Programming Question

COMP 4356Software Project Management
Midterm Exam
10/17/2022
Time: 90 minutes
Name: __________________________ Grade: ___________________________
Make sure that you have THREE questions:
Question
1
2
3
Neat Work
Est. Time
25 min.
05 min.
20 min.
Weight
20 points
20 points
35 points
05 points
Grade
Notes
Total Points: 30 points
Total Estimated Time: 85 minutes + 5 minutes to upload
your exam to the portal
This test is worth 20% of your final course grade.
This test is an open-book exam. You are allowed to use your PC, Mobile, or any
other communication devices.
Good Luck!!!!
Consider the following Network Diagram
I.
Schedule Table
Fill in the following table by calculating the ES, EF, LS, and LF times (if the required
completion time is 60 days) and the slack for each activity in the figure below.
Responsibility
Activity
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Estim.
Duration
Earliest
start
Finish
Latest
start
Total
Finish Slack
II.
Critical Path
Find the critical path and its estimated duration.
III.
Updated Schedule Table
Refill the schedule table if the actual finish or task1 is 4, task2 is 4, task3 is 6, task4 is 9,
task5 is 12, and task6 is 14.
Responsibility
Activity
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Estim.
Duration
Earliest
start
Finish
Latest
start
Finish
Total
Slack
Actual
Finish

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
Still stressed from student homework?
Get quality assistance from academic writers!

Order your essay today and save 25% with the discount code LAVENDER