CST 650 University of Management and Technology CST 650 Agile and Iterative Project Management

CST 650. Agile and Iterative Project Management

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Assignment 2

1.Michelle Grancesos is the visionary CEO of Appliance Masters Toaster Co. While taking a shower, she has a breakthrough insight into a new concept of toaster that Appliance Masters should be developing. In Michelle’s view, the toaster can take advantage of new information technology and become the brains of the kitchen. Following are some features she envisions in the New Age Toaster:

? Voice recognition, so that it can understand spoken instructions

? Voice synthesizer, so that it can speak to user

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

? Toasts bread

  • ? Oven toasting capabilities to cook small items (e.g., hot dogs)
  • ? Command center, so that it controls all kitchen appliances – the oven, the dishwasher, the range, the garbage disposal, vents, and lights.

  • Using the Poor Man’s Hierarchy, prioritize the features that Michelle proposes to include in her New Age Toaster.
  • 2. In brainstorming features of a “new age” toaster at Appliance Masters, the five following features stood out. As a consequence of a market survey of 20 panelists, market researchers were able to develop “value scores” for each of the features. These are shown in parentheses and they add up to 1.00.

  • Voice recognition, so that it can understand spoken instructions (0.10)
  • Voice synthesizer, so that it can speak to user (0.15)

  • Toasts bread (0.50)
  • Oven toasting capabilities to cook small items (e.g., hot dogs) (0.20)

  • Command center, so that it controls all kitchen appliances – the oven, the dishwasher, the range, the garbage disposal, vents, and lights (0.05).
  • Create a Pareto diagram that reflects potential customer preferences for features. Which features should be contained in early versions of the toaster?

  • 3. A big challenge facing iterative projects is to estimate what work efforts should be undertaken in individual iterations. One approach to estimating work efforts per iteration is to start by creating a rough PERT/CPM chart that lays out your best understanding of what needs to be done on the project. It is important that the PERT/CPM chart show both tasks and resulting milestones, where milestones reflect executable code.
  • The PERT/CPM chart below shows task sequences and durations associated with a hypothetical project.Using the information contained in the PERT/CPM chart:

    a) Calculate the critical path;

    b) Calculate latest and earliest start dates for each task and milestone;

    c) Calculate float for each task.

  • Assuming the target length of an iteration is about 4 weeks (20 days if you ignore weekends), identify how you would organize the tasks by iteration. Assume you have all the resources you need. Explain how working with known resource constraints would affect how you carry out this exercise.
  • 1. 4. Exercise: Catching the 7:00 am Metroliner Train to New York

  • In order to make her 10:30 am client meeting in New York City, Marsha needs to catch the 7:00 am Metroliner train at Union Station in Washington, DC.When she arrives at the Union Station parking lot, it is 6:40 am, so she has 20 minutes before her train leaves.The trip from the parking lot to the ticket counter typically takes three minutes.Following is a list of things she hopes to do:
  • • Purchase tickets (min: 3 minutes, max: 8 minutes if there is a long line)
  • • Buy coffee and donuts (min: 1 minute, max: 4 minutes if there is a long line)
  • • Consume coffee and donuts at food court table (min: 4 minutes, max: 6 minutes) (The alternative is to consume the coffee and donuts on the train.)
  • • Buy newspaper (min: 1 min, max: 2 minutes)
  • • Board train at 6:50 am to be assured of locating a good seat

    • Browse through bookstore, where there is currently a fantastic sale on best sellers

    Question:How should Marsha schedule her time?

    Tutorial on Project Scheduling
    with PERT/CPM
    Page 1 of 36
    Tutorial on PERT/CPM
    Background
    Page 2 of 36
    Tutorial on PERT/CPM
    Introduction
    The best known planning tool in the project manager’s tool box is
    the PERT/CPM network diagram. This tutorial is designed to provide
    scheduling novices with a more detailed treatment of developing
    PERT/CPM charts than what is contained in the basic planning
    module.
    Page 3 of 36
    Tutorial on PERT/CPM
    What Is PERT/CPM?
    PERT was developed by the US Navy in 1957. It is an acronym that
    stands for Project Evaluation and Review Technique. It is a systems
    diagram that shows how project tasks should be sequenced.
    CPM was developed by DuPont Corporation in 1958. Conceptually,
    it is quite similar to PERT networks. Like PERT, it shows how
    project tasks should be sequenced.
    What we call PERT/CPM in this course has taken on the name
    precedence diagrams. Precedence diagrams are a hybrid of the
    PERT and CPM approaches. Use of precedence diagrams to
    schedule projects is called the precedence diagram method (PDM).
    Page 4 of 36
    Tutorial on PERT/CPM
    Tasks
    Tasks represent work effort of some sort. Examples of tasks include:
    Testing a piece of software code (working time task)
    Laying brick (working time task)
    Paint drying (elapsed time task)
    Note that the first two examples of tasks entail the application of
    people to carry out the work. If the people stop work (e.g., during
    lunch break, over weekends), the work does not get done. This type
    of task is called a working time task
    Note that in the third example, work is carried out passively. There is
    no application of physical effort by workers. This type of task is
    called an elapsed time task. It operates according to a 24/7
    schedule – paint will dry 24 hours a day, seven days a week.
    Page 5 of 36
    Tutorial on PERT/CPM
    Milestones
    Milestones are markers. Unlike tasks, they don’t reflect active or
    passive work effort.
    Milestones are usually set up to establish targets toward which we
    can direct work efforts. For example, “Design Phase Is Finished, 15
    October” may be a milestone indicating that a series of designrelated tasks should be completed by 15 October.
    Milestones are good for tracking work. As a project is carried out,
    project staff can check off the milestones they have achieved and
    report these accomplishments to senior managers.
    Page 6 of 36
    Tutorial on PERT/CPM
    Representing Tasks and Milestones
    on a PERT/CPM Chart
    Tasks
    Start
    Dig hole
    Pour
    concrete
    Milestone Markers
    Page 7 of 36
    Tutorial on PERT/CPM
    Concrete
    cure
    Excavation
    phase ended
    PERT/CPM Charts Are Systems Diagrams
    The development of PERT/CPM network charts was a consequence
    of advances in systems engineering in the 1950s. The use of flow
    charts became big at this time. Flow charts are diagrams that clearly
    illustrate processes.
    In the 1950s, engineers began asking how flow chart concepts could
    be applied to scheduling projects. Ultimately, this quest led to the
    development of PERT and CPM
    Page 8 of 36
    Tutorial on PERT/CPM
    Traditional Flowchart: Picnic Project
    Check weather
    Note that in this flow chart,
    the rectangular boxes
    represent processes (e.g.,
    “Prepare indoor activities”) and
    the diamond represents a
    decision that needs to be made
    (e.g., “Rain?”; if “Yes,” proceed
    down one path; if “No,”
    proceed down the other path).
    The terminator (i.e., “Hold
    picnic”) represents the end of
    the decision sequence. When
    properly constructed, flow
    charts like the one portrayed
    here give system developers
    the precise information they
    need to build solutions that
    meet the specifications.
    Yes
    Rain?
    No
    Prepare indoor
    activities
    Prepare outdoor
    activities
    Caterer sets
    up indoors
    Caterer sets
    up outdoors
    Hold picnic
    Page 9 of 36
    Tutorial on PERT/CPM
    Basic PERT/CPM Network Logic
    Good practice requires that
    all PERT/CPM charts start
    with a “Start” milestone
    Start
    Plan
    picnic
    “Get food” and “Get
    sports equipment” are
    carried out in parallel
    Good practice requires that
    all PERT/CPM charts end
    with an “End” milestone
    Get food
    Drive to
    site
    Get
    sports
    equip
    Page 10 of 36
    Tutorial on PERT/CPM
    Hold
    picnic
    End
    Differences between
    Flow Charts and PERT/CPM Charts
    Flow charts have conditional logic, e.g., “If it is raining, then do X. If
    it is not raining, then do Y.” PERT/CPM charts do not have
    conditional logic. The chart does not incorporate decision making.
    Flow charts allow you to go back to an earlier activity, e.g., “If fewer
    than 20 orders have been filled, then go back to step 3 and repeat
    the process.” PERT/CPM charts do not go back to earlier tasks.
    They move inexorably forward in time. If a given set of steps need to
    be repeated, these steps are laid out all over again in the chart.
    Page 11 of 36
    Tutorial on PERT/CPM
    Critical Path Concept
    Page 12 of 36
    Tutorial on PERT/CPM
    Identifying the Critical Path
    Wire
    house
    Start
    Lay
    foundation
    14 days
    Frame house
    20 days
    2 days
    Put up
    dry wall
    Install
    plumbing
    4 days
    End
    3 days
    Note that there are two paths in this PERT/CPM chart
    Upper path: Foundation → Frame → Wire → Dry wall
    Duration: 40 days
    Lower path: Foundation → Frame → Plumbing → Dry wall
    Duration: 41 days
    The path indicated by thick red arrows is called the critical path. It is the
    longest path in the network. As such, it defines the length of the project.
    In this case, the project is scheduled to last 41 days.
    Page 13 of 36
    Tutorial on PERT/CPM
    Task Durations May Depend
    on Number of Resources Used (1)
    In the previous example of a PERT/CPM chart, the duration of
    “Frame house” was listed as 20 days. Let’s say this duration is
    based on using 4 carpenters to do the job. The overall level of effort
    to do the job is defined as:
    LOE = duration x number of resources
    LOE = 20 days x 4 carpenters = 80 carpenter-days
    Level of effort is useful in computing task duration when we know
    how many resources can be applied to the task. For example, if we
    have only two carpenters available to frame the house
    Duration = 80 carpenter-days/2 carpenters = 40 days
    If we have eight carpenters,
    Duration = 80 carpenter-days/8 carpenters = 10 days
    Page 14 of 36
    Tutorial on PERT/CPM
    Task Durations May Depend
    on Number of Resources Used (2)
    In working with level of effort data, the trick, of course, is
    computing what the value is. The best way to compute level of
    effort is to follow the approach taken here. Let’s say that we
    usually work with teams of four carpenters, and that we find on a
    typical house building project it takes them 20 days to frame the
    house. Consequently, this one example tells us that the level of
    effort for framing a house is 80 carpenter-days of effort.
    In working with level of effort, you need to employ good sense.
    While saying that the house can be framed in twenty days with
    four carpenters or forty days with two carpenters sounds
    reasonable, it is silly to extend this logic to its extreme and to say
    that 160 carpenters can do the job in one day!
    Page 15 of 36
    Tutorial on PERT/CPM
    Importance of the Critical Path
    The critical path is called critical because it defines the length of the project.
    Any delays along the critical path can translate into delays in the project
    overall. For example, if it takes 5 days to install the plumbing instead of the
    scheduled 3 days, this can result in a two day schedule slippage.
    Note that the “Wire house” task is non-critical. The network shows that it is
    scheduled to take 2 days, while the parallel plumbing task (which is a critical
    path task) is scheduled to take 3 days. Consequently, “Wire house” has one
    day of float (also called slack by some schedulers). You can have a one day
    delay on this non-critical task without causing the project to slip its schedule.
    On large projects, you do not need to monitor progress on every path. The
    important thing is to monitor progress on the critical path.
    Page 16 of 36
    Tutorial on PERT/CPM
    Earliest Start, Latest Start, Float (Slack)
    Task A
    Task B
    3 days
    5 days
    Start
    Task C
    Task D
    8 days
    2 days
    Task E
    5 days
    End
    The critical path is the longest path. Add up the durations on different
    paths, and identify the longest path. In this case, the longest path is
    pictured in red. Its duration is 15 days. This means the project duration
    is scheduled to be 15 days.
    Page 17 of 36
    Tutorial on PERT/CPM
    Calculating Earliest Start
    ES = Day 0
    ES = Day 3
    Task A
    Task B
    3 days
    5 days
    Start
    Task E
    Task C
    Task D
    5 days
    8 days
    2 days
    ES = Day 10
    ES = Day 0
    ES = Day 8
    End
    To calculate the earliest time a task can begin, start at the left of the chart and work your way to
    the right. Add the duration of a newly encountered task to the total up to that point.
    Begin computing earliest start dates with the critical path. In the network above, the earliest Task C
    can begin is at time t = 0. If C takes 8 days to complete, the earliest Task D can begin is at time t =
    8. If D takes 2 days to complete, then the earliest Task E can begin is at time t = 10.
    On the top, non-critical path above, the earliest Task A can begin is at time t=0. If it takes 3 days to
    complete, then earliest Task B can begin is at t = 3. Note that we have already determined by our
    critical path computation that Task E begins at time t = 10.
    Page 18 of 36
    Tutorial on PERT/CPM
    Calculating Latest Start
    LS = 2 days
    LS = Day 5
    Task A
    Task B
    3 days
    5 days
    Start
    Task E
    Task C
    Task D
    5 days
    8 days
    2 days
    LS = Day 10
    LS = Day 0
    LS = Day 8
    End
    To calculate the latest time a task can begin, start at the right side of the chart and work your way to the subtracting
    durations, task by task.
    Note that calculating latest task dates for the critical path is easy, because on the critical path earliest starts and latest
    starts are the same (ES = LS) – there is no leeway.
    On the top, non-critical path above, the latest Task E can begin is 5 days before the project end. Since the project will
    last 15 days, LS for Task E is 10. The latest start for Task B is 5 days before the latest start of Task E, or 10 – 5, so LS
    = 5. Finally, the latest start for Task A is 3 days before the latest start of Task B, or 5-3, so LS = 2.
    Note that the latest start is sometimes called the “drop dead” date. If you begin later than the latest start date,
    then you can cause the project to encounter schedule slippage. For example, in the network diagram provided
    here, If Task B begins on Day 7 (two days later than Task B’s latest start date), this can cause a two day delay in
    the project overall. What was initially a non-critical path has now become critical.
    Page 19 of 36
    Tutorial on PERT/CPM
    Calculating Float (Also Called Slack)
    ES = Day 0
    ES = Day 3
    LS = Day 2
    LS = Day 5
    Float = 2
    Float = 2
    Task A
    Task B
    3 days
    5 days
    Start
    Float = LS – LE
    Task E
    Task C
    Task D
    5 days
    8 days
    2 days
    ES = Day 10
    ES = Day 0
    ES = Day 8
    LS = Day 10
    LS = Day 0
    LS = Day 8
    Float = 0
    Float = 0
    Float = 0
    End
    Float measures scheduling leeway
    for a task. Note that critical path
    tasks have zero float – there is no
    leeway!
    In a sense, float is a measure of forgiveness. For example, Task A has 2 days of float associated with it. I can begin
    Task A a day late, and this will not affect the project schedule. However, if I begin it three days late, this can
    contribute to a slip of the overall schedule.
    Critical path tasks are unforgiving. This is indicated by the fact that each of them has zero float. If you begin a
    critical path task even a little late, this translates into overall schedule slippage. The idea that there is no
    forgiveness on the critical path is a common sense one. Remember, the critical path defines project length. So if
    there is even a small delay on any of the critical path tasks, this can extend the project schedule.
    Page 20 of 36
    Tutorial on PERT/CPM
    Hard Logic and Soft Logic
    Page 21 of 36
    Tutorial on PERT/CPM
    Not All Precedence Links Are Equal
    Non-critical path
    Hard logic link: Pour coffee
    must follow Fix coffee
    Start
    Fix Coffee
    Pour Coffee
    8 minutes
    2 minutes
    Fix Cereal
    Make Toast
    6 minutes
    6 minutes
    Duration = 10 min
    Float = 2 min
    End
    Critical path
    Duration = 12 min
    Soft logic link: It doesn’t
    matter which of these two
    tasks is predecessor and
    which is successor
    With hard logic links, tasks must occur in a prescribed sequence. These links cannot be
    broken. With soft logic links, the sequence is immaterial. These links can be broken.
    Page 22 of 36
    Tutorial on PERT/CPM
    Soft Logic Links Can Be Broken
    Start
    Fix Coffee
    Pour Coffee
    8 minutes
    2 minutes
    End
    Fix Cereal
    6 minutes
    Make Toast
    6 minutes
    By breaking the soft logic link between “Fix Cereal” and “Make Toast,” I am
    able to reconfigure the network diagram to have these two tasks carried out
    in parallel. This has the effect of shortening the project duration, because
    the new critical path is the top path – it has a 10 minute duration. Two
    minutes have been shaved off duration! (See previous chart.)
    Page 23 of 36
    Tutorial on PERT/CPM
    Estimating Task Duration
    Page 24 of 36
    Tutorial on PERT/CPM
    Estimating Task Durations with PERT/CPM
    When PERT networks were first developed in the late 1950s, one of
    their distinguishing features was the way they estimated task
    duration. To compute the expected time [e(t)] of a task, they
    employed the following formula:
    e(t) = a + 4b + c , [where a = best case, b = typical case, and
    6
    c = worst case]
    Example:
    e(t) = 40 + 4×43 + 47 , [where a = 40 hrs, b= 44 hrs, c = 47 hrs]
    6
    = 44.33 hours
    Page 25 of 36
    Tutorial on PERT/CPM
    Estimating Standard Deviation for Task Durations
    Standard deviation is an indicator of the “slop” of a measure. A
    measure that is right on target has a low standard deviation. The
    rougher the measure, the greater its standard deviation.
    The inventors of PERT developed a simple formula that provides an
    approximation of the standard deviation (SD) associated with the
    estimate of the expected duration of a task:
    SD(t) = c – a , where c = worst case, a = best case
    6
    Example: If c = 47 hrs and a = 43 hrs, SD(t) = 0.67 hrs
    Page 26 of 36
    Tutorial on PERT/CPM
    Using Expected Duration with Its
    Standard Deviation (1)
    In the previous examples, we have
    e(t) = 44.33 and SD(t) = 0.67
    Combining the two pieces of information we report that:
    e(t) = 44.33 +/- 0.67 hours
    That is, we have reason to believe that the true amount of time it will
    take to carry out the target task lies somewhere between 43.67
    hours and 45.00 hours. We know from our understanding of the
    normal distribution that about 68% of observations lie within +/- 1
    standard deviation from the mean. Very roughly, we have a sense
    that two-thirds of the time, the amount of time it will take to carry out
    our task lies within the range of 43.67 and 45.00 hours.
    Page 27 of 36
    Tutorial on PERT/CPM
    Using Expected Duration with Its
    Standard Deviation (2)
    Note, that we have to be very careful when talking about assuming that deductions arising from
    the normal distribution apply to the Beta distribution (the (a + 4b +c)/6 formula we are using here
    provides an estimate of the mean of the Beta distribution). Clearly, the normal distribution is
    symmetric about the mean, while the Beta distribution is skewed. Still, it turns out that about twothirds of the observations on a typically encountered Beta distribution (such as presented in this
    example) lie within a range slightly larger than +/- 1 standard deviation from the mean, so the 1
    standard deviation rule for normal distributions roughly applies to the Beta distribution. However,
    the 2 standard deviation scenarios differ significantly between the normal and Beta distributions.
    For the normal distribution, roughly 95 percent of the observations lie within +/- 2 standard
    deviations from the mean. However, with the Beta distribution 95% of the observations lie in the
    following range: μ – 1.5 x (c – a)/6 and μ + 1.95 x (c – a)/6, where μ is a measure of the mean.
    Thus in the present case, we estimate that 95% of the time, the actual amount of time it will take
    to carry out the task being examined lies in the range 43.3 hours and 45.6 hours.
    For a typical Beta distribution – as reflected in the data presented in this example – about 70% of
    the observations lie at 0.82.
    Page 28 of 36
    Tutorial on PERT/CPM
    Estimating the Duration of the Critical Path (1)
    To estimate the duration of the critical path, merely add up the
    duration of the individual tasks that lie on the critical path.
    To estimate the standard deviation of the critical path, carry out the
    following computation:
    SDPath = SQRT(SD12 + SD22 + SD32 + … + SDi2) for i tasks on the
    path.
    Page 29 of 36
    Tutorial on PERT/CPM
    Estimating the Duration of the Critical Path (2)
    Note: The units of analysis in this table are hours.
    Task
    A
    B
    C
    D
    E
    Best case
    3
    12
    6
    10
    2
    Most typical Worst case
    4
    15
    8
    13
    4
    7
    18
    12
    18
    6
    Duration =
    Expected
    duration
    Standard
    deviation
    4.33
    0.67
    15.00
    1.00
    8.33
    1.00
    13.33
    1.33
    4.00
    0.67
    45.00 SD Sqrd =
    SD =
    Duration of path = 45 hours +/- 2.16 hours
    SD Squared
    0.44
    1.00
    1.00
    1.78
    0.44
    4.67
    2.16
    In this example, Tasks A, B, C, D, and E comprise the critical path. For each task, we compute expected duration
    based on our assessment of the best case, most typical case, and worst case (using the Beta distribution). By
    adding up these numbers, we get the expected duration of the critical path (45). Given this data, we are also able
    to estimate the standard deviation associated with the duration of each task. By squaring these values and
    summing them, we get the sum of 4.67 (which in statistics is called variance). Standard deviation is the square root
    of variance, so in this example it is 2.16. Thus we estimate that the critical path will consume 45 hours of effort,
    plus or minus 2.16 hours. As a rough rule of thumb, about two-thirds of our observations lie within one standard
    deviation from the mean, so we are saying that there is a about a 30-35% chance of the true value lying outside
    the specified range.
    Page 30 of 36
    Tutorial on PERT/CPM
    The Need to Estimate a Range of Duration Times
    Up until now, all of our estimates of task duration have been point
    estimates. That is, we use a single value of duration. In reality, we
    know that these estimates are likely to be wrong. When we say it
    takes 1.2 days to test a software algorithm, we don’t seriously
    expect it to take exactly 1.2 days. We figure it will take 1.2 days, plus
    or minus some segment of time.
    In statistics, the “plus or minus” factor is determined by a measure
    called standard deviation (SD). By calculating SD for a task, you
    have a better idea of how much faster or slower the task will be than
    what you speculate with your point estimate.
    Page 31 of 36
    Tutorial on PERT/CPM
    Practical Steps in Building a PERT/CPM Chart
    Page 32 of 36
    Tutorial on PERT/CPM
    Step 1. Draw a Logic Diagram by Hand
    Sometimes you see project workers trying to develop a PERT/CPM
    chart by working directly with a scheduling software package.
    Generally, this is an ineffective way to begin. The computer screen
    is limited in size and only lets you see a handful of tasks at one time.
    Seasoned professionals always begin by drawing the logic relations
    of tasks by hand on large sheets of paper or on large white boards
    mounted onto a wall. This way they can work with big chunks of the
    project and perhaps even see the whole project at one time.
    Page 33 of 36
    Tutorial on PERT/CPM
    Step 2. Build a PERT/CPM Chart
    Based on Your Hand Drawn Chart
    If you are using computer software, now is the time to build a
    PERT/CPM network on the computer, using the large hand drawn
    chart as your guide. As you build the chart, enter task duration data.
    If you are building a PERT/CPM network by hand, copy your large
    rough chart, and enter task duration figures into each box that
    represents a task.
    Page 34 of 36
    Tutorial on PERT/CPM
    Step 3. Identify the Critical Path
    On a computerized scheduling package, once the scheduling data
    are entered into the system, the critical path will be identified
    automatically. It is usually pictured as a red path.,
    If you have created a PERT/CPM network manually, look at all the
    paths that run through the network and find the one that is longest.
    This is the critical path. Color it red.
    Page 35 of 36
    Tutorial on PERT/CPM
    Dealing with Weekends, Holidays, and Such
    Computerized scheduling packages can deal with weekends,
    holidays, and such automatically. Each of these packages contains
    a central calendar, where you can define what days are weekend
    days (in Muslim countries, you set weekends for Friday and
    Saturday), what days are holidays (e.g., you can set New Years Day
    as a holiday). Beyond this, with computerized scheduling packages
    you can identify elapsed time activities (e.g., paint drying, concrete
    curing), so that these activities are carried out according to a 24/7
    calendar. That is, if you set “Paint dry” as an elapsed time activity,
    the software will schedule it to dry on weekends (when appropriate)
    as well as weekdays.
    When you create PERT/CPM networks by hand, you need to track
    weekends, holidays, and elapsed time tasks manually.
    Page 36 of 36
    Tutorial on PERT/CPM

    Still stressed from student homework?
    Get quality assistance from academic writers!

    Order your essay today and save 25% with the discount code LAVENDER