Tanner Furniture Company concluded its FIRST year of operations in

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

    

which it made sales of $1,500,000, ALL on installment. Collections

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

     during the year from down payments and installments totaled

     $600,000.  Purchases for the year totaled $900,000; the cost of

     merchandise on hand at the end of the year was $180,000.

    

     INSTRUCTIONS

     Using the installment-sales method, make summary entries to record:

     (a) the installment sales and cash collections;

     (b) the cost of installment sales;

     (c) the unrealized gross profit;

     (d) the realized gross profit.

6. On February 1, 2003, Miley Contractors agreed to construct a

     building at a contract price of $5,600,000. Miley estimated total

     construction costs would be $4,000,000 and the project would be

     finished in 2005. Information relating to the costs and billings for

     this contract is as follows:

                                  2003      2004         2005

                      ——————————  ————   ————

     Total costs incurred to date   $1,500,000   $2,640,000   $4,600,000

     Estimated costs

to complete   2,500,000    1,760,000       -0-

     Customer billings to date     2,200,000    4,000,000    5,600,000

     Collections to date          2,000,000    3,500,000    5,500,000

          INSTRUCTIONS

     Fill in the correct amounts on the following schedule. For

     percentage-of-completion accounting and for completed-contract

     accounting, show the gross profit that should be recorded for 2003,

     2004, and 2005.

    

           Percentage-of-Completion                  Completed-Contract

 ——————————————————      ———————————————

                 Gross Profit                           Gross Profit

                 ————————————      ————————————

        2003     ____________                   2003    ____________

    

        2004     ____________                   2004    ____________

    

        2005     ____________                   2005    ____________

 

                       ————————-

Section 3.Problems

 

 7. Cherry Construction specializes in the construction of commercial

     and industrial buildings.  The contractor is experienced in bidding

     long-term construction projects of this type, with the typical

     project lasting fifteen to twenty-four months.  The contractor uses

     the percentage-of-completion method of revenue recognition since,

     given the characteristics of the contractor’s business and con-

     tracts, it is the most appropriate method.  Progress toward comple-

     tion is measured on a cost to cost basis.  Cherry began work on a

     lump-sum contract at the beginning of 2004.  As bid, the statistics

     were as follows:

    

     Lump-sum price (contract price)                           $4,000,000

     Estimated costs

        Labor                                $  850,000

        Materials and subcontractor                1,750,000

        Indirect costs                             400,000     3,000,000

                                        ————————  ——————

                                                          $1,000,000

                                                              

     At the end of the first year, the following was the status of the contract:

    

     Billings to date                                        $2,230,000

     Costs incurred to date

        Labor                                $  414,000

        Materials and subcontractor                1,098,000

        Indirect costs                            150,000    1,662,000

                                                   ————————

     Latest forecast total cost                                 3,000,000

    

     It should be noted that included in the above costs incurred to date

     were standard electrical and mechanical materials stored on the job

     site, but not yet installed, costing $102,000.  These costs should

     not be considered in the costs incurred to date.

          INSTRUCTIONS

     (a) Compute the percentage of completion on the contract at the end

         of 2004.

     (b) Indicate the amount of gross profit that would be reported on

         this contract at the end of 2004.

     (c) Make the journal entry to record the income (loss) for 2004 on

         Cherry’s books.

     (d) Indicate the account(s) and the amount(s) that would be shown on

         the balance sheet of Cherry Construction at the end of 2004

         related to its construction accounts.  Also indicate where these

         items would be classified on the balance sheet.  Billings

         collected during the year amounted to $1,960,000.

     (e) Assume the latest forecast on total costs at the end of 2004 was

         $4,100,000.  How much income (loss) would Cherry report for

         the year 2004?

  