FINANCE

 

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Option #1: Calculating Earned Value, Actual Cost, and Planned Value

Download and read the Module 3 Critical Thinking Assignment (option 1) file from the link at the bottom of the page. Then, in the document, complete the highlighted sections as directed. Refer to Chapter 15 from the Project Management text and Chapter 7 from the PMBOK® Guide for directions on how to calculate these financials. Follow the APA for the essay question writing portions of the assignment.

Module

3

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Critical Thinking Assignment

Calculating BCWP

You are the sponsor for project XY. The project manager has provided you the following three status reports. The project started on

2

/

1

and it is now the end of the 4th week. For this assignment, complete this packet in its entirety to include all tables, blanks, and questions. Complete the file and submit as your completed assignment.

Percent: Completion Report

2/1

2/1

100

Completed

3

Activity

Date Started

Percent completed

Time to Complete (weeks)

AB

2/1

1

0

0

Completed

AC

60

2

AD

DE

Not started—delayed

n/a

3

BF

2/14

40

Project Planning Budget: Dollars Budgeted Per Week for Each Activity, Project Starting 2/1

Activity

AB

2,000

2,000

AC

4,000

4,000

AD

2,000

3,000

BF

2,000

3,000

4,000

3,000

3,000

2,500

2,500

DE

3,500

3,500

3,000

3,000

6,000

3,000

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

Total

$

2,000

6,000

3,000

4,000

5,000

20,000

2,500

7,500

15,000

CE

3,500

10,500

EF

Total:

7,000

9,000

8,500

9,500

11,500

10,000

6

4,500

Cost Summary

Budget Cost

Actual

(Over) / Under

AB

6,000

AC

4,000

15,000

2,500

AD

7,500

100

BF

2,000

2,000

4,500

DE

3,500

3,500

3,500

3,500

9,500

(200)

Week Ending

Cumulative to Date

Activity

Budget Cost

Actual

(Over) / Under

6,200

(200)

4,500

(500)

12,500

2,400

(2,400)

7,400

2,800

(800)

(2,500)

Total

9,700

34,000

30,600

3,400

It is now the end of Week 4 and you want to determine the status of the project using earned value management. Complete the table and earned value metrics below. Some of the information has already been entered for you.

Activity

AB

 

 

 

 

AC

60

 

 

 

 

AD

 

 

 

 

 

 

BF

 

 

 

 

 

CE

 

0

 

 

 

0

 

0

 

 

 

EF

0

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

% Complete

Planned Value (PV)

Earned Value (EV)

Actual Cost (AC)

Cost Variance

Schedule Variance

Total Budget

 

 6200

6000

12000

20000

7500

 6000

15000

0

2500

DE*

10500

3000

TOTAL

64500

* Note that activity DE has been delayed and does not impact the calculations.

Calculate each of the following:

Cost Variance ($) = EV – AC

Schedule Variance ($) = EV – PV

Schedule Variance (weeks) = Schedule Variance ($) / Average Weekly PV

Cost-at-Completion = (Rate of Spending x Total Budget) = ([AC / EV] * Total Budget)

CPI = EV / AC

SPI = EV / PV

Add your written analysis below by answering three questions:

1. What is the state of the project?

2. Which activity has had the most positive impact on the project?

3. Which activity has had the most negative impact on the project?

1

Still stressed from student homework?
Get quality assistance from academic writers!

Order your essay today and save 25% with the discount code LAVENDER