Figure 16.42 shows the BOMs for two products, A and B. Table 16.5 shows the MPS quantity start date for each one. Table 16.6 contains data from inventory records for items C, D, and E. There are no safety stock requirements for any of the items.
a. Determine the material requirements plan for items C, D, and E for the next 8 weeks.
b. What specific managerial actions are required in week 1?
c. Suppose that a very important customer places an emergency order for a quantity of product A. In order to satisfy this order, a new MPS of 200 units of product A is now required in week 5. Determine the changes to the material requirements plan if this order is accepted and note any problems that you detect.
figure 16.42
B
A
D (2)
E (1)
D (1)
E (2)
E (1)
D (1)
E (1)
C (2)
E (2)
>Sheet . ate
s
1 2 5 6 ategory
C D 1
Table 1
6
5
MPS Quantity Start
D
Date
Product
3
4
7
8
A
125
95
150
130
B
80
70
Table 16.6
Inventory Record Data
Data
C
E
Lot-sizing rule
L4L
POQ (P = 3)
FOQ = 800
Lead time
3 weeks
2 weeks
1 week
Scheduled receipts
200 (week 2)
None
800 (week 1)
Beginning Inventory
85
625
350