Project Execution With Monitoring & Control
DUE DATE: 30 Jan 2018; DUE TIME: 15 & 20:00Hrs; TOTAL Budget: $20.00
Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
DUE DATE: 30 Jan 2018 DUE TIME: 12:00Hrs GMT
In this Assignment, you are provided your sponsor-approved financials for your project’s labor. You will need to go back to the project plan, or Gauchito Project Workbook.xls (in Course Resources), to pull out your incremental material and equipment costs from the M&E Forecast tab. Your job will be to lay out only your Planned Value (PV) section of your Gauchito EVM Tool and/or Project (in Course Resources). You will need to bring over your approved Gantt schedule for the Project Workbook to accomplish this. Based on the information from the Gauchito project plan, your company finance department provided you with the following:
(Please find attached a better formatted question saved as GM593_U2Assignmt)
ID Job Description Immediate Predecessors Planned Duration (Weeks) Staff (Number) Rate/Person/Week Task Cost (BAC) A 1.0 ASSEMBLE ENGINE MOUNT Start 2 4 $1,440 $11,520 B 2.0 FIN PREPARATION Start 1 3 $1,440 $4,320 C 3.0 MARK FIN AND LAUNCH LUG LINES Start 1 3 $1,440 $4,320 D 4.0 INSERTING ENGINE MOUNT A 2 3 $1,440 $8,640 E 5.0 ATTACH FINS D 1 3 $1,440 $4,320 F 6.0 ATTACH SHOCK CORD Start 2 3 $1,440 $8,640 G 7.0 ASSEMBLE NOSE CONE Start 1 2 $1,440 $2,880 H 8.0 ATTACH PARACHUTE/SHOCK CORD G 1 1 $1,440 $1,440 I 9.0 ATTACH LAUNCH LUG E 1 1 $1,440 $1,440 J 10.0 PAINTING THE ROCKET I 1 4 $1,440 $5,760 K 11.0 APPLICATION OF DECALS J 1 1 $1,440 $1,440 L 12.0 APPLYING CLEAR COAT K 1 1 $1,440 $1,440 M 13.0 DISPLAY NOZZLE ASSEMBLY K 1 3 $1,440 $4,320 N 14.0 ROCKET PREFLIGHT L 1 2 $1,440 $2,880 O 15.0 PREPARE FOR TEST LAUNCH N 1 1 $1,440 $1,440
ASSIGNMENT RUBRIC
Calculating Project Budget Estimate Updates Points Possible Points Earned Content
The necessary data for labor, equipment, material, duration, start, finish, and predecessors are correctly annotated as provided by the instructions into the Gauchito EVM tool. 10 points
A Gantt bar graph for the project BCWS (PV) was constructed in the EVM tool template according to the provided table. 5 points
All tasks (deliverables) are executed according to the Gauchito project plan appendix WG: Gantt and/or Gauchito Project Workbook tabs for labor costs, material costs, equipment costs, and schedule. 10
Task level activities are correctly scheduled with predecessors and successor according to precedence relationships from the project plan or project workbook. 5
A critical path is displayed according to CPM. 5points
The depicted Cumulative Cost Curve/Baseline graph correctly reflects the Planned Value. 5points
The graph correctly depicts the project BAC and EAC for the start of the project. 5points
Analysis Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Submission shows original thought. 10 points
Analysis includes proper classifications, explanations, comparisons, and inferences.
10 points
Critical thinking includes appropriate judgments, conclusions, and assessment based on evaluation and synthesis of information. 10points
Total 75
Sheet1
|
|
|
|
|
|
|
|
|
|
| |
CATEGORY |
WEEK 1 |
WEEK 2 |
WEEK 3 |
WEEK 4 |
WEEK 5 |
| Labor |
|
|
|
| $500.00 |
$500.00 $500.00 $500.00
Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
|
| $300.00 |
| Material |
$300.00
|
| $200.00 |
$100.00 |
| Equipment |
$200.00 $200.00
| TOTAL |
| $1,000.00 |
$500.00
$700.00 |
$800.00 |
$300.00
| $3,300.00 |
The grand
| total of this line |
| B |
B+C |
B+C+D |
B+C+D+E |
B+C+D+E+F |
should match the cumulative |
| CUMULATIVE |
$1,000.00
$1,500.00 |
$2,200.00 |
$3,000.00 |
$3,300.00 total of this line
| Graph the cumulative total |
Sheet1
Sheet2
EAC $3,300.00
Sheet3
PABLO DE LEON & ASSOCIATES GAUCHITO RESUPPLY VEHICLE
Pablo de Leon and Associates (Pablo de Leon y Asociados) is an Argentine-based team formed to design, build and operate a suborbital space transportation system.
Our team was created to compete for the Ansari X Prize and was accepted by the X Prize Foundation on February 10, 1997. Our team is formed by Argentine specialists in several fields, including propulsion, mechanical design, aerodynamics, thermal systems, cryogenics, computer science, etc.
Pablo de Leon, Team Leader, is an Argentine aerospace engineer with wide experience in space systems design, project management and development of space vehicles and components.
More than 42 scientists, engineers, technicians and volunteers have worked on this program for years in order to one day achieve the first suborbital manned flight in Latin America. Our team, conscientious of the past, believes it is necessary to learn from those who preceded us, and reach a level of technological development comparable with the times.
If Argentina wants to be once more an industrialized nation, we need to invest heavily in science and technology.
That is why we are working in this project, because we believe it is valuable and it will help to inspire a new generation of young Argentines and Latin Americans.
The VESA “Gauchito” is a conventional style rocket launch vehicle, using 4 hybrid rocket engines in cluster configuration. The length of the “Gauchito” is 12 meters without the escape tower, with a diameter of 2.20 meters in the main body, and 6.60 meters including the aerodynamic fins. The weight of the rocket is 8,000 kilograms while the empty weight is 2,400 kilograms.
The capsule can accommodate 1 crewmember with a maximum weight of 300 kilograms of cargo. The capsule maintains a controlled atmosphere of oxygen and nitrogen and the crew will use full pressure suits with 100%.oxygen
The propulsion system of the “Gauchito” was designed by Prof. Jorge Lassig. Its combines safety, economy, and reusability. The propellant grain, shaped as a cylinder and using several channels with geometrical shapes is placed in the combustion chamber. The “Gauchito” uses 4 hybrid rocket engines which burns Polyester Resin as propellant, and liquid oxygen (LOX) as oxidizer for 60 seconds. The throttle can be regulated and the engines are re-startable. The propulsion system has redundant safety devices and can be stopped in case of malfunction. The total thrust is 250,000 newtons (52,910 lb).
Each engine uses 380 kilograms of polyester resin and 1,080 kilograms of LOX. This requires a volume of 4 m3 for the 4 rocket engines. The LOX is feed by high pressure nitrogen coming from an additional tank located at the top of the rocket body. The total length of the rocket body is almost 8 meters, with a 2 meters diameter. The pressurized nitrogen tank is ½ meter diameter and the spherical LOX tank is 2 meters diameter. The longitude of each motor tube is 3,3 meters with a diameter of .60 meter.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
>Deliverables
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 0 |
|
|
|
|
|
|
|
| |
ASSEMBLE ENGINE MOUNT
|
|
|
|
|
| 2.0 FIN PREPARATION |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 3 |
.0 MARK FIN AND LAUNCH LUG LINES
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 4 |
.0 INSERTING ENGINE MOUNT
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 5 |
.0 ATTACH FINS
|
|
|
|
|
|
|
|
|
|
|
| 6 |
.0 ATTACH SHOCK CORD
|
|
|
|
|
|
|
|
| 7 |
.0 ASSEMBLE NOSE CONE
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 8 |
.0 ATTACH PARACHUTE/SHOCK CORD
|
|
|
|
|
|
|
| 9 |
.0 ATTACH LAUNCH LUG
|
|
|
|
|
|
|
| 10 |
.0 PAINTING THE ROCKET
|
|
|
|
| 11 |
.0 APPLICATION OF DECALS
|
|
|
|
|
|
|
|
|
| 12 |
.0 APPLYING CLEAR COAT
|
|
|
|
|
| 13 |
.0 DISPLAY NOZZLE ASSEMBLY
|
|
|
|
| 14 |
.0 ROCKET PREFLIGHT
|
|
|
| 15 |
.0 PREPARE FOR TEST LAUNCH
TITLE
| GAUCHITO ROCKET PROJECT |
| PROJECT WORKBOOK |
| Doubleclick to open |
Hi-Level WBS
|
| 1.0 ASSEMBLE ENGINE MOUNT |
|
| 1.1 Measure, Mark and Cut Engine Tube |
|
|
| 1.2 Cut Engine Tube |
| 1.3
| Glue |
, Tube, Assemble Hook
| 1.3.1 Apply thin line of glue completely around engine at 3/4″ mark |
|
|
| 1.3.2 Position Hook per diagram |
| 1.3.3 Insert Engine Hook into 1/8″ Slit on Engine Mount Tube |
|
|
| 1.4 Assemble Mylar Ring to Tube |
|
|
| 1.5 Assemble Yellow Engine Block to Engine Mount Tube |
|
|
| 1.6 Assemble Centering Rings |
|
|
| 1.7 Application of Glue Fillets |
2.0 FIN PREPARATION
|
|
| 2.1 Sand/Cut fins |
|
|
| 2.2 Cutting Out Fins |
|
|
| 2.3 Stack and Sand Fins |
| 3.0 MARK FIN AND LAUNCH LUG LINES |
| 3.1 Cut Tape |
| 3.2 Remove guide, connect fins and lug lines, extend LL line |
|
|
| 3.3 Extend Launch Lug Line |
| 4.0 INSERTING ENGINE MOUNT |
| 4.1 Mark inside of tube @ 5/8″ where LL is |
|
|
| 4.2 Glue Tube |
|
|
| 4.3 Assemble Engine Hook |
|
|
| 4.4 Gluing Center Body Ring |
| 5.0 ATTACH FINS |
|
|
| 5.1 Attach Fin #1 |
|
|
| 5.2 Attach Fin #2 |
|
|
| 5.3 Attach Fin #3 |
|
|
| 5.4 Attach Fin #4 |
|
|
| 5.5 Check Fin Alignment |
|
|
| 5.6 Allow glue to dry |
| 6.0 ATTACH SHOCK CORD |
|
|
| 6.1 Cut out shock cord mount |
|
|
| 6.2 First Glue Application |
|
|
| 6.3 Second Glue Application |
| 6.4 Squueze and Hold |
|
|
| 6.5 Attaching Shock Cord Mount |
| 7.0 ASSEMBLE NOSE CONE |
|
|
| 7.1 Glue nose cone |
| 8.0 ATTACH PARACHUTE/SHOCK CORD |
|
|
| 8.1 Attach Lines |
|
|
| 8.2 Attach Parachute |
|
|
| 8.3 Tie Lines |
9.0 ATTACH LAUNCH LUG |
|
|
| 9.1 Glue launch lines |
|
|
| 9.2 Application of Glue Fillets |
| 10.0 PAINTING THE ROCKET |
|
|
| 10.1 Apply first coat |
|
|
| 10.2 Sand |
|
|
| 10.3 Apply final coat |
| 11.0 APPLICATION OF DECALS |
|
|
| 11.1 Apply first decal |
|
|
| 11.2 Apply second decal |
|
|
| 11.3 Apply third decal |
|
|
| 11.4 Apply fourth decal |
|
|
| 11.5 Apply fifth decal |
|
|
| 11.6 Apply sixth Decal |
| 11.7 Apply seventh Decal |
| 12.0 APPLYING CLEAR COAT |
|
|
| 12.1 Apply clear coat to entire rocket |
| 13.0 DISPLAY NOZZLE ASSEMBLY |
|
|
| 13.1 Spray Nozzle Base White |
|
|
| 13.2 Apply Glue |
| 14.0 ROCKET PREFLIGHT |
|
|
| 14.1 Prepare Rocket for Preflight |
|
|
|
| 14.2 Spike |
|
|
|
| 14.3 Fold |
|
|
|
| 14.4 Roll |
| 14.5 Reinsert |
15.0 PREPARE FOR TEST LAUNCH |
|
|
| 15.1 Insert Engine |
Activity List
1.0 ASSEMBLE ENGINE MOUNT
1.1 Measure, Mark and Cut Engine Tube
| –
|
| 1.1.1 Lay ruler along engine tube |
| -1.1.2 Measure engine from left of engine tube tube @ 1/8″ |
| -1.1.3 Mark left end of Engine Tube @ 1/8′ |
| -1.1.4 Measure engine from left of engine tube @ 3/4″ |
| -1.1.5 Mark from left of EngineTube @ 3/4″ |
| -1.1.6 Measure engine tube from left of engine tube @ 11/2″ |
| -1.1.7 Mark from left of Engine Tube @ 1 1/2″ |
| -1.2 Cut Engine Tube |
| -1.2.1 Cut Slit of 1/8″ @ 1 1/2 inch Mark on Engine Tube |
| -1.3 Glue, Tube, Assemble Hook |
| -1.3.1 Apply thin line of glue completely around engine at 3/4″ mark |
| -1.3.2 Position Hook per diagram |
| -1.3.3 Insert Engine Hook into 1/8″ Slit on Engine Mount Tube |
| -1.4 Assemble Mylar Ring to Tube |
| -1.4.1 Slide Mylar ring onto Engline Mount tube at 3/4″ mark |
| –
|
| 1.4.2 Let Dry |
| -1.5 Assemble Yellow Engine Block to Engine Mount Tube |
| –
|
| 1.5.1 Apply glue inside front of Engine Mount tube |
| –
|
| 1.5.2 Insert Yellow Engine Block flush with the right end per diagram |
| –
|
| 1.5.3 Let Dry |
| -1.6 Assemble Centering Rings |
| –
|
| 1.6.1 Remove Centering rings from card with modeling knife |
| -1.6.2 Apply thin line of Glue around engine mount tube @ 1/8″ mark |
| -1.6.3 Slide notched Centering Ring onto glued line @ 1/8″ mark |
| –
|
| 1.6.4 Let Glue Set |
| –
|
| 1.6.5 Apply thin line of Glue to opposite side of notched center ring flush with end of engine mount tube |
| -1.6.6 Slide unnotched Centering Ring in place over glue flush with end of engine tube mount |
| –
|
| 1.6.7 Let Dry |
| -1.7 Application of Glue Fillets |
| –
|
| 1.7.1 Apply Glue Fillets to both sides of Centering Rings for reinforcement |
| –
|
| 1.7.2 Let Dry |
2.0 FIN PREPARATION
| -2.1 Sand/Cut fins |
| –
|
| 2.1.1 Sand Laser Cut Balsa Sheet w/Fine Sandpaper |
| -2.2 Cutting Out Fins |
|
|
| 2.2.1 Cut out fin #1 w/modeling knife |
|
|
| 2.2.2 Cut out fin #2 w/modeling knife |
|
|
| 2.2.3 Cut out fin #3 w/ modeling knife |
|
|
| 2.2.4 Cut out fin #4 w/modeling knife |
| -2.3 Stack and Sand Fins |
| –
|
| 2.3.1 Stack Fins |
| –
|
| 2.3.2 Sand Edges of fins |
3.0 MARK FIN AND LAUNCH LUG LINES
| –
|
| 3.1 Cut – Tape |
|
| 3.1.1 Cut out tube marking guide |
| –
|
| 3.1.2 Tape tube marking guide around body tube |
| –
|
| 3.1.3 Mark body tube at arrows |
| –
|
| 3.1.4 Mark Launch Lug Line as LL on Body tube |
| -3.2 Remove guide, connect fins and lug lines, extend LL line |
| –
|
| 3.2.1 Remove Tube Marking guide from body tube |
| –
|
| 3.2.2 Connect Fins using door frame |
| –
|
| 3.2.3 Connect launch lug lines using door frame |
| -3.3 Extend Launch Lug Line |
| -3.3.1 Extend launch lug line 3 3/4″ from end of tube |
4.0 INSERTING ENGINE MOUNT
| -4.1 Mark inside of tube @ 5/8″ where LL is |
| -4.1.1 Measure inside tube to 5/8″ position on tube |
| -4.1.2 Mark inside tube at 5/8″ |
| -4.2 Glue Tube |
| –
|
| 4.2.1 Measure inside rear of body tube to 1 3/4′ position on tube |
| -4.2.2 Use finger to smear glue 1 3/4″ inside rear of body tube along LL. |
| -4.3 Assemble Engine Hook |
| –
|
| 4.3.1 Align engine hook with LL line |
| -4.3.2 Insert engine mount into body tube until centering ring is even w/the 5/8″ glue mark |
| –
|
| 4.3.3 Let Dry |
| -4.4 Gluing Center Body Ring |
| –
|
| 4.4.1 Locate scrap piece of balsa to apply glue |
| –
|
| 4.4.2 Apply glue to centering/body tube joint |
| –
|
| 4.4.3 Let Dry |
5.0 ATTACH FINS
| -5.1 Attach Fin #1 |
| –
|
| 5.1.1 Apply thin layer of glue to edge of fin |
| –
|
| 5.1.2 Allow to dry (1 minute for model) |
| –
|
| 5.1.3 Apply second layer of glue to edge of fin |
| –
|
| 5.1.4 Attach Fin to body tube along one of fin lines flush w/end |
| -5.2 Attach Fin #2 |
| –
|
| 5.2.1 Apply thin layer of glue to edge of fin#2 |
| –
|
| 5.2.2 Allow to dry (1 minute for model) |
| –
|
| 5.2.3 Apply second layer of glue to edge of fin #2 |
| –
|
| 5.2.4 Attach Fin #2 to body tube along one of fin lines flush w/end |
| -5.3 Attach Fin #3 |
| –
|
| 5.3.1 Apply thin layer of glue to edge of fin #3 |
| –
|
| 5.3.2 Allow to dry (1 minute for model) |
| –
|
| 5.3.3 Apply second layer of glue to edge of fin #3 |
| –
|
| 5.3.4 Attach Fin #3 to body tube along one of fin lines flush w/end |
| -5.4 Attach Fin #4 |
| –
|
| 5.4.1 Apply thin layer of glue to edge of fin #4 |
| –
|
| 5.4.2 Allow to dry (1 minute for model) |
| –
|
| 5.4.3 Apply second layer of glue to edge of fin #4 |
| –
|
| 5.4.4 Attach Fin #4 to body tube along one of fin lines flush w/end |
| -5.5 Check Fin Alignment |
| –
|
| 5.5.1 Check Fin #1 Alignment as shown in diagram |
| –
|
| 5.5.2 Check Fin #2 Alignment as shown in diagram |
| –
|
| 5.5.3 Check Fin #3 Alignment as shown in diagram |
| –
|
| 5.5.4 Check Fin #4 Alignment as shown in diagram |
| -5.6 Allow glue to dry |
| –
|
| 5.6.1 Let Glue Set |
| –
|
| 5.6.2 Stand Rocket on end |
| –
|
| 5.6.3 let glue dries completely |
6.0 ATTACH SHOCK CORD
| -6.1 Cut out shock cord mount |
| –
|
| 6.1.1 Cut out shock cord from front page |
| -6.2 First Glue Application |
| –
|
| 6.2.1 Attach shock cord to shock cord mount |
| –
|
| 6.2.2 Apply glue to shock cord mount |
| –
|
| 6.2.3 Fold edge of shock cord mount forward over glued shock cord |
| -6.3 Second Glue Application |
| –
|
| 6.3.1 Apply glue to shock cord mount |
| –
|
| 6.3.2 Fold forward again-see diagram for clarification |
| -6.4 Squueze and Hold |
| –
|
| 6.4.1 Squeeze shock cord/shock cord mount tightly |
| –
|
| 6.4.2 Hold for 1 minute |
| -6.5 Attaching Shock Cord Mount |
| -6.5.1 Glue mount 1″ inside body tube |
| –
|
| 6.5.2 Hold until glue sets |
| –
|
| 6.5.3 Let Dry Completely |
7.0 ASSEMBLE NOSE CONE
| -7.1 Glue nose cone |
| -7.1.1 Apply plastic cememt to inside rim of nose cone |
| –
|
| 7.1.2 Press Nose Cone Insert into place over plastic cement inside of nose cone rim |
| -7.1.3 Let Dry Completely |
8.0 ATTACH PARACHUTE/SHOCK CORD
| -8.1 Attach Lines |
| -8.1.1 Pass shroud line on parachute through eyelit |
| -8.2 Attach Parachute |
| -8.2.1 Pass parachute through loop in shroud-look to diagram for clarification |
| -8.3 Tie Lines |
| –
|
| 8.3.1 Tie shock cord to nose cone using a double knot |
9.0 ATTACH LAUNCH LUG
| -9.1 Glue launch lines |
| -9.1.1 Glue LL centerd onto LL Line on rocket body |
| -9.2 Application of Glue Fillets |
| –
|
| 9.2.1 Apply glue fillets along launch lug |
| –
|
| 9.2.2 Apply glue fillets along fin/body tube joints |
| –
|
| 9.2.3 Smooth each fillet with finger |
| -9.2.4 Let glue dry completely |
10.0 PAINTING THE ROCKET
| -10.1 Apply first coat |
| –
|
| 10.1.1 Spray rocket with white primer |
| –
|
| 10.1.2 Let Dry |
| -10.2 Sand |
| –
|
| 10.1.2 Sand entire rocket |
| -10.3 Apply final coat |
| -10.3.1 Spray completed rocket with white second coat of primer |
| -10.3.2 Let Dry |
| –
|
| 10.3.3 Spray Nose Cone with Copper paint |
| –
|
| 10.3.4 Let Dry |
11.0 APPLICATION OF DECALS
| -11.1 Apply first decal |
| –
|
| 11.1.1 Remove First decal from back sheet |
| -11.1.2 Place on Rocket where indicated |
| -11.1.3 Rub decal to remove bubbles |
| -11.2 Apply second decal |
| –
|
| 11.2.1 Remove second decal from backing sheet |
| –
|
| 11.2.2 Place on Rocket where indicated |
| –
|
| 11.2.3 Rub decal to remove bubbles |
| -11.3 Apply third decal |
| -11.3.1 Remove third decal from backing sheet |
| –
|
| 11.3.2 Place on Rocket where indicated |
| –
|
| 11.3.3 Rub decal to remove bubbles |
| -11.4 Apply fourth decal |
| –
|
| 11.4.1 Remove fourth decal from backing sheet |
| –
|
| 11.4.2 Place on Rocket where indicated |
| –
|
| 11.4.3 Rub decal to remove bubbles |
| -11.5 Apply fifth decal |
| –
|
| 11.5.1 Remove fifth decal from backing sheet |
| –
|
| 11.5.2 Place on Rocket where indicated |
| -11.5.3 Rub decal to remove bubbles |
| -11.6 Apply sixth Decal |
| -11.6.1 Remove sixth decal from backing sheet |
| –
|
| 11.6.2 Place on Rocket where indicated |
| –
|
| 11.6.3 Rub decal to remove bubbles |
| -11.7 Apply seventh Decal |
| –
|
| 11.7.1 Remove seventh decal from backing sheet |
| –
|
| 11.7.2 Place on Rocket where indicated |
| -11.7.3 Rub decal to remove bubbles |
12.0 APPLYING CLEAR COAT
| -12.1 Apply clear coat to entire rocket |
|
|
| 12.1.1 Apply clear coat to entire rocket |
|
|
| 12.1.2 Dry Completely |
13.0 DISPLAY NOZZLE ASSEMBLY
| -13.1 Spray Nozzle Base White |
| –
|
| 13.1.1 Paint Nozzle #1 w/Silver Paint Pen |
| –
|
| 13.1.2 Paint Nozzle #2 w/ Silver Paint Pen |
| –
|
| 13.1.3 Paint Nozzle #3 w/ Silver Paint Pen |
| –
|
| 13.1.4 Paint Nozzle #4 w/ Silver Paint Pen |
| -13.1.5 Allow to dry |
| -13.2 Apply Glue |
| -13.2.1 Apply glue to tab on nozzle #1 |
| –
|
| 13.2.2 Place Nozzle #1 into hole on base |
| -13.2.3 Apply glue to tab on nozzle #2 |
| -13.2.4 Place Nozzle #2 into hole on base |
| -13.2.5 Apply glue to tab on nozzle #3 |
| -13.2.6 Place Nozzle #3 into hole on base |
| -13.2.7 Apply glue to tab on nozzle #4 |
| -13.2.8 Place Nozzle #4 into hole on base |
14.0 ROCKET PREFLIGHT
| 14.1 prepare |
| –
|
| 14.1.1 Remove Nose Cone from Rocket |
| –
|
| 14.1.2 Locate recovery wadding |
| –
|
| 14.1.3 Insert 4-5 loosely crumpled squares of recovery wadding |
14.2 Spike
| –
|
| 14.2.1 Pull parachute into a spike-see diagram for clarification |
14.3 Fold
| –
|
| 14.3.1 Fold parachute according to diagram |
14.4 Roll
| –
|
| 14.4.1 Roll parachute according to diagram |
|
|
| 14.5 Re-insert |
| -14.5.1 Wrap lines loosly around rolled parachute-see diagram for clarification |
| –
|
| 14.5.2 Insert parachute into body tube of rocket |
| –
|
| 14.5.3 Insert shock cord into body tube of rocket |
| –
|
| 14.5.4 Insert nose cone into body tube of rocket |
15.0 PREPARE FOR TEST LAUNCH
| -15.1 Insert Engine |
| –
|
| 15.1.1 Remove engine |
| –
|
| 15.1.2 Insert tip to touch propellant |
| –
|
| 15.1.3 Insert engine into rocket |
Decomposed WBS
1.0 ASSEMBLE ENGINE MOUNT
|
| 1.1 Measure, Mark and Cut Engine Tube “ |
1.1.1 Lay ruler along engine tube
|
| 1.1.2 Measure engine from left of engine tube @ 1/8″”” |
|
| 1.1.3 Mark left end of engine Tube @ 1/8′ |
|
| 1.1.4 Measure engine from left of engine tube @ 3/4″”” |
|
| 1.1.5 Mark from left of engine tube @ 3/4″” “ |
|
| 1.1.6 Measure engine tube from left of engine tube @ 11/2″”” |
|
| 1.1.7 Mark from left of engine tube @ 1 1/2″”” |
1.2 Cut Engine Tube
|
| 1.2.1 Cut Slit of 1/8″” @ 1 1/2 inch Mark on Engine Tube” |
|
| 1.3 Glue, Tube, Assemble Hook “ |
|
| 1.3.1 Apply thin line of glue completely around engine at 3/4″” mark” |
1.3.2 Position Hook per diagram
|
| 1.3.3 Insert Engine Hook into 1/8″” Slit on Engine Mount Tube” |
1.4 Assemble Mylar Ring to Tube
|
| 1.4.1 Slide Mylar ring onto Engine Mount tube at 3/4″” mark “ |
1.4.2 Let Dry
1.5 Assemble Yellow Engine Block to Engine Mount Tube
1.5.1 Apply glue inside front of Engine Mount tube
1.5.2 Insert Yellow Engine Block flush with the right end per diagram
1.5.3 Let Dry
1.6 Assemble Centering Rings
1.6.1 Remove Centering rings from card with modeling knife
|
| 1.6.2 Apply thin line of Glue around engine mount tube @ 1/8″” mark” |
|
| 1.6.3 Slide notched Centering Ring onto glued line @ 1/8″” mark” |
1.6.4 Let Glue Set
1.6.5 Apply thin line of Glue to opposite side of notched center ring flush with end of engine mount tube
|
| 1.6.6 Slide un-notched Centering Ring in place over glue flush with end of engine tube mount |
1.6.7 Let Dry
1.7 Application of Glue Fillets
1.7.1 Apply Glue Fillets to both sides of Centering Rings for reinforcement
1.7.2 Let Dry
2.0 FIN PREPARATION
2.1 Sand/Cut fins
2.1.1 Sand Laser Cut Balsa Sheet w/Fine Sandpaper
2.2 Cutting Out Fins
2.2.1 Cut out fin #1 w/modeling knife
2.2.2 Cut out fin #2 w/modeling knife
2.2.3 Cut out fin #3 w/ modeling knife
2.2.4 Cut out fin #4 w/modeling knife
2.3 Stack and Sand Fins
2.3.1 Stack Fins
2.3.2 Sand Edges of fins
3.0 MARK FIN AND LAUNCH LUG LINES
3.1 Cut – Tape
3.1.1 Cut out tube marking guide
3.1.2 Tape tube marking guide around body tube
3.1.3 Mark body tube at arrows
3.1.4 Mark Launch Lug Line as LL on Body tube
|
| 3.2 Remove guide, connect fins and lug lines, extend LL line” |
3.2.1 Remove Tube Marking guide from body tube
3.2.2 Connect Fins using door frame
3.2.3 Connect launch lug lines using door frame
3.3 Extend Launch Lug Line
|
| 3.3.1 Extend launch lug line 3 3/4″” from end of tube” |
4.0 INSERTING ENGINE MOUNT
|
| 4.1 Mark inside of tube @ 5/8″” where LL is” |
|
| 4.1.1 Measure inside tube to 5/8″” position on tube” |
|
| 4.1.2 Mark inside tube at 5/8″”” |
4.2 Glue Tube
4.2.1 Measure inside rear of body tube to 1 3/4′ position on tube
|
| 4.2.2 Use finger to smear glue 1 3/4″” inside rear of body tube along LL.” |
4.3 Assemble Engine Hook
4.3.1 Align engine hook with LL line
|
| 4.3.2 Insert engine mount into body tube until centering ring is even w/the 5/8″” glue mark” |
4.3.3 Let Dry
4.4 Gluing Center Body Ring
4.4.1 Locate scrap piece of balsa to apply glue
4.4.2 Apply glue to centering/body tube joint
4.4.3 Let Dry
5.0 ATTACH FINS
5.1 Attach Fin #1
5.1.1 Apply thin layer of glue to edge of fin
5.1.2 Allow to dry (1 minute for model)
5.1.3 Apply second layer of glue to edge of fin
5.1.4 Attach Fin to body tube along one of fin lines flush w/end
5.2 Attach Fin #2
5.2.1 Apply thin layer of glue to edge of fin#2
5.2.2 Allow to dry (1 minute for model)
5.2.3 Apply second layer of glue to edge of fin #2
5.2.4 Attach Fin #2 to body tube along one of fin lines flush w/end
5.3 Attach Fin #3
5.3.1 Apply thin layer of glue to edge of fin #3
5.3.2 Allow to dry (1 minute for model)
5.3.3 Apply second layer of glue to edge of fin #3
5.3.4 Attach Fin #3 to body tube along one of fin lines flush w/end
5.4 Attach Fin #4
5.4.1 Apply thin layer of glue to edge of fin #4
5.4.2 Allow to dry (1 minute for model)
5.4.3 Apply second layer of glue to edge of fin #4
5.4.4 Attach Fin #4 to body tube along one of fin lines flush w/end
5.5 Check Fin Alignment
5.5.1 Check Fin #1 Alignment as shown in diagram
5.5.2 Check Fin #2 Alignment as shown in diagram
5.5.3 Check Fin #3 Alignment as shown in diagram
5.5.4 Check Fin #4 Alignment as shown in diagram
5.6 Allow glue to dry
5.6.1 Let Glue Set
5.6.2 Stand Rocket on end
5.6.3 let glue dries completely
6.0 ATTACH SHOCK CORD
6.1 Cut out shock cord mount
6.1.1 Cut out shock cord from front page
6.2 First Glue Application
6.2.1 Attach shock cord to shock cord mount
6.2.2 Apply glue to shock cord mount
6.2.3 Fold edge of shock cord mount forward over glued shock cord
6.3 Second Glue Application
6.3.1 Apply glue to shock cord mount
6.3.2 Fold forward again-see diagram for clarification
|
| 6.4 Squeeze and Hold |
6.4.1 Squeeze shock cord/shock cord mount tightly
6.4.2 Hold for 1 minute
6.5 Attaching Shock Cord Mount
|
| 6.5.1 Glue mount 1″” inside body tube” |
6.5.2 Hold until glue sets
6.5.3 Let Dry Completely
7.0 ASSEMBLE NOSE CONE
7.1 Glue nose cone
|
| 7.1.1 Apply plastic cement to inside rim of nose cone |
7.1.2 Press Nose Cone Insert into place over plastic cement inside of nose cone rim
|
| 7.1.3 Let Dry Completely |
8.0 ATTACH PARACHUTE/SHOCK CORD
8.1 Attach Lines
|
| 8.1.1 Pass shroud line on parachute through eyelet |
8.2 Attach Parachute
|
| 8.2.1 Pass parachute through loop in shroud-look to diagram for clarification |
8.3 Tie Lines
8.3.1 Tie shock cord to nose cone using a double knot
9.0 ATTACH LAUNCH LUG
9.1 Glue launch lines
|
| 9.1.1 Glue LL centered onto LL Line on rocket body |
9.2 Application of Glue Fillets
9.2.1 Apply glue fillets along launch lug
9.2.2 Apply glue fillets along fin/body tube joints
9.2.3 Smooth each fillet with finger
|
| 9.2.4 Let glue dry completely |
10.0 PAINTING THE ROCKET
10.1 Apply first coat
10.1.1 Spray rocket with white primer
10.1.2 Let Dry
10.2 Sand
10.1.2 Sand entire rocket
10.3 Apply final coat
|
| 10.3.1 Spray completed rocket with white second coat of primer |
|
| 10.3.2 Let Dry |
10.3.3 Spray Nose Cone with Copper paint
10.3.4 Let Dry
11.0 APPLICATION OF DECALS
11.1 Apply first decal
11.1.1 Remove First decal from back sheet
|
| 11.1.2 Place on Rocket where indicated |
|
| 11.1.3 Rub decal to remove bubbles |
11.2 Apply second decal
11.2.1 Remove second decal from backing sheet
11.2.2 Place on Rocket where indicated
11.2.3 Rub decal to remove bubbles
11.3 Apply third decal
|
| 11.3.1 Remove third decal from backing sheet |
11.3.2 Place on Rocket where indicated
11.3.3 Rub decal to remove bubbles
11.4 Apply fourth decal
11.4.1 Remove fourth decal from backing sheet
11.4.2 Place on Rocket where indicated
11.4.3 Rub decal to remove bubbles
11.5 Apply fifth decal
11.5.1 Remove fifth decal from backing sheet
11.5.2 Place on Rocket where indicated
|
| 11.5.3 Rub decal to remove bubbles |
11.6 Apply sixth Decal
|
| 11.6.1 Remove sixth decal from backing sheet |
11.6.2 Place on Rocket where indicated
11.6.3 Rub decal to remove bubbles
|
| 11.7 Apply seventh Decal |
11.7.1 Remove seventh decal from backing sheet
11.7.2 Place on Rocket where indicated
|
| 11.7.3 Rub decal to remove bubbles |
12.0 APPLYING CLEAR COAT
12.1 Apply clear coat to entire rocket
12.1.1 Apply clear coat to entire rocket
12.1.2 Dry Completely
13.0 DISPLAY NOZZLE ASSEMBLY
13.1 Spray Nozzle Base White
13.1.1 Paint Nozzle #1 w/Silver Paint Pen
13.1.2 Paint Nozzle #2 w/ Silver Paint Pen
13.1.3 Paint Nozzle #3 w/ Silver Paint Pen
13.1.4 Paint Nozzle #4 w/ Silver Paint Pen
|
| 13.1.5 Allow to dry |
13.2 Apply Glue
|
| 13.2.1 Apply glue to tab on nozzle #1 |
13.2.2 Place Nozzle #1 into hole on base
|
| 13.2.3 Apply glue to tab on nozzle #2 |
|
| 13.2.4 Place Nozzle #2 into hole on base |
|
| 13.2.5 Apply glue to tab on nozzle #3 |
|
| 13.2.6 Place Nozzle #3 into hole on base |
|
| 13.2.7 Apply glue to tab on nozzle #4 |
|
| 13.2.8 Place Nozzle #4 into hole on base |
14.0 ROCKET PREFLIGHT
14.1 Prepare Rocket for Preflight
14.1.1 Remove Nose Cone from Rocket
14.1.2 Locate recovery wadding
14.1.3 Insert 4-5 loosely crumpled squares of recovery wadding
14.2 Spike
14.2.1 Pull parachute into a spike-see diagram for clarification
14.3 Fold
14.3.1 Fold parachute according to diagram
14.4 Roll
14.4.1 Roll parachute according to diagram
14.5 Re-insert
|
| 14.5.1 Wrap lines loosely around rolled parachute-see diagram for clarification |
14.5.2 Insert parachute into body tube of rocket
14.5.3 Insert shock cord into body tube of rocket
14.5.4 Insert nose cone into body tube of rocket
|
| 15.0 PREPARE FOR TEST LAUNCH |
15.1 Insert Engine
15.1.1 Remove engine
15.1.2 Insert tip to touch propellant
15.1.3 Insert engine into rocket
| Cost |
Estimate
| Resource types – estimates in man-hours for
| Duration |
Estimate
| TASKS |
Fitter |
Draftsman |
Gluer |
Cutter |
SanderI |
SanderII |
Painter I |
Painter II |
Engineer |
Dummy |
1.0 ASSEMBLE ENGINE MOUNT 14
|
|
|
| 30 |
7 4 0 0 0 0 0
| 40 |
|
|
|
| 95 |
1.1 Measure, Mark and Cut Engine Tube ” 5 30 0 0 0 0 0 0 0 0
1.1.1 Lay ruler along engine tube 5
1.1.2 Measure engine from left of engine tube @ 1/8″”” 5
1.1.3 Mark left end of engine Tube @ 1/8′ 5
1.1.4 Measure engine from left of engine tube @ 3/4″”” 5
1.1.5 Mark from left of engine tube @ 3/4″” ” 5
1.1.6 Measure engine tube from left of engine tube @ 11/2″”” 5
1.1.7 Mark from left of engine tube @ 1 1/2″”” 5
1.2 Cut Engine Tube 0 0 0 2 0 0 0 0 0 0
1.2.1 Cut Slit of 1/8″” @ 1 1/2 inch Mark on Engine Tube” 2
1.3 Glue, Tube, Assemble Hook ” 5 0 2 0 0 0 0 0 0 0
1.3.1 Apply thin line of glue completely around engine at 3/4″” mark” 2
1.3.2 Position Hook per diagram 2
1.3.3 Insert Engine Hook into 1/8″” Slit on Engine Mount Tube” 3
1.4 Assemble Mylar Ring to Tube 1 0 0 0 0 0 0 0 0 8
1.4.1 Slide Mylar ring onto Engine Mount tube at 3/4″” mark ” 1
1.4.2 Let Dry 8
1.5 Assemble Yellow Engine Block to Engine Mount Tube 1 0 1 0 0 0 0 0 0 8
1.5.1 Apply glue inside front of Engine Mount tube 1
1.5.2 Insert Yellow Engine Block flush with the right end per diagram 1
1.5.3 Let Dry 8
1.6 Assemble Centering Rings 2 0 2 2 0 0 0 0 0
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 16 |
1.6.1 Remove Centering rings from card with modeling knife 2
1.6.2 Apply thin line of Glue around engine mount tube @ 1/8″” mark” 1
1.6.3 Slide notched Centering Ring onto glued line @ 1/8″” mark” 1
1.6.4 Let Glue Set 8
1.6.5 Apply thin line of Glue to opposite side of notched center ring flush with end of engine mount tube 1
1.6.6 Slide un-notched Centering Ring in place over glue flush with end of engine tube mount 1
1.6.7 Let Dry 8
1.7 Application of Glue Fillets 0 0 2 0 0 0 0 0 0 8
1.7.1 Apply Glue Fillets to both sides of Centering Rings for reinforcement 2
1.7.2 Let Dry 8
2.0 FIN PREPARATION 2 0 0 12 16 0 0 0 0 0 30
2.1 Sand/Cut fins 0 0 0 0 8 0 0 0 0 0
2.1.1 Sand Laser Cut Balsa Sheet w/Fine Sandpaper 8
2.2 Cutting Out Fins 0 0 0 12 0 0 0 0 0 0
2.2.1 Cut out fin #1 w/modeling knife 3
2.2.2 Cut out fin #2 w/modeling knife 3
2.2.3 Cut out fin #3 w/ modeling knife 3
2.2.4 Cut out fin #4 w/modeling knife 3
2.3 Stack and Sand Fins 2 0 0 0 8 0 0 0 0 0
2.3.1 Stack Fins 2
2.3.2 Sand Edges of fins 8
3.0 MARK FIN AND LAUNCH LUG LINES
|
|
| 19 |
12 0 2 0 0 0 0 0 0
|
|
| 33 |
3.1 Cut – Tape 3 8 0 2 0 0 0 0 0 0
| 3.1.2 Cut out tube marking guide |
2
3.1.2 Tape tube marking guide around body tube 3
3.1.3 Mark body tube at arrows 4
3.1.4 Mark Launch Lug Line as LL on Body tube 4
3.2 Remove guide, connect fins and lug lines, extend LL line” 16 0 0 0 0 0 0 0 0 0
3.2.1 Remove Tube Marking guide from body tube 4
3.2.2 Connect Fins using door frame 4
3.2.3 Connect launch lug lines using door frame 8
3.3 Extend Launch Lug Line 0 4 0 0 0 0 0 0 0 0
3.3.1 Extend launch lug line 3 3/4″” from end of tube” 4
4.0 INSERTING ENGINE MOUNT 11 10 6 0 0 0 0 0 0 16
| 43 |
4.1 Mark inside of tube @ 5/8″” where LL is” 0 7 0 0 0 0 0 0 0 0
4.1.1 Measure inside tube to 5/8″” position on tube” 4
4.1.2 Mark inside tube at 5/8″”” 3
4.2 Glue Tube 0 3 2 0 0 0 0 0 0 0
4.2.1 Measure inside rear of body tube to 1 3/4′ position on tube 3
4.2.2 Use finger to smear glue 1 3/4″” inside rear of body tube along LL.” 2
4.3 Assemble Engine Hook 10 0 0 0 0 0 0 0 0 8
4.3.1 Align engine hook with LL line 5
4.3.2 Insert engine mount into body tube until centering ring is even w/the 5/8″” glue mark” 5
4.3.3 Let Dry 8
4.4 Gluing Center Body Ring 1 0 4 0 0 0 0 0 0 8
4.4.1 Locate scrap piece of balsa to apply glue 1
4.4.2 Apply glue to centering/body tube joint 4
4.4.3 Let Dry 8
5.0 ATTACH FINS
|
|
|
|
| 20 |
16 20 0 0 0 0 0 0
|
|
| 17 |
73 |
5.1 Attach Fin #1 4 0 5 0 0 0 0 0 0 1
5.1.1 Apply thin layer of glue to edge of fin 3
5.1.2 Allow to dry (1 minute for model) 1
5.1.3 Apply second layer of glue to edge of fin 2
5.1.4 Attach Fin to body tube along one of fin lines flush w/end 4
5.2 Attach Fin #2 4 0 5 0 0 0 0 0 0 1
5.2.1 Apply thin layer of glue to edge of fin#2 3
5.2.2 Allow to dry (1 minute for model) 1
5.2.3 Apply second layer of glue to edge of fin #2 2
5.2.4 Attach Fin #2 to body tube along one of fin lines flush w/end 4
5.3 Attach Fin #3 4 0 5 0 0 0 0 0 0 1
5.3.1 Apply thin layer of glue to edge of fin #3 3
5.3.2 Allow to dry (1 minute for model) 1
5.3.3 Apply second layer of glue to edge of fin #3 2
5.3.4 Attach Fin #3 to body tube along one of fin lines flush w/end 4
5.4 Attach Fin #4 4 0 5 0 0 0 0 0 0 1
5.4.1 Apply thin layer of glue to edge of fin #4 3
5.4.2 Allow to dry (1 minute for model) 1
5.4.3 Apply second layer of glue to edge of fin #4 2
5.4.4 Attach Fin #4 to body tube along one of fin lines flush w/end 4
5.5 Check Fin Alignment 0 16 0 0 0 0 0 0 0 0
5.5.1 Check Fin #1 Alignment as shown in diagram 4
5.5.2 Check Fin #2 Alignment as shown in diagram 4
5.5.3 Check Fin #3 Alignment as shown in diagram 4
5.5.4 Check Fin #4 Alignment as shown in diagram 4
5.6 Allow glue to dry 4 0 0 0 0 0 0 0 0 13
5.6.1 Let Glue Set 5
5.6.2 Stand Rocket on end 4
5.6.3 let glue dries completely 8
6.0 ATTACH SHOCK CORD 16 0 19 5 0 0 0 0 0 8
|
|
|
| 48 |
6.1 Cut out shock cord mount 0 0 0 5 0 0 0 0 0 0
6.1.1 Cut out shock cord from front page 5
6.2 First Glue Application 8 0 4 0 0 0 0 0 0 0
6.2.1 Attach shock cord to shock cord mount 4
6.2.2 Apply glue to shock cord mount 4
6.2.3 Fold edge of shock cord mount forward over glued shock cord 4
6.3 Second Glue Application 4 0 4 0 0 0 0 0 0 0
6.3.1 Apply glue to shock cord mount 4
6.3.2 Fold forward again-see diagram for clarification 4
6.4 Squeeze and Hold 0 0 6 0 0 0 0 0 0 0
6.4.1 Squeeze shock cord/shock cord mount tightly 2
6.4.2 Hold for 1 minute 4
6.5 Attaching Shock Cord Mount 4 0 5 0 0 0 0 0 0 8
6.5.1 Glue mount 1″” inside body tube” 4 4
6.5.2 Hold until glue sets 1
6.5.3 Let Dry Completely 8
7.0 ASSEMBLE NOSE CONE 4 0 4 0 0 0 0 0 0 8 16
7.1 Glue nose cone 4 0 4 0 0 0 0 0 0 8
7.1.1 Apply plastic cement to inside rim of nose cone 4
7.1.2 Press Nose Cone Insert into place over plastic cement inside of nose cone rim 4
7.1.3 Let Dry Completely 8
8.0 ATTACH PARACHUTE/SHOCK CORD
|
|
| 18 |
0 0 0 0 0 0 0 0 0 18
8.1 Attach Lines 7 0 0 0 0 0 0 0 0 0
8.1.1 Pass shroud line on parachute through eyelet 7
8.2 Attach Parachute 5 0 0 0 0 0 0 0 0 0
8.2.1 Pass parachute through loop in shroud-look to diagram for clarification 5
8.3 Tie Lines 6 0 0 0 0 0 0 0 0 0
8.3.1 Tie shock cord to nose cone using a double knot 6
9.0 ATTACH LAUNCH LUG 0 0
|
|
| 24 |
0 0 0 0 0 0 8
|
|
|
|
|
|
| 32 |
9.1 Glue launch lines 0 0 4 0 0 0 0 0 0 0
9.1.1 Glue LL centered onto LL Line on rocket body 4
9.2 Application of Glue Fillets 0 0 20 0 0 0 0 0 0 8
9.2.1 Apply glue fillets along launch lug 4
9.2.2 Apply glue fillets along fin/body tube joints 12
9.2.3 Smooth each fillet with finger 4
9.2.4 Let glue dry completely 8
10.0 PAINTING THE ROCKET 0 0 0 0 1 16 8 48 0 24
| 97 |
10.1 Apply first coat 0 0 0 0 0 0 8 0 0 8
10.1.1 Spray rocket with white primer 8
10.1.2 Let Dry 8
10.2 Sand 0 0 0 0 1 16 0 0 0 0
10.1.2 Sand entire rocket 1 16
10.3 Apply final coat 0 0 0 0 0 0 0 48 0 16
10.3.1 Spray completed rocket with white second coat of primer 16
10.3.2 Let Dry 8
10.3.3 Spray Nose Cone with Copper paint 32
10.3.4 Let Dry 8
11.0 APPLICATION OF DECALS 0
|
|
| 35 |
0 0 0 0 0 0 0 0 35
11.1 Apply first decal 0 5 0 0 0 0 0 0 0 0
11.1.1 Remove First decal from back sheet 1
11.1.2 Place on Rocket where indicated 3
11.1.3 Rub decal to remove bubbles 1
11.2 Apply second decal 0 5 0 0 0 0 0 0 0 0
11.2.1 Remove second decal from backing sheet 1
11.2.2 Place on Rocket where indicated 3
11.2.3 Rub decal to remove bubbles 1
11.3 Apply third decal 0 5 0 0 0 0 0 0 0 0
11.3.1 Remove third decal from backing sheet 1
11.3.2 Place on Rocket where indicated 3
11.3.3 Rub decal to remove bubbles 1
11.4 Apply fourth decal 0 5 0 0 0 0 0 0 0 0
11.4.1 Remove fourth decal from backing sheet 1
11.4.2 Place on Rocket where indicated 3
11.4.3 Rub decal to remove bubbles 1
11.5 Apply fifth decal 0 5 0 0 0 0 0 0 0 0
11.5.1 Remove fifth decal from backing sheet 1
11.5.2 Place on Rocket where indicated 3
11.5.3 Rub decal to remove bubbles 1
11.6 Apply sixth Decal 0 5 0 0 0 0 0 0 0 0
11.6.1 Remove sixth decal from backing sheet 1
11.6.2 Place on Rocket where indicated 3
11.6.3 Rub decal to remove bubbles 1
11.7 Apply seventh Decal 0 5 0 0 0 0 0 0 0 0
11.7.1 Remove seventh decal from backing sheet 1
11.7.2 Place on Rocket where indicated 3
11.7.3 Rub decal to remove bubbles 1
12.0 APPLYING CLEAR COAT 0 0 0 0 0 0 0 8 0 8 16
12.1 Apply clear coat to entire rocket 0 0 0 0 0 0 0 8 0 8
12.1.1 Apply clear coat to entire rocket 8
12.1.2 Dry Completely 8
13.0 DISPLAY NOZZLE ASSEMBLY 8 0 8 0 0 0 9 0 0 8 33
13.1 Spray Nozzle Base White 0 0 0 0 0 0 9 0 0 8
13.1.1 Paint Nozzle #1 w/Silver Paint Pen 2
13.1.2 Paint Nozzle #2 w/ Silver Paint Pen 2
13.1.3 Paint Nozzle #3 w/ Silver Paint Pen 2
13.1.4 Paint Nozzle #4 w/ Silver Paint Pen 3
13.1.5 Allow to dry 8
13.2 Apply Glue 8 0 8 0 0 0 0 0 0 0
13.2.1 Apply glue to tab on nozzle #1 2
13.2.2 Place Nozzle #1 into hole on base 2
13.2.3 Apply glue to tab on nozzle #2 2
13.2.4 Place Nozzle #2 into hole on base 2
13.2.5 Apply glue to tab on nozzle #3 2
13.2.6 Place Nozzle #3 into hole on base 2
13.2.7 Apply glue to tab on nozzle #4 2
13.2.8 Place Nozzle #4 into hole on base 2
14.0 ROCKET PREFLIGHT
|
|
| 42 |
0 0 0 0 0 0 0 0 0 42
14.1 Prepare Rocket for Preflight 13 0 0 0 0 0 0 0 0 0
14.1.1 Remove Nose Cone from Rocket 6
14.1.2 Locate recovery wadding 1
14.1.3 Insert 4-5 loosely crumpled squares of recovery wadding 6
14.2 Spike 4 0 0 0 0 0 0 0 0 0
14.2.1 Pull parachute into a spike-see diagram for clarification 4
14.3 Fold 4 0 0 0 0 0 0 0 0 0
14.3.1 Fold parachute according to diagram 4
14.4 Roll 4 0 0 0 0 0 0 0 0 0
14.4.1 Roll parachute according to diagram 4
14.5 Re-insert 17 0 0 0 0 0 0 0 0 0
14.5.1 Wrap lines loosely around rolled parachute-see diagram for clarification 5
14.5.2 Insert parachute into body tube of rocket 6
14.5.3 Insert shock cord into body tube of rocket 2
14.5.4 Insert nose cone into body tube of rocket 4
15.0 PREPARE FOR TEST LAUNCH 0 0 0 0 0 0 0 0 32 0 32
15.1 Insert Engine 0 0 0 0 0 0 0 0 32 0
15.1.1 Remove engine 10
15.1.2 Insert tip to touch propellant 10
15.1.3 Insert engine into rocket 12
| RESOURCE
|
| TOTAL |
S
154 |
103 |
88 |
23 |
17 16 17
56 |
32
137 |
| 643 |
| Add resource totals as cross check |
643
| RESOURCE HOURLY RATES |
|
| $50 |
.00
| $40.00 |
|
|
|
| $25 |
.00
$40.00 $25.00
| $30.00 |
$25.00 $30.00
$55.00 |
$36 |
BLENDED RATES |
| RESOURCE COSTS |
$7,700.00 |
$4,120.00 |
$2,200.00 |
$920.00 |
| $425.00 |
$480.00 |
$425.00
$1,680.00 |
$1,760.00 |
$19,710.00 |
| Number Staff Hours |
| Week-1 |
40
27 |
18 19 16
| Week-2 |
33 15 12 7
| Week-3 |
6 5 3
| Week-4 |
5 5 3
| Week-5 |
20 16 20
| Week-6 |
24
| Week-7 |
1 16 8 48
| Week-8 |
35
| Week-9 |
8 8 9 8
| Week-10 |
42
| Week-11 |
32
Spend Plan-Baseline
| CATEGORY |
|
| Week 1 |
|
| Week 2 |
|
| Week 3 |
|
| Week 4 |
|
| Week 5 |
|
| Week 6 |
|
| Week 7 |
|
| Week 8 |
|
| Week 9 |
|
| Week 10 |
|
| Week 11 |
|
| Week 12 |
|
| Week 13 |
|
| Week 14 |
|
| Week 15 |
|
| Week 16 |
| Labor |
$21,600 |
$11,520 |
|
|
|
| $4,320 |
$4,320 $4,320
|
| $1,
|
| 44 |
0
| $5,760 |
$1,440 $5,760
$2,880 |
$1,440
$64,800 |
|
| Material |
| $15,685 |
|
|
|
| $2,500 |
|
|
|
| $5,800 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| $0 |
$0
|
|
|
| $375 |
|
| $270 |
|
|
|
| $650 |
|
| $1,875 |
|
|
|
| $550 |
|
|
|
| $50,000 |
$0 $0 $0 $0 $0
| $77,705 |
|
| Equipment |
/
|
|
| $1,025 |
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,025
| parts |
TOTAL
|
| $38,310 |
$14,020 |
$10,120 |
$4,320 $4,320
$1,815 |
$6,030 |
$2,090 |
$7,635 |
$3,430 |
$51,440 |
$0 $0 $0 $0 $0
|
|
|
|
|
|
| $143,530 |
| CUMULATIVE |
$38,310
$52,330 |
$62,450 |
$66,770 |
$71,090 |
$72,905 |
$78,935 |
$81,025 |
$88,660 |
$92,090 |
$143,530 $143,530 $143,530 $143,530 $143,530 $143,530
| PROJECT BASELINE |
| EAC= |
$143,530
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 38310 52330 62450 66770 71090 72905 78935 81025 88660 92090 143530
GANTT Schedule
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16
1.0 ASSEMBLE ENGINE MOUNT
2.0 FIN PREPARATION
3.0 MARK FIN AND LAUNCH LUG LINES
4.0 INSERTING ENGINE MOUNT
5.0 ATTACH FINS
6.0 ATTACH SHOCK CORD
7.0 ASSEMBLE NOSE CONE
8.0 ATTACH PARACHUTE/SHOCK CORD
9.0 ATTACH LAUNCH LUG
10.0 PAINTING THE ROCKET
11.0 APPLICATION OF DECALS
12.0 APPLYING CLEAR COAT
13.0 DISPLAY NOZZLE ASSEMBLY
14.0 ROCKET PREFLIGHT
15.0 PREPARE FOR TEST LAUNCH
Network Diagram
0
| 95h |
95
1:
Assemble Engine Mount |
0 0 95 95
| 4
| 3h |
|
|
|
| 138 |
|
|
| 307 |
35h |
|
|
| 342 |
4:
Insert Engine Mount |
11:
Application of Decals |
0
| 33h |
33 95 0 138 138
73h |
|
|
| 211 |
211
|
| 32h |
|
|
|
| 243 |
307 0 342
3:
Mark Fin & LL Lines |
5:
Attach Fins |
9:
Attach Launch Lug |
138 0 211 211 0 243
342
|
| 16h |
|
|
| 358 |
0
| 30h |
30
12:
Applying Clear Coat |
2:
Fin Preparation |
342 0 358
|
| 108 |
108 138
0
| 44h |
44 243
64h |
307 358
42h |
|
|
|
|
| 400 |
6:
Attach Shock Cord |
10:
Painting the Rocket |
14:
Rocket Pre-Flight |
|
| 196 |
196
|
| 240 |
44 3h
47 |
243 0 307 358 0 400
8:
Attach Chute Shock Cord |
0 16h 16 240
| 198 |
243
7:
Assemble Nose Cone |
400 32h
|
| 432 |
|
| 224 |
224 240
15:
Prepare for Test Launch |
400 0 432
0 32h 32
13:
Display Nozzle Assembly |
400 400 432
| Legend |
| Early Start |
Duration
Early Finish |
| Task Name |
Late
Start |
Slack |
Late Finish |
M& E Forecast
| Code |
Item |
Cost Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16
Equipment $1,025 $1,025 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
| Scissors x 10 |
|
|
|
|
| $100 |
$100
| Pencil x10 |
$25 $25
| Ruler x10 |
$50 $50
| Modeling Knife x 5 |
$100 $100
| Guide, Tube Marking |
|
|
| $500 |
$500
| Tool, Framing x 1 |
|
|
|
|
| $125 |
$125
| Tool, Fin Alignment x 1 |
$125 $125
Material $77,705 $15,685 $2,500 $5,800 $0 $0 $375 $270 $650 $1,875 $550 $50,000 $0 $0 $0 $0 $0
| Guide, Shock Cord Mount |
|
|
|
|
| $250 |
$250
| Sand Paper (Course) |
|
|
| $75 |
$75
| Sand Paper (Fine) |
$75 $75
Glue
|
| $150 |
$150
| Cement |
| $120 |
$120
| Tape, Masking |
$100 $100
| Primer, Spray |
| $110 |
$110
| Paint, Spray (White) |
| $160 |
$160
| Paint, Spray (Clear) |
$125 $125
| Pen, Paint (Silver) |
$250 $250
| Tube, Body BT-58 |
$5,800 $5,800
| Block, Engine EB-5B |
| $5,000 |
$5,000
| Cord, Shock, Rubber |
| $115 |
$115
| Hook, Mini Engine EH-3 |
|
|
| $300 |
$300
| Tube, Engine Mount BT-5 |
$500 $500
| Ring, Retainer (Mylar) |
$250 $250
| Sheet, Decal #60859 |
$650 $650
| Card, Centering Ring RA5-58 |
$550 $550
| Lug Launch LL-2A |
$375 $375
| Fins, Laser Cut x4 |
| $4,000 |
$4,000
| Parachute Assembly 12′ x 1 |
$2,500 $2,500
| Base, Nozzle, Display x 1 |
| $750 |
$750
| Nozzles x 4 |
| $1,000 |
$1,000
| Cone, Nose x 1 |
| $3,000 |
$3,000
| Insert, Nose Cone x 1 |
| $1,200 |
$1,200
| Wadding, Recovery x 1pk |
$300 $300
| Engine Assembly, A10-3T x 1 |
$50,000 $50,000
TOTAL
| $16,710 |
$2,500 $5,800 $0 $0 $375 $270 $650 $1,875 $550 $50,000 $0 $0 $0 $0 $0
|
|
|
|
|
|
|
|
|
| 2 |
>Gradebook
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Gradebook Breakdown |
| Unit # |
|
| 1 |
2
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 4 |
5 |
6 |
|
|
|
|
|
|
|
|
|
|
|
|
| Total |
| Assignment 1 |
|
|
|
|
| 4
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 0 |
|
|
|
|
|
| 40 |
40 40 40 40
240 |
| Assignment 2 |
|
|
|
|
|
|
|
|
| 50 |
50 50 50 50
| 2
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 10 |
460 |
| Discussion |
|
|
|
|
| 35 |
35 35 35 35 35
210 |
| Seminar |
|
|
|
|
|
|
|
|
|
|
| 15 |
15 15 15 15 15
90 |
Total
|
|
|
|
| 140 |
140 140 140 140
| 30 |
0
1000 |
0
Unit 1
| GM592 Unit 1 Individual Assignment: 40
| Points |
|
|
|
|
|
|
|
|
|
|
| Points Possible |
|
|
|
|
|
|
|
|
|
|
| Points Earned |
|
|
|
|
| Content (0-24 points) |
| 1. Tool Development (WBS) |
| a) A hierarchical decomposition of the total scope of the project to be carried out by the project to accomplish project objectives according to required deliverables? |
|
|
|
|
|
|
|
|
|
|
| 12 |
| b) Each descending level (from task to subtask to work package) represents an increasing detail definition of project work? |
|
| c) Work packages are accurate and controllable? |
| d) There are no overlaps in scope definition between two activities at the work package level? |
| e) Each activity is assigned a WBS control number that uniquely identifies it for hierarchal summation of costs, schedule, and resource allocation? |
| 2. Tool Development (Scope Statement) |
| a) Project scope description that is in more detail from the project charter? |
12
| b) Acceptance criteria specifying a set of conditions that must be met before deliverables are accepted? |
| c) Project deliverables that correlate to the WBS tasks that is required to be produced to complete the project’s product? |
| d) Project exclusion(s) that identify what is specifically excluded from the project (What constitutes “Out of Scope”)? |
| e) Is there a description of known constraints identifying factors that limit the execution of the project or a process within the project in scope, time, cost, or quality)? |
| f) Is there a description of known assumptions identifying factors in the planning process that is considered to true, real, or certain, without proof or demonstration to include those impacts should the assumptions prove to be false? |
| Analysis (0-12 points) |
|
|
|
|
|
|
|
|
|
|
| Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. |
3
|
|
|
|
|
|
|
|
|
|
| Analysis includes proper classifications, explanations, comparisons and inferences. |
3
|
|
|
|
|
|
|
|
|
|
| Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. |
3
|
| Writing (0-7 points) |
|
|
|
|
|
|
|
|
|
|
| Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. |
3
|
|
|
|
|
|
|
|
|
|
| Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). |
2
|
|
|
|
|
|
|
|
|
|
| Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. |
2
Total 40 0
| GM592 Unit 1 Team Assignment: 50 Points |
Points Possible Points Earned
|
|
|
|
| Content (0-30 points) |
| 1. Tool Development (Scope Management Plan) |
| a) Process for preparing a detailed scope statement? |
10
| b) Process that enables the creation of the WBS from the detailed scope statement? |
| c) Process that establishes how the WBS will be maintained and approved? |
|
| d) Process that specifies how formal acceptances of the completed project deliverables will be obtained? |
|
| e) Process to control how requests for changes to the detailed scope statement will be processed as defined in the Integrated Change Control process (PMBOK section 4.5)? |
| 2. Tool Development (Requirements Traceability Matrix) |
| a) Business needs, opportunities, goals, and objectives? |
10
| b) Project objectives? |
| c) Project scope/WBS deliverables? |
| d) Product design? |
| e) Product development? |
| f) Test cases? |
|
| g) Unique identifier (WBS number, ID, Associate ID, etc.) |
| 3. Tool Development (Communications Management Plan) |
| a) Stakeholder communications requirements? |
10
| b) Information to be communicated (language, format, content, and level of detail)? |
| c) Reason for distribution of information? |
| d) Time frame and frequency for distribution of required information? |
| e) Person responsible for communicating information? |
| f) Person/Group(s) who will receive information? |
| g) Methods or technologies used to convey information (memos, email, fax, press release, etc.)? |
| h) Escalation process with time frames and management chain for escalation of issues not resolved at lower levels? |
| i) Method for updating and refining the communications management plan as project develops? |
| j) Glossary of common project related terminology (minimum
| 20 |
terms)?
| k) Flow charts of the information flow in project? |
| l) Communication constraints (regulations, codes, technologies, organizational policies, etc.)? |
|
|
|
| Analysis (0-
|
|
|
| 11 |
points)
Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 3
Analysis includes proper classifications, explanations, comparisons and inferences. 4
Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. 4
|
|
|
| Writing (
| 0-9 points |
)
Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 3
Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 3
Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. 3
|
|
|
|
|
| Peer Evaluation |
(0,-1:-
15 points |
)
|
|
|
|
|
| Minus points lost on Peer Evaluation (15= 0, 14= -1, 13= -2, etc.) |
0
Total 50 0
Unit 2
| GM592 Unit 2 Individual Assignment: 40 Points |
Points Possible Points Earned
Content (0-24 points)
| 1. Tool Development (Resource Allocation Matrix) |
| a) Contains all project WBS tasks? |
|
| 8 |
| b) Contains all requisite/identified labor resources? |
| c) Identifies method of cross-impacting labor resources to project WBS tasks? |
| 2. Tool Development (Gantt schedule) |
| a) All WBS tasks depicted? |
8
| b) Each task level activity depicted with incremental bar(s) |
| c) Schedule relationships specified using Critical Path Method (CPM) |
|
| d) Critical path correctly identified according to CPM? |
| 3. Tool Development (Network Diagram) |
| a) Utilizes activity-on-node format? |
8
| b) Project divided into all task level activities with task number, task name, and predecessors identified? |
| c) Task level activities correctly sequenced according to precedence (reflects Gantt schedule)? |
d) Critical path correctly identified according to CPM?
| e) Durations for all activities correctly entered (same as Gantt durations)? |
| f) Forward pass correctly performed? |
| g) Backward pass correctly performed? |
| h) Float correctly calculated? |
| i) Minimum project duration same as reflected on Gantt schedule? |
|
| Analysis (0-9 points) |
Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 3
Analysis includes proper classifications, explanations, comparisons and inferences. 3
Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. 3
Writing (0-7 points)
Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 3
Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 2
Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. 2
Total 40 0
| GM592 Unit 2 Team Assignment |
Points Possible Points Earned
Content (0-30 points)
| 1. Tool Development (Definitive Duration Estimate) |
| a) Project scope (WBS) correctly entered down to work package level? |
15
| b) All labor skill sets accounted for with own column? |
| c) Levels of effort correctly entered at the work package levels? |
| d) Level of effort (in hours) correctly rolled-up (totaled) to each requisite sub-task level? |
| e) Sub-task totals correctly rolled-up (totaled) to each requisite task level? |
| f) Task level totals for each labor skill set totals to reflect total task labor hours? |
| g) Each labor skill set task totals tallied at bottom of each skill set column to reflect each skill set total labor for the project? |
| h) All labor total hours tallied to show total labor hours for the project. |
| i) All labor levels of effort calculated to show total labor for each increment by task? |
| 2. Tool Development (Schedule Management Plan) |
| a) Scheduling methodology/Tool to be used for project schedule specified? |
15
| b) Level of accuracy specified to determine activity duration estimates (round up to the next 1 hour/day/month)? |
| c) Units of measure (hours/days/weeks/months)? |
| d) Organizational procedures links (WBS numbering mapped to accounting numbering mapped to general ledger/budget line, etc.)? |
| e) Process identified for updating the status and recording of progress in the schedule tool and defined? |
| f) Control thresholds specified for schedule variances between planned value and actual costs (EVM variances thresholds)? |
| g) Rules for performance measures specified (SV, SPI, etc.) with definitions? |
| h) Reporting formats and frequency for schedule reports defined? |
| i) Process descriptions documented? |
Analysis (0-11 points)
Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 3
Analysis includes proper classifications, explanations, comparisons and inferences. 4
Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. 4
Writing (0-9 points)
Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 3
Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 3
Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. 3
Peer Evaluation
Minus points lost on Peer Evaluation (15= 0, 14= -1, 13= -2, etc.) 0
Total 50 0
Unit 3
| GM592 Unit 3 Individual Assignment: 40 Points |
Points Possible Points Earned
Content (0-24 points)
| 1. Tool Development (Definitive Cost Estimate) |
| a) Durations reflect task totals that match with deliverables? |
12
| b) Sub-task totals properly calculated and rolled up? |
c) Work packages are accurate and controllable?
| d) Work packages total to sub-tasks correctly? |
| e) Levels of effort reflect activity effort correctly? |
| f) Skill-sets totaled correctly? |
| g) Skill-set costs reflect rates and hour totals? |
| h) Duration total matches the total of all skill-sets? |
| 2. Tool Development (Spend Plan with Baseline) |
| a) Reflects schedule planning increments (day/week/month)? |
12
| b)Incremental costs reflect labor/equipment/material costs (not counting indirect costs) and totaled incrementally as well as cumulatively? |
| c) Cumulative costs are depiction of total project costs? |
| d) Cumulative cost curve graph (S-curve graph)? |
| e) Cost baseline (S-Curve) based on total project cost? |
| f) Estimate at Completion (EAC) depicted on cost baseline graph? |
|
| Analysis (9 points) |
Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 3
Analysis includes proper classifications, explanations, comparisons and inferences. 3
Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. 3
|
| Writing (7 points) |
Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 3
Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 2
Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. 2
Total 40 0
| GM592 Unit 3 Team Assignment: 50 Points |
Points Possible Points Earned
Content (0-30 points)
| 1. Tool Development (Cost Management Plan) |
| a) Units of measure. Each unit used in measurements (such as staff hours, staff days, weeks for time measures; or meters, liters, tons, kilometers, or cubic yards for quantity measures; or lump sum in currency form) is defined for each of the resources. |
10
| b) Level of precision. The degree to which activity cost estimates will be rounded up or down (e.g.,US$100.49 to US$100, or US$995.59 to US$1,000), based on the scope of the activities and magnitude of the project |
| c) Level of accuracy. The acceptable range (e.g., :1
| 0% |
) used in determining realistic activity cost estimates is specified, and may include an amount for contingencies
d) Process that specifies how formal acceptances of the completed project deliverables will be obtained?
e) Process to control how requests for changes to the detailed scope statement will be processed as defined in the Integrated Change Control process (PMBOK section 4.5)?
| f) Organizational procedures links. The WBS component used for the project cost accounting is called the control account. Each control account is assigned a unique code or account number(s) that links directly to the performing organizations accounting system. |
| g) Control thresholds. Variance thresholds for monitoring cost performance may be specified to indicate an agreed—upon amount of variation to be allowed before some action needs to be taken. Thresholds are typically expressed as percentage deviations from the baseline plan. |
| h) Rules of performance measurement. Earned value management (EVM) rules of performance measurement are set. |
| i) Reporting formats. The formats and frequency for the various cost reports are defined. |
| j) Process descriptions. Descriptions of each of the other cost management processes are documented. |
| 2. Tool Development (Human Resource Management Plan) |
| a) Roles and responsibilities of assigned skill sets? |
10
| i) Role? |
| ii) Authority? |
| iii) Responsibility? |
| iv) Competency? |
| b) Project organization charts? |
| c) Staffing management plan? |
| i) Staff acquisition? |
| ii) Resource calendars? |
| iii) Staff release plan? |
| iv) Training needs? |
| v) Recognition and rewards? |
| vi) Compliance? |
| vii) Safety? |
g) Unique identifier (WBS number, ID, Associate ID, etc.)
| 3. Tool Development (Procurement Management Plan) |
| a) Procurement management approach? Identifies the necessary steps and responsibilities for procurement from the beginning to the end of a project. |
10
| b) Procurement definition? Describes, in specific terms, what items will be procured and under what conditions. |
| c) Type of contract to be used? Describes the type of contract to be used so the contracts and purchasing department can proceed accordingly. |
| d) Procurement risks? Identifies any potential risks associated with procurement for the project. |
| e) Procurement risk management? Describes how risks related specifically to procurement activities will be managed. |
| f) Cost determination? Describes how costs will be determined and if/how they will be used as part of the selection criteria (RFQ, RFP, RFB). |
| g) Standardized procurement documentation? Describes what standard procurement documentation will be used as part of the procurement (Organizational procurement forms). |
| h) Procurement constraints? Describes any constraints which must be considered as part of the project’s procurement management process. |
| i) Contract approval process? Defines the process through which contracts must be approved. |
| j) Decision criteria? Defines the criteria used by the contract review board to decide on what contract(s) to award. |
| k) Vendor management? Describes the roles and actions the project team and purchasing and contracts department will take |
| l) Performance metrics for procurement activities? Describes the metrics to be used for procurement activities associated with the project. |
Analysis (0-11 points)
Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 3
Analysis includes proper classifications, explanations, comparisons and inferences. 4
Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. 4
Writing (0-9 points)
Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 3
Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 3
Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. 3
Peer Evaluation
Minus points lost on Peer Evaluation (15= 0, 14= -1, 13= -2, etc.) 0
Total 50 0
Unit 4
| GM592 Unit 4 Individual Assignment: 40 Points |
Points Possible Points Earned
Content (0-24 points)
| 1. Tool Development (Ishikawa Analysis) |
| a) Identifies the problem. |
12
| b) Draws the problem and prime arrow. |
| c) Identifies defect categories and causes then list causes under each problem/defect category box using analysis techniques. |
| d) Identifies action(s) to correct problem. |
| 2. Tool Development (Pareto Analysis) |
| a) Sets up data from the number of causes by category |
12
| b) Sorts data by the largest cause category to the smallest cause category by amount of causes called defects. |
| c) Uses the SUM() function to add Amount range. |
| d) Creates a Cumulative Amount column. |
| e) Fills-in the rest of the columns. |
| f) Creates a Cumulative Percent column. |
| g) Identifies the vital few contributors that account for most quality problems in any system using 80/20 rule. |
Analysis (9 points)
Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 3
Analysis includes proper classifications, explanations, comparisons and inferences. 3
Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. 3
Writing (7 points)
Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 3
Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 2
Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. 2
Total 40 0
| GM592 Unit 4 Team Assignment |
Points Possible Points Earned
Content (0-30 points)
| 1. Tool Development (Quality Management Plan) |
| a) Quality assurance processes. Specifies how the quality assurance processes should be applied. |
15
| b) Quality control procedures. Describe how the project team will define and document the process for monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes. |
| c) Quality thresholds. Defines the criteria for the effective execution of key project activities, processes, and deliverables. |
| d) Management responsibilities. Defines quality management responsibilities for the project |
| e) Checklists and templates. Identifies or includes any checklists or templates that should be used by project team members. |
| f) Project quality audit process. |
| · Identifies all good and best practices being implemented; |
| · Identifies all nonconformity, gaps, and shortcomings; |
| · Shares good practices introduced or implemented in similar projects in the organization and/or industry; |
| · Proactively offers assistance in a positive manner to improve implementation of processes to help the team raise productivity; and |
| · Highlights contributions of each audit in the lessons learned repository of the organization. |
| 2. Tool Development (Process Improvement Management Plan) |
| a) Details the steps tor analyzing project management and product development processes to identify activities that enhance their value. |
15
| b) Areas to consider include: |
| • Process boundaries. Describe the purpose of the process, the start |
| and end of the process, its inputs and outputs, the process owner, |
| and the stakeholders of the process. |
| • Process configuration. Provides a graphic depiction to processes, |
| with interfaces identified, and used to facilitate analysis. |
| • Process metrics. Along with control limits, allows analysis of process |
| efficiency. |
| • Targets for improved performance. Guide the process improvement |
| activities. |
Analysis (0-11 points)
Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 3
Analysis includes proper classifications, explanations, comparisons and inferences. 4
Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. 4
Writing (0-9 points)
Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 3
Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 3
Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. 3
Peer Evaluation
Minus points lost on Peer Evaluation (15= 0, 14= -1, 13= -2, etc.) 0
Total 50 0
| Unit 5 |
| GM592 Unit 5 Individual Assignment: 40 Points |
Points Possible Points Earned
Content (0-24 points)
| 1. Tool Development (Qualitative Risk Analysis) |
| a) Identifies a minimum of five risk events having to with cost, time, scope, quality and an additional risk event of choice? |
12
| b) Builds an Impact Scales Matrix to address each of the assigned project objectives according to the matrix in PMBOK figure 11-5? |
| c) Applies the impact scales to where the project might go to a Probability-Impact Matrix design based on the example given in PMBOK figure 11-10? |
| d) Identifies each risk event’s score from the P-I matrix? |
| e) Prioritizes five risk events from greatest threat to least threat and suggests means of mitigation or remediation for each? |
| 2. Tool Development (Quantitative Risk Analysis) |
| a) Conducts a quantitative risk analysis of the effect of one of the five identified risk events using the Decision Tree methodology? |
12
| b) Identifies the decision to be made? |
| c) Establishes a minimum of two decision nodes with correct input and output? |
| d) Builds out chance nodes for each decision node with correct input and outputs? |
| e) Computes net path value correctly? |
| f) Finalizes conclusion(s) into a decision using either a Maxi-Min or Mini-Max decision philosophy and justifies decision based on expected project outcomes. |
Analysis (0-9 points)
Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 3
Analysis includes proper classifications, explanations, comparisons and inferences. 3
Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. 3
| Writing (0-7) points) |
Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 3
Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 2
Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. 2
Total 40 0
| GM592 Unit 5 Team Assignment: 50 Points |
Points Possible Points Earned
Content (0-30 points)
| 1. Tool Development Risk Management Plan) |
| a) Risk management methodology? Defines approaches, tools, and date sources used to perform the project’s risk management. |
15
| b) Roles and responsibilities? Defines lead, support, and risk management team member for each risk activity. |
| c) Risk budgeting? Provides estimates for funds needed in cost baseline and sets process for applying contingency and management reserves. |
| d) Timing? Defines when and how often risk management processes will be performed during the project’s life cycle. |
| e) Risk categories? Provides a means for grouping potential causes of risk (i.e. Risk Breakdown Structure, Knowledge Areas). |
| f) Definitions of risk probability and impact? (See PMBOK, Table 11-1). |
| g) Probability and impact matrix for the project? |
| h) Revised stakeholder tolerances? Any adjustments to the stakeholders different risk thresholds over time. |
| i) Reporting formats? Templates for use in documenting risk process activities/analyses. |
| j) Tracking? Specifies documentation to be used in tracking identified risk events. |
| 2. Tool Development (Stakeholder Management Plan) |
| a) Desired/current engagement levels of stakeholders? |
15
| b) Scope and impact of change to stakeholders? |
| c) Identified interrelationships and potential overlaps between stakeholders? Stakeholder analysis. |
| d) Stakeholder communication requirements for the project? |
| e) Information to be distributed to stakeholders? |
| f) Reason for distribution of information to stakeholder and expected impact to stakeholder engagement? |
| g) Time frame and frequency for distribution of information to stakeholders? |
| h) Method for updating and refining stakeholder management plan? |
| Analysis (11 points) |
Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 3
Analysis includes proper classifications, explanations, comparisons and inferences. 4
Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. 4
| Writing (9 points) |
Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 3
Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 3
Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. 3
Peer Evaluation
Minus points lost on Peer Evaluation (15= 0, 14= -1, 13= -2, etc.) 0
Total 50 0
Unit 6
| GM592 Unit 6 CAP Assignment: 40 Points |
Points Possible Points Earned
Unit 5
| Total Points |
| Professional Goal |
4
| Insights Profile: MBA/MSM Only |
4
| Job Title |
1
| Key Job Title Competencies |
4
| Assessment of Key Job Competencies |
1
| How did this class help develop this Competency? (completed and evidence of reflection) |
11
| Next Steps (completed and evidence of reflection) |
11
| Writing/Spelling/Grammar/Punctuation/not APA |
4
Total 40
| GM592 Unit 6 Team Assignment: 210 Points |
Points Possible Points Earned
| Content (0-140 points) |
| 1. Project Scope Baseline |
| a) Project scope statement |
10
| b) Work Breakdown Structure (fully decomposed) |
| c) Work Breakdown Structure Dictionary |
| 2. Project Schedule Baseline |
| a) Definitive duration estimate |
10
| b) Gantt schedule with critical path |
| c) Milestone chart |
| d) Resource schedule |
| e) Material and equipment forecast |
| 3. Project Cost Baseline |
| a) Definitive cost estimate |
10
| b) Project spend plan |
| c) Project baseline graph with EAC identified |
| 4. Scope Management Plan |
| a) Introduction (The purpose of the scope management plan) |
10
| b) How the detailed scope statement is prepared |
| c) How the decomposed WBS is developed from the detail scope statement |
| d) How the WBS will be maintained and validated |
| e) How formal acceptance of deliverables will be obtained |
| f) How changes to the scope will be controlled through the change control process |
| 5. Requirements Management Plan |
| a) Introduction (The purpose of the requirements management plan) |
10
| b) How requirements activities are to be planned, tracked, and documented |
| c) How configuration management will be conducted |
| d) How requirements will be prioritized |
| e) What metrics will be used in defining project requirements and how they will be used |
| f) Method to be used in documenting, cataloging and tracking requirements |
| 6. Schedule Management Plan |
| a) Introduction (The purpose of the schedule management plan) |
10
| b) Project schedule type/application to be used and how it will be used |
| c) Level of accuracy that the schedule will depict |
| d) Units of measure to be used (hours, days, weeks, etc.) |
| e) Organizational link mapping (e.g. WBS used to develop the Resource Allocation Matrix, that is used to develop the Duration Estimate to be used to develop the schedule) |
| f) Schedule maintenance (how to update the schedule, document it, and when to update it) |
| g) Control thresholds to identify the extent of variance from the schedule before actions need to be taken |
| h) Performance measurement rules (percent complete levels, schedule performance formulae to be used (i.e. EVM formulae for schedule performance) |
| i) Report formats |
| 7. Cost Management Plan |
| a) Introduction (The purpose of the cost management plan) |
10
| b) Units of measurement to be used (dollars, euros, drachmas) |
| c) Levels of precision (degree of estimation rounding such as “All hour estimates will be rounded up to the next hour, or next 5 hours, etc.”) |
| d) Levels of accuracy (e.g., Parametric cost estimations can be accurate to +75% to -25% of the final Estimate at Complete. The Definitive cost estimate should be accurate to +10% to -5% of final EAC.) |
| e) Organizational link mapping (e.g., Fully decomposed WBS will be used along with the definitive duration estimate to develop the definitive cost estimate.) |
| f) Control thresholds to identify the extent of variance from the baseline costs before actions need to be taken (i.e., Project costs not to exceed +10% to – 5% of EAC for any given period.) |
| g) Performance measurement rules (percent complete levels, cost performance formulae to be used (i.e., EVM formulae for cost performance) |
| 8. Quality Management Plan |
| a) Introduction (The purpose of the quality management plan) |
10
| b) Quality management methodology (Describes the approach to quality) |
| c) Quality requirements/standards (reference any specifications documents that provide these specifications) |
| d) Product/Service quality |
| e) Process quality |
| f) Quality assurance (QA) (explain how to define and document the process for auditing the quality requirements to ensure that quality standards and operational definitions are met during the process.) |
| g) Quality control (QC) (explain how to define and document the process for monitoring and recording the results of activities outputs to assess performance and recommend necessary changes. |
| h) Quality control measurements (checklists and log examples to be used in taking quality measurements and comparing them against standards/requirements.) |
| 9. Process Improvement Plan |
| a) Introduction (The purpose of the process improvement management plan) |
10
| b) Process boundaries (description of each activity process from start to finish, process owner, stakeholders for the process) |
| c) Process configuration (graphic depiction of the process flow for each activity) |
| d) Process metrics (control limits, variances, out-of-bounds specifications) |
| e) Improved performance targets (performance measures to work towards to ensure process improvement) |
| 10. Human Resource Management Plan |
| a) Introduction (The purpose of the human resources management plan) |
10
| b) Roles and responsibilities (Roles and responsibilities of team members and stakeholders must be clearly defined in any project. Depending on the organizational structure, project team members may represent many different groups/departments and act in the interest of different functional managers. Additionally, team members may have varying degrees of authority and responsibility. |
| c) Organizational charts (graphic displays of the project tasks and team members. The purpose of this is to illustrate the responsibilities of team members as they relate to the project tasks. Tools such as responsible, accountable, consult, inform (RACI) or responsibility assignment matrix (RAM) may be used to aid in communicating roles and responsibilities for the project team. ) |
| d) Staffing management (contains information on several areas including: when and how human resource requirements will be acquired, the timeline for when resources are needed and may be released, training for any resources with identified gaps in skills required, how performance reviews will be performed, and the rewards and recognition system to be used.) |
| 11. Communications Management Plan |
| a) Introduction (The purpose of the communications management plan) |
10
| b) Stakeholder communications requirements |
| c) Information to be communicated |
| d) Reason for information distribution |
| e) Time frame for information distribution |
| f) Person(s) transmitting information |
| g) Person(s) to receive information |
| h) Mode of information transmittal |
| i) Allocated resources for communication activities (time, cost, labor, equipment, material) |
| j) Escalation process (for escalation of issues to included time and management chain positions that escalation must follow) |
| k) Method to update and refine the communication management plan |
| l) Glossary of project related terminology |
| m) Flow charts of the project information flow, report type examples, meeting guides, etc. |
| n) Organizational constraints to communication distribution (regulatory, SOP, policy, proprietary, etc.) |
| 12. Risk Management Plan |
| a) Introduction (The purpose of the risk management plan) |
10
| b) Risk methodology (The approach, tools, and resources that will be used in conducting risk management) |
| c) Roles and responsibilities (Defining the risk management team lead and team members with their responsibilities in risk even identification, qualitative analysis, quantitative analysis, and response to risks. |
| d) Risk budgeting (What funds will be needed to be included in the cost baseline for contingency and management reserves.) |
| e) Risk timing (Specifies when risk assessments will be conducted throughout the project lifecycle and what points the management and contingency reserves can be applied.) |
| f) Definitions of probability and impact (The conditions chart that defines and standardizes the impact of identified risk events.) |
| g) Probability and impact (The P-I Matrix that the conditional impacts will be measured against the probabilities of occurrence to identify the risk score) |
| h) Revised stakeholder tolerances (Identified stakeholder tolerances to risk that will continue to be revised with each risk assessment throughout the project lifecycle.) |
| i) Reporting formats (Documented formats for addressing risk in the project; examples) |
| j) Tracking (specifying how risks will be recorded and the tracking process to ensure all risks are address and responded to.) |
| 13. Procurement Management Plan |
| a) Introduction (The purpose of the procurement management plan) |
10
| b) Contract Types (What types of contracts are to be used on the project for procurement.) |
| c) Risk management issues (Identified procurement risks and how they will be responded.) |
| d) Estimates for Procurement (Whether independent estimates will be used as evaluation criteria, i.e. Organizational contractor lists.) |
| e) Methodology (The process that all project procurement actions will follow in acquiring resources to include vendor solicitation, evaluation, down-selection, and administration.) |
| f) Standardize procurement documents (a listing or facsimiles of required procurement documents to be used for project procurement.) |
| g) Supplier management (Specifies who is the responsible action person(s) for managing multiple suppliers, vendors, and/or contractors to the project.) |
| h) Procurement coordinating instructions (Actins required to coordinate procurement activities with scheduled on site needs.) |
| i) Procurement constraints and assumptions (all actions affecting the conduct of the project and expectations to avoid, accept, or mitigate.) |
| j) Lead times (Identification of lead times to have acquisitions on site at time of needs by the project.) |
| k) Make-or-buy management (how make-or-buy decision will be made for all scheduled procurement needs.) |
| 14. Stakeholder Management Plan |
| a) Introduction (The purpose of the stakeholder management plan) |
10
| b) Stakeholder analysis (For primary external stakeholder who can affect the conduct of the project.) |
| c) Stakeholder register |
| d) Stakeholder engagement levels |
| e) Stakeholder changer (The scope and impact to the change of each primary stakeholder.) |
| f) Stakeholder communications requirements |
| g) Information distribution (A communications planner for stakeholders can be used.) |
| Analysis
| (30 points) |
Response exhibits strong higher-order critical thinking and analysis (e.g., evaluation). Paper shows original thought. 12
Analysis includes proper classifications, explanations, comparisons and inferences. 12
Critical thinking includes appropriate judgments, conclusions and assessment based on evaluation and synthesis of information. 12
| Writing (30 points) |
Grammatical skills are strong with typically less than one error per page. Correct use of APA when assigned. 12
Appropriate to the assignment, fresh (interesting to read), accurate, (no far-fetched, unsupported comments), precise (say what you mean), and concise (not wordy). 11
Project is in 12-point font. Narrative sections are double-spaced with a double space between. Project is free of serious errors; grammar, punctuation, and spelling help to clarify the meaning by following accepted conventions. 11
Peer Evaluation
Minus points lost on Peer Evaluation (15= 0, 14= -1, 13= -2, etc.) 0
Total 210 0
Discussion Board
| Unit Discussion Rubric |
| Quality (40%) of your post will be measured on the following criteria: |
| ● All assigned Discussion topics were answered completely (Analysis) |
| ● Posts were on topic and unique in content (Application) |
● All posts demonstrated knowledge of the topic (Knowledge)
● Adequate rationale provided Comprehension)
● Adequate support provided (Evaluation)
● Adequate conclusion(s) arrived at (Synthesis) |
| No quality criteria were met. |
|
|
| One criterion was met. |
|
|
| Two criteria were met. |
|
|
| Criteria were fully met. |
40
|
|
|
| pts. |
|
|
|
| (0 points) |
(8 points) |
(24 points) |
(40 points) |
| Participation Guidelines (30%) will be measured on the following criteria: |
| ● Initial post no later than Saturday, 11:59 p.m. ET |
| ● Posts made to each Discussion topic on at least 3 different days |
| ● The original post to be no less than 100 words |
| No participation criteria met. |
One criterion was met. Two criteria were met. Criteria were fully met. 30 pts.
(0 points)
|
| (6 points) |
(18 points) |
(30 points)
| Clarity and Organization of Writing (20%) of your post will be measured on the following criteria: |
| ● Posts were presented in an organized and logical argument composed of a minimum of two complete paragraphs |
| ● No spelling or grammatical errors |
| ● References were used and cited properly (according to APA) |
|
| Criteria were not met at all. |
One criterion was met. Two criteria were met. Criteria were fully met. 20 pts.
(0 points)
| (4 points) |
(12 points) |
(20 points) |
| Professional and Netiquette (10%) in your post will be measured on the following criteria: |
| ● Respect and consideration toward peers/instructors |
| ● Appropriate language |
| ● Professional use of abbreviations and acronyms spelled out the first time |
Criteria were not met at all. One criterion was met. Two criteria were met. Criteria were fully met. 10 pts.
(0 points)
| (2 points) |
(6 points)
(10 points) |
| Total Points in percentage |
0%
| Total points x (DQ post value) |
0 pts.
| ( ___% x 35 pts) |
Seminar
| Unit Seminar Grading Rubric |
| Seminar Criteria |
Points
| – Student posted frequently and was actively engaged in the Seminar. |
15 points
| – Student’s comments improved the Seminar quality and advanced the discussion by raising new issues and/or ideas. |
| – Alternative Assignment was completed according to the guidelines. |
| – Student posted infrequently and/or comments were brief and did not demonstrate an understanding of the material (for example: “Good point” or “I agree”). |
10–14 points |
| – Student’s comments did not improve Seminar quality or advance the discussion by raising new issues or ideas. |
| – Alternative Assignment was not completed according to the guidelines. |
| – Student attended, but failed to post any messages. |
0-9 points
| – Student did not log into the Seminar session. |
| – Alternative Assignment was not completed. |
|
|
|
| 2 |
>
|
|
| C |
alculation Sheet
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
| I |
|
|
|
| D |
|
|
|
|
| J |
ob Description
Immediate Predecessors |
Planned Duration (Weeks) |
Staff (
|
|
|
|
| N |
umber)
Rate/Person/Week |
Task Cost (
|
|
|
| B |
|
|
|
| A |
C)
A
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
.
|
|
|
|
| 0 |
ASS
|
|
|
| E |
|
|
| M |
B
|
|
|
| L |
E EN
|
|
|
| G |
INE M
|
|
| O |
UNT
|
|
|
| Start |
2
| 4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| $1,440 |
$11,520 |
B
| 2.0
|
|
|
| F |
IN PREPARATION
Start 1
|
|
|
|
| 3 |
$1,440
|
|
| $4,320 |
C
| 3.0 MAR
|
|
|
|
|
| K |
FIN AND LAUNC
|
|
| H |
LUG LINES
Start 1 3 $1,440 $4,320
D
|
|
|
| 4.0 INSERTING ENGINE MOUNT |
A 2 3 $1,440
| $8,640 |
E
|
|
|
| 5.0 ATTACH FINS |
D 1 3 $1,440 $4,320
F
|
|
|
| 6.0 ATTACH SHOCK CORD |
Start 2 3 $1,440 $8,640
G
|
|
|
| 7.0 ASSEMBLE NOSE CONE |
Start 1 2 $1,440
| $2,880 |
H
|
|
|
| 8.0 ATTACH PARACHUTE/SHOCK CORD |
G 1 1 $1,440 $1,440
I
|
|
|
| 9.0 ATTACH LAUNCH LUG |
E 1 1 $1,440 $1,440
J
|
|
|
| 10.0 PAINTING THE ROCKET |
I 1 4 $1,440
$5,760 |
K
|
|
|
| 11.0 APPLICATION OF DECALS |
J 1 1 $1,440 $1,440
L
|
|
|
| 12.0 APPLYING CLEAR COAT |
K 1 1 $1,440 $1,440
M
|
|
|
| 13.0 DISPLAY NOZZLE ASSEMBLY |
K 1 3 $1,440 $4,320
N
|
|
|
| 14.0 ROCKET PREFLIGHT |
L 1 2 $1,440 $2,880
O
|
|
|
| 15.0 PREPARE FOR TEST LAUNCH |
N 1 1 $1,440 $1,440
| 24 weeks Level of Effort |
| Blended Rate= |
$1,440
11 weeks duration |
Performance Sheet
| BCWS (PV) TASK |
|
|
| Week 1 |
|
|
| Week 2 |
|
|
| Week 3 |
|
|
| Week 4 |
|
|
| Week 5 |
|
|
| Week 6 |
|
|
| Week 7 |
|
|
| Week 8 |
|
|
| Week 9 |
|
|
| Week 10 |
|
|
| Week 11 |
|
|
| Week 12 |
|
|
| Week 13 |
|
|
| Week 14 |
|
|
| Week 15 |
|
|
| Week 16 |
B
| AC Totals |
A
|
|
| 1.0 ASSEMBLE ENGINE MOUNT |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| $0 |
B
|
|
| 2.0 FIN PREPARATION |
$0
C
|
|
| 3.0 MARK FIN AND LAUNCH LUG LINES |
$0
D 4.0 INSERTING ENGINE MOUNT $0
E 5.0 ATTACH FINS $0
F 6.0 ATTACH SHOCK CORD $0
G 7.0 ASSEMBLE NOSE CONE $0
H 8.0 ATTACH PARACHUTE/SHOCK CORD $0
I 9.0 ATTACH LAUNCH LUG $0
J 10.0 PAINTING THE ROCKET $0
K 11.0 APPLICATION OF DECALS $0
L 12.0 APPLYING CLEAR COAT $0
M 13.0 DISPLAY NOZZLE ASSEMBLY $0
N 14.0 ROCKET PREFLIGHT $0
O 15.0 PREPARE FOR TEST LAUNCH $0
|
|
| Equipment |
$0
|
|
| Material |
$0
$0
|
|
| Weekly Total |
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
|
| Cumulative Cost (PV) |
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
|
| ID |
ACWP (AC) TASK |
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 AC Totals
A 1.0 ASSEMBLE ENGINE MOUNT $0
B 2.0 FIN PREPARATION $0
C 3.0 MARK FIN AND LAUNCH LUG LINES $0
D 4.0 INSERTING ENGINE MOUNT $0
E 5.0 ATTACH FINS $0
F 6.0 ATTACH SHOCK CORD $0
G 7.0 ASSEMBLE NOSE CONE $0
H 8.0 ATTACH PARACHUTE/SHOCK CORD $0
I 9.0 ATTACH LAUNCH LUG $0
J 10.0 PAINTING THE ROCKET $0
K 11.0 APPLICATION OF DECALS $0
L 12.0 APPLYING CLEAR COAT $0
M 13.0 DISPLAY NOZZLE ASSEMBLY $0
N 14.0 ROCKET PREFLIGHT $0
O 15.0 PREPARE FOR TEST LAUNCH $0
Equipment $0
Material $0
$0
Weekly Total $0 $0 $0
|
| Cumulative Cost (AC) |
$0 $0 $0
ID
| BCWP (EV) TASK |
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16
EV Totals |
A 1.0 ASSEMBLE ENGINE MOUNT $0
B 2.0 FIN PREPARATION $0
C 3.0 MARK FIN AND LAUNCH LUG LINES $0
D 4.0 INSERTING ENGINE MOUNT $0
E 5.0 ATTACH FINS $0
F 6.0 ATTACH SHOCK CORD $0
G 7.0 ASSEMBLE NOSE CONE $0
H 8.0 ATTACH PARACHUTE/SHOCK CORD $0
I 9.0 ATTACH LAUNCH LUG $0
J 10.0 PAINTING THE ROCKET $0
K 11.0 APPLICATION OF DECALS $0
L 12.0 APPLYING CLEAR COAT $0
M 13.0 DISPLAY NOZZLE ASSEMBLY $0
N 14.0 ROCKET PREFLIGHT $0
O 15.0 PREPARE FOR TEST LAUNCH $0
Equipment $0
Material $0
$0
Weekly Total $0 $0 $0
|
| Cumulative Cost (EV) |
$0 $0 $0
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16
Cumulative Cost (PV) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Cumulative Cost (AC) $0 $0 $0
Cumulative Cost (EV) $0 $0 $0
| BAC= |
0
| BCWS (PV)= |
0
| ACWP (AC)= |
0
| BCWP (EV)= |
0
|
|
| SV= |
BCWP-BCWS |
|
| CV= |
BCWP-ACWP |
SV= CV=
SV= $0 CV= $0
| Project is $xxK behind schedule |
Project is $xxK over budget |
|
|
| SPI= |
BCWP/BCWS |
|
| CPI= |
BCWP/ACWP |
SPI= CPI=
SPI= 0 CPI= 0
For every dollar spent on scheduled
effort we realize $0.xx worth of progress. |
For every dollar spent, we realize $0.xx of planned result. |
|
|
|
| EAC |
=
BAC/CPI |
|
| PM Eval= |
+1
| 0% |
to -5% EAC
EAC = PM Eval=
| EAC/BAC |
EAC =
| $0.00 |
PM Eval= 0% EAC
| The PM’s EAC isxx% over/under BAC and is/is not in trouble. |
May 22-28
May 29-Jun 4
Jun 5-Jun 11
Jun 12-Jun18
Jun 19-Jun 25
Jun 26-Jul 2
Jul 3-Jul9
Jul 10-Jul 16
Jul 17-Jul23
Jul 24-Jul30
Jul 31-Aug 6
Aug 7-Aug 13
Performance Sheet
Cumulative Cost (PV)
Cumulative Cost (AC)
Cumulative Cost (EV)
BAC=$xxx,xxxx
EAC=$xxx,xxx
Planned Value (PV) Section
Earned Value (EV) Section
Actual Cost (AC) Section
Cumulative or S-Curve Graph
Performance Measures Section
Budget
BCWS or,
PV
Actual
Cost
AC
WP or,
AC
Earned Value
BCWP or,
EV
SV = BCWP – BCWS
CV = BCWP – ACWP
Date
Cost
EAC
Time
S – Curves
NCC
OTB
CBB
TAB Profit / Fees
Contract Price
Earned Value Management
‘Gold Card’‘Gold Card’
Management
Reserve
OVERRUN
AUW
Control
Accounts
Undistributed
Budget
OTB
PMB
Summary Level
Planning Packages
Management Reserve
EAC
PMB
TAB
BAC
TERMINOLOGY
NCC Negotiated Contract Cost Contract price less profit / fee(s)
AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitized
CBB Contract Budget Base Sum of NCC and AUW
OTB O T t B li S f CBB d i d
Work Packages Planning Packages
g g g
Cost
Variance
Schedule Variance
ACWP
BCWS
$
OTB Over Target Baseline Sum of CBB and recognized overrun
TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB
BAC Budget At Completion Total budget for total contract thru any given level
PMB Performance Measurement Baseline Contract time-phased budget plan
MR Management Reserve Budget withheld by Ktr PM for unknowns / risk management
UB Undistributed Budget Broadly defined activities not yet distributed to CAs
CA Control Account Lowest CWBS element assigned to a single focal point to plan & control
scope / schedule / budget
WP W k P k N t d t il l d ti iti ithi CAVARIANCES Favorable is Positive Unfavorable is Negative
BCWP
Time
Now
Completion
Date
Time
WP Work Package Near-term, detail-planned activities within a CA
PP Planning Package Far-term CA activities not yet defined into WPs
BCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUE
BCWP Budgeted Cost for Work Performed Value of work accomplished = EARNED VALUE
ACWP Actual Cost of Work Performed Cost of work accomplished = ACTUAL COST
EAC Estimate At Completion Estimate of total cost for total contract thru any given level;
may be generated by Ktr, PMO, DCMA, etc. = EACKtr / PMO / DCMA
LRE Latest Revised Estimate Ktr’s EAC or EACKtr
SLPP S L l Pl i P k F t ti iti t t d fi d i t CA
VARIANCES Favorable is Positive, Unfavorable is Negative
Cost Variance CV = BCWP – ACWP CV % = (CV / BCWP) *100
Schedule Variance SV = BCWP – BCWS SV % = (SV / BCWS) * 100
Variance at Completion VAC = BAC – EAC
OVERALL STATUS
% Schedule = (BCWSCUM / BAC) * 100
% Complete = (BCWPCUM / BAC) * 100 SLPP Summary Level Planning Package Far-term activities not yet defined into CAs
TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve an EAC
EVM POLICY: DoDI 5000.02, Encl 4. Table 5. EVMS in accordance with ANSI/EIA-748 is required for cost or
incentive contracts, subcontracts, intra-government work agreements, & other agreements valued > $20M (Then-Yr $).
EVMS contracts > $50M (TY $) require that the EVM system be formally validated by the cognizant contracting officer.
Additional Guidance in Defense Acquisition Guidebook and the Earned Value Management Implementation Guide
(EVMIG). EVMS is discouraged on Firm-Fixed Price, Level of Effort, & Time & Material efforts regardless of cost.
DoD TRIPWIRE METRICS Favorable is > 1.0, Unfavorable is < 1.0
Cost Efficiency CPI = BCWP / ACWP
Schedule Efficiency SPI = BCWP / BCWS
p ( CUM )
% Spent = (ACWPCUM / BAC) * 100
BASELINE EXECUTION INDEX (BEI) (Schedule Metric)
BEI = # of Baseline Tasks Actually Completed / # of Baseline Tasks Scheduled for Completion
EVM CONTRACTING REQUIREMENTS:
Non-DoD FAR Clauses – Solicitation – 52.234-2 (Pre-Award IBR) or 52.234-3 (Post Award IBR)
– Solicitation & Contract – 52.234-4
DoD( ≥ $20M) DFAR Clauses – 252.234-7001 for solicitations and 252.234-7002 for solicitations & contracts
Contract Performance Report – DI-MGMT-81466A * 5 Formats (WBS, Organization, Baseline, Staffing & Explanation)
Integrated Master Schedule – DI-MGMT-81650 * (Mandatory for DoD EVMS contracts)
Integrated Baseline Review (IBR) – Mandatory for all EVMS contracts
BEI = # of Baseline Tasks Actually Completed / # of Baseline Tasks Scheduled for Completion
CPLI = (Critical Path Duration + Float Duration (to baseline finish)) / Critical Path Duration
CRITICAL PATH LENGTH INDEX (CPLI) (Schedule Metric)
TO COMPLETE PERFORMANCE INDEX (TCPI) # §
TCPIEAC = Work Remaining / Cost Remaining = (BAC – BCWPCUM) / (EAC – ACWPCUM)
ESTIMATE AT COMPLETION #
EAC A t l t D t + [(R i i W k) / (Effi i F t )]
EVM Home Page = https://acc.dau.mil/evm eMail Address: EVM.dau@dau.mil
DAU POC: (703) 805-5259 (DSN 655)
Revised January 2009
g ( ) y
* See the EVMIG for CPR & IMS tailoring guidance.EAC = Actuals to Date + [(Remaining Work) / (Efficiency Factor)]
EACCPI = ACWPCUM + [(BAC – BCWPCUM) / CPICUM ] = BAC / CPICUM
EACComposite = ACWPCUM + [(BAC – BCWPCUM) / (CPICUM * SPICUM)]
# To Determine a Contract Level TCPI or EAC; You May Replace BAC with TAB
§ To Determine the TCPI BAC or LRE Replace EAC with BAC or LRE
|
|
|
|
|
|
|
|
|
|
| 2 |
>Recovered_Sheet
|
|
|
|
|
|
|
|
|
|
| 1 |
Summary
| Application |
Requested |
Previous |
| Delta |
Issues/Risks/
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Dec |
isions
| AP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| $ |
21,
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 0 |
2
| 6 |
|
|
| $0 |
.00
-$
|
| 21,026 |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 10 |
0
% AP decoms dependent on purchase of final eight
| SAVE |
S @ ~ $1M (UFR).
| BDRE |
$
|
| 108,
|
|
|
| 5 |
58
| $0.00 |
-$108,558 |
Review of this application with customers resulted in a coonversion requirement @ $108.6K + Capital expense (UFR). |
| DSE |
$126,
|
| 29 |
| 7 |
$
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 100 |
,6
|
|
|
|
|
|
|
|
| 3 |
9.25
-$25,
| 65 |
8
System under delay for stress testing and code defect remediation. Delay may cause slip past morotorium. |
| HOBIC |
N/A |
$0.00 $0
System transferred . No langer a NIS Y2K responsibility. |
| MM |
| $
|
|
|
| 17,675 |
$0.00
| -$17,675 |
System undergoing migration from M/F host. Y2K Compliance integral part of migration coding. |
| NAP |
$17,675 $0.00 -$17,675
Decomission dependent on NEMAS acceptance of NAP as front-end processor or utilization of TCP/IP. |
| NIC |
$122,
| 20 |
6
$105,
|
| 57 |
1.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 50 |
-$
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 16 |
,63
|
|
| 4 |
On Schedule, Under Requested Budget. Certain actuals not posted to date. |
SAVE
| $
|
|
|
| 60 |
4,179
$
|
| 11 |
2,773.75
-$491,
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 40 |
5
In order to meet Y2K Compliance by EOY, SAVE dependent on purchace of eight additional SAVEs @ $1M (UFR). |
| TOTAL= |
| $
| 1,017,6
|
|
|
| 15 |
$318,984.50 |
| 98 Allocation |
$
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 38 |
2,000
$382,000.00 |
Delta
| -$6
|
|
| 35 |
,615
$63,015.50 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Feb |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Mar |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Apr |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| May |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jun |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jul |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Aug |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Sep |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Oct |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Nov |
Dec
|
|
|
|
|
|
|
| BCWS |
| $
|
|
|
| 4,655 |
| $11,7
| 80 |
$
|
|
| 23 |
,
3
|
|
| 32 |
$26,173 |
$154,
|
|
|
| 45 |
4
$
| 198 |
,992
$281,197 |
$331,507 |
$387,998 |
$462,
|
|
|
|
| 70 |
8
$9
|
|
| 96 |
,077
$1,017,615
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| ACWP |
$4,655 $11,780
$23,920 |
$27,3
|
| 30 |
$158,826 |
$209,292 |
$
| 240,259 |
Summary
Jan Jan
Feb Feb
Mar Mar
Apr Apr
May May
Jun Jun
Jul Jul
Aug Aug
Sep Sep
Oct Oct
Nov Nov
Dec Dec
BCWS
ACWP
Cumulative Cost for NIS Y2K (7/14/98)
4655
4655
11780
11780
23332
23919.6
26172.5
27330.1
15
| 44 |
54.197142
|
| 85 |
7
158825.63952381
198992.38
76 |
190
|
|
|
|
|
|
|
|
| 48 |
209292.249047619
281197.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 43 |
5238095
2
| 402 |
59.106190476
3
315 |
07.459047619
387998.459047619
46
270 |
8.3
638 |
09524
996076.720952381
10
| 176 |
14.86380952
Roll-Up
| BCWS
|
|
|
| 6/6/98 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1998 |
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Total |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Internal (MCI Staff) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Hours |
| 122.5 |
|
| 187 |
.5
304 |
74.75 |
1148 |
881 |
|
|
|
|
| 120 |
6
622 |
790 |
732 |
332
| 205 |
6,605 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Rate |
38 38 38 38 38 38 38 38 38 38 38 38
$ 4,655
| 7,
|
| 125 |
.00
| 1
|
| 1,552 |
.00
2,
| 840 |
.50
43,624.00 |
33,478.00 |
45,828.00 |
23,636.00 |
30,020.00 |
27,816.00 |
12,
| 616 |
.00
| 7,790.00 |
250,981 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| External (Contractors) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Grade |
Hours 0 0 0 0 120 176
212 |
253 |
294 |
| 248 |
183 |
|
| 174 |
1,
| 66 |
0
Rate
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 56 |
56 56 56 56 56 56 56 56 56 56 56
$
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| – 0 |
– 0 – 0 – 0
| 6,722.86 |
| 9,860 |
.19
11,877.05 |
14,174.02 |
16,471.00 |
13,893.90 |
10,252.36 |
| 9,748 |
.14
9
| 3,000 |
Grade Hours 0 0 0 0 0 0 70 125 100
| 290 |
65 0
650 |
Rate 100 100 100 100 100 100 100 100 100 100 100 100
$ – 0 – 0 – 0 – 0 – 0 – 0
|
| 7,000.00 |
| 12,500.00 |
| 10,000.00 |
2
| 9,000 |
.00
6,500.00 |
– 0
65,000 |
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Total Contractor |
Hours – 0 – 0 – 0 – 0 120 176
282 |
378 |
394 |
538 |
248 174
2,310 |
$ – 0 – 0 – 0 – 0
|
| 6,723 |
9,860
18,877 |
26,674 |
26,471 |
42,894 |
16,752 |
9,748
158,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Capital (Detail Items) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Hardware |
$ 0 0 0 0 0
| 1200 |
|
| 1500 |
0
0 0
|
|
|
|
| 1000 |
501000 |
1000
519,200 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Software |
$ 0 0 0 0 0 0 0 0 0 0 0 0 – 0
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Other Costs (Detail Items) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Team/Factory Costs |
$ 0 0 0 0
77934.84 |
0 0 0 0 0 0 0
77,935 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Travel |
$ 0 0 0 0 0 0
2500 |
0 0
|
|
|
|
|
|
| 300 |
0
3000 3000
1
| 1,500 |
$ 0 0 0 0 0 0 0 0 0 0 0 0 – 0
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Total 1998 |
$ 4,655
| 7,125 |
11,552
2,841 |
128,282 |
44,538 |
82,205 |
50,310 |
56,491 |
74,710 |
533,368 |
21,538 |
1,017,615
| ACWP 6/2/98 |
1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours 122.5 187.5 174
| 89.75 |
784.5 |
963.5 |
638 0 0 0 0 0
2,960 |
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ 4,655
| 7,125.00 |
6,612.00 |
3,410.50 |
29,811.00 |
36,613.00 |
24,244.00 |
– 0 – 0 – 0 – 0 – 0
|
|
|
| 112 |
,471
External (Contractors)
Grade Hours 0 0 0 0
|
|
| 160 |
160 120 0 0 0 0 0
| 440 |
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0
|
| 8,963.81 |
8,963.81 6,722.86 – 0 – 0 – 0 – 0 – 0
24,650 |
Grade Hours 0 0
|
|
|
|
|
| 130 |
0
| 82.5 |
| 115 |
0 0 0 0 0 0
328 |
Rate 43 43 43 43 43 43 43 43 43 43 43 43
$ – 0 – 0
| 5,
| 527 |
.60
– 0
| 3,507.90 |
| 4,889.80 |
– 0 – 0 – 0 – 0 – 0 – 0
13,925 |
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 130 – 0
|
| 243 |
275 |
120 – 0 – 0 – 0 – 0 – 0
768 |
$ – 0 – 0
|
|
| 5,528 |
– 0
12,472 |
13,854 |
6,723 – 0 – 0 – 0 – 0 – 0
38,576 |
Capital (Detail Items)
Hardware $ 0 0 0 0 0 0 0 0 0 0 0 0 – 0
Software $ 0 0 0 0 0 0 0 0 0 0 0 0 – 0
Other Costs (Detail Items)
Team/Factory Costs $ 0 0 0 0
| 89212.83 |
0 0 0 0 0 0 0
89,213 |
Travel $ 0 0 0 0 0 0 0 0 0 0 0 0 – 0
$ – 0
Total 1998 $ 4,655 7,125
| 12,140 |
3,411 |
131,496 |
50,467 |
30,967 |
– 0 – 0 – 0 – 0 – 0 240,259
1998 Y2K Budget Revision
&L&D&C&P&R&T
AP
| Budget Description: Update |
|
|
|
|
|
| App Mgr Name |
|
| Larry Lafreniere |
| Application Name: Adjunct Processor (AP) |
|
|
|
|
|
| Project Coord Name |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jeff Tyler |
|
| Phase: Decom Assessment |
|
|
|
|
|
| VP Name |
|
|
|
|
|
| Patrice Carroll |
|
|
|
|
|
|
| Work Request # |
|
|
|
|
|
| Director Name |
|
|
|
|
|
|
|
|
|
| Bob Laird |
|
|
|
|
|
|
| Work Request Name |
|
|
|
|
|
| Authorized Dep’ts |
|
|
|
|
|
| 2895 |
|
|
|
|
|
|
| Project # |
|
|
|
|
|
| Date |
6/7/98 |
|
|
|
|
|
|
| Company # |
| SHL
|
|
| Project Code # |
1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours 32 32 32 96
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
|
|
| 1,216.00 |
1,216.00 1,216.00
3,
| 64 |
8
External (Contractors)
Grade Hours 16 16 16 16 16 16 96
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0 – 0 – 0
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 896 |
.38
|
|
|
|
|
|
|
|
|
|
|
|
| 896.38 |
896.38 896.38 896.38 896.38
| 5,378 |
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 – 0 – 0 16 16 16 16 16 16 96
$ – 0 – 0 – 0 – 0 – 0 – 0 896 896 896 896 896 896 5,378
Capital (Detail Items)
Hardware $ 1000 1000 1000 3,000
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $ – 0
Travel $ 3000 3000 3000 9,000
$ – 0
Total 1998 $ – 0 – 0 – 0 – 0 – 0 – 0 896 896 896
|
|
| 6,112 |
6,112 6,112 21,026
ACWP 1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours – 0
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
External (Contractors)
Grade Hours – 0
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Capital (Detail Items)
Hardware $ – 0
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $ – 0
Travel $ – 0
$ – 0
Total 1998 $ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
BCWS – 0 – 0 – 0 – 0 – 0 – 0 896
| 1,793 |
|
|
|
|
| 2,689 |
8,802 |
14,914 |
21,026
|
|
|
|
|
|
| BCWP |
0 0 0 0 0 0
ACWP 0 – 0 – 0 – 0 – 0 – 0
AP
Jan Jan Jan
Feb Feb Feb
Mar Mar Mar
Apr Apr Apr
May May May
Jun Jun Jun
Jul Jul Jul
Aug Aug Aug
Sep Sep Sep
Oct Oct Oct
Nov Nov Nov
Dec Dec Dec
BCWS
BCWP
ACWP
Cumulative Costs for AP Y2K Decommission
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
896.380952381
1792.7619047619
2689.1428571429
8801.5238095238
14913.9047619048
| 210 |
26.2857142857
BDRR
| Budget Description: Update |
App Mgr Name
|
|
|
| Larry LaFreniere |
| Application Name:Billing Detail Record Reporting (BDRR) |
Project Coord Name Jeff Tyler
| Phase: Conversion Assessment |
VP Name Patrice Carroll
Work Request # Director Name Bob Laird
Work Request Name Authorized Dep’ts 2895
Project # Date 6/6/98
Company #
Project Code #
1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours
|
| 215 |
255 |
340 |
315 70 10
1,205 |
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ – 0 – 0 – 0 – 0 – 0 – 0
| 8,170.00 |
9,690.00 |
12,920.00 |
11,970.00 |
2,660.00 |
| 380.00 |
45,790 |
External (Contractors)
Grade Hours 50 85 80 85 20 15
| 335 |
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0 – 0 – 0
|
|
|
|
| 2,801 |
.19
| 4,762.02 |
4,481.90 |
4,762.02
1,120.48 |
840.36 |
18,768 |
Grade Hours 70 125 100 130 15 0 440
Rate 100 100 100 100 100 100 100 100 100 100 100 100
$ – 0 – 0 – 0 – 0 – 0 – 0 7,000.00 12,500.00 10,000.00
| 13,000.00 |
1,500.00 |
– 0
44,000 |
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 – 0 – 0 120 210
| 180 |
215 35 15
775 |
$ – 0 – 0 – 0 – 0 – 0 – 0
| 9,801 |
17,262 |
14,482 |
17,762 |
2,620 |
840
62,768 |
Capital (Detail Items)
Hardware $ – 0
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $ – 0
Travel $ – 0
$ – 0
Total 1998 $ – 0 – 0 – 0 – 0 – 0 – 0
|
| 17,971 |
26,952 |
27,402 |
29,732 |
5,280 |
1,220 |
108,558
ACWP 1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours – 0
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
External (Contractors)
Grade Hours – 0
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate 100 100 100 100 100 100 100 100 100 100 100
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Capital (Detail Items)
Hardware $ – 0
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $ – 0
Travel $ – 0
$ – 0
Total 1998 $ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
BCWS – 0 – 0 – 0 – 0 – 0 – 0 17,971
| 44,923 |
72,325 |
102,057 |
107,338 |
108,558
BCWP 0 0 0 0 0 0
ACWP 0 – 0 – 0 – 0 – 0 – 0
Jeff Tyler:
Est cost of shipping and hanling of stratus boxes for turn-in credit.
Jeff Tyler:
Est cost of shipping and hanling of stratus boxes for turn-in credit.
Jeff Tyler:
Est cost of shipping and hanling of stratus boxes for turn-in credit.
Jeff Tyler:
Est. cost of trips to two sites for unexpected problems.
Jeff Tyler:
Est. cost of trips to two sites for unexpected problems.
Jeff Tyler:
Est. cost of trips to two sites for unexpected problems.
BDRR
Jan Jan Jan
Feb Feb Feb
Mar Mar Mar
Apr Apr Apr
May May May
Jun Jun Jun
Jul Jul Jul
Aug Aug Aug
Sep Sep Sep
Oct Oct Oct
Nov Nov Nov
Dec Dec Dec
BCWS
BCWP
ACWP
Cumulative Cost Of BDR Y2K Conversion
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
17971.1904761905
44923.2142857
143 |
72325.119047619
102057.142857143
107337.619047619
108557.976190476
DSE
|
|
|
| Budget Description: 1998 Y2K Update |
App Mgr Name Larry Lafreniere
| Application Name: ISP\NIS\DSE |
Project Coord Name Jeff Tyler
| Phase: Conversion
|
|
| Analysis |
VP Name Patrice Carroll
Work Request #
| 120743 |
Director Name
Open |
Work Request Name Authorized Dep’ts 2895
Project # Date
| 5/7/98 |
Company #
|
| SHL Project Code # |
1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours 29
|
| 37.75 |
220.5 |
23
|
|
| 413 |
66 76 187 270 205 50 23
1,600 |
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$
|
|
|
| 1,102 |
| 1,434.50 |
| 8,379 |
.00
|
|
| 874 |
.00
|
|
| 15,694.00 |
2,508.00 |
2,888.00 |
7,106.00 |
10,260.00 |
7,790.00
|
|
|
|
|
|
|
|
|
|
|
| 1,900.00 |
874.00 |
60,810 |
External (Contractors)
Grade Hours 40 48 38 40 70 35 35 11
| 317 |
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0
|
|
|
|
|
|
|
|
|
|
| 2,240.95 |
|
|
|
| 2,689.14 |
|
| 2,128.90 |
2,240.95
3,921.67 |
| 1,960.83 |
1,960.83
616.26 |
17,760 |
Grade Hours 160 50 210
Rate 100 100 100 100 100 100 100 100 100 100 100 100
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
| 16,000.00 |
5,000.00 |
– 0
2
| 1,000 |
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 40 48 38 40 70
| 195 |
85 11 527
$ – 0 – 0 – 0 – 0
|
|
|
|
|
|
|
|
|
|
| 2,241 |
2,689
|
| 2,129 |
2,241
3,922 |
17,961 |
6,961 |
616
38,760 |
Capital (Detail Items)
Hardware $ – 0
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $
| 26,727.88 |
26,728 |
Travel $ – 0
$ – 0
Total 1998 $ 1,102
|
| 1,435 |
8,379 874
44,663 |
5,197 |
5,017 |
9,347 |
14,182 |
25,751 |
8,861 |
1,490 |
| 126,297 |
|
|
| Ass/Req |
Analysis
Stress
|
|
| Test |
Delay (DP&D)
|
| Coding |
Test
|
| FVO |
|
| Roll-Out |
| 93.00% |
7
| 9.00% |
74.00% |
5
| 8.00% |
9.00% 8.00%
| 1,024.86 |
2,158.12 |
8,358.58 |
8,865.50 |
12,885.15 |
13,300.92 |
1998
ACWP Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours 29 37.75
| 90.5 |
23 15 10
60.5 |
266 |
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ 1,102 1,434.50
| 3,439.00 |
874.00
570.00 |
380.00
2,299.00 |
– 0 – 0 – 0 – 0 – 0
10,099 |
External (Contractors)
Grade Hours 40 43 30
| 113 |
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0 2,240.95
|
| 2,409 |
.02
1,680.71 |
– 0 – 0 – 0 – 0 – 0
6,331 |
Grade Hours 130 130
Rate 43 43 43 43 43 43 43 43 43 43 43 43
$ – 0 – 0
| 5,527.60 |
– 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 5,528
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 130 – 0 40 43 30 – 0 – 0 – 0 – 0 – 0 243
$ – 0 – 0 5,528 – 0 2,241 2,409
| 1,681 |
– 0 – 0 – 0 – 0 – 0
11,858 |
Capital (Detail Items)
Hardware $ – 0
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $
|
| 27,763 |
.06
27,763
Travel $ – 0
$ – 0
Total 1998 $ 1,102 1,435
| 8,967 |
874
30,574 |
2,789 |
3,980 |
– 0 – 0 – 0 – 0 – 0
49,720 |
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
BCWS
|
| 1102 |
| 2,537 |
10,916 |
11,790 |
56,452 |
61,649 |
66,666 |
76,013 |
90,195 |
115,946 |
124,807 |
126,297
BCWP
| 1,025 |
3,183 |
11,542 |
20,407 |
33,292 |
35,052 |
ACWP 1102 2,537
| 11,503 |
12,377 |
42,951 |
45,740 |
&L&D&C&A&R&T
DSE
Jan Jan Jan
Feb Feb Feb
Mar Mar Mar
Apr Apr Apr
May May May
Jun Jun Jun
Jul Jul Jul
Aug Aug Aug
Sep Sep Sep
Oct Oct Oct
Nov Nov Nov
Dec Dec Dec
BCWS
BCWP
ACWP
Cumulative Costs for DSE Y2K (7/14/98)
1102
1024.86
1102
2536.5
3182.975
2536.5
10915.5
115
| 41.5 |
5
11503.1
11789.5
20407.045
12377.1
56452.3323809524
33292.1949142857
42951.1123809524
61649.4752380952
35051.5662571429
45740.1361904762
66666.38
76013.3323809524
90194.999047619
115945.832380952
124806.665714286
126296.927619048
MM
| Budget Description: 1998 Y2K Update |
App Mgr Name Larry LaFreniere
| Application Name: Match Merge (MM) |
Project Coord Name Jeff Tyler
Phase: Decom Assessment VP Name Patrice Carroll
Work Request # Director Name Bob Laird
Work Request Name Authorized Dep’ts 2895
Project # Date 6/6/98
Company #
SHL Project Code #
1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours 50 50 50 50 50 50 300
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ – 0 – 0 – 0 – 0 – 0 – 0 1,900.00 1,900.00 1,900.00 1,900.00 1,900.00 1,900.00
|
| 11,400 |
External (Contractors)
Grade Hours 16 16 16 16 16 16 16 112
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0 – 0 896.38 896.38 896.38 896.38 896.38 896.38 896.38
|
|
|
| 6,275 |
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 – 0 16 16 16 16 16 16 16 112
$ – 0 – 0 – 0 – 0 – 0 896 896 896 896 896 896 896 6,275
Capital (Detail Items)
Hardware $ – 0
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $ – 0
Travel $ – 0
$ – 0
Total 1998 $ – 0 – 0 – 0 – 0 – 0 896
|
|
|
|
|
|
|
|
|
|
|
| 2,796 |
2,796 2,796 2,796 2,796 2,796 17,675
ACWP 1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours – 0
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
External (Contractors)
Grade Hours – 0
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Capital (Detail Items)
Hardware $ – 0
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $ – 0
Travel $ – 0
$ – 0
Total 1998 $ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
BCWS – 0 – 0 – 0 – 0 – 0 896
|
| 3,693 |
| 6,489 |
| 9,286 |
| 12,082 |
| 14,878 |
17,675
BCWP 0 0 0 0 0 0
ACWP 0 – 0 – 0 – 0 – 0 – 0
Jeff Tyler:
Lack of tester will require product testing in ICCA with a contracted teser.
Jeff Tyler:
Lack of tester will require product testing in ICCA with a contracted teser.
MM
Jan Jan Jan
Feb Feb Feb
Mar Mar Mar
Apr Apr Apr
May May May
Jun Jun Jun
Jul Jul Jul
Aug Aug Aug
Sep Sep Sep
Oct Oct Oct
Nov Nov Nov
Dec Dec Dec
BCWS
BCWP
ACWP
Cumulative Cost Of Match Merge Y2K Conversion
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
896.380952381
0
0
3692.7619047619
6489.1428571429
9285.5238095238
12081.9047619048
14878.2857142857
17674.6666666667
NAP
Budget Description: 1998 Y2K Update App Mgr Name Larry LaFreniere
| Application Name: NIC Adjunct Processor (NAP) |
Project Coord Name Jeff Tyler
| Phase: Decom Assessment |
VP Name Patrice Carroll
Work Request # Director Name Bob Laird
Work Request Name Authorized Dep’ts 2895
Project # Date 6/6/98
Company #
Project Code #
1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours 50 50 50 50 50 50 300
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ – 0 – 0 – 0 – 0 – 0 – 0 1,900.00 1,900.00 1,900.00 1,900.00 1,900.00 1,900.00 11,400
External (Contractors)
Grade Hours 16 16 16 16 16 16 16 112
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0 – 0 896.38 896.38 896.38 896.38 896.38 896.38 896.38 6,275
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 – 0 16 16 16 16 16 16 16 112
$ – 0 – 0 – 0 – 0 – 0 896 896 896 896 896 896 896 6,275
Capital (Detail Items)
Hardware $ – 0
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $ – 0
Travel $ – 0
$ – 0
Total 1998 $ – 0 – 0 – 0 – 0 – 0 896 2,796 2,796 2,796 2,796 2,796 2,796 17,675
ACWP 1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours – 0
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
External (Contractors)
Grade Hours – 0
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Capital (Detail Items)
Hardware $ – 0
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $ – 0
Travel $ – 0
$ – 0
Total 1998 $ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
BCWS – 0 – 0 – 0 – 0 – 0 896 3,693 6,489 9,286 12,082 14,878 17,675
BCWP 0 0 0 0 0 0
ACWP 0 – 0 – 0 – 0 – 0 – 0
NAP
Jan Jan Jan
Feb Feb Feb
Mar Mar Mar
Apr Apr Apr
May May May
Jun Jun Jun
Jul Jul Jul
Aug Aug Aug
Sep Sep Sep
Oct Oct Oct
Nov Nov Nov
Dec Dec Dec
BCWS
BCWP
ACWP
Cumulative Cost Of NAP Y2K Claimed Compliance
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
896.380952381
0
0
3692.7619047619
6489.1428571429
9285.5238095238
12081.9047619048
14878.2857142857
17674.6666666667
NIC
Budget Description: 1998 Y2K Update App Mgr Name Larry LaFreniere
| Application Name:Network Information Concentrator (NIC) |
Project Coord Name Jeff Tyler
| Phase: Conversion Analysis |
VP Name Patrice Carroll
Work Request #
| 120742 |
Director Name Bob Laird
Work Request Name Authorized Dep’ts 2895
Project # Date 6/6/98
Company #
SHL Project Code #
1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours 38 41.5 44
| 29.5 |
413 413 413 40 40 40 40 0 1,552
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$
|
|
|
|
|
| 1,444 |
|
| 1,577 |
.00
|
| 1,672 |
.00
| 1,121 |
.00
15,694.00 15,694.00 15,694.00
|
|
|
|
|
|
|
| 1,520.00 |
1,520.00 1,520.00 1,520.00 – 0
58,976 |
External (Contractors)
Grade Hours 40 48 38 40 48 40 40 50
|
|
|
| 344 |
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0 2,240.95 2,689.14 2,128.90 2,240.95 2,689.14 2,240.95 2,240.95
| 2,801.19 |
|
|
| 19,272 |
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 40 48 38 40 48 40 40 50 344
$ – 0 – 0 – 0 – 0 2,241 2,689 2,129 2,241 2,689 2,241 2,241 2,801 19,272
Capital (Detail Items)
Hardware $ 15000
| 15,000 |
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $
|
| 27,457 |
.32
27,457
Travel $ 1500 1,500
$ – 0
Total 1998 $ 1,444 1,577 1,672 1,121
| 45,392 |
18,383 |
34,323 |
|
|
|
| 3,761 |
| 4,209 |
3,761 3,761 2,801
| 122,206 |
Ass/Req Analysis Coding Test FVO Roll-Out
| 90.00% |
81.00% |
88.00% |
77.00% |
56.00% |
17.00% |
| 1,299.60 |
2,576.97 |
2,770.96 |
3,634.13 |
29,053.80 |
32,178.94 |
ACWP 1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours 38 41.5 44
| 44.5 |
89.25 |
147 |
64
468 |
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ 1,444
| 1,577.00 |
1,672.00 |
| 1,691 |
.00
3,391.50 |
5,586.00 |
2,432.00 |
– 0 – 0 – 0 – 0 – 0
17,794 |
External (Contractors)
Grade Hours 60 57 45
|
| 162 |
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0
|
| 3,361 |
.43
| 3,193 |
.36
|
| 2,521 |
.07
– 0 – 0 – 0 – 0 – 0
| 9,076 |
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 60 57 45 – 0 – 0 – 0 – 0 – 0 162
$ – 0 – 0 – 0 – 0 3,361 3,193 2,521 – 0 – 0 – 0 – 0 – 0 9,076
Capital (Detail Items)
Hardware $ – 0
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $
|
| 28,538 |
.09
28,538
Travel $ – 0
$ – 0
Total 1998 $ 1,444 1,577 1,672 1,691
| 35,291 |
8,779 |
4,953 |
– 0 – 0 – 0 – 0 – 0
55,407 |
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
BCWS 1,444
|
| 3,021 |
| 4,693 |
5,814 |
51,206 |
69,589 |
103,912 |
107,673 |
111,882 |
115,643 |
119,404 |
122,206
BCWP
| 1,300 |
3,877 |
5,348 |
6,405 |
32,688 |
61,233 |
ACWP 1,444 3,021 4,693
| 6,384 |
41,675 |
50,454 |
&L&D&C&A&R&T
NIC
Jan Jan Jan
Feb Feb Feb
Mar Mar Mar
Apr Apr Apr
May May May
Jun Jun Jun
Jul Jul Jul
Aug Aug Aug
Sep Sep Sep
Oct Oct Oct
Nov Nov Nov
Dec Dec Dec
BCWS
BCWP
ACWP
Cumulative Costs for NIC Y2K (7/14/98)
1444
1299.6
1444
3021
3876.57
3021
4693
5347.93
4693
5814
6405.09
6384
51206.2723809524
32687.9325333333
41675.0185714286
69589.4152380952
61232.739352381
50454.3757142857
103912.32
107673.272380952
111882.415238095
115643.367619048
119404.32
122205.51047619
SAVE
Budget Description: 1998 Y2K Update App Mgr Name Larry LaFreniere
| Application Name:Storage And Verification Element (SAVE) |
Project Coord Name Jeff Tyler
| Phase: Conversion
| Design |
& Planning
VP Name Patrice Carroll
Work Request #
| 120741 |
Director Name Bob Laird
Work Request Name Authorized Dep’ts 2895
Project # Date
| 6/6//1998 |
Company #
Project Code #
1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours
|
| 55.5 |
| 108.25 |
| 39.5 |
| 22.25 |
322 |
402 402 40 40 40 40 40 1,552
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$
|
|
|
|
| 2,109 |
| 4,113.50 |
|
| 1,501 |
.00
| 845.50 |
12,236.00 |
| 15,276.00 |
15,276.00 1,520.00 1,520.00 1,520.00 1,520.00 1,520.00
58,957 |
External (Contractors)
Grade Hours 40 48 38 40 48 40 40 50 344
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0 2,240.95 2,689.14 2,128.90 2,240.95 2,689.14 2,240.95 2,240.95 2,801.19 19,272
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 40 48 38 40 48 40 40 50 344
$ – 0 – 0 – 0 – 0 2,241 2,689 2,129 2,241 2,689 2,241 2,241 2,801 19,272
Capital (Detail Items)
Hardware $ 1200
| 500,000 |
501,200 |
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $
| 23,749.64 |
23,750 |
Travel $ 1000 1,000
$ – 0
Total 1998 $ 2,109
|
| 4,114 |
1,501
| 846 |
38,227 |
19,
| 165 |
18,405 |
3,761 4,209 3,761
503,761 |
4,321 |
| 604,179 |
Ass/Req Analysis Design Coding Test FVO Roll-Out
| 100.0% |
87.0% |
78.0% |
79.0% |
71.0% |
11.0% |
| 2,109.00 |
5,687.75 |
1,170.78 |
667.95 |
27,140.88 |
2,108.17 |
ACWP 1998
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Internal (MCI Staff) Hours 55.5 108.25 39.5 22.25
| 680.25 |
806.5 |
513.5 |
2,226 |
Rate 38 38 38 38 38 38 38 38 38 38 38 38
$ 2,109 4,113.50
| 1,501.00 |
845.50
25,849.50 |
30,647.00 |
19,513.00 |
– 0 – 0 – 0 – 0 – 0
84,579 |
External (Contractors)
Grade Hours 60 60 45 165
Rate 56 56 56 56 56 56 56 56 56 56 56 56
$ – 0 – 0 – 0 – 0
|
| 3,361.43 |
3,361.43
2,521.07 |
– 0 – 0 – 0 – 0 – 0
9,244 |
Grade Hours 82.5 115 198
Rate 43 43 43 43 43 43 43 43 43 43 43 43
$ – 0 – 0 – 0 – 0 3,507.90 4,889.80 – 0 – 0 – 0 – 0 – 0 – 0
| 8,398 |
Grade Hours – 0
Rate – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
$ – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0 – 0
Total Contractor Hours – 0 – 0 – 0 – 0 143
| 175 |
45 – 0 – 0 – 0 – 0 – 0
363 |
$ – 0 – 0 – 0 – 0
| 6,869 |
8,251 |
2,521 – 0 – 0 – 0 – 0 – 0
17,642 |
Capital (Detail Items)
Hardware $ – 0
Software $ – 0
Other Costs (Detail Items)
Team/Factory Costs $
| 32,911.68 |
32,912 |
Travel $ – 0
$ – 0
Total 1998 $ 2,109 4,114 1,501 846
| 65,631 |
38,898 |
22,034 |
– 0 – 0 – 0 – 0 – 0
135,132 |
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
BCWS 2,109
|
| 6,223 |
| 7,724 |
| 8,569 |
46,796 |
65,961 |
84,366 |
88,127 |
92,336 |
96,097 |
599,858 |
604,179
BCWP 0
| 5,688 |
6,859 |
7,526 |
34,667 |
36,776 |
ACWP
| 2109 |
6,223 7,724 8,569
74,200 |
113,098 |
Jeff Tyler: The NAP box in Perryman needs to have an OS upgrade to VOS 12.4. This is necessary for Y2K compliance, and to stay current with the kit revision level (build 08). We have been requested to fund Sheldons trip to Perryman for this activity. The costs should not exceed $1200, and this should be billable to the Y2K funds.
The maintenance is necessary before May 29, and is requested for a Sunday afternoon due to the behavior patterns of the NAP.
Jeff Tyler:
Estimated cost of memory repacement for NIC testing box canibalized to support Lab in Y2K testing.
&L&D&C&A&R&T
SAVE
BCWS
BCWP
ACWP
Cumulative Cost of SAVE Y2K (7/14/98)
Risk Assessment
| ID |
Risk Event |
Probability |
Impact |
Response |
Priority |
Resonsibility |
| NIS Adjunct Processor (AP) Y2K Project |
1
| Decom by 12/31/98 |
|
|
|
|
|
|
|
| Med |
|
|
|
|
| Hi |
1
Edie Smith |
2
| Use as Tape Drive for NIC |
Hi
|
|
|
|
|
|
|
|
|
| Low |
2 Jeff Tyler
3
| Get
| Exemption |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| HI |
Low 3 Jeff Tyler
| NIS Billing Detail Record Reporting (BDRR) Y2K Project |
1
|
| Not decom’d |
HI HI
(a)
|
| Get exmption |
(b) Xfer to DSS
(c)
Claim Compliance |
(d)
Convert |
1
2 Get exmption HI Low 5 Jeff Tyler
3
| Transfer to DSS |
Low HI 3 Bob Laird
4 Claim Compliance
| Low-Med |
HI 4 Jeff Tyler
5 Convert HI Med
| Ramp up staffing ASAP |
2 Larry Lafreniere
| NIS Data Server for EVS (DSE) Y2K Project |
1
| Coding Slip |
Med Hi
Request Exemption |
2 Jeff Tyler
2
| No test capability |
Hi Hi
ICCA product test |
1
| John Anderson |
3
| No PM |
Med Hi
Job Req. |
3 John Anderson
| NIS Match Merge (MM) Y2K Project |
1 Not decom’d HI HI Exemption 2 Jeff Tyler
2
| Host migration delays |
HI HI
Requires Assesment |
1
John Libermann |
3 Get exmption HI Low 3 Jeff Tyler
| NIS NIC Adjunct Processor (NAP) Y2K Project |
1
| Not decom’d by 12/31/98 |
Med Low
(a) Submit exception.
(b) Xfer to NEMAS as front end processor.
(c) See if TEFAC can replace it.
(d)
| Institute TCP/IP with NEMAS |
.
(e) Resort to Claimed Compliance.
1 Bob Laird
2
| Receive exmption |
| Med-HI |
Low 2 Jeff Tyler
3
| Transfer to NEMAS |
Low HI
If not then goto TEFAC |
3 Bob Laird
4
| TEFEC to replace need for NAP |
Med-Low |
HI
If not then goto TCP/IP |
4
Kim Greer |
5 Institute TCP/IP with NEMAS Med-HI Med
| If not then goto Claimed Compliance |
5
Dave Weis |
6
| Go Claimed Compliance |
Low Med
If not then retire |
6 Jeff Tyler
7
| Retire |
Low Low
Escalate Business Case |
7 Bob Laird
| NIS Storage And Verification Element (SAVE) Y2K Project |
1
| Not Compliant by 12/31/98 |
HI HI
Purchase remaining eight SAVE boxes |
1 Bob Laird
2
| RolLowut by Moratorium |
Med Med
Apply for exemption |
2 Jeff Tyler
Jeff Tyler:
Estimated cost of O/S upgrade
Jeff Tyler:
Includes $6K in change controls not planned for
All you ever wanted to know about earned value analysis
*
ACWP
BCWP
BCWS
CV =
CPI =
= SV
= SPI
Minus
Divided By
Minus
Divided By
*
IF
ACWP>BCWP
ACWP=BCWP
ACWP 0
CPI > 1
The
Project is
Over
Budget
On
Budget
Under
Budget
*
IF
BCWS>BCWP
BCWS =BCWP
BCWS 0
SPI > 1
The
Project is
Behind
Schedule
On
Schedule
Ahead of
Schedule
*
EV – Previously called BCWP or Budgeted Cost of Work Performed, Earned Value or actual work.
PV – Previously call BCWS or Budgeted Cost of Work Scheduled, Planned Value or the project budget.
AC – Previously called ACWP or Actual Cost of Work Performed, Actual Costs
CV – Cost Variance = BCWP – ACWP
SC – Schedule Variance = BCWP – BCWS
CPI – Cost Performance Index = BCWP/ACWP
SPI – Schedule Performance Index = BCWP/BCWS
EAC – Estimate At Completion, a forecast of most likely total project cost based upon project performance and risk.
Schedule = Original Schedule/SPI
Cost = Min: Original Budget/CPI or Max: Original Budget/(CPI * SPI)
*
BAC – Budgeted at Completion = Σ of all the budgets (PV or BCWS)
VAC – Variance at Completion = BAC – EAC
ETC – Estimate to Complete = EAC – AC
*
*
Value of the future of fund available today
FV = PV * (1 + i) n
If you have $1,000 invested for three years at 10% how much will you have at the end of year three?
EOY 1 = $1,000 * (1 + 10%) = $1,100
EOY 2 = $1,100 * (1 + 10%) = $1,210
EOY 3 = $1,210 * (1 + 10%) = $1,331
*
Value today of funds available in the future.
PV = FV / (1 + i)n
If you want $1,000 in three years, how much do you have to invest today at 8% to receive your $1,000?
EOY 1 = $1,000 / (1 + 10%) = $925.93
EOY 2 = $925.93 / (1 + 10%) = $857.34
EOY 3 = $857.34 / (1 + 10%) = $793.83
*
Net Present Value – Present Value minus present cost.
Internal Rate of Return – Average rate of return earned over the life of the project. It is where discounted cash flow minus up front cost equals zero.
*
PERT
Weighted
Average
=
Optimistic + 4XMost Likely + Pessimistic
6
PERT
Standard
Deviation
=
Optimistic – Pessimistic
6
*
GM593:Project Execution with Monitoring and Control
1 of
3
Unit 2 Assignment: Calculating Project Budget
Estimate
Updates
In this Assignment, you are provided your sponsor-approved financials for your project’s labor. You
will need to go back to the project plan, or Gauchito Project W orkbook.xls (in Course Resources), to
pull out your incremental material and equipment costs from the M&E Forecast tab. Your job will be to
lay out only your Planned Value (PV) section of your Gauchito EVM Tool and/or Project (in Course
Resources). You will need to bring over your approved Gantt schedule for the Project W orkbook to
accomplish this.
Based on the information from the Gauchito project plan, your company finance department provided
you with the
following:
ID
Job Description
Immediate
Predecessors
Planned
Duration
(Weeks)
Staff
(Number)
Rate/Pers
on/Week
Task Cost
(BAC)
A
1.0 ASSEMBLE ENGINE
MOUNT
Start
2
4
$1,440
$11,520
B 2.0 FIN PREPARATION Start 1 3 $1,440
$4,320
C
3.0 MARK FIN AND
LAUNCH LUG LINES
Start
1
3
$1,440
$4,320
D
4.0 INSERTING ENGINE
MOUNT
A
2
3
$1,440
$8,640
E 5.0 ATTACH FINS D 1 3 $1,440 $4,320
F 6.0 ATTACH SHOCK CORD Start 2 3 $1,440 $8,640
G 7.0 ASSEMBLE NOSE CONE Start 1 2 $1,440 $2,880
H
8.0 ATTACH
PARACHUTE/SHOCK CORD
G
1
1
$1,440
$1,440
I 9.0 ATTACH LAUNCH LUG E 1 1 $1,440 $1,440
J 10.0 PAINTING THE ROCKET I 1 4 $1,440 $5,760
K
11.0 APPLICATION OF
DECALS
J
1
1
$1,440
$1,440
L
12.0 APPLYING CLEAR
COAT
K
1
1
$1,440
$1,440
M
13.0 DISPLAY NOZZLE
ASSEMBLY
K
1
3
$1,440
$4,320
N 14.0 ROCKET PREFLIGHT L 1 2 $1,440 $2,880
O
15.0 PREPARE FOR TEST
LAUNCH
N
1
1
$1,440
$1,440
2 of 3
You will notice that the accounting guys are running with a blended rate for all skill sets to include the
outsourced contracted fitters. Because this is the latest information, you include it in your Project
W orkbook to supersede what was provided in the Gauchito project plan, and then complete the
following:
Using the information in the Gauchito Project Plan, your Gauchito Project W orkbook (in Course
Resources) your team put together as working references, and your company provided EVM
Tool Template (in Course Resources), construct in the EVM tool template your Planned Value
(PV) section with a Gantt bar graph for the project depicting your critical path.
Graph your baseline with BAC and EAC identified.
Considerations:
All work packages within a subtask are executed in serial (F–S) fashion.
All subtasks within a task are executed in a serial (F–S) fashion.
All tasks (deliverables) are executed according to the Gauchito project plan appendix W G:
Gantt.
You will need an evening for data collection, an evening for compiling the data, and an evening to
write up your findings. For your project tools, use the examples and tools available in Course
Resources or the Internet that meets all the criteria of the grading rubric and complete the
requirement, using your assigned project scenario found in the Course Resources section of the
class website.
Directions for Submitting
1. Upload your Excel EVM tool in the Assignment Dropbox.
2. Ensure that your documents address the criteria of the rubric and follow the stated
requirements.
3. Submit your Assignment to the Unit 2 Assignment link located in the Dropbox.
3 of 3
GM593 Unit 2 Assignment: Calculating Project Budget Estimate
Updates
Points
Possible
Points
Earned
Content
The necessary data for labor, equipment, material, duration, start,
finish, and predecessors are correctly annotated as provided by
the instructions into the Gauchito EVM tool.
10
A Gantt bar graph for the project BCW S (PV) was constructed in the
EVM tool template according to the provided table.
5
All tasks (deliverables) are executed according to the Gauchito
project plan appendix WG: Gantt and/or Gauchito Project
W orkbook tabs for labor costs, material costs, equipment costs,
and schedule.
10
Task level activities are correctly scheduled with predecessors and
successor according to precedence relationships from the project plan
or project workbook.
5
A critical path is displayed according to CPM.
5
The depicted Cumulative Cost Curve/Baseline graph correctly
reflects the Planned Value.
5
The graph correctly depicts the project BAC and EAC for the start of
the project.
5
Analysis
Response exhibits strong higher-order critical thinking and
analysis (e.g., evaluation). Submission shows original thought.
10
Analysis includes proper classifications, explanations, comparisons,
and inferences.
10
Critical thinking includes appropriate judgments, conclusions,
and assessment based on evaluation and synthesis of
information.
10
Total
75
COMPUTERWORLD April 3 , 2 0 0 6 MAIU6EMENT www.computerworld.com
Earned Value
Management
^ ” ^ ” ••• ^ ” ^ ” ^ ” • • ” ^ ^ * ^ » ^ ” ^ ” • • ^ » ^ « ^ « ^ » mtt ••• ^m ^m mm mm ^m ^m • • MH ^ B ^ B ^M ^m ^m
What it is, how it works and why your
projects need it. By Mary K. Pratt
• ^ YOUR IT shop isn’t using
I ^l earned value management,
I ^ P you may want to start thinking
I I about it. EVM, which has its
I I roots in the U.S. Department
I I ofDefense, is moving into
private industry. More important, it’s
coming to IT.
When used properly, EVM helps
team members, project managers and
their bosses accurately gauge progress
against an established project plan.
EVM also enables teams to accurately
assess where they’ll be in the future,
allowing managers to make key deci-
sions on resource allocation or revi-
sions before projects unexpectedly
spin out of control.
“When people report percent com-
plete, you might get ‘I’m 50% complete,’
based on that person’s intuitive knowl-
edge. Earned value analysis takes that
guesswork out of it,” says Robert Leto,
director of the IT effectiveness prac-
tice at PricewaterhouseCoopers Advi-
sory Services LLP in New York.
The Defense Department has em-
ployed EVM for years, requiring its
contractors to use it for reporting on
federal projects.
So, what exactly is EVM? “It eomes
with a reputation for being complicated
and difficult, hut I don’t think anything
could be farther from the truth,” says
John M. Nevison, president of Oak
Associates Inc., a Maynard, Mass.-
bascd firm that provides consulting
and training services related to project
management.
EVM is hased on several figures that
are used in calculations to determine
whether a project is adhering to sched-
ule and budget. Results can be mea-
sured in terms of money or time.
EVM is not about producing perfect
scores. “It’s accepted that you’re going
to vary from your plan,” says Marilyn
S. McCauley, owner of McManage-
ment Group, an EVM consulting and
training firm in Dayton, Ohio. “If I see
[perfect scores] every time, someone’s
cooking the books, because that’s not
reality.”
The point of EVM, she says, is “to
see how close we are against what we
planned, and when we’re not close,
to ask, ‘Why aren’t we there, and
what are we doing about it?'”
This is where EVM offers much
of its value. If project managers and
their executives can see early on that
projects are falling behind schedule
or going over budget, they can make
key decisions about how to proceed,
rather than reacting to problems after
the fact.
“What earned value does is provide
you navigational tools early to let you
look ahead to see where you’ll be if you
do nothing,” Nevison says.
Early Warning
Earned value calculations can be done
at various points during a project, but
the numbers tend to stabilize when
you’re about 20% through, says Quen-
tin W. Eleming, co-author of Earned
Value Project Management (Project
Management Institute, 2006) and a
management instructor at the Univer-
sity of California, Irvine.
“So the point is, if you’re 20%
through the project, you can predict
what the final costs are going to be,
plus or minus 10%,” Fleming says. “It’s
a very powerful tool, and here’s what’s
powerful: If you’re 20% through a proj-
ect and you’ve heen authorized $1 mil-
lion, and your cost efficiency to date
suggests you’re going to need $2 mil-
lion to finish the project, then manage-
ment has decisions [to make].”
An EVM Primer
Earned value management is
based on several figures that
are used to calculate a project’s
progress. Vou can measure in
dollars or time.
Planned value (PV): This is the
value of all resources needed to do
the work to meet the project’s ob-
jective. Although most project man-
agers calculate PV in dollar terms,
some calculate it in terms of time
– the number ot hours it’s expected
io take to complete the project.
Let’s take a very basic example.
We’ve budgeted $200 to buy, set
up, network and test a new system.
We’ve budgeted $50, $75, $50
and $25, respectively, in materials,
labor and other costs for those four
phases.
Keep in mind, though, that the
$50 set aside to buy the system
doesn’t just cover the cost of the
actual hardware and software. It
also takes into account the value of
time that will be required to find the
right system, the time that will be
needed to fill out the purchase or-
ders, the time it will take to actually
buy the system and so on.
“The basis for earned value
management is worked performed,
not money spent,” says Marilyn S.
McCauley, owner of McManage-
ment Group, an EVM consulting
and training firm. Our PVs are $50,
$75, S50 and $25.
Budgeted (cost) at completion
(BAC): This is the sum of all PVs
– the total for all phases. In our
example, BAC is S200.
Earned value (EV): As our team
completes portions of the planned
work, we check off that work
and the amount of money (or
time) it should have taken to do
it according to the project plan.
Project managers caiculate EV at
predetermined times based on the
plan, typically at the end of the
company’s accounting period.
McCauley says.
We’ve completed Phase 1 – buy-
ing the system – within the planned
time frame. Check that off as done.
Our EV is S50.
Actual cost (AC): This can also
be measured in dollars or time. In
a perfectly executed project, EV
and AC are the same. Bui in our
example, let’s say we actually used
S60 in resources to buy that sys-
tem. Our AC is S60.
Once you have these figures
– PV, BAC. EV and AC – you can
calculate other numbers that
tell you about your progress
on a project. Here are some of
those calculations:
Schedule performance index
(SPI):EV divided by PV for a
particular phase of a project. In our
example, that’s 50/50 = 1, a per-
fect score for Phase 1, indicating
that we’re on target for schedule.
“I said I’d do $50 worth of work,
and I did $50 worth of work,” Mc-
Cauley says.
Cost performance index (CPI):
EV divided by AC. For our project
that’s 50/60 = 0.83, indicating
that we’re underperforming for our
costs. “For every dollar I’m spend-
ing, I’m oniy getting 83 cents worth
of work,” McCauley explains.
In a perfect project, the answer
is 1. But most projects fall below
that because most projects miss
their targets.
Estimated (costs) at completion
(EAC): BAC divided by CPI. Tfie
answer is a forecast value in either
dollars or hours that indicates the
projected final project costs or
time. There are various formulas for
EAC, McCauley says, but this is one
of the easiest to use. In our exam-
ple, that’s 200/0.83 = 240.96. This
indicates that at the rate we’re go-
ing, the final cost will be $240.96
rather than our planned $200,
Schedule variance (SV): Sub-
tract PV from EV. In our example,
our earned value is $50 because
we’ve done the first of our four
phases: We bought the system.
The PV for that first phase was
actually $50, So 5 0 – 5 0 = 0,
That’s a perfect score, so we’re on
schedule.
Cost variance (CV): Subtract
AC from EV. In our exampie, that’s
50 • 60 = -10, indicating that we’ve
overspent by $10. If we were on
target, CV would be zero.
-MARY K.PRATT
www.computerworld.com MANAGEMENT April 3 , 2 0 0 6 COMPUTERWORLD 49
Despite EVM’s reputation for offer-
ing insight into project progress, many
IT executives aren’t yet embracing the
discipline, partly because the under-
pinnings that make it work aren’t in
place.
“The concept of earned value is
really elementary project management.
But the problem with many IT organi-
zations is that they don’t use rigorous
project management methodology,”
says Dan Gingras, a partner in the in-
formation technology leadership prac-
tice at Tatum LLC, a consulting firm in
Atlanta.
“In order to do earned value man-
agement, you have to have a good hud-
get,” he says. “In order to have a good
budget, you have to back up one step
further and follow a good project man-
agement methodology.”
Project managers and IT leaders
need to accurately define a project’s
scope and requirements, develop spe-
cific work packages and work break-
down structures, and then establish
a good hudget, says Gingras, who
also teaches technology strategy and
system design as an adjunct faculty
member at Boston University’s Metro-
politan College.
Moreover, Gingras and others say
that employing EVM in projects takes
plenty of training. There are books
and multiday courses that teach the
practice.
So, why go through all this upfront
work? Gingras points to a well-known
fact: “Significant numhers of projects
aren’t completed on time or on budget,
or they don’t deliver what they’re sup-
posed to deliver.”
EVM can help improve your chances
of project success, says McGauley.
“The idea hehind earned value is see-
ing what you need and when you need
it. It’s all about management, and it’s all
ahout control.” •
Pratt is a Computerworld contributing
writer in Waltham, Mass. Contact her at
marykpratt@verizon.net.
Whos Driving
The EVM Bandwagon?
Earned value management is beginning
to catch on, says Quentin W. Flaming,
a management instructor at the Uni-
versity of California, Irvine, but many
in IT resist it because it would require
changes in how they set up and manage
projects. For example, IT shops would
have to thoroughly define, scope and
budget their projects in advance rather
than employ incremental development,
as many currently do, Fleming says.
Despite this reluctance, CtOs may
find CEOs and CFOs asking them to use
EVM as a way to bring more transpar-
ency to projects, says Robert Leto,
director of the IT effectiveness practice
at PricewaterhiHiseCoopers Advisory
Services. “Will the (T community em-
brace it? t don’t know if they will, or if
they’ll be mandated by the boards or
the CFOs,” he says.
Pressure to use EVM in IT is also
coming from the federal govemment.
Marilyn S. McCauley, owner of EVM
consulting and training firm McManage-
ment Group, says the Sarbanes-Oxley
Act’s requirements for greater financial
transparency are becoming a driver for
EVM. And the president’s hscal 2 0 0 7
budget calls for IT departments at more
government agencies and organizations
to apply EVM.
“It’s becoming a requirement in IT
industries that deal with the govern-
ment,” says McCautey. And that, she
says, wilt have a ripple effect that could
spread well beyond federal departments
and contractors.
Using EVM In IT, McCauley says,
“is not a matter of if; it’s a matter of
when.”
– MARY K. PRATT
IT supports and controls the
applications that run the business.
Now there’s an application to support
and control the business of IT.
Maximo” ITSM, the most comprehensive IT asset and service
management solution, substantially improves the business of IT,
significantly increasing the value IT brings to an organization. By
unifying IT service, asset and work management on a single
software platform, Maximo ITSM delivers the control and visibility
you need to align IT service levels with your overall business goals.
All you need to integrate and automate processes, reduce unplanned
outages, standardize and share information and surpass service-level
commitments. To make your IT organization more efficient and
more valuable, download our whitepaper at www.maximoit.cDm/cw
or call 800-326-5765.
C O U N T E D C O N T R O L L E D M A X I M I Z E D
mro software
m a k e i t . 1 / / c o u n t
©2005. MRO Software. Inc. All rights res
tradernarli and MRO Software is a trader
rved, Maximo is a registered
ark of MRO Software, Inc.
Turn in your highest-quality paper
Get a qualified writer to help you with
“ Project Execution 2 ”
Get high-quality paper
Guarantee! All work is written by expert writers!