Project Management (crashing/shortening/etc.) Please have Project 2010/2013 and above.

Please see attached.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

 

 (crashing/shortening/etc.)

Project Management Exercise.

The instructions for Part 2 are as follows:

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

1. Access your MS Project file submitted (See attached .mpp file).  Now, shorten this project so that the concert can take place as planned (September 4th).

2. Identify the tasks you will shorten to achieve this goal and adjust the durations of these activities so that the “finish time” indicates the concert can take place as scheduled. This is your “After” or “Crashed” entry screen.

3.

This will be your “After” Network Diagram

Tips:

1. Find the tasks on the critical path(s).

2. Crash the least expensive task(s)  on the critical path(s).

MUSIC FEST TABLE.

Activity

Description

Predecessors

Normal Time
in Days

Normal Time
Cost

Task can be
shortened to

Total Cost of
Shortened Time

1

Finalize sites & facility contracts

 

28

$10,000

 

 

2

Select concert promoter

1

14

$7,500

 

 

3

Hire Production Manager

2

21

$5,000

 

 

4

Design Promotional Website

2

25

$15,000

 

 

5

Finalize TV right

2

60

$8,000

50

$12,000

6

Hire Director

2

28

$7,500

 

 

7

Plan for TV camera placement

6

13

$7,250

 

 

8

Target Headline entertainers

2

45

$12,500

41

$18,000

9

Target Support entertainers

8

43

$11,000

 

 

10

Travel accommodations for talent

9

4

$6,000

3

$8,000

11

Set venue capacity

3

3

$2,000

 

 

12

Sign Ticket Master Contract

2,4,11

17

$6,000

 

 

13

On-site ticketing

12

6

$1,500

5

$4,000

14

Lease sound and staging equipment

3

8

$5,500

 

 

15

Passes & stage credentials

7,16,18

4

$2,500

2

$3,000

16

Travel accommodations for staff

21,23

4

$4,000

 

 

17

Hire Sponsor Coordinator

2

21

$5,900

 

 

18

Finalize sponsors

17

35

$9,000

32

$12,000

19

Define & place signage for sponsors

5,17,24

8

$3,000

 

 

20

Sign Concession Contracts

2,11

32

$8,000

 

 

21

Hire Operations Manager

2

48

$5,500

43

$10,000

22

Develop site plan

21

31

$9,000

28

$9,000

23

Hire Security Director

2

20

$4,200

 

 

24

Hire Support Staff

21,23

17

$3,600

 

 

25

Develop police/fire security plan

23

55

$10,000

50

$15,000

26

Develop Traffic Plan

10,13,20,23

20

$9,500

18

$10,350

27

Determine Reqmts for Power, Facilities

22

30

$6,200

26

$7,200

28

Secure Merchandise sales

2

25

$6,100

 

 

29

Secure Online merchandise sales

28

20

$4,700

 

 

30

Install Power/plumbing/AC/Toilet Svcs

27

6

$9,500

 

 

31

Construct Stage

3,14,22,27,30

2

$7,000

 

 

32

Test Sound/Lighting

15,30,31

2

$3,000

1

$4,500

33

Ready for Concert

19,25,26,29,32

1

 

 

 