side Apply glue to other side Set assembly aside Allow to dry Round leading edge fin #1 Round trailing edge fin #1 Streamline training edge fin #1 Round leading edge fin #2 Round trailing edge fin #2 Streamline training edge fin #2 Round leading edge fin #3 Round trailing edge fin #3 Streamline training edge fin #3 Glue drying Stand rocket on drying table Wipe away excess glue Allow to dry 9.0 Shock Cord Mount Attachment -Impact
5.0 Tube Marking Detail Sander 1.0 Engine Mount Assembly Take pencil 1.3.2 Mark tube 10.4.2 Tie lines together 112 27 32 22 4 2 11 18 $9.00 $35.00 $12.25 $8.00 $11.50 $7.50 $13.00 Glue Parachute 1.0 Engine Mount Assembly 1.0 Engine Mount Assembly 1.2.1 Move tube to ruler 1.3.1 Take pencil 1.3.2.1 Mark 25mm 1.4.1 Cut 3mm slit 1.7.1.1 Apply glue to one side 2.2.1 Cut cord mount along outline 2.4.1 Spread glue 2.5.3 Fold again 3.2.1 Trace fin #1 3.3.1 Cut fin #1 3.5.1 Lay sandpaper 3.6.1 Fine sand fin #1 4.2.1 Measure body tube 38 mm 4.3.1 Spread glue around body tube 5.2.1 Wrap guide around body tube 5.3.1 Mark tube for fins 5.3.3 Remove guide 5.4.1.1 Draw straight line 6.0 Fin Attachment 6.1.1 Apply to fin #1 6.2.1 Apply more glue to Fin #1 7.1.1 Measure 41mm 7.2.1 Apply glue to launch lug 8.1 Reinforce fins 9.1.1 Measure 25mm 9.2.1 Apply glue to shock cord 9.4.1 Hold mount attachment 10.1.1 Cut parachute along line 10.3.1 Attach tape rings 10.4.1 Pass shroud line through hole 12.2.1 Apply primer coat #1 12.3.1 Insert paint handle 12.4.1.1 Decal #1 12.4.1 Apply spray to rocket 12.5.4 Peel off backing Budget BCWS or, PV Actual Cost AC WP or, AC Earned Value BCWP or, EV SV = BCWP – BCWS CV = BCWP – ACWP Date Cost EAC Time S – Curves >Gantt
11 12 13 14 h
107 107 142 228 268 11h 49 325 0 336 28h 228 279 0 300 336 52 228 26 268 336 0 393 325 er
Duration 48 0 10 25 0 0 19 5 107 12 0 0 0 0 0 0 0 6 6 0 0 10 0 0 0 0 0 5 5 0 0 0 5 0 0 13 0 5 5 8 8 0 0 0 0 0 0 1 8 1 0 0 0 4 0 0 6 1 4 6 Let Dry 1 5 0 0 0 0 0 0 0 5 .
23 0 0 11 0 0 0 2 5 5 6 1 6 6 6 Let Dry 1 0 0 0 5 0 0 0 1 5 Let Dry 1 0 0 5 0 5 0 0 0 5 5 0 0 7 0 0 0 0 0 7 5 0 0 0 6 0 0 0 5 6 , Tape tube, Mark body tube & launch lug line
13 0 12 0 0 0 0 0 Cut out tube marking guide 6 6 8 5 14 0 0 0 0 0 6 0 6 8 6 0 0 0 0 0 0 4 0 4 7 0 0 0 0 0 0 0 7 0 0 0 6 0 0 0 0 6 12 0 0 0 0 0 0 1 6 6 Let Dry 1 0 0 0 8 0 0 0 1 8 Let dry 1 3 0 0 6 0 0 0 1 1 6 3 3 0 0 12 0 0 0 1 Apply glue to edge of fin 6 Wait for 1 minute for model 1 Apply second layer of glue to edge of fin 6 Attach Fin to body tube along one of fin lines flush w/end 3 5 0 0 12 0 0 0 1 Apply glue to edge of fin 6 Wait for 1 minute for model 1 Apply second layer of glue to edge of fin 6 Attach Fin to body tube along one of fin lines flush w/end 5 5 0 0 12 0 0 0 1 Apply glue to edge of fin 6 Wait for 1 minute for model 1 Apply second layer of glue to edge of fin 6 Attach Fin to body tube along one of fin lines flush w/end 5 16 0 0 0 0 0 0 1 4 4 4 4 1 0 0 0 0 0 0 6 1 6 1 0 0 4 0 0 0 0 0 4 0 5 0 6 0 0 0 0 6 forward
5 0 4 0 7 0 0 0 0 Apply glue to shock cord mount 7 Fold forward 4 4 0 0 0 0 0 0 1 4 1 0 0 0 8 0 0 0 1 5 3 1 5 0 0 5 0 0 0 1 5 5 Let Dry 1 0 0 0 0 0 0 4 0 4 0 0 0 0 0 0 4 0 4 6 0 0 0 0 0 0 0 6 0 0 0 4 0 0 0 0 4 0 0 0 16 0 0 0 1 5 5 6 1 0 0 0 0 6 8 0 1 8 Let Dry 1 Sand 6 0 0 0 0 4 5 0 1 5 Let dry 1 Sand 4 0 3 0 0 0 0 5 0 3 2 3 0 3 0 0 0 0 5 0 3 Place on Rocket where indicated 2 Rub decal to remove bubbles 3 0 3 0 0 0 0 5 0 3 Place on Rocket where indicated 2 Rub decal to remove bubbles 3 0 3 0 0 0 0 7 0 3 Place on Rocket where indicated 4 Rub decal to remove bubbles 3 0 0 0 0 0 6 0 5 6 Dry Completely 5 0 0 0 0 0 16 0 1 4 4 4 4 Let dry 1 16 0 0 20 0 0 0 4 5 4 1 5 4 Let to dry 1 5 4 Let to dry 1 5 4 1 16 0 0 0 0 0 0 0 6 2 8 0 0 0 0 0 0 5 0 5 Fold 0 6 0 0 0 0 0 0 6 6 0 0 0 0 0 0 0 6 12 3 0 0 0 0 0 0 3 4 4 4 9 0 0 0 0 0 3 0 3 4 5 30 38 21 35 29 Painter Engineer Dummy 205 30 38 147 21 35 73 29 578 Table of Contents
Cost Management Plan
1.1 Units of Measure 1.2 Level of Precision 1.3 Level of Accuracy 1.4 Process for Formal Acceptances 1.5 Process to Control Requests for Changes 1.6 Organizational Procedural Links
1.7 Control Thresholds
1.8 Rules of Performance Measurement
1.9 Reporting Formats
1.10 Process Descriptions
2.1 Roles and Responsibilities
2.2 Project Organization Charts
2.3 Staffing Management Plan
Procurement Management Plan
3.1 Procurement Management Approach 3.2 Procurement Definition 3.3 Type of Contract to be Used 3.4 Procurement Risks 3.5 Procurement Risk Management 3.6 Cost Determination 3.7 Standardized Procurement Documentation 3.8 Procurement Constraints 3.9 Contract Approval Process 3.10 Decision Criteria 3.11 Vendor Management 3.12 Performance Metrics
2
WBS
WBS #
TASKS
1
0
Engine Mount Assembly
1.1
Locate engine mount parts
1.2
Laying mout to ruler
1.
3
Marking mount
1.
4
Cutting mount
1.
5
Inserting hook
1.
6
Testing adapter ring
1.
7
Glue
2.0
Shock Cord Mount Assembly
2.1
Locate cord mount parts
2.2
Cut cord mount
2.3
Crease assembly
2.4
Glue mount assembly
2.5
Fold mount assembly
2.6
Clamp mount assembly
3.0
Fin Preparation
3.1
Select fin pattern
3.2
Trace fin patterns
3.3
Cut fin patterns
3.4
Save scrap
3.5
Course sand fins
3.6
Fine sand fins
4.0
Engine Mount Installation
4.1
Locate body tube
4.2
Measure body tube
4.3
Spread glue
4.4
Insert engine mount
5.0
Tube Marking Detail
5.1
Locate tube marking guide
5.2
Wrap guide
5.3
Mark tube
5.4
Draw fin markings
6.0
Fin Attachment
6.1
Apply glue
6.2
Apply second layer glue
6.3
Adjust fin
6.4
Set aside to dry
7.0
Launch Lug Attachment
7.1
Measure lug attachement
7.2
Glue lug attachment
7.3
Dry lug attachment
8
Glue Reinforcement
8.1
Reinforce fins
8.2
Glue dry
9
Shock Cord Mount Attachment
9.1
9.2
9.3
Set mount
9.4
Set glue
10
Parachute
10.1
Cut out parachute
10.2
Tape removal
10.3
Tape attachment
10.4
Shroud line assembly
10.5
Shroud line attachment
11
Parachute & Shock Cord Attachment to Nose Cone
11.1
Shroud line threading
11.2
Parachute pass throough
1
1.3
Line tightening
1
1.4
Shock cord tie down
12
Finishing Rocket
12.1
Verify dryness
12.2
Prime rocket
12.3
Paint rocket
12.4
Decal rocket
12.5
Decal qualitry assurance
12.6
Large decals
Activity List
DELIVERABLES & TASKS
ACTIVITIES
Locate engine mount parts
Locate light blue engine mount tube
Locate engine hook
Locate green adapter ring
Laying mount to ruler
Move tube to ruler
Align with zero mark
Take pencil
Mark tube
Mark
25
Mark
64
Cut 3mm slit
Insert hook
Extend hook
Slide ring into front of engine tube
Slide ring over engine hook to 25mm mark
Glue & Dry
Apply glue
Apply glue to one side
Apply glue to other side
Dry glue
Set assembly aside
Allow to dry
Locate cord mount parts
Locate cord mount on pattern sheet
Cut cord mount along outline
Fold on dotted lines
Crease on dotted lines
Spread glue
Lay end of shock cord in glue
Fold section 1
Apply glue section 3
Fold again
Clamp assembly
Fin Preparation
Select fin pattern
Cut fin pattern from sheet
Trace fin #1
Match fin #1
Trace fin #2
Match fin #2
Match fin #2
Cut fin patterns
Cut fin #1
Chect fin #1
Cut fin #2
Chect fin #2
Cut fin #3
Chect fin #3
Set aside piece scrap basa wood
Lay sandpaper
Stack fins
Sand fins
Fine sand fin #1
Round leading edge fin #1
Round trailing edge fin #1
Streamline training edge fin #1
Fine sand fin #2
Round leading edge fin #2
Round trailing edge fin #2
Streamline training edge fin #2
Fine sand fin #3
Round leading edge fin #3
Round trailing edge fin #3
Streamline training edge fin #3
Locate body tube Locate body tube
Measure body tube
38
Spread glue around body tube
Insert engine mount assembly into body tube
Locate tube marking guide
Locate tube marking guide on pattern sheet
Cut guide alone outline
Wrap guide around body tube
Tape guide to body tube
Mark tube for fins
Mark tube for fin #1
Mark tube for fin #2
Mark tube for fin #3
Write LL on body tube
Remove guide
Fin #1
Draw straight line
Extend line
76
Fin #2
Extend line 76mm
Fin #3
Extend line 76mm
Draw launch lug line
Draw line
102
Apply glue to root edges of fins
Apply to fin #1
Allow fin #1 to dry
Apply to fin #2
Allow fin #2 to dry
Apply to fin #3
Allow fin #3 to dry
Apply more glue to Fin #1
Set fin #1
Press fin #1
Apply more glue to Fin #2
Set fin #2
Press fin #2
Apply more glue to Fin #3
Set fin #3
Press fin #3
Adjust fins
Adjust fin #1
Attach fin #1
Adjust fin #2
Attach fin #2
Adjust fin #3
Attach fin #3
Stand rocket on drying table
Allow fins to dry
Measure lug attachement
Measure
41
Mark attachment point
Apply glue to launch lug
Attach launch lug to body tube
Ensure launch lug alignment
Glue Reinforcement
Reinforce fins
Reinforce fin fin #1
Reinforce fin fin #2
Reinforce fin fin #3
Reinforce launch lug
Reinforch side 1
Reinforce side 2
Glue drying
Wipe away excess glue
Shock Cord Mount Attachment
Measure body tube
Measure 25mm
Apply glue to shock cord
Insert cord into tube
Set mount 25mm
Press mount into glue
Hold mount attachment
Parachute Assembly
Cut parachute along line
Remove tape
Fold shroud lines
Cut shroud lines
Attach tape rings
Attach tape ring #1
Attach tape ring #2
Attach tape ring #3
Attach tape ring #4
Attach tape ring #5
Attach tape ring #6
Press tape tape rings into place
Press tape tape rings into place #1
Press tape tape rings into place #2
Press tape tape rings into place #3
Press tape tape rings into place #4
Press tape tape rings into place #5
Press tape tape rings into place #6
Punch tape ring holes
Punch tape ring holes #1
Punch tape ring holes #2
Punch tape ring holes #3
Punch tape ring holes #4
Punch tape ring holes #5
Punch tape ring holes #6
Pass shroud line through hole
Tie lines together
Shroud line threading
Thread shroud lines
Pass parachute through loop
Pull lines tight
Tie down shock cord free end
Verify dryness
Check to ensure glue joint are dry
Apply primer coat #1
Sand rocket body #1
Apply primer coat #2
Sand rocket body #2
Insert paint handle
Apply paint to rocket
Apply Water Decals
Cut decals
Decal #1
Decal #2
Decal #3
Decal #4
Decal #5
Decal #6
Decal #7
Decal #8
Decal #9
Decal #10
Decal #11
Decal #12
Decal #
13
Dip in water
Decal #2
Decal #3
Decal #4
Decal #5
Decal #6
Decal #7
Decal #8
Decal #9
Decal #10
Decal #11
Decal #12
Decal #13
Slip decals
Decal #2
Decal #3
Decal #4
Decal #5
Decal #6
Decal #7
Decal #8
Decal #9
Decal #10
Decal #11
Decal #12
Decal #13
Blot decals
Decal #2
Decal #3
Decal #4
Decal #5
Decal #6
Decal #7
Decal #8
Decal #9
Decal #10
Decal #11
Decal #12
Decal #13
Dry decals
Allow to dry overnight
Apply clear spray to decals
Apply spray to rocket
Apply large decals
Peel backing
Cut away backing
Align decal
Peel off backing
Smooth decal
WBS # TASKS
1.0
1.1 Locate engine mount parts
1.1.1
1.1.2
1.1.3
1.2 Laying mount to ruler
1.2.1
1.2.2
1.3 Marking mount
1.3.1
1.3.2
1.
3.2.1
Mark 25mm
1.
3.2.2
Mark 64 mm
1.4 Cutting mount
1.4.1
1.5
1.5.1
1.5.2
1.6
1.6.1
1.6.2
1.7
1.7.1
1.
7.1.1
1.
7.1.2
1.7.2
1.
7.2.1
1.
7.2.2
2.0 Shock Cord Mount Assembly
2.1 Locate cord mount parts
2.1.1
2.2 Cut cord mount
2.2.1
2.3 Crease assembly
2.3.1
2.3.2
2.4 Glue mount assembly
2.4.1
2.4.2
2.5 Fold mount assembly
2.5.1
2.5.2
2.5.3
2.6 Clamp mount assembly
2.6.1
2.6.2
3.0 Fin Preparation
3.1.1
3.1.2
3.2 Trace fin patterns
3.2.1 Trace fin #1
3.2.2 Match fin #1
3.2.3
3.2.4
3.2.5
3.2.6
3.3 Cut fin patterns
3.3.1
3.3.2
3.3.3
3.3.4
3.3.5
3.3.6
3.4 Save scrap
3.4.1
3.5 Course sand fins
3.5.1
3.5.2
3.5.3
3.6 Fine sand fins
3.6.1
3.
6.1.1
3.
6.1.2
3.
6.1.3
3.6.2
3.
6.2.1
3.
6.2.2
3.
6.2.3
3.6.3
3.
6.3.1
3.
6.3.2
3.
6.3.3
4.0 Engine Mount Installation
4.1 Locate body tube
4.1.1
4.2 Measure body tube
4.2.1
Measure body tube 38 mm
4.3 Spread glue
4.3.1
4.4 Insert engine mount
4.4.1
5.0 Tube Marking Detail
5.1 Locate tube marking guide
5.1.1
5.1.2
5.2 Wrap guide
5.2.1
5.2.2
5.3 Mark tube
5.3.1
5.3.1.1
5.3.1.2
5.3.1.3
5.3.2
5.3.3
5.4 Draw fin markings
5.4.1
5.4.1.1
5.4.1.2
5.4.2
5.4.2.1
5.4.2.2
5.4.3
5.4.3.1
5.4.3.2
5.4.4
5.4.4.1
Draw line 102 mm
6.0 Fin Attachment
6.1 Apply glue to root edges of fins
6.1.1 Apply to fin #1
6.1.2 Allow fin #1 to dry
6.1.3 Apply to fin #2
6.1.4
6.1.5
6.1.6
6.2 Apply second layer glue
6.2.1 Apply more glue to Fin #1
6.2.2 Set fin #1
6.2.3 Press fin #1
6.2.4
6.2.5
6.2.6
6.2.7
6.2.8
6.2.9
6.3 Adjust fins
6.3.1 Adjust fin #1
6.3.2 Attach fin #1
6.3.3 Adjust fin #2
6.3.4
6.3.5
6.3.6
6.4 Set aside to dry
6.4.1
6.4.2
7.0 Launch Lug Attachment
7.1 Measure lug attachement
7.1.1
Measure 41mm
7.1.2 Mark attachment point
7.2 Glue lug attachment
7.2.1 Apply glue to launch lug
7.2.2 Attach launch lug to body tube
7.3 Dry lug attachment
7.3.1
7.3.2
8.0
8.1 Reinforce fins
8.1.1
8.1.2
8.1.3
8.2 Reinforce launch lug
8.2.1
8.2.2
8.2 Glue drying
8.2.1 Stand rocket on drying table
8.2.2 Wipe away excess glue
8.2.3
9.0
9.1.1
9.2.1
9.2.2
9.3 Set mount
9.3.1
9.3.2
9.4 Set glue
9.4.1
9.4.2
10.0
10.1 Cut out parachute
10.1.1
10.2 Tape removal
10.2.1
10.2.2
10.2.3
10.3 Tape attachment
10.3.1
10.3.1.1
10.3.1.2
10.3.1.3
10.3.1.4
10.3.1.5
10.3.1.6
10.3.2
10.3.2.1
10.3.2.2
10.3.2.3
10.3.2.4
10.3.2.5
10.3.2.6
10.3.3
10.3.3.1
10.3.3.2
10.3.3.3
10.3.3.4
10.3.3.5
10.3.3.6
10.4 Shroud line assembly
10.4.1
10.4.2
11.0
11.1 Shroud line threading
11.1.1
11.2 Parachute pass throough
11.2.1
11.3
11.3.1
11.4
11.4.1
12.0
12.1 Verify dryness
12.1.1
12.2 Prime rocket
12.2.1
12.2.2
12.2.3
12.2.4
12.3 Paint rocket
12.3.1
12.3.2
12.3.3
12.4 Apply Water Decals
12.4.1
12.4.1.1
12.4.1.2
12.4.1.3
12.4.1.4
12.4.1.5
12.4.1.6
12.4.1.7
12.4.1.8
12.4.1.9
12.4.1.10
12.4.1.11
12.4.1.12
12.4.1.13
12.4.2
12.4.2.1
12.4.2.2
12.4.2.3
12.4.2.4
12.4.2.5
12.4.2.6
12.4.2.7
12.4.2.8
12.4.2.9
12.4.2.10
12.4.2.11
12.4.2.12
12.4.2.13
12.4.3
12.4.3.1
12.4.3.2
12.4.3.3
12.4.3.4
12.4.3.5
12.4.3.6
12.4.3.7
12.4.3.8
12.4.3.9
12.4.3.10
12.4.3.11
12.4.3.12
12.4.3.13
12.4.4
12.4.4.1
12.4.4.2
12.4.4.3
12.4.4.4
12.4.4.5
12.4.4.6
12.4.4.7
12.4.4.8
12.4.4.9
12.4.4.10
12.4.4.11
12.4.4.12
12.4.4.13
12.4.5
12.5.1
12.4.6
12.4.1 Apply spray to rocket
12.5 Apply large decals
12.5.1 Peel backing
12.5.2
12.5.3
12.5.4
12.5.5
Network
Engine Mount Assembly Engine Mount Installation Launch Lug Attachment
Fin Preparation Tube Marking Detail Fin Attachment Glue Reinforcement
Shock Cord Mount Assembly Finishing Rocket
Parachute & Shock Cord Attachment to Nose Cone Shock Cord Mount Attachment
Gantt
DAY 1
DAY 2
DAY 3
DAY 4
DAY 5
DAY 6
DAY 7
DAY 8
DAY 9
DAY 10
DAY 11
DAY 12
DAY 13
DAY
14
DAY
15
DAY
16
DAY
17
DAY
18
DAY
19
WBS # TASKS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
20
21
22
23
24
26
27
28
29
30
31
32
33
34
35
36
37
39
40
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
65
66
67
68
69
70
71
72
73
74
75
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
2.0 Shock Cord Mount Assembly
3.0 Fin Preparation
4.0 Engine Mount Installation
5.0 Tube Marking Detail
6.0 Fin Attachment
7.0 Launch Lug Attachment
8.0 Glue Reinforcement
9.0 Shock Cord Mount Attachment
10.0 Parachute Assembly
11.0 Parachute & Shock Cord Attachment to Nose Cone
12.0 Finishing Rocket
Duration
WBS # TASKS
1.0 Engine Mount Assembly
1.1 Locate engine mount parts
1.1.1 Locate light blue engine mount tube
1.1.2 Locate engine hook
1.1.3 Locate green adapter ring
1.2 Laying mount to ruler
1.2.1 Move tube to ruler
1.2.2 Align with zero mark
1.3 Marking mount
1.3.1 Take pencil
1.3.2 Mark tube
1.3.2.1
1.3.2.2
1.4 Cutting mount
1.4.1 Cut 3mm slit
1.5 Inserting hook
1.5.1 Insert hook
1.5.2 Extend hook
1.6 Testing adapter ring
1.6.1 Slide ring into front of engine tube
1.6.2 Slide ring over engine hook to 25mm mark
1.7 Glue & Dry
1.7.1 Apply glue
1.7.1.1
1.7.1.2
1.7.2 Dry glue
1.7.2.1
1.7.2.2
2.0 Shock Cord Mount Assembly
2.1 Locate cord mount parts
2.1.1 Locate cord mount on pattern sheet
2.2 Cut cord mount
2.2.1 Cut cord mount along outline
2.3 Crease assembly
2.3.1 Fold on dotted lines
2.3.2 Crease on dotted lines
2.4 Glue mount assembly
2.4.1 Spread glue
2.4.2 Lay end of shock cord in glue
2.5 Fold mount assembly
2.5.1 Fold section 1
2.5.2 Apply glue section 3
2.5.3 Fold again
2.6 Clamp mount assembly
2.6.1 Clamp assembly
2.6.2 Allow to dry
3.0 Fin Preparation
3.1 Select fin pattern
3.1.1 Select fin pattern
3.1.2 Cut fin pattern from sheet
3.2 Trace fin patterns
3.2.1 Trace fin #1
3.2.2 Match fin #1
3.2.3 Trace fin #2
3.2.4 Match fin #2
3.2.5 Trace fin #2
3.2.6 Match fin #2
3.3 Cut fin patterns
3.3.1 Cut fin #1
3.3.2 Chect fin #1
3.3.3 Cut fin #2
3.3.4 Chect fin #2
3.3.5 Cut fin #3
3.3.6 Chect fin #3
3.4 Save scrap
3.4.1 Set aside piece scrap basa wood
3.5 Course sand fins
3.5.1 Lay sandpaper
3.5.2 Stack fins
3.5.3 Sand fins
3.6 Fine sand fins
3.6.1 Fine sand fin #1
3.6.1.1
3.6.1.2
3.6.1.3
3.6.2 Fine sand fin #2
3.6.2.1
3.6.2.2
3.6.2.3
3.6.3 Fine sand fin #3
3.6.3.1
3.6.3.2
3.6.3.3
4.0 Engine Mount Installation
4.1 Locate body tube
4.1.1 Locate body tube
4.2 Measure body tube
4.2.1 Measure body tube 38 mm
4.3 Spread glue
4.3.1 Spread glue around body tube
4.4 Insert engine mount
4.4.1 Insert engine mount assembly into body tube
5.0 Tube Marking Detail
5.1 Locate tube marking guide
5.1.1 Locate tube marking guide on pattern sheet
5.1.2 Cut guide alone outline
5.2 Wrap guide
5.2.1 Wrap guide around body tube
5.2.2 Tape guide to body tube
5.3 Mark tube
5.3.1 Mark tube for fins
5.3.1.1 Mark tube for fin #1
5.3.1.2 Mark tube for fin #2
5.3.1.3 Mark tube for fin #3
5.3.2 Write LL on body tube
5.3.3 Remove guide
5.4 Draw fin markings
5.4.1 Fin #1
5.4.1.1 Draw straight line
5.4.1.2 Extend line 76mm
5.4.2 Fin #2
5.4.2.1 Draw straight line
5.4.2.2 Extend line 76mm
5.4.3 Fin #3
5.4.3.1 Draw straight line
5.4.3.2 Extend line 76mm
5.4.4 Draw launch lug line
5.4.4.1 Draw line 102 mm
6.0 Fin Attachment
6.1 Apply glue to root edges of fins
6.1.1 Apply to fin #1
6.1.2 Allow fin #1 to dry
6.1.3 Apply to fin #2
6.1.4 Allow fin #2 to dry
6.1.5 Apply to fin #3
6.1.6 Allow fin #3 to dry
6.2 Apply second layer glue
6.2.1 Apply more glue to Fin #1
6.2.2 Set fin #1
6.2.3 Press fin #1
6.2.4 Apply more glue to Fin #2
6.2.5 Set fin #2
6.2.6 Press fin #2
6.2.7 Apply more glue to Fin #3
6.2.8 Set fin #3
6.2.9 Press fin #3
6.3 Adjust fins
6.3.1 Adjust fin #1
6.3.2 Attach fin #1
6.3.3 Adjust fin #2
6.3.4 Attach fin #2
6.3.5 Adjust fin #3
6.3.6 Attach fin #3
6.4 Set aside to dry
6.4.1 Stand rocket on drying table
6.4.2 Allow fins to dry
7.0 Launch Lug Attachment
7.1 Measure lug attachement
7.1.1 Measure 41mm
7.1.2 Mark attachment point
7.2 Glue lug attachment
7.2.1 Apply glue to launch lug
7.2.2 Attach launch lug to body tube
7.3 Dry lug attachment
7.3.1 Ensure launch lug alignment
7.3.2 Allow to dry
8.0 Glue Reinforcement
8.1 Reinforce fins
8.1.1 Reinforce fin fin #1
8.1.2 Reinforce fin fin #2
8.1.3 Reinforce fin fin #3
8.2 Reinforce launch lug
8.2.1 Reinforch side 1
8.2.2 Reinforce side 2
8.3
8.3.1
8.3.2
8.3.3
9.1 Measure body tube
9.1.1 Measure 25mm
9.2 Apply glue
9.2.1 Apply glue to shock cord
9.2.2 Insert cord into tube
9.3 Set mount
9.3.1 Set mount 25mm
9.3.2 Press mount into glue
9.4 Set glue
9.4.1 Hold mount attachment
9.4.2 Allow to dry
10.0 Parachute Assembly
10.1 Cut out parachute
10.1.1 Cut parachute along line
10.2 Tape removal
10.2.1 Remove tape
10.2.2 Fold shroud lines
10.2.3 Cut shroud lines
10.3 Tape attachment
10.3.1 Attach tape rings
10.3.1.1 Attach tape ring #1
10.3.1.2 Attach tape ring #2
10.3.1.3 Attach tape ring #3
10.3.1.4 Attach tape ring #4
10.3.1.5 Attach tape ring #5
10.3.1.6 Attach tape ring #6
10.3.2 Press tape tape rings into place
10.3.2.1 Press tape tape rings into place #1
10.3.2.2 Press tape tape rings into place #2
10.3.2.3 Press tape tape rings into place #3
10.3.2.4 Press tape tape rings into place #4
10.3.2.5 Press tape tape rings into place #5
10.3.2.6 Press tape tape rings into place #6
10.3.3 Punch tape ring holes
10.3.3.1 Punch tape ring holes #1
10.3.3.2 Punch tape ring holes #2
10.3.3.3 Punch tape ring holes #3
10.3.3.4 Punch tape ring holes #4
10.3.3.5 Punch tape ring holes #5
10.3.3.6 Punch tape ring holes #6
10.4 Shroud line assembly
10.4.1 Pass shroud line through hole
10.4.2 Tie lines together
11.0 Parachute & Shock Cord Attachment to Nose Cone
11.1 Shroud line threading
11.1.1 Thread shroud lines
11.2 Parachute pass throough
11.2.1 Pass parachute through loop
11.3 Line tightening
11.3.1 Pull lines tight
11.4 Shock cord tie down
11.4.1 Tie down shock cord free end
12.0 Finishing Rocket
12.1 Verify dryness
12.1.1 Check to ensure glue joint are dry
12.2 Prime rocket
12.2.1 Apply primer coat #1
12.2.2 Sand rocket body #1
12.2.3 Apply primer coat #2
12.2.4 Sand rocket body #2
12.3 Paint rocket
12.3.1 Insert paint handle
12.3.2 Apply paint to rocket
12.3.3 Allow to dry
12.4 Apply Water Decals
12.4.1 Cut decals
12.4.1.1 Decal #1
12.4.1.2 Decal #2
12.4.1.3 Decal #3
12.4.1.4 Decal #4
12.4.1.5 Decal #5
12.4.1.6 Decal #6
12.4.1.7 Decal #7
12.4.1.8 Decal #8
12.4.1.9 Decal #9
12.4.1.10 Decal #10
12.4.1.11 Decal #11
12.4.1.12 Decal #12
12.4.1.13 Decal #13
12.4.2 Dip in water
12.4.2.1 Decal #1
12.4.2.2 Decal #2
12.4.2.3 Decal #3
12.4.2.4 Decal #4
12.4.2.5 Decal #5
12.4.2.6 Decal #6
12.4.2.7 Decal #7
12.4.2.8 Decal #8
12.4.2.9 Decal #9
12.4.2.10 Decal #10
12.4.2.11 Decal #11
12.4.2.12 Decal #12
12.4.2.13 Decal #13
12.4.3 Slip decals
12.4.3.1 Decal #1
12.4.3.2 Decal #2
12.4.3.3 Decal #3
12.4.3.4 Decal #4
12.4.3.5 Decal #5
12.4.3.6 Decal #6
12.4.3.7 Decal #7
12.4.3.8 Decal #8
12.4.3.9 Decal #9
12.4.3.10 Decal #10
12.4.3.11 Decal #11
12.4.3.12 Decal #12
12.4.3.13 Decal #13
12.4.4 Blot decals
12.4.4.1 Decal #1
12.4.4.2 Decal #2
12.4.4.3 Decal #3
12.4.4.4 Decal #4
12.4.4.5 Decal #5
12.4.4.6 Decal #6
12.4.4.7 Decal #7
12.4.4.8 Decal #8
12.4.4.9 Decal #9
12.4.4.10 Decal #10
12.4.4.11 Decal #11
12.4.4.12 Decal #12
12.4.4.13 Decal #13
12.4.5 Dry decals
12.5.1 Allow to dry overnight
12.4.6 Apply clear spray to decals
12.4.1 Apply spray to rocket
12.5 Apply large decals
12.5.1 Peel backing
12.5.2 Cut away backing
12.5.3 Align decal
12.5.4 Peel off backing
12.5.5 Smooth decal
X
WBS # TASKS
Fitter
Draftsman
Cutter
Gluer
Sander
1.0 Engine Mount Assembly X X X X
2.0 Shock Cord Mount Assembly X X X
3.0 Fin Preparation X X X X
4.0 Engine Mount Installation X X X
6.0 Fin Attachment
7.0 Launch Lug Attachment
8.0 Glue Reinforcement
9.0 Shock Cord Mount Attachment
10.0 Parachute Assembly
11.0 Parachute & Shock Cord Attachment to Nose Cone
12.0 Finishing Rocket
RAM
WBS # TASKS Fitter Draftsman Cutter Gluer
Painter
Sr Sander
Dummy
1.1 Locate engine mount parts
1.1.1 Locate light blue engine mount tube
1.1.2 Locate engine hook
1.1.3 Locate green adapter ring
1.2 Laying mount to ruler
1.2.1 Move tube to ruler
1.2.2 Align with zero mark
1.3 Marking mount
1.3.1 Take pencil
1.3.1.1
1.3.2.1 Mark 25mm
1.3.2.2 Mark 64 mm
1.4 Cutting mount
1.4.1 Cut 3mm slit
1.5 Inserting hook
1.5.1 Insert hook
1.5.2 Extend hook
1.6 Testing adapter ring
1.6.1 Slide ring into front of engine tube
1.6.2 Slide ring over engine hook to 25mm mark
1.7 Glue & Dry
1.7.1 Apply glue
1.7.1.1 Apply glue to one side
1.7.1.2 Apply glue to other side
1.7.2 Dry glue
1.7.2.1 Set assembly aside
1.7.2.2 Allow to dry
2.0 Shock Cord Mount Assembly
2.1 Locate cord mount parts
2.1.1 Locate cord mount on pattern sheet
2.2 Cut cord mount
2.2.1 Cut cord mount along outline
2.3 Crease assembly
2.3.1 Fold on dotted lines
2.3.2 Crease on dotted lines
2.4 Glue mount assembly
2.4.1 Spread glue
2.4.2 Lay end of shock cord in glue
2.5 Fold mount assembly
2.5.1 Fold section 1
2.5.2 Apply glue section 3
2.5.3 Fold again
2.6 Clamp mount assembly
2.6.1 Clamp assembly
2.6.2 Allow to dry
3.0 Fin Preparation
3.1 Select fin pattern
3.1.1 Select fin pattern
3.1.2 Cut fin pattern from sheet
3.2 Trace fin patterns
3.2.1 Trace fin #1
3.2.2 Match fin #1
3.2.3 Trace fin #2
3.2.4 Match fin #2
3.2.5 Trace fin #2
3.2.6 Match fin #2
3.3 Cut fin patterns
3.3.1 Cut fin #1
3.3.2 Chect fin #1
3.3.3 Cut fin #2
3.3.4 Chect fin #2
3.3.5 Cut fin #3
3.3.6 Chect fin #3
3.4 Save scrap
3.4.1 Set aside piece scrap basa wood
3.5 Course sand fins
3.5.1 Lay sandpaper
3.5.2 Stack fins
3.5.3 Sand fins
3.6 Fine sand fins
3.6.1 Fine sand fin #1
3.6.1.1 Round leading edge fin #1
3.6.1.2 Round trailing edge fin #1
3.6.1.3 Streamline training edge fin #1
3.6.2 Fine sand fin #2
3.6.2.1 Round leading edge fin #2
3.6.2.2 Round trailing edge fin #2
3.6.2.3 Streamline training edge fin #2
3.6.3 Fine sand fin #3
3.6.3.1 Round leading edge fin #3
3.6.3.2 Round trailing edge fin #3
3.6.3.3 Streamline training edge fin #3
4.0 Engine Mount Installation
4.1 Locate body tube
4.1.1 Locate body tube
4.2 Measure body tube
4.2.1 Measure body tube 38 mm
4.3 Spread glue
4.3.1 Spread glue around body tube
4.4 Insert engine mount
4.4.1 Insert engine mount assembly into body tube
5.0 Tube Marking Detail
5.1 Locate tube marking guide
5.1.1 Locate tube marking guide on pattern sheet
5.1.2 Cut guide alone outline
5.2 Wrap guide
5.2.1 Wrap guide around body tube
5.2.2 Tape guide to body tube
5.3 Mark tube
5.3.1 Mark tube for fins
5.3.1.1 Mark tube for fin #1
5.3.1.2 Mark tube for fin #2
5.3.1.3 Mark tube for fin #3
5.3.2 Write LL on body tube
5.3.3 Remove guide
5.4 Draw fin markings
5.4.1 Fin #1
5.4.1.1 Draw straight line
5.4.1.2 Extend line 76mm
5.4.2 Fin #2
5.4.2.1 Draw straight line
5.4.2.2 Extend line 76mm
5.4.3 Fin #3
5.4.3.1 Draw straight line
5.4.3.2 Extend line 76mm
5.4.4 Draw launch lug line
5.4.4.1 Draw line 102 mm
6.0 Fin Attachment
6.1 Apply glue to root edges of fins
6.1.1 Apply to fin #1
6.1.2 Allow fin #1 to dry
6.1.3 Apply to fin #2
6.1.4 Allow fin #2 to dry
6.1.5 Apply to fin #3
6.1.6 Allow fin #3 to dry
6.2 Apply second layer glue
6.2.1 Apply more glue to Fin #1
6.2.2 Set fin #1
6.2.3 Press fin #1
6.2.4 Apply more glue to Fin #2
6.2.5 Set fin #2
6.2.6 Press fin #2
6.2.7 Apply more glue to Fin #3
6.2.8 Set fin #3
6.2.9 Press fin #3
6.3 Adjust fins
6.3.1 Adjust fin #1
6.3.2 Attach fin #1
6.3.3 Adjust fin #2
6.3.4 Attach fin #2
6.3.5 Adjust fin #3
6.3.6 Attach fin #3
6.4 Set aside to dry
6.4.1 Stand rocket on drying table
6.4.2 Allow fins to dry
7.0 Launch Lug Attachment
7.1 Measure lug attachement
7.1.1 Measure 41mm
7.1.2 Mark attachment point
7.2 Glue lug attachment
7.2.1 Apply glue to launch lug
7.2.2 Attach launch lug to body tube
7.3 Dry lug attachment
7.3.1 Ensure launch lug alignment
7.3.2 Allow to dry
8.0 Glue Reinforcement
8.1 Reinforce fins
8.1.1 Reinforce fin fin #1
8.1.2 Reinforce fin fin #2
8.1.3 Reinforce fin fin #3
8.2 Reinforce launch lug
8.2.1 Reinforch side 1
8.2.2 Reinforce side 2
8.3 Glue drying
8.3.1 Stand rocket on drying table
8.3.2 Wipe away excess glue
8.3.3 Allow to dry
9.0 Shock Cord Mount Attachment
9.1 Measure body tube
9.1.1 Measure 25mm
9.2 Apply glue
9.2.1 Apply glue to shock cord
9.2.2 Insert cord into tube
9.3 Set mount
9.3.1 Set mount 25mm
9.3.2 Press mount into glue
9.4 Set glue
9.4.1 Hold mount attachment
9.4.2 Allow to dry
10.0 Parachute Assembly
10.1 Cut out parachute
10.1.1 Cut parachute along line
10.2 Tape removal
10.2.1 Remove tape
10.2.2 Fold shroud lines
10.2.3 Cut shroud lines
10.3 Tape attachment
10.3.1 Attach tape rings
10.3.1.1 Attach tape ring #1
10.3.1.2 Attach tape ring #2
10.3.1.3 Attach tape ring #3
10.3.1.4 Attach tape ring #4
10.3.1.5 Attach tape ring #5
10.3.1.6 Attach tape ring #6
10.3.2 Press tape tape rings into place
10.3.2.1 Press tape tape rings into place #1
10.3.2.2 Press tape tape rings into place #2
10.3.2.3 Press tape tape rings into place #3
10.3.2.4 Press tape tape rings into place #4
10.3.2.5 Press tape tape rings into place #5
10.3.2.6 Press tape tape rings into place #6
10.3.3 Punch tape ring holes
10.3.3.1 Punch tape ring holes #1
10.3.3.2 Punch tape ring holes #2
10.3.3.3 Punch tape ring holes #3
10.3.3.4 Punch tape ring holes #4
10.3.3.5 Punch tape ring holes #5
10.3.3.6 Punch tape ring holes #6
10.4 Shroud line assembly
10.4.1 Pass shroud line through hole
10.4.2 Tie lines together
11.0 Parachute & Shock Cord Attachment to Nose Cone
11.1 Shroud line threading
11.1.1 Thread shroud lines
11.2 Parachute pass throough
11.2.1 Pass parachute through loop
11.3 Line tightening
11.3.1 Pull lines tight
11.4 Shock cord tie down
11.4.1 Tie down shock cord free end
12.0 Finishing Rocket
12.1 Verify dryness
12.1.1 Check to ensure glue joint are dry
12.2 Prime rocket
12.2.1 Apply primer coat #1
12.2.2 Sand rocket body #1
12.2.3 Apply primer coat #2
12.2.4 Sand rocket body #2
12.3 Paint rocket
12.3.1 Insert paint handle
12.3.2 Apply paint to rocket
12.3.3 Allow to dry
12.4 Apply Water Decals
12.4.1 Cut decals
12.4.1.1 Decal #1
12.4.1.2 Decal #2
12.4.1.3 Decal #3
12.4.1.4 Decal #4
12.4.1.5 Decal #5
12.4.1.6 Decal #6
12.4.1.7 Decal #7
12.4.1.8 Decal #8
12.4.1.9 Decal #9
12.4.1.10 Decal #10
12.4.1.11 Decal #11
12.4.1.12 Decal #12
12.4.1.13 Decal #13
12.4.2 Dip in water
12.4.2.1 Decal #1
12.4.2.2 Decal #2
12.4.2.3 Decal #3
12.4.2.4 Decal #4
12.4.2.5 Decal #5
12.4.2.6 Decal #6
12.4.2.7 Decal #7
12.4.2.8 Decal #8
12.4.2.9 Decal #9
12.4.2.10 Decal #10
12.4.2.11 Decal #11
12.4.2.12 Decal #12
12.4.2.13 Decal #13
12.4.3 Slip decals
12.4.3.1 Decal #1
12.4.3.2 Decal #2
12.4.3.3 Decal #3
12.4.3.4 Decal #4
12.4.3.5 Decal #5
12.4.3.6 Decal #6
12.4.3.7 Decal #7
12.4.3.8 Decal #8
12.4.3.9 Decal #9
12.4.3.10 Decal #10
12.4.3.11 Decal #11
12.4.3.12 Decal #12
12.4.3.13 Decal #13
12.4.4 Blot decals
12.4.4.1 Decal #1
12.4.4.2 Decal #2
12.4.4.3 Decal #3
12.4.4.4 Decal #4
12.4.4.5 Decal #5
12.4.4.6 Decal #6
12.4.4.7 Decal #7
12.4.4.8 Decal #8
12.4.4.9 Decal #9
12.4.4.10 Decal #10
12.4.4.11 Decal #11
12.4.4.12 Decal #12
12.4.4.13 Decal #13
12.4.5 Dry decals
12.5.1 Allow to dry overnight
12.4.6 Apply clear spray to decals
12.4.1 Apply spray to rocket
12.5 Apply large decals
12.5.1 Peel backing
12.5.2 Cut away backing
12.5.3 Align decal
12.5.4 Peel off backing
12.5.5 Smooth decal
Rates
Fitter Draftsman Cutter Gluer Painter Sander Sr Sander
$9.00
$35.00
$12.25
$8.00
$11.50
$7.50
$13.00
Roll-Up Est
WBS # TASKS Fitter Draftsman Cutter Gluer Painter Sander Sr Sander Dummy Duration
1.0 Engine Mount Assembly 10 4 1 2 0 0 0 1 18
1.1 Locate engine mount parts 3 0 0 0 0 0 0 0
1.1.1 Locate light blue engine mount tube 1
1.1.2 Locate engine hook 1
1.1.3 Locate green adapter ring 1
1.2 Laying mount to ruler 2 0 0 0 0 0 0 0
1.2.1 Move tube to ruler 1
1.2.2 Align with zero mark 1
1.3 Marking mount 0 3 0 0 0 0 0 0
1.3.1 Take pencil 1
1.3.2 Mark tube 0 2 0 0 0 0 0 0
1.3.2.1 Mark 25mm 1
1.3.2.2 Mark 64 mm 1
1.4 Cutting mount 0 0 1 0 0 0 0 0
1.4.1 Cut 3mm slit 1
1.5 Inserting hook 2 0 0 0 0 0 0 0
1.5.1 Insert hook 1
1.5.2 Extend hook 1
1.6 Testing adapter ring 2 1 0 0 0 0 0 0
1.6.1 Slide ring into front of engine tube 1
1.6.2 Slide ring over engine hook to 25mm mark 1 1
1.7 Glue & Dry 1 0 0 2 0 0 0 1
1.7.1 Apply glue 0 0 0 2 0 0 0 0
1.7.1.1 Apply glue to one side 1
1.7.1.2 Apply glue to other side 1
1.7.2 Dry glue 1 0 0 0 0 0 0 1
1.7.2.1 Set assembly aside 1
1.7.2.2 Allow to dry 1
2.0 Shock Cord Mount Assembly 7 0 1 3 0 0 0 1 12
2.1 Locate cord mount parts 1 0 0 0 0 0 0 0
2.1.1 Locate cord mount on pattern sheet 1
2.2 Cut cord mount 0 0 1 0 0 0 0 0
2.2.1 Cut cord mount along outline 1
2.3 Crease assembly 2 0 0 0 0 0 0 0
2.3.1 Fold on dotted lines 1
2.3.2 Crease on dotted lines 1
2.4 Glue mount assembly 1 0 0 2 0 0 0 0
2.4.1 Spread glue 1
2.4.2 Lay end of shock cord in glue 1 1
2.5 Fold mount assembly 2 0 0 1 0 0 0 0
2.5.1 Fold section 1 1
2.5.2 Apply glue section 3 1
2.5.3 Fold again 1
2.6 Clamp mount assembly 1 0 0 0 0 0 0 1
2.6.1 Clamp assembly 1
2.6.2 Allow to dry 1
3.0 Fin Preparation 6 6 7 0 0 2 9 0 30
3.1 Select fin pattern 1 0 1 0 0 0 0 0
3.1.1 Select fin pattern 1
3.1.2 Cut fin pattern from sheet 1
3.2 Trace fin patterns 3 6 0 0 0 0 0 0
3.2.1 Trace fin #1 1
3.2.2 Match fin #1 1 1
3.2.3 Trace fin #2 1
3.2.4 Match fin #2 1 1
3.2.5 Trace fin #2 1
3.2.6 Match fin #2 1 1
3.3 Cut fin patterns 0 0 6 0 0 0 0 0
3.3.1 Cut fin #1 1
3.3.2 Chect fin #1 1
3.3.3 Cut fin #2 1
3.3.4 Chect fin #2 1
3.3.5 Cut fin #3 1
3.3.6 Chect fin #3 1
3.4 Save scrap 1 0 0 0 0 0 0 0
3.4.1 Set aside piece scrap basa wood 1
3.5 Course sand fins 1 0 0 0 0 2 0 0
3.5.1 Lay sandpaper 1
3.5.2 Stack fins 1
3.5.3 Sand fins 1
3.6 Fine sand fins 0 0 0 0 0 0 9 0
3.6.1 Fine sand fin #1 0 0 0 0 0 0 3 0
3.6.1.1 Round leading edge fin #1 1
3.6.1.2 Round trailing edge fin #1 1
3.6.1.3 Streamline training edge fin #1 1
3.6.2 Fine sand fin #2 0 0 0 0 0 0 3 0
3.6.2.1 Round leading edge fin #2 1
3.6.2.2 Round trailing edge fin #2 1
3.6.2.3 Streamline training edge fin #2 1
3.6.3 Fine sand fin #3 0 0 0 0 0 0 3 0
3.6.3.1 Round leading edge fin #3 1
3.6.3.2 Round trailing edge fin #3 1
3.6.3.3 Streamline training edge fin #3 1
4.0 Engine Mount Installation 2 1 0 1 0 0 0 0 4
4.1 Locate body tube 1 0 0 0 0 0 0 0
4.1.1 Locate body tube 1
4.2 Measure body tube 0 1 0 0 0 0 0 0
4.2.1 Measure body tube 38 mm 1
4.3 Spread glue 0 0 0 1 0 0 0 0
4.3.1 Spread glue around body tube 1
4.4 Insert engine mount 1 0 0 0 0 0 0 0
4.4.1 Insert engine mount assembly into body tube 1
5.0 Tube Marking Detail 4 11 1 0 0 0 0 0 16
5.1 Locate tube marking guide 1 0 1 0 0 0 0 0
5.1.1 Locate tube marking guide on pattern sheet 1
5.1.2 Cut guide alone outline 1
5.2 Wrap guide 2 0 0 0 0 0 0 0
5.2.1 Wrap guide around body tube 1
5.2.2 Tape guide to body tube 1
5.3 Mark tube 1 4 0 0 0 0 0 0
5.3.1 Mark tube for fins 0 3 0 0 0 0 0 0
5.3.1.1 Mark tube for fin #1 1
5.3.1.2 Mark tube for fin #2 1
5.3.1.3 Mark tube for fin #3 1
5.3.2 Write LL on body tube 1
5.3.3 Remove guide 1
5.4 Draw fin markings 0 7 0 0 0 0 0 0
5.4.1 Fin #1 0 2 0 0 0 0 0 0
5.4.1.1 Draw straight line 1
5.4.1.2 Extend line 76mm 1
5.4.2 Fin #2 0 2 0 0 0 0 0 0
5.4.2.1 Draw straight line 1
5.4.2.2 Extend line 76mm 1
5.4.3 Fin #3 0 2 0 0 0 0 0 0
5.4.3.1 Draw straight line 1
5.4.3.2 Extend line 76mm 1
5.4.4 Draw launch lug line 0 1 0 0 0 0 0 0
5.4.4.1 Draw line 102 mm 1
6.0 Fin Attachment 13 0 0 6 0 0 0 4 23
6.1 Apply glue to root edges of fins 0 0 0 3 0 0 0 3
6.1.1 Apply to fin #1 1
6.1.2 Allow fin #1 to dry 1
6.1.3 Apply to fin #2 1
6.1.4 Allow fin #2 to dry 1
6.1.5 Apply to fin #3 1
6.1.6 Allow fin #3 to dry 1
6.2 Apply second layer glue 6 0 0 3 0 0 0 0
6.2.1 Apply more glue to Fin #1 1
6.2.2 Set fin #1 1
6.2.3 Press fin #1 1
6.2.4 Apply more glue to Fin #2 1
6.2.5 Set fin #2 1
6.2.6 Press fin #2 1
6.2.7 Apply more glue to Fin #3 1
6.2.8 Set fin #3 1
6.2.9 Press fin #3 1
6.3 Adjust fins 6 0 0 0 0 0 0 0
6.3.1 Adjust fin #1 1
6.3.2 Attach fin #1 1
6.3.3 Adjust fin #2 1
6.3.4 Attach fin #2 1
6.3.5 Adjust fin #3 1
6.3.6 Attach fin #3 1
6.4 Set aside to dry 1 0 0 0 0 0 0 1
6.4.1 Stand rocket on drying table 1
6.4.2 Allow fins to dry 1
7.0 Launch Lug Attachment 1 3 0 1 0 0 0 1 6
7.1 Measure lug attachement 0 2 0 0 0 0 0 0
7.1.1 Measure 41mm 1
7.1.2 Mark attachment point 1
7.2 Glue lug attachment 1 0 0 1 0 0 0 0
7.2.1 Apply glue to launch lug 1
7.2.2 Attach launch lug to body tube 1
7.3 Dry lug attachment 0 1 0 0 0 0 0 1
7.3.1 Ensure launch lug alignment 1
7.3.2 Allow to dry 1
8.0 Glue Reinforcement 1 0 0 6 0 0 0 1 8
8.1 Reinforce fins 0 0 0 3 0 0 0 0
8.1.1 Reinforce fin fin #1 1
8.1.2 Reinforce fin fin #2 1
8.1.3 Reinforce fin fin #3 1
8.2 Reinforce launch lug 0 0 0 2 0 0 0 0
8.2.1 Reinforch side 1 1
8.2.2 Reinforce side 2 1
8.3 Glue drying 1 0 0 1 0 0 0 1
8.3.1 Stand rocket on drying table 1
8.3.2 Wipe away excess glue 1
8.3.3 Allow to dry 1
9.0 Shock Cord Mount Attachment 4 1 0 2 0 0 0 1 8
9.1 Measure body tube 0 1 0 0 0 0 0 0
9.1.1 Measure 25mm 1
9.2 Apply glue 1 0 0 1 0 0 0 0
9.2.1 Apply glue to shock cord 1
9.2.2 Insert cord into tube 1
9.3 Set mount 2 0 0 1 0 0 0 0
9.3.1 Set mount 25mm 1
9.3.2 Press mount into glue 1 1
9.4 Set glue 1 0 0 0 0 0 0 1
9.4.1 Hold mount attachment 1
9.4.2 Allow to dry 1
10.0 Parachute Assembly 15 0 8 0 0 0 0 0 23
10.1 Cut out parachute 0 0 1 0 0 0 0 0
10.1.1 Cut parachute along line 1
10.2 Tape removal 2 0 1 0 0 0 0 0
10.2.1 Remove tape 1
10.2.2 Fold shroud lines 1
10.2.3 Cut shroud lines 1
10.3 Tape attachment 12 0 6 0 0 0 0 0
10.3.1 Attach tape rings 6 0 0 0 0 0 0 0
10.3.1.1 Attach tape ring #1 1
10.3.1.2 Attach tape ring #2 1
10.3.1.3 Attach tape ring #3 1
10.3.1.4 Attach tape ring #4 1
10.3.1.5 Attach tape ring #5 1
10.3.1.6 Attach tape ring #6 1
10.3.2 Press tape tape rings into place 6 0 0 0 0 0 0 0
10.3.2.1 Press tape tape rings into place #1 1
10.3.2.2 Press tape tape rings into place #2 1
10.3.2.3 Press tape tape rings into place #3 1
10.3.2.4 Press tape tape rings into place #4 1
10.3.2.5 Press tape tape rings into place #5 1
10.3.2.6 Press tape tape rings into place #6 1
10.3.3 Punch tape ring holes 0 0 6 0 0 0 0 0
10.3.3.1 Punch tape ring holes #1 1
10.3.3.2 Punch tape ring holes #2 1
10.3.3.3 Punch tape ring holes #3 1
10.3.3.4 Punch tape ring holes #4 1
10.3.3.5 Punch tape ring holes #5 1
10.3.3.6 Punch tape ring holes #6 1
10.4 Shroud line assembly 1 0 0 0 0 0 0 0
10.4.1 Pass shroud line through hole 1
11.0 Parachute & Shock Cord Attachment to Nose Cone 4 0 0 0 0 0 0 0 4
11.1 Shroud line threading 1 0 0 0 0 0 0 0
11.1.1 Thread shroud lines 1
11.2 Parachute pass throough 1 0 0 0 0 0 0 0
11.2.1 Pass parachute through loop 1
11.3 Line tightening 1 0 0 0 0 0 0 0
11.3.1 Pull lines tight 1
11.4 Shock cord tie down 1 0 0 0 0 0 0 0
11.4.1 Tie down shock cord free end 1
12.0 Finishing Rocket 45 1 14 1 4 0 2 9 76
12.1 Verify dryness 0 0 0 1 0 0 0 0
12.1.1 Check to ensure glue joint are dry 1
12.2 Prime rocket 0 0 0 0 2 0 2 0
12.2.1 Apply primer coat #1 1
12.2.2 Sand rocket body #1 1
12.2.3 Apply primer coat #2 1
12.2.4 Sand rocket body #2 1
12.3 Paint rocket 1 0 0 0 1 0 0 1
12.3.1 Insert paint handle 1
12.3.2 Apply paint to rocket 1
12.3.3 Allow to dry 1
12.4 Apply Water Decals 39 0 13 0 1 0 0 8
12.4.1 Cut decals 0 0 13 0 0 0 0 0
12.4.1.1 Decal #1 1
12.4.1.2 Decal #2 1
12.4.1.3 Decal #3 1
12.4.1.4 Decal #4 1
12.4.1.5 Decal #5 1
12.4.1.6 Decal #6 1
12.4.1.7 Decal #7 1
12.4.1.8 Decal #8 1
12.4.1.9 Decal #9 1
12.4.1.10 Decal #10 1
12.4.1.11 Decal #11 1
12.4.1.12 Decal #12 1
12.4.1.13 Decal #13 1
12.4.2 Dip in water 13 0 0 0 0 0 0 0
12.4.2.1 Decal #1 1
12.4.2.2 Decal #2 1
12.4.2.3 Decal #3 1
12.4.2.4 Decal #4 1
12.4.2.5 Decal #5 1
12.4.2.6 Decal #6 1
12.4.2.7 Decal #7 1
12.4.2.8 Decal #8 1
12.4.2.9 Decal #9 1
12.4.2.10 Decal #10 1
12.4.2.11 Decal #11 1
12.4.2.12 Decal #12 1
12.4.2.13 Decal #13 1
12.4.3 Slip decals 13 0 0 0 0 0 0 0
12.4.3.1 Decal #1 1
12.4.3.2 Decal #2 1
12.4.3.3 Decal #3 1
12.4.3.4 Decal #4 1
12.4.3.5 Decal #5 1
12.4.3.6 Decal #6 1
12.4.3.7 Decal #7 1
12.4.3.8 Decal #8 1
12.4.3.9 Decal #9 1
12.4.3.10 Decal #10 1
12.4.3.11 Decal #11 1
12.4.3.12 Decal #12 1
12.4.3.13 Decal #13 1
12.4.4 Blot decals 13 0 0 0 0 0 0 0
12.4.4.1 Decal #1 1
12.4.4.2 Decal #2 1
12.4.4.3 Decal #3 1
12.4.4.4 Decal #4 1
12.4.4.5 Decal #5 1
12.4.4.6 Decal #6 1
12.4.4.7 Decal #7 1
12.4.4.8 Decal #8 1
12.4.4.9 Decal #9 1
12.4.4.10 Decal #10 1
12.4.4.11 Decal #11 1
12.4.4.12 Decal #12 1
12.4.4.13 Decal #13 1
12.4.5 Dry decals 0 0 0 0 0 0 0 8
12.5.1 Allow to dry overnight 8
12.4.6 Apply clear spray to decals 0 0 0 0 1 0 0 0
12.4.1 Apply spray to rocket 1
12.5 Apply large decals 3 1 1 0 0 0 0 0
12.5.1 Peel backing 1
12.5.2 Cut away backing 1
12.5.3 Align decal 1
12.5.4 Peel off backing 1
12.5.5 Smooth decal 1
RESOURCE TOTALS
228
TOTAL DURATION ESTIMATE
RESOURCE RATES
RESOURCE COSTS
$1,008.00
$945.00
$392.00
$176.00
$46.00
$15.00
$143.00
$0.00
$2,725.00
TOTAL RESOURCE COST
M&E List
WBS #
WBS Task
Ball Point Pen
Scissors
Tube Marking Guide
Knife
Ruler
Sandpaper
Masking Tape
Enamel Spray Paint
Sanding Primer
Pencil
Shroud Lines
Engine Hook
2.0 Shock Cord Mount Assembly
3.0 Fin Preparation
4.0 Engine Mount Installation
5.0 Tube Marking Detail
6.0 Fin Attachment
7.0 Launch Lug Attachment
8.0 Glue Reinforcement
9.0 Shock Cord Mount Attachment
10.0 Parachute Assembly
11.0 Parachute & Shock Cord Attachment to Nose Cone
12.0 Finishing Rocket
M&E Forecast
WBS # TASKS
Day 1
Day 2
Day 3
Day 4
Day 5
Day 6
Day 7
Day 8
Day 9
Day 10
Day 11
Day 12
Day 13
Day 14
Day 15
Day 16
Day 17
Day 18
Day 19
1.1 Locate engine mount parts
1.1.1 Locate light blue engine mount tube
1.1.2 Locate engine hook
1.1.3 Locate green adapter ring 1.2 Laying mount to ruler Ruler
1.2.2 Align with zero mark 1.3 Marking mount Pencil
1.3.2 Mark tube Tube Marking Guide
1.3.2.2 Mark 64 mm 1.4 Cutting mount Knife
1.5 Inserting hook
1.5.1 Insert hook
1.5.2 Extend hook
1.6 Testing adapter ring
1.6.1 Slide ring into front of engine tube
1.6.2 Slide ring over engine hook to 25mm mark
1.7 Glue & Dry 1.7.1 Apply glue Glue
1.7.1.2 Apply glue to other side
1.7.2 Dry glue
1.7.2.1 Set assembly aside
1.7.2.2 Allow to dry
2.0 Shock Cord Mount Assembly
2.1 Locate cord mount parts
2.1.1 Locate cord mount on pattern sheet 2.2 Cut cord mount Scissors
2.3 Crease assembly
2.3.1 Fold on dotted lines
2.3.2 Crease on dotted lines 2.4 Glue mount assembly Glue
2.4.2 Lay end of shock cord in glue
2.5 Fold mount assembly
2.5.1 Fold section 1 2.5.2 Apply glue section 3 Glue
2.6 Clamp mount assembly
2.6.1 Clamp assembly
2.6.2 Allow to dry
3.0 Fin Preparation
3.1 Select fin pattern
3.1.1 Select fin pattern 3.1.2 Cut fin pattern from sheet Scissors
3.2 Trace fin patterns Pencil
3.2.2 Match fin #1
3.2.3 Trace fin #2
3.2.4 Match fin #2
3.2.5 Trace fin #2
3.2.6 Match fin #2 3.3 Cut fin patterns Scissors
3.3.2 Chect fin #1
3.3.3 Cut fin #2
3.3.4 Chect fin #2
3.3.5 Cut fin #3
3.3.6 Chect fin #3
3.4 Save scrap
3.4.1 Set aside piece scrap basa wood 3.5 Course sand fins Sandpaper
3.5.2 Stack fins
3.5.3 Sand fins 3.6 Fine sand fins Sandpaper Sandpaper
3.6.1.1 Round leading edge fin #1
3.6.1.2 Round trailing edge fin #1
3.6.1.3 Streamline training edge fin #1
3.6.2 Fine sand fin #2
3.6.2.1 Round leading edge fin #2
3.6.2.2 Round trailing edge fin #2
3.6.2.3 Streamline training edge fin #2
3.6.3 Fine sand fin #3
3.6.3.1 Round leading edge fin #3
3.6.3.2 Round trailing edge fin #3
3.6.3.3 Streamline training edge fin #3
4.0 Engine Mount Installation
4.1 Locate body tube
4.1.1 Locate body tube 4.2 Measure body tube Ruler
4.3 Spread glue Glue
4.4 Insert engine mount
4.4.1 Insert engine mount assembly into body tube
5.0 Tube Marking Detail
5.1 Locate tube marking guide
5.1.1 Locate tube marking guide on pattern sheet 5.1.2 Cut guide alone outline Scissors
5.2 Wrap guide Masking Tape
5.2.2 Tape guide to body tube 5.3 Mark tube Pencil
5.3.1.1 Mark tube for fin #1
5.3.1.2 Mark tube for fin #2
5.3.1.3 Mark tube for fin #3 5.3.2 Write LL on body tube Ball Point Pen
5.4 Draw fin markings Pencil
5.4.1 Fin #1 Ruler
5.4.1.2 Extend line 76mm
5.4.2 Fin #2
5.4.2.1 Draw straight line
5.4.2.2 Extend line 76mm
5.4.3 Fin #3
5.4.3.1 Draw straight line
5.4.3.2 Extend line 76mm 5.4.4 Draw launch lug line Pencil
5.4.4.1 Draw line 102 mm Ruler
6.1 Apply glue to root edges of fins Glue
6.1.2 Allow fin #1 to dry
6.1.3 Apply to fin #2
6.1.4 Allow fin #2 to dry
6.1.5 Apply to fin #3
6.1.6 Allow fin #3 to dry 6.2 Apply second layer glue Glue
6.2.2 Set fin #1
6.2.3 Press fin #1
6.2.4 Apply more glue to Fin #2
6.2.5 Set fin #2
6.2.6 Press fin #2
6.2.7 Apply more glue to Fin #3
6.2.8 Set fin #3
6.2.9 Press fin #3
6.3 Adjust fins
6.3.1 Adjust fin #1
6.3.2 Attach fin #1
6.3.3 Adjust fin #2
6.3.4 Attach fin #2
6.3.5 Adjust fin #3
6.3.6 Attach fin #3
6.4 Set aside to dry
6.4.1 Stand rocket on drying table
6.4.2 Allow fins to dry
7.0 Launch Lug Attachment 7.1 Measure lug attachement Ruler
7.1.2 Mark attachment point Pencil
7.2 Glue lug attachment Glue
7.2.2 Attach launch lug to body tube
7.3 Dry lug attachment
7.3.1 Ensure launch lug alignment
7.3.2 Allow to dry 8.0 Glue Reinforcement Glue
8.1.1 Reinforce fin fin #1
8.1.2 Reinforce fin fin #2
8.1.3 Reinforce fin fin #3
8.2 Reinforce launch lug
8.2.1 Reinforch side 1
8.2.2 Reinforce side 2
8.3 Glue drying
8.3.1 Stand rocket on drying table
8.3.2 Wipe away excess glue
8.3.3 Allow to dry
9.0 Shock Cord Mount Attachment 9.1 Measure body tube Ruler
9.2 Apply glue Glue
9.2.2 Insert cord into tube
9.3 Set mount
9.3.1 Set mount 25mm
9.3.2 Press mount into glue 9.4 Set glue Glue
9.4.2 Allow to dry
10.0 Parachute Assembly 10.1 Cut out parachute
Sissors
10.2 Tape removal
10.2.1 Remove tape
10.2.2 Fold shroud lines 10.2.3 Cut shroud lines Knife
10.3 Tape attachment Masking Tape
10.3.1.1 Attach tape ring #1
10.3.1.2 Attach tape ring #2
10.3.1.3 Attach tape ring #3
10.3.1.4 Attach tape ring #4
10.3.1.5 Attach tape ring #5
10.3.1.6 Attach tape ring #6
10.3.2 Press tape tape rings into place
10.3.2.1 Press tape tape rings into place #1
10.3.2.2 Press tape tape rings into place #2
10.3.2.3 Press tape tape rings into place #3
10.3.2.4 Press tape tape rings into place #4
10.3.2.5 Press tape tape rings into place #5
10.3.2.6 Press tape tape rings into place #6
10.3.3 Punch tape ring holes
10.3.3.1 Punch tape ring holes #1
10.3.3.2 Punch tape ring holes #2
10.3.3.3 Punch tape ring holes #3
10.3.3.4 Punch tape ring holes #4
10.3.3.5 Punch tape ring holes #5
10.3.3.6 Punch tape ring holes #6 10.4 Shroud line assembly Shroud Lines
10.4.2 Tie lines together
11.0 Parachute & Shock Cord Attachment to Nose Cone
11.1 Shroud line threading
11.1.1 Thread shroud lines
11.2 Parachute pass throough
11.2.1 Pass parachute through loop
11.3 Line tightening
11.3.1 Pull lines tight
11.4 Shock cord tie down
11.4.1 Tie down shock cord free end
12.0 Finishing Rocket
12.1 Verify dryness
12.1.1 Check to ensure glue joint are dry 12.2 Prime rocket Sanding Primer
12.2.2 Sand rocket body #1
12.2.3 Apply primer coat #2
12.2.4 Sand rocket body #2 12.3 Paint rocket Enamel Spray Paint
12.3.2 Apply paint to rocket
12.3.3 Allow to dry
12.4 Apply Water Decals 12.4.1 Cut decals Sissors
12.4.1.2 Decal #2
12.4.1.3 Decal #3
12.4.1.4 Decal #4
12.4.1.5 Decal #5
12.4.1.6 Decal #6
12.4.1.7 Decal #7
12.4.1.8 Decal #8
12.4.1.9 Decal #9
12.4.1.10 Decal #10
12.4.1.11 Decal #11
12.4.1.12 Decal #12
12.4.1.13 Decal #13
12.4.2 Dip in water
12.4.2.1 Decal #1
12.4.2.2 Decal #2
12.4.2.3 Decal #3
12.4.2.4 Decal #4
12.4.2.5 Decal #5
12.4.2.6 Decal #6
12.4.2.7 Decal #7
12.4.2.8 Decal #8
12.4.2.9 Decal #9
12.4.2.10 Decal #10
12.4.2.11 Decal #11
12.4.2.12 Decal #12
12.4.2.13 Decal #13
12.4.3 Slip decals
12.4.3.1 Decal #1
12.4.3.2 Decal #2
12.4.3.3 Decal #3
12.4.3.4 Decal #4
12.4.3.5 Decal #5
12.4.3.6 Decal #6
12.4.3.7 Decal #7
12.4.3.8 Decal #8
12.4.3.9 Decal #9
12.4.3.10 Decal #10
12.4.3.11 Decal #11
12.4.3.12 Decal #12
12.4.3.13 Decal #13
12.4.4 Blot decals
12.4.4.1 Decal #1
12.4.4.2 Decal #2
12.4.4.3 Decal #3
12.4.4.4 Decal #4
12.4.4.5 Decal #5
12.4.4.6 Decal #6
12.4.4.7 Decal #7
12.4.4.8 Decal #8
12.4.4.9 Decal #9
12.4.4.10 Decal #10
12.4.4.11 Decal #11
12.4.4.12 Decal #12
12.4.4.13 Decal #13
12.4.5 Dry decals
12.5.1 Allow to dry overnight 12.4.6 Apply clear spray to decals Enamel Spray Paint
12.5 Apply large decals
12.5.1 Peel backing 12.5.2 Cut away backing Sissors
12.5.3 Align decal Knife
12.5.5 Smooth decal
2
week
1
week 2
week
3
week
4
week
5
week
6
week
7
week
8
week
9
week
1
0
week
11
week
12
week
13
week
14
1 2 3 4 5 6 7 8 9
10
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
WBS #
TASKS
1.0
ENGINE MOUNT ASSEMBLY
2.0
FIN PREPARATION
3.0
MARK FIN AND LAUNCH LUG LINES
4.0
INSERTING ENGINE MOUNT
5.0
ATTACH FINS
6.0
ATTACH SHOCK CORD
7.0
ASSEMBLE NOSE CONE
8.0
ATTACH PARACHUTE/SHOCK CORD
9.0
ATTACH LAUNCH LUG
10.0
PAINT SCHEME
11.0
APPLICATION OF DECALS
12.0
APPLYING CLEAR COAT
13.0
DISPLAY NOZZLE ASSEMBLY
14.0
ROCKET PREFLIGHT
15.0
PREPARE FOR TEST LAUNCH
Network-New
0
107
1:
Assemble Engine Mount35h
142
86
228
40h
268
11h
2
79
0 0 107
4:
Insert Engine Mount5:
Attach Fins6:
Attach Shock Cord7:
Attach Launch Lug 107 0 142 142 0 228 228 0 268 268 0 279
325
336
0
49h
12:
Applying Clear Coat
2:
Fin Preparation
0 0 49 279
21h
300
142
34h
176
9:
Attach Launch Lug 0
28h
11:
Application of Decals14h
242
57h
393
3:
Mark Fin And Launch Lug Lines194
8:
Attach Chute Shock Cord13:
Applying Clear Coat 79 79 107
254
300
25h
10:
Painting the Rocket 300 0 325 393
48h
441
14:
Rocket Pre-Flight 393 0 441
441
12h
453
15:
Prepare for Test Launch 441 0 453
Legend
Early Start
Duration
Early Finish
Task Name
Late
StartSlack
Late Finish
Duration Est
WBS # TASKS
Fitter
Drafter
Cutter
Gluer
Sand
Painter
Engineer
Dummy
1.0
Engine Mount Assembly
1.1
Measure, Mark and Cut & Slit Engine Tube
1.1.1
Measure engine tube
1.
1.2
Mark engine Tube
1.2
Cut and Slit engine tube
1.
2.1
Cut @ 1/8″
1.
2.2
Slit @ 1 1/2″
1.3
Apply glue, Position, Insert Hook
1.
3.1
Apply glue around tube at 3/4″” mark”
1.
3.2
Position Hook
1.
3.3
Insert Engine Hook into slit
1.4
Slide Mylar Retainer Ring
1.
4.1
Slide Mylar ring onto Engine Mount tube at 3/4″ mark
1.
4.2
Let Dry
1.5
Apply glue, insert engine block, let dry
1.
5.1
Apply glue inside front of Engine Mount tube
1.
5.2
Insert Yellow Engine Block flush with end
1.
5.3
1.6
Remove Centering Rings
1.
6.1
Remove Centering rings from card with modeling knife
1.7
Apply glue, mark and slide notched, Ring into place, Let glue, apply glue, slide un-notched centering ring, flush with end tube,
Let dry
1.
7.1
Apply glue around tube @ 1/8″” mark”
1.7.2
Mark notched Ring into place
1.7.3
Slide notched Centering Ring
1.7.4
Let Glue Set
1.7.5
Apply glue around end of tube
1.7.6
Slide un-notched Centering Ring in place
1.7.7
Flush with end tube
1.7.8
1.8
Application of Glue Fillets, let dry
1.
8.1
Apply Glue Fillets to both sides of Centering Rings
1.
8.2
2.0 FIN PREPARATION 5 0 12 0 11 0 0 0 28
2.1
Sand/Cut fins
2.1.1
Sand Laser
2.1.2
Cut Balsa Sheet w/Fine Sandpaper
2.2
Cutting Out Fins
2.2.1
Cut out fins free with modeling knife
2.3
Stack and Sand Fins
2.3.1
Stack Fins
2.3.2
Sand Edges of fins
3.0 MARK FIN AND LAUNCH LUG LINES 27 0 12 0 0 0 10 0 49
3.1
Cut out tube marking guide
3.1.1
3.1.2
Tape tube marking guide around body tube
3.1.3
Mark body tube at arrows
3.1.4
Mark Launch Lug Line as LL on Body tube
3.2
Remove guide, connect fins and launch lug lines
3.2.1
Remove the guide
3.2.2
Connect Fins
3.2.3
Launch lug lines using door frame
3.3
Extend Launch Lug Line
3.3.1
Extend launch lug line 3 3/4″” from end of tube”
4.0 INSERTING ENGINE MOUNT 19 0 0 14 0 0 0 2 35
4.1
Mark inside of tube @ 5/8″
4.1.1
Mark inside tube at 5/8″
4.2
Glue Tube
4.2.1
Use finger to smear glue 1 3/4″” inside rear of body tube
4.3
Align Engine Hook, insert engine mount, let dry
4.3.1
Align engine hook with Launch Lug line
4.3.2
Insert engine mount until centering ring is even with 5/8″ mark”
4.3.3
4.4
Gluing, Let dry
4.4.1
Use a scrap piece of balsa to apply glue fill to Centering Ring/Body Tube joint.
4.4.2
5.0 ATTACH FINS 32 0 0 42 0 0 6 6 86
5.1
Attach Fin 1, Apply glue #1, Wait, Apply glue # 2, Attach fin to body tube
5.1.1
Apply glue to edge of fin
5.1.2
Wait for 1 minute for model
5.1.3
Apply second layer of glue to edge of fin
5.1.4
Attach Fin to body tube along one of fin lines flush w/end
5.2
Attach Fin 2
5.2.1
5.2.2
5.2.3
5.2.4
5.3
Attach Fin 3
5.3.1
5.3.2
5.3.3
5.3.4
5.4
Attach Fin 4
5.4.1
5.4.2
5.4.3
5.4.4
5.5
Check Fin Alignment, allow glue to set
5.5.1
Check Fin #1 as per diagram
5.5.2
Check Fin #2 as per diagram
5.5.3
Check Fin #3 as per diagram
5.5.4
Check Fin #4 as per diagram
5.5.5
Allow glue to set
5.6
Stand rocket, let glue dry
5.6.1
Stand rocket on flat table
5.
6.2
Let Glue dry completely
6.0 ATTACH SHOCK CORD 4 9 4 21 0 0 0 2 40
6.1
Cut out shock cord mount
6.1.1
Cut out shock cord from front page
6.2
Glue Application, fold forward
6.2.1
Apply glue to shock cord mount
6.2.2
Fold
6.3
Glue Application 2, fold forward
6.3.1
6.3.2
6.4
Squeeze and Hold
6.4.1
Squeeze shock cord/shock cord mount tightly
6.4.2
Hold for 1 minute
6.5
Glue mount, hold, let glue dry
6.5.1
Glue mount 1″” inside body tube”
6.5.2
Hold until glue sets
6.5.3
Let
Dry Completely
7.0 ASSEMBLE NOSE CONE 5 0 0 5 0 0 0 1 11
7.1
Apply tube type cement, press insert, let dry
7.1.1
Apply tube type cement to inside nose cone
7.1.2
Press Insert into place
7.1.3
8.0 ATTACH PARACHUTE/SHOCK CORD 6 0 0 0 0 0 8 0 14
8.1
Pass Lines
8.1.1
Pass shroud line on parachute through eyelet
8.2
Pass chute
8.2.1
Pass chute through loop
8.3
Tie Shock Cord
8.3.1
Tie shock cord to nose cone using a double knot
9.0 ATTACH LAUNCH LUG 0 0 0 20 0 0 0 1 21
9.1
Glue launch lines
9.1.1
Glue LL centered onto LL Line where shown
9.2
Apply Glue Fillets & Fin/body tube joints, smoothing each, let dry
9.2.1
Apply glue fillets along launch lug
9.2.2
Apply glue fillets along fin/body tube joints
9.2.3
Smooth each fillet with finger
9.2.4
Let glue dry completely
10.0 PAINT SCHEME 0 0 0 0 10 13 0 2 25
10.1
Spray, let dry, sand
10.1.1
Spray rocket with white primer
10.1.2
10.1.3
10.2
Apply final Spray, let dry, sand
10.2.1
Spray completed rocket with white second coat of primer
10.2.2
10.2.3
11.0 APPLICATION OF DECALS 0 12 0 0 0 0 22 0 34
11.1
Remove decal #1, place on rocket, and rub decal
11.1.1
Remove First decal from back sheet
11.1.2
Place on Rocket where indicated
11.1.3
Rub decal to remove bubbles
11.2
Remove decal #2, place on rocket, and rub decal
11.2.1
Remove second decal from backing sheet
11.2.2
11.2.3
11.3
Remove decal #3, place on rocket, and rub decal
11.3.1
Remove third decal from backing sheet
11.3.2
11.3.3
11.4
Remove decal #4, place on rocket, and rub decal
11.4.1
Remove fourth decal from backing sheet
11.4.2
11.4.3
12.0 APPLYING CLEAR COAT 0 0 0 0 0 6 0 5 11
12.1
Apply clear coat, and let dry
12.1.1
Apply clear coat to entire rocket
12.1.2
13.0 DISPLAY NOZZLE ASSEMBLY 16 0 0 20 0 16 0 5 57
13.1
Spray Nozzle Base white with silver paint, let dry
13.1.1
Paint Nozzle #1 w/Silver Paint Pen
13.1.2
Paint Nozzle #2 w/Silver Paint Pen
13.1.3
Paint Nozzle #3 w/Silver Paint Pen
13.1.4
Paint Nozzle #4 w/Silver Paint Pen
13.1.5
13.2
Apply tube type cement, place nozzle tab, let dry
13.2.1
Apply glue to tab on nozzle #1
13.2.2
Place Nozzle #1 into hole on base
13.2.3
Let to dry
13.2.4
Apply glue to tab on nozzle #2
13.2.5
Place Nozzle #2 into hole on base
13.2.6
13.2.7
Apply glue to tab on nozzle #3
13.2.8
Place Nozzle #3 into hole on base
13.2.9
13.2.10
Apply glue to tab on nozzle #4
13.2.11
Place Nozzle #4 into hole on base
13.2.12
let to dry
14.0 ROCKET PREFLIGHT 34 9 0 0 0 0 5 0 48
14.1
Remove cone, locate wadding, and insert squares
14.1.1
Remove Nose Cone from Rocket
14.1.2
Locate recovery wadding
14.1.3
Insert 4-5 loosely crumpled squares of recovery wadding
14.2
Pull parachute
14.2.1
Pull parachute into a spike
14.3
14.3.1
Fold parachute
14.4
Roll
14.4.1
Roll parachute
14.5
Wrap lines, Insert parachute, insert shock cord, and insert nose cone
14.5.1
Wrap lines around rolled parachute
14.5.2
Insert parachute into body tube of rocket
14.5.3
Insert shock cord into body tube of rocket
14.5.4
Insert nose cone into body tube of rocket
15.0 PREPARE FOR TEST LAUNCH 9 0 0 0 0 0 3 0 12
15.1
Remove Engine, Insert tip, Insert engine
15.1.1
Remove engine
15.1.2
Insert tip to touch propellant
15.1.3
3 Insert engine into rocket
Resource Totals
205
147
73
578
DURATION
WBS # TASKS Fitter Drafter Cutter Gluer
Sander
Hrs
Days
1.0 ENGINE MOUNT ASSEMBLY 48 0 10 25 0 0 19 5 107 13
2.0 FIN PREPARATION 5 0 12 0 11 0 0 0 28 4
3.0 MARK FIN AND LAUNCH LUG LINES 27 0 12 0 0 0 10 0 49 6
4.0 INSERTING ENGINE MOUNT 19 0 0 14 0 0 0 2 35 4
5.0 ATTACH FINS 32 0 0 42 0 0 6 6 86 11
6.0 ATTACH SHOCK CORD 4 9 4 21 0 0 0 2 40 5
7.0 ASSEMBLE NOSE CONE 5 0 0 5 0 0 0 1 11 1
8.0 ATTACH PARACHUTE/SHOCK CORD 6 0 0 0 0 0 8 0 14 2
9.0 ATTACH LAUNCH LUG 0 0 0 20 0 0 0 1 21 3
10.0 PAINT SCHEME 0 0 0 0 10 13 0 2 25 3
11.0 APPLICATION OF DECALS 0 12 0 0 0 0 22 0 34 4
12.0 APPLYING CLEAR COAT 0 0 0 0 0 6 0 5 11 1
13.0 DISPLAY NOZZLE ASSEMBLY 16 0 0 20 0 16 0 5 57 7
14.0 ROCKET PREFLIGHT 34 9 0 0 0 0 5 0 48 6
15.0 PREPARE FOR TEST LAUNCH 9 0 0 0 0 0 3 0 12 2
RESOURCE TOTALS
72
Human Resource Management Plan