Project management

 

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Using the idea of your chosen project, and Table 3-7 on page 98 of your book, choose five areas to develop further by defining an additional Planning Process under a Knowledge Area or an additional Output under a specific Planning Process.  For example I may choose to add (or change) ‘Collect Requirements’ under Project Scope Management to ‘Schedule Requirement Interviews’ and then make the Requirements Documentation and Traceability matrix subservient to that. Potentially you could also add and additional column to Table 3-7 between ‘Planning Process’ and ‘Outputs’ and discuss and Activities that would take place to accomplish those outputs.

Your work should be handed in as either a Word or Excel document.

 

Briefly describe what happens in each of the five project management process groups. What types of activities will occur in each of the groups for your project?

I N F O R M AT I O N T E C H N O L O G Y
P R O J E C T M A N A G E M E N T
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Kathy Schwalbe, Ph.D., PMP
Professor Emeritus, Augsburg College
I N F O R M AT I O N T E C H N O L O G Y
P R O J E C T M A N A G E M E N T
Eighth Edition
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

This is an electronic version of the print textbook. Due to electronic rights restrictions,
some third party content may be suppressed. Editorial review has deemed that any suppressed
content does not materially affect the overall learning experience. The publisher reserves the right
to remove content from this title at any time if subsequent rights restrictions require it. For
valuable information on pricing, previous editions, changes to current editions, and alternate
formats, please visit www.cengage.com/highered to search by ISBN#, author, title, or keyword for
materials in your areas of interest.
portant otice e ia content reference ithin the pro ct escription or the pro ct
te t a not e availa le in the e oo version
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

© 2016 Cengage Learning
ALL RIGHTS RESERVED. No part of this work covered by the copyright
herein may be reproduced, transmitted, stored, or used in any form or by
any means—graphic, electronic, or mechanical, including but not limited
to photocopying, recording, scanning, digitizing, taping, web distribution,
information networks, or information storage and retrieval systems, except
as permitted under Section 107 or 108 of the 1976 United States Copyright
Act—without the prior written permission of the publisher.
Library of Congress Control Number: 2015950371
Student Edition:
ISBN-13: 978-1-285-45234-0
Cengage Learning
20 Channel Center Street
Boston, MA 02210
USA
Screenshots for this book were created using Microsoft Project, and were used with permission
from Microsoft.
Microsoft and the Office logo are either registered trademarks or trademarks of Microsoft
Corporation in the United States and/or other countries. Cengage Learning is an independent
entity from the Microsoft Corporation, and not affiliated with Microsoft in any manner.
Screenshots from MindView Business software are used with permission from MatchWare.
iPhone, iPad, iPod, and MacBook are registered trademarks of Apple Inc.
Information pertaining to Northwest Airlines was used with their express permission. No part
of it may be reproduced or used in any form without prior written permission from Cengage
Learning
This publication is a derivative work of A Guide to the Project Management Body of Knowledge
(PMBOK® Guide)—Fifth Edition, which is copyrighted material of and owned by Project Manage-
ment Institute, Inc. (PMI), Copyright 2013. This publication has been developed and reproduced
with the permission of PMI. Unauthorized reproduction of this material is strictly prohibited. The
derivative work is the copyrighted material of and owned by Cengage Learning, Copyright 2016.
PMI, PMP, CAPM, PgMP, PMI-RMP, PMI-ACP, PMI-SP, OPM3, and PMBOK are registered marks of
the Project Management Institute, Inc.
Cengage Learning reserves the right to revise this publication and make changes from time to
time in its content without notice.
Cengage Learning is a leading provider of customized learning solutions with office
locations around the globe, including Singapore, the United Kingdom, Australia, Mexico,
Brazil, and Japan. Locate your local office at: www.cengage.com/global
Cengage Learning products are represented in Canada by Nelson Education, Ltd.
To learn more about Cengage Learning, visit www.cengage.com
Purchase any of our products at your local college store or at our preferred online store:
www.cengagebrain.com
Information Technology Project
Management, Eighth Edition
Kathy Schwalbe
Product Director: Mike Schenk
Senior Product Manager/Team Lead:
Joe Sabatino
Content Development Manager:
Jennifer King
Content Developer: Anne Merrill
Product Assistant: Adele Scholtz
Intellectual Property Analyst:
Christina Ciaramella
Senior Intellectual Property Manager:
Kathryn Kucharek
Marketing Manager: Eric La Scola
Manufacturing Planner: Ron Montgomery
Art and Cover Direction, Production
Management, and Composition:
Lumina Datamatics, Inc.
Cover Images:
©everything possible/shutterstock.com
(man looking at a network structure)
©Stuart Jenner/shutterstock.com (back view
of group of people)
For product information and technology assistance, contact
Cengage Learning Customer & Sales Support, 1-800-354-9706.
For permission to use material from this text or product,
submit all requests online at cengage.com/permissions
Further permissions questions can be e-mailed to
permissionrequest@cengage.com
Printed in the United States of America
Print Number: 01 Print Year: 2015
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
WCN: 02-200-203

For Dan, Anne, Bobby, and Scott
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Preface xix
Chapter 1
Introduction to Project Management 1
Chapter 2
The Project Management and Information Technology Context 43
Chapter 3
The Project Management Process Groups: A Case Study 79
Chapter  4
Project Integration Management 137
Chapter 5
Project Scope Management 183
Chapter 6
Project Time Management 221
Chapter 7
Project Cost Management 263
Chapter 8
Project Quality Management 299
Chapter 9
Project Human Resource Management 343
Chapter 10
Project Communications Management 389
Chapter11
Project Risk Management 425
BRIEF CONTENTS
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Brief Contentsviii
Chapter 12
Project Procurement Management 465
Chapter 13
Project Stakeholder Management 495
Appendix A
Guide to Using Microsoft Project 2010 A.1
Glossary G.1
Index I.1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Preface xix
Chapter 1 Introduction to Project Management 1
1.1 Introduction 2
1.2 What Is a Project? 4
1.2a Examples of IT Projects 4
1.2b Project Attributes 6
1.2c Project Constraints 7
1.3 What Is Project Management? 9
1.3a Project Stakeholders 10
1.3b Project Management Knowledge Areas 11
1.3c Project Management Tools and Techniques 12
1.3d Project Success 15
1.4 Program and Project Portfolio Management 17
1.4a Programs 17
1.4b Project Portfolio Management 18
1.5 The Role of the Project Manager 22
1.5a Project Manager Job Description 22
1.5b Suggested Skills for Project Managers 23
1.5c Importance of People Skills and Leadership Skills 25
1.5d Careers for IT Project Managers 27
1.6 The Project Management Profession 28
1.6a History of Project Management 28
1.6b The Project Management Institute 32
1.6c Project Management Certification 33
1.6d Ethics in Project Management 34
1.6e Project Management Software 35
Chapter Summary 37
Quick Quiz 37
Quick Quiz Answers 39
Discussion Questions 39
Exercises 40
Key Terms 41
End Notes 41
Chapter 2 The Project Management and Information Technology Context 43
2.1 A Systems View of Project Management 45
2.1a What Is a Systems Approach? 45
2.1b The Three-Sphere Model for Systems Management 46
TABLE OF CONTENTS
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Table of Contentsx
2.2 Understanding Organizations 47
2.2a The Four Frames of Organizations 47
2.2b Organizational Structures 49
2.2c Organizational Culture 51
2.3 Focusing on Stakeholder Needs 52
2.3a The Importance of Top Management Commitment 54
2.3b The Need for Organizational Commitment to Information Technology 55
2.3c The Need for Organizational Standards 56
2.4 Project Phases and the Project Life Cycle 57
2.4a Product Life Cycles 59
2.4b The Importance of Project Phases and Management Reviews 62
2.5 The Context of Information Technology Projects 64
2.5a The Nature of IT Projects 64
2.5b Characteristics of IT Project Team Members 64
2.5c Diverse Technologies 65
2.6 Recent Trends Affecting Information Technology Project Management 65
2.6a Globalization 65
2.6b Outsourcing 66
2.6c Virtual Teams 67
2.6d Agile Project Management 69
2.6e The Manifesto for Agile Software Development 69
2.6f Scrum 70
2.6g Agile, the PMBOK® Guide, and a New Certification 71
Chapter Summary 73
Quick Quiz 74
Quick Quiz Answers 75
Discussion Questions 75
Exercises 76
Key Terms 77
End Notes 77
Chapter 3 The Project Management Process Groups: A Case Study 79
3.1 Project Management Process Groups 80
3.2 Mapping the Process Groups to the Knowledge Areas 85
3.3 Developing an It Project Management Methodology 86
3.4 Case Study 1: JWD Consulting’s Project Management Intranet Site Project
(Predictive Approach) 89
3.4a Project Pre-Initiation and Initiation 89
3.4b Pre-Initiation Tasks 90
3.4c Initiating 93
3.4d Project Planning 98
3.4e Project Execution 107
3.4f Project Monitoring and Controlling 111
3.4g Project Closing 114
3.5 Case Study 2: JWD Consulting’s Project Management Intranet Site Project
(Agile Approach) 117
3.5a Scrum Roles, Artifacts, and Ceremonies 118
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Table of Contents xi
3.5b Project Pre-Initiation and Initiation 121
3.5c Planning 122
3.5d Executing 124
3.5e Monitoring and Controlling 124
3.5f Closing 126
3.6 Templates by Process Group 126
Chapter Summary 130
Quick Quiz 130
Quick Quiz Answers 132
Discussion Questions 132
Exercises 133
Key Terms 134
End Notes 134
Chapter 4 Project Integration Management 137
4.1 What is Project Integration Management? 138
4.2 Strategic Planning and Project Selection 141
4.2a Strategic Planning 141
4.2b Identifying Potential Projects 143
4.2c Aligning IT with Business Strategy 144
4.3 Methods for Selecting Projects 146
4.3a Focusing on Broad Organizational Needs 146
4.3b Categorizing IT Projects 146
4.3c Performing Financial Analyses 147
4.3d Using a Weighted Scoring Model 152
4.3e Implementing a Balanced Scorecard 154
4.4 Developing a Project Charter 155
4.5 Developing a Project Management Plan 158
4.5a Project Management Plan Contents 158
4.5b Using Guidelines to Create Project Management Plans 161
4.6 Directing and Managing Project Work 162
4.6a Coordinating Planning and Execution 163
4.6b Providing Strong Leadership and a Supportive Culture 163
4.6c Capitalizing on Product, Business, and Application Area Knowledge 164
4.6d Project Execution Tools and Techniques 165
4.7 Monitoring and Controlling Project Work 166
4.8 Performing Integrated Change Control 168
4.8a Change Control on IT Projects 169
4.8b Change Control System 169
4.9 Closing Projects or Phases 172
4.10 Using Software to Assist in Project Integration Management 172
Chapter Summary 175
Quick Quiz 175
Quick Quiz Answers 177
Discussion Questions 177
Exercises 177
Running Case 178
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Table of Contentsxii
Tasks 180
Key Terms 180
End Notes 181
Chapter 5 Project Scope Management 183
5.1 What Is Project Scope Management? 184
5.2 Planning Scope Management 186
5.3 Collecting Requirements 188
5.4 Defining Scope 191
5.5 Creating the Work Breakdown Structure 194
5.5a Approaches to Developing Work Breakdown Structures 199
5.5b The WBS Dictionary 203
5.5c Advice for Creating a WBS and WBS Dictionary 204
5.6 Validating Scope 205
5.7 Controlling Scope 207
5.7a Suggestions for Improving User Input 208
5.7b Suggestions for Reducing Incomplete and Changing Requirements 209
5.8 Using Software to Assist in Project Scope Management 210
Chapter Summary 212
Quick Quiz 212
Quick Quiz Answers 214
Discussion Questions 214
Exercises 214
Running Case 216
Tasks 217
End Notes 218
Chapter 6 Project Time Management 221
6.1 The Importance of Project Schedules 222
6.2 Planning Schedule Management 225
6.3 Defining Activities 225
6.4 Sequencing Activities 228
6.4a Dependencies 228
6.4b Network Diagrams 229
6.5 Estimating Activity Resources 232
6.6 Estimating Activity Durations 233
6.7 Developing the Schedule 234
6.7a Gantt Charts 234
6.7b Adding Milestones to Gantt Charts 236
6.7c Using Tracking Gantt Charts to Compare Planned and Actual Dates 237
6.7d Critical Path Method 238
6.7e Calculating the Critical Path 239
6.7f Growing Grass Can Be on the Critical Path 240
6.7g Using Critical Path Analysis to Make Schedule Trade-Offs 240
6.7h Using the Critical Path to Shorten a Project Schedule 242
6.7i Importance of Updating Critical Path Data 243
6.7j Critical Chain Scheduling 243
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Table of Contents xiii
6.7k Program Evaluation and Review Technique (PERT) 247
6.7l Agile and Time Management 248
6.8 Controlling the Schedule 248
6.8a Reality Checks on Scheduling and the Need for Discipline 249
6.9 Using Software to Assist in Project Time Management 250
Words of Caution on Using Project Management Software 251
Chapter Summary 253
Quick Quiz 254
Quick Quiz Answers 256
Discussion Questions 256
Exercises 256
Running Case 259
Tasks 259
Key Terms 259
End Notes 260
Chapter 7 Project Cost Management 263
7.1 The Importance of Project Cost Management 264
7.1a What Is Cost? 265
7.1b What Is Project Cost Management? 266
7.2 Basic Principles of Cost Management 266
7.3 Planning Cost Management 270
7.4 Estimating Costs 271
7.4a Types of Cost Estimates 271
7.4b Cost Estimation Tools and Techniques 273
7.4c Typical Problems with IT Cost Estimates 274
7.4d How to Develop a Cost Estimate 275
7.5 Determining the Budget 281
7.6 Controlling Costs 282
7.6a Earned Value Management 282
7.6b Project Portfolio Management 288
7.7 Using Project Management Software to Assist in Project Cost Management 289
Chapter Summary 291
Quick Quiz 291
Quick Quiz Answers 293
Discussion Questions 293
Exercises 294
Running Case 295
Tasks 295
Key Terms 297
End Notes 297
Chapter 8 Project Quality Management 299
8.1 The Importance of Project Quality Management 300
8.2 What Is Project Quality Management? 302
8.3 Planning Quality Management 304
8.4 Performing Quality Assurance 306
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Table of Contentsxiv
8.5 Controlling Quality 307
8.6 Tools and Techniques for Quality Control 308
8.6a Statistical Sampling 314
8.6b Six Sigma 315
8.6c Testing 320
8.7 Modern Quality Management 322
8.7a Deming and His 14 Points for Management 322
8.7b Juran and the Importance of Top Management Commitment to Quality 323
8.7c Crosby and Striving for Zero Defects 323
8.7d Ishikawa’s Guide to Quality Control 324
8.7e Taguchi and Robust Design Methods 324
8.7f Feigenbaum and Workers’ Responsibility for Quality 325
8.7g Malcolm Baldrige National Quality Award 325
8.7h ISO Standards 325
8.8 Improving It Project Quality 326
8.8a Leadership 326
8.8b The Cost of Quality 327
8.8c The Impact of Organizational Influences, and Workplace Factors on Quality 329
8.8d Expectations and Cultural Differences in Quality 329
8.8e Maturity Models 330
8.9 Using Software to Assist in Project Quality Management 333
Chapter Summary 334
Quick Quiz 334
Quick Quiz Answers 336
Discussion Questions 336
Exercises 337
Running Case 338
Tasks 338
Key Terms 338
End Notes 339
Chapter 9 Project Human Resource Management 343
9.1 The Importance of Human Resource Management 344
9.1a The Global IT Workforce 344
9.1b Implications for the Future of IT Human Resource Management 345
9.2 What is Project Human Resource Management? 347
9.3 Keys to Managing and Leading People 348
9.3a Motivation Theories 349
9.3b Influence and Power 353
9.3c Covey and Improving Effectiveness 355
9.3d Emotional Intelligence 357
9.3e Leadership 358
9.4 Developing the Human Resource Plan 359
9.4a Project Organizational Charts 360
9.4b Responsibility Assignment Matrices 362
9.4c Staffing Management Plans and Resource Histograms 363
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Table of Contents xv
9.5 Acquiring the Project Team 364
9.5a Resource Assignment 364
9.5b Resource Loading 366
9.5c Resource Leveling 367
9.6 Developing the Project Team 369
9.6a Training 370
9.6b Team-Building Activities 371
9.6c Reward and Recognition Systems 375
9.7 Managing the Project Team 375
9.7a Tools and Techniques for Managing Project Teams 376
9.7b General Advice on Managing Teams 378
9.8 Using Software to Assist in Human Resource Management 379
Chapter Summary 381
Quick Quiz 382
Quick Quiz Answers 384
Discussion Questions 384
Exercises 384
Running Case 385
Key Terms 386
End Notes 387
Chapter 10 Project Communications Management 389
10.1 The Importance of Project Communications Management 390
10.2 Keys to Good Communications 392
10.2a Focusing on Group and Individual Communication Needs 392
10.2b Formal and Informal Methods for Communicating 394
10.2c Distributing Important Information in an Effective and Timely Manner 395
10.2d Setting the Stage for Communicating Bad News 395
10.2e Determining the Number of Communication Channels 396
10.3 Planning Communications Management 398
10.4 Managing Communications 399
10.4a Using Technology to Enhance Information Creation and Distribution 400
10.4b Selecting the Appropriate Communication Methods and Media 401
10.4c Reporting Performance 403
10.5 Controlling Communications 404
10.6 Suggestions for Improving Project Communications 405
10.6a Developing Better Communication Skills 405
10.6b Running Effective Meetings 406
10.6c Using E-Mail, Instant Messaging, Texting, Kanban Boards, and
Collaborative Tools Effectively 408
10.6d Using Templates for Project Communications 411
10.7 Using Software to Assist in Project Communications 414
Chapter Summary 418
Quick Quiz 418
Quick Quiz Answers 420
Discussion Questions 420
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Table of Contentsxvi
Exercises 421
Running Case 422
Key Terms 422
End Notes 422
Chapter 11 Project Risk Management 425
11.1 The Importance of Project Risk Management 426
11.2 Planning Risk Management 433
11.3 Common Sources of Risk on IT Projects 434
11.4 Identifying Risks 438
11.4a Suggestions for Identifying Risks 439
11.4b The Risk Register 440
11.5 Performing Qualitative Risk Analysis 442
11.5a Using Probability/Impact Matrixes to Calculate Risk Factors 443
11.5b Top Ten Risk Item Tracking 444
11.6 Performing Quantitative Risk Analysis 447
11.6a Decision Trees and Expected Monetary Value 447
11.6b Simulation 449
11.6c Sensitivity Analysis 451
11.7 Planning Risk Responses 452
11.8 Controlling Risks 454
11.9 Using Software to Assist in Project Risk Management 455
Chapter Summary 457
Quick Quiz 458
Quick Quiz Answers 460
Discussion Questions 460
Exercises 460
Running Case 461
End Notes 463
Chapter 12 Project Procurement Management 465
12.1 The Importance of Project Procurement Management 466
12.2 Planning Procurement Management 471
12.2a Types of Contracts 471
12.2b Tools and Techniques for Planning Procurement Management 476
12.2c Procurement Management Plan 477
12.2d Statement of Work 478
12.2e Procurement Documents 478
12.2f Source Selection Criteria 481
12.3 Conducting Procurements 481
12.4 Controlling Procurements 483
12.5 Closing Procurements 484
12.6 Using Software to Assist in Project Procurement Management 485
Chapter Summary 488
Quick Quiz 489
Quick Quiz Answers 490
Discussion Questions 490
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Table of Contents xvii
Exercises 491
Running Case 492
Key Terms 492
End Notes 493
Chapter 13 Project Stakeholder Management 495
13.1 The Importance of Project Stakeholder Management 496
13.2 Identifying Stakeholders 498
13.3 Planning Stakeholder Management 502
13.4 Managing Stakeholder Engagement 503
13.5 Controlling Stakeholder Engagement 506
13.6 Using Software to Assist in Project Stakeholder Management 508
Chapter Summary 511
Quick Quiz 511
Quick Quiz Answers 513
Discussion Questions 513
Exercises 513
Running Case 514
Key Terms 514
End Notes 514
Appendix A Guide to Using Microsoft Project 2013 A.1
Introduction A.2
Project Management Software Reviews A.3
Basic Features of Project Management Software A.6
What’s New in Project 2013 A.7
Using Project 2013 A.7
Before You Begin A.7
Using the 60-Day Trial of Project 2013 A.8
Overview of Project 2013 A.9
Exploring Project 2013 Using an Existing File A.15
Project 2013 Views A.17
Project 2013 Reports A.19
Project 2013 Filters A.21
Creating a New File and Entering Tasks in a Work Breakdown Structure A.23
Creating a New Project File A.23
Creating a Work Breakdown Structure Hierarchy A.25
Creating Summary Tasks A.26
Numbering Tasks A.27
Saving Project Files Without a Baseline A.28
Developing the Schedule A.29
Calendars A.29
Task Durations A.31
Entering Task Durations A.34
Establishing Task Dependencies A.38
Gantt Charts, Network Diagrams, and Critical Path Analysis A.43
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Table of Contentsxviii
Project Cost and Resource Management A.46
Entering Fixed and Variable Cost Estimates A.46
Entering Baseline Plans, Actual Costs, and Actual Times A.52
Viewing Earned Value Management Data A.56
Integrating Project 2013 with Other Applications and Apps for Office A.57
Copying Information Between Applications A.57
Creating Hyperlinks to Other Files A.59
Using Project 2013 Apps A.60
Glossary G.1
Index I.1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

The future of many organizations depends on their ability to harness the power of in-
formation technology, and good project managers continue to be in high demand. Col-
leges have responded to this need by establishing courses in project management and
making them part of the information technology, management, engineering, and other
curricula. Corporations are investing in continuing education to help develop and
deepen the effectiveness of project managers and project teams. This text provides
a much-needed framework for teaching courses in project management, especially
those that emphasize managing information technology projects. The first seven edi-
tions of this text were extremely well received by people in academia and the work-
place. The Eighth Edition builds on the strengths of the previous editions and adds
new, important information and features.
It’s impossible to read a newspaper, magazine, or web page without hearing about
the impact of information technology on our society. Information is traveling faster
and being shared by more people than ever before. You can buy just about anything
online, surf the web on a mobile phone, or use a wireless Internet connection just
about anywhere. Companies have linked their systems together to help them fill or-
ders on time and better serve their customers. Software companies are continually
developing new products to help streamline our work and get better results. When
technology works well, it is almost invisible. But did it ever occur to you to ask, “Who
makes these complex technologies and systems happen?”
Because you’re reading this text, you must have an interest in the “behind- the-
scenes” aspects of technology. If I’ve done my job well, you’ll begin to see the many
innovations society is currently enjoying as the result of thousands of success-
ful information technology projects. In this text, you’ll read about IT projects in
organizations around the world that went well, including the National University
Hospital in Singapore, which used critical chain scheduling to decrease patient
admission times by more than 50 percent; retailer Zulily, one of a growing number of
organizations developing software in-house to meet their need for speed and innova-
tion; Dell’s green computing project that saves energy and millions of dollars; Google’s
driverless car project, striving to reduce traffic accidents and save lives; and many
more.
Of course, not all projects are successful. Factors such as time, money, and un-
realistic expectations, among many others, can sabotage a promising effort if it is not
properly managed. In this text, you’ll also learn from the mistakes made on many
projects that were not successful.
I have written this book in an effort to educate you, tomorrow’s project manag-
ers, about what will help make a project succeed—and what can make it fail. You’ll
also see how projects are used in everyday media, such as television and film, and
how companies use best practices in project management. Many readers tell me how
much they enjoy reading these real-world examples in the What Went Right?, What
PREFACE
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Prefacexx
Went Wrong?, Media Snapshot, and Best Practice features. As practitioners know,
there is no “one size fits all” solution to managing projects. By seeing how different
organizations in different industries successfully implement project management, you
can help your organization do the same.
Although project management has been an established field for many years, man-
aging information technology projects requires ideas and information that go beyond
standard practices. For example, many information technology projects fail because
of a lack of executive support, poor user involvement, and unclear business objec-
tives. This book includes many suggestions for dealing with these issues. New tech-
nologies can also aid in managing information technology projects, and examples of
using software to assist in project management are included throughout the book.
Information Technology Project Management, Eighth Edition, is the only text-
book to apply all 10 project management knowledge areas and all five process groups
to information technology projects. As you will learn, the project management
knowledge areas are project integration, scope, time, cost, quality, human resource,
communications, risk, procurement, and stakeholder management. The five process
groups are initiating, planning, executing, monitoring and controlling, and closing.
This text builds on the PMBOK® Guide, Fifth Edition, an American National Stan-
dard, to provide a solid framework and context for managing information technology
projects. It also includes an appendix, Guide to Using Microsoft Project 2013, that
many readers find invaluable.
In addition to the physical text, several resources are available online. Additional
case studies, including the one from the Seventh Edition, Manage Your Health,
are available, as well as over fifty template files that students can use to create
their own project management documents. The author’s personal website (www
.kathyschwalbe.com or www.pmtexts.com) also provides additional, up-to-date
resources and links related to the field of project management, including topics like
Agile, PMP and CAPM certification, simulation software, leadership, mind mapping,
sample student projects, and more.
Information Technology Project Management, Eighth Edition, provides practi-
cal lessons in project management for students and practitioners alike. By weaving
together theory and practice, this text presents an understandable, integrated view
of the many concepts, skills, tools, and techniques of information technology project
management. The comprehensive design of the text provides a strong foundation for
students and practitioners in project management.
N E W T O T H E E I G H T H E D I T I O N
Building on the success of the previous editions, Information Technology Project
Management, Eighth Edition, introduces a uniquely effective combination of features.
The main changes in the Eighth Edition include the following:
A new running case at the end of Chapters 4–13, the ten knowledge
area chapters. Instructors often like to assign running cases to reinforce
application of key concepts. The “Manage Your Health” running case from
the Seventh Edition is provided online along with several additional
running cases.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Preface xxi
Updated and additional exercises to enhance student learning and give in-
structors more options for in-class or out-of-class work.
Additional content on important topics like leadership and agile.
New examples that highlight IT project management at work in real, news-
worthy companies. These timely, relevant examples help illustrate the real-
world applications and impact of key project management concepts. They
also serve as mini-case stories, suitable for class discussion.
Many recent studies of IT project management and related topics. Summaries
of classic, updated, and the most current research throughout the text build a
rich context for essential IT project management concepts.
User feedback is incorporated. Based on feedback from reviewers, students,
instructors, practitioners, and translators, you’ll see a variety of changes that
help clarify information. (This book has been translated into Chinese, Japa-
nese, Russian, and Czech.)
Many people have been practicing some form of project management with little or
no formal study in this area. New books and articles are written each year as we dis-
cover more about the field and as project management software continues to advance.
Because the project management field and the technology industry change rapidly,
you cannot assume that what worked even a few years ago is still the best approach
today. This text provides up-to-date information on how good project management
and effective use of software can help you manage projects, especially information
technology projects. Distinct features of this text include its relationship to the
Project Management Body of Knowledge, its value in preparing for certification, its
detailed guide for using Microsoft Project 2013, its inclusion of running case studies
and online templates, its emphasis on IT projects, its coverage of several software
tools that assist with project management, and its companion website.
Based on PMBOK® Guide, Fifth Edition and Preparing for Certification
The Project Management Institute (PMI) created the Guide to the Project Manage-
ment Body of Knowledge (the PMBOK® Guide) as a framework and starting point for
understanding project management. It includes an introduction to project manage-
ment, brief descriptions of all 10 project management knowledge areas, and a glos-
sary of terms. The PMBOK® Guide is, however, just that—a guide. This text uses the
PMBOK® Guide, Fifth Edition (2013) as a foundation, but goes beyond it by providing
more details, discussing the how and why of the knowledge areas, highlighting addi-
tional topics, and providing a real-world context for IT project management. This text
is an excellent resource for preparing for PMI certifications, such as the Project Man-
agement Professional (PMP) and Certified Associate in Project Management (CAPM).
Detailed Guide to Microsoft Project 2013
Software has become a critical tool for helping project managers and their teams ef-
fectively manage information technology projects. Information Technology Project
Management, Eighth Edition, includes a detailed guide in Appendix A for using the
leading project management software on the market—Microsoft Project 2013. Exam-
ples that use Project 2013 and other software tools are integrated throughout the text.
Appendix A, Guide to Using Microsoft Project 2013, teaches you in a systematic way
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Prefacexxii
to use this powerful software to help in project scope, time, cost, human resource,
and communications management.
Emphasis on IT Projects and Use of Software Tools
Most of the examples of projects in this text are based on IT projects. Research stud-
ies and advice are specific to managing IT projects, and include expanded information
on agile. Each of the knowledge area chapters includes examples as well as a separate
section describing how software can be used to assist in managing that knowledge
area. For example, Chapter 5, Project Scope Management, includes examples of us-
ing mind maps created with MindView Business software to create a work breakdown
structure. Chapter 11, Project Risk Management, shows an example of using Monte
Carlo simulation software to help quantify project risk.
Exercises, Running Cases, Templates, and Sample Documents
Based on feedback from readers, the Eighth Edition continues to provide challeng-
ing exercises and running cases to help students apply concepts in each chapter. The
text includes more than 50 templates and examples of real project documents that
students can use to help them apply their skills to their own projects.
Students can access all of these materials for free through the companion
CourseMate product, and for an additional fee, students who purchase the
CourseMate product will gain access to a complete, interactive e-book, crossword
puzzles, and additional study tools.
A C C E S S I N G T H E C O U R S E M A T E S I T E
To access the CourseMate site, open a web browser and go to www.cengagebrain
.com. Search by ISBN, author name, or title, and click Create My Account to begin
the registration process.
O R G A N I Z A T I O N A N D C O N T E N T
Information Technology Project Management, Eighth Edition, is organized into three
main sections, which provide a framework for project management, a detailed de-
scription of each project management knowledge area, and an appendix of practical
information for applying project management. The first three chapters form the first
section, which introduces the project management framework and sets the stage for
the remaining chapters.
Chapters 4 through 13 form the second section, which describes each of the proj-
ect management knowledge areas—project integration, scope, time, cost, quality, hu-
man resource, communications, risk, procurement, and stakeholder management—in
the context of information technology projects. An entire chapter is dedicated to each
knowledge area. Each of these chapters includes sections that map to their major
processes as described in the PMBOK® Guide, Fifth Edition. For example, the chapter
on project quality management includes sections on planning quality management,
performing quality assurance, and controlling quality. Additional sections highlight
other important concepts related to each knowledge area, such as Six Sigma, testing,
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Preface xxiii
maturity models, and using software to assist in project quality management. Each
chapter also includes detailed examples of key project management tools and tech-
niques as applied to information technology projects. For example, the chapter on
project integration management includes samples of various project-selection tech-
niques, such as net present value analyses, ROI calculations, payback analyses, and
weighted scoring models. The project scope management chapter includes a sample
project charter, a project scope statement, and several work breakdown structures for
information technology projects.
Appendix A forms the third section of the text, which provides practical infor-
mation to help you learn how to use the most popular project management software
available today. By following the detailed, step-by-step guide in Appendix A, which
includes more than 60 screen illustrations, you will learn how to use Project 2013.
You can download a free trial from the Microsoft website, use your school or company
license, or purchase this powerful software.
P E D A G O G I C A L F E A T U R E S
Several pedagogical features are included in this text to enhance presentation of
the materials so that you can more easily understand the concepts and apply them.
Throughout the text, emphasis is placed on applying concepts to current, real-world
information technology project management.
Opening Case and Case Wrap-Up
To set the stage, each chapter begins with an opening case related to the material
presented in that chapter. These real-life case scenarios, most of which are based on
the author’s experiences, spark student interest and introduce important concepts in
a real-world context. As project management concepts and techniques are discussed,
they are applied to the opening case and other similar scenarios. Each chapter then
closes with a case wrap-up—with some ending successfully and some failing—to
further illustrate the real world of project management.
What Went Right? and What Went Wrong?
Failures, as much as successes, can be valuable learning experiences. Each chapter of
the text includes one or more examples of real information technology projects that
went right, as well as examples of projects that went wrong. These examples further
illustrate the importance of mastering key concepts in each chapter.
Media Snapshot
The world is full of projects. Television shows, movies, newspapers, websites, and other
media highlight project results that are good and bad. Relating project management con-
cepts to the types of projects highlighted in the media helps you understand the impor-
tance of this growing field. Why not get excited about studying project management by
seeing its concepts at work in popular television shows, movies, or other media?
Best Practice
Every chapter includes an example of a best practice related to topics in that chapter.
For example, Chapter 1 describes best practices written by Robert Butrick, author of
The Project Workout, from the Ultimate Business Library’s Best Practice book. He
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Prefacexxiv
instructs organizations to ensure that their projects are driven by their strategy and
to engage project stakeholders.
Global Issues
Every chapter includes an example of global issues of importance today. For example,
Chapter 2 describes some of the problems with outsourcing, such as rioting in Beijing
when customers could not buy the latest iPhones. Chapter 12 describes the recent
development of urban onshoring, one response to problems with offshoring.
Key Terms
The fields of information technology and project management include many unique
terms that are vital to creating a workable language when the two fields are combined.
Key terms are displayed in boldface and are defined the first time they appear. Definitions
of key terms are provided in alphabetical order at the end of each chapter and in a glos-
sary at the end of the text. You can also find them by chapter on the companion website.
Application Software
Learning becomes much more dynamic with hands-on practice using the top project
management software tool in the industry, Microsoft Project 2013, as well as other
tools, such as spreadsheet software and the Internet. Each chapter offers many oppor-
tunities to get hands-on experience and build new software skills. This text is written
from the point of view that reading about something only gets you so far—to really
understand project management, you have to do it for yourself. In addition to the ex-
ercises and running cases at the end of each chapter, several challenging exercises are
provided at the end of Appendix A, Guide to Using Microsoft Project 2013.
S T U D E N T A N D I N S T R U C T O R R E S O U R C E S
Student and Instructor Companion Websites
The free Student Companion Website accessed through www.cengagebrain.com pro-
vides the template files mentioned in the text, Project 2013 files, a case study describ-
ing initiating through closing the ResNet project for Northwest Airlines (now part of
Delta), and additional running cases that instructors can assign to students to prac-
tice their skills. There is also a link to the author’s website, which provides up-to-date
resources on important topics like agile, certifications, and more.
The Instructor Companion Website, also accessed with a single sign-on (SSO) account
through www.cengagebrain.com, contains even more resources only for instructors:
Instructor’s Manual The Instructor’s Manual that accompanies this textbook
includes additional instructional material to assist in class preparation, such
as suggestions for lecture topics and additional discussion questions.
Solution Files Solutions to end-of-chapter questions are available on the
Instructor Companion Website.
PowerPoint Presentations This text comes with Microsoft PowerPoint slides
for each chapter. These slides are included as a teaching aid for classroom
presentation, to make available to students on the network for chapter re-
view, or to print for classroom distribution. Instructors can add their own
slides for additional topics they introduce to the class.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Preface xxv
Test Banks In addition to the Test Bank available online through Cognero
(see below), the Test Bank is also available in a number of file formats on the
Instructor Companion Website. Each chapter’s bank of questions includes
dozens of True/False, Multiple Choice, and Essay questions. Instructors can
retrieve the appropriate file formats to administer tests through their schools’
learning management systems (Blackboard, Canvas, Moodle, Desire2Learn,
etc.), or they can opt for Word documents.
NEW! Test Banks in Cognero
The Test Bank for Information Technology Project Management, Eighth Edition, is
now available online in the new Cognero system. Cengage Learning Testing Powered
by Cognero is a flexible, online system that allows instructors to:
Author, edit, and manage test bank content.
Use searchable metadata to ensure tests are complete and compliant.
Create multiple test versions in an instant.
Deliver tests from your learning management system (LMS), classroom, or
wherever you want.
Cengage Learning Testing Powered by Cognero works on any operating system or
browser with no special installs or downloads needed. With its intuitive tools and
familiar desktop drop-down menus, Cognero enables instructors to easily create and
edit tests from school or home—anywhere with Internet access.
IT Project Management CourseMate
Engaging, trackable, and affordable, the IT Project Management CourseMate website
offers a dynamic way to bring course concepts to life with interactive learning, study,
and exam preparation tools that support the printed edition of the text. Watch stu-
dent comprehension soar with all-new flashcards and engaging crossword puzzles,
test-prep quizzes, and more. A complete e-book provides students and instructors
alike with the choice of an entire online learning experience. IT Project Management
CourseMate goes beyond the book to deliver what students need.
The complete CourseMate companion product is available for an additional fee,
but students can also use the CourseMate website to access the text’s supplemental
materials, including project documents, templates, and cases, at no additional charge.
A C K N O W L E D G M E N T S
I never would have taken on the project of writing this book, including all the prior
editions, without the help of many people. I thank the staff at Cengage Learning, in-
cluding Joe Sabatino, Jason Guyler, Anne Merrill, Jennifer King, Eric LaScola, Chris-
tina Ciaramella, and Kathy Kucharek, for their dedication and hard work in helping
me produce this book and in doing such an excellent job of marketing it. I’d also like
to thank Marilyn Freedman for her excellent assistance in researching and preparing
the manuscript, and many more people who did a great job in planning and executing
this book and its supplemental materials.
I thank my many colleagues and experts in the field who contributed informa-
tion to this book. Joseph W. Kestel, PMP, provided outstanding feedback on the agile
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Prefacexxvi
information in this text based on his personal experience in leading agile projects.
David Jones, Rachel Hollstadt, Cliff Sprague, Michael Branch, Barb Most, Jodi Curtis,
Rita Mulcahy, Karen Boucher, Bill Munroe, Tess Galati, Joan Knutson, Neal Whitten,
Brenda Taylor, Quentin Fleming, Jesse Freese, Nick Matteucci, Nick Erndt, Dragan
Milosevic, Bob Borlink, Arvid Lee, Kathy Christenson, Peeter Kivestu, and many other
people provided excellent materials included in this book. I enjoy the network of proj-
ect managers, authors, and consultants in this field who are passionate about improv-
ing the theory and practice of project management.
I also thank my students and colleagues at Augsburg College and the University
of Minnesota for providing feedback on the earlier editions of this book. I received
many valuable comments from them on ways to improve the text and structure of my
courses. I learn something new about project management and teaching all the time
by interacting with students, faculty, and staff.
I also thank the faculty reviewers for providing excellent feedback for me in
writing this book over the years. I thank the many instructors and readers who have
contacted me directly with praise as well as suggestions for improving this text. I
appreciate the feedback and do my best to incorporate as much as I can. In particular,
I’d like to thank the following:
Jody Allen, Mid-America Christian University
William Baker, Southern New Hampshire University
Tonya Barrier, Missouri State University
Kevin Daimi, University of Detroit Mercy
Antonio Drommi, University of Detroit Mercy
Roger Engle, Franklin University
Lisa Foster, Walsh College of Business & Accountancy
Esther Frankel, Santa Barbara City College
Guy Garrett, Gulf Coast State College
James Gibbs, Mount St Joseph University
Thomas Haigh, University of Wisconsin, Milwaukee
Kay Hammond, Lindenwood University
Sam Hijazi, Saint Leo University
Henry Jackson, Schreiner University
Karen Johnson, Indiana University Northwest
Donna Karch, The College of St. Scholastica
Carol Kaszynski, Inver Hills Community College
Cyril Keiffer, Owens Community College
Thomas King, Pennsylvania State University
Sang Joon Lee, Mississippi State University
Sunita Lodwig, University of South Florida
Barbara Miller, Zane State College
Kimberly Mitchell, Illinois State University
Tim Moriarty, Waubonsee Community College
Brandon Olson, The College of St. Scholastica
Olga Petkova, Central Connecticut State University
April Reed, East Carolina University
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Preface xxvii
Jason Riley, Sam Houston State University
Carl Scott, University of Houston
Ferris Sticksel, Webster University
David Syverson, Embry-Riddle Aeronautical University
Barbara Warner, Wake Technical Community College
Steven White, Anne Arundel Community College
Most of all, I am grateful to my family. Without their support, I never could have
written this book. My wonderful husband, Dan, has always supported me in my
career, and he helps me keep up-to-date with software development because he is a
lead architect for Milner Technologies, Inc. (formerly ComSquared Systems, Inc.).
Our three children, Anne, Bobby, and Scott, think it’s cool that their mom writes
books and speaks at conferences. They also see me managing projects all the time.
Anne, now 31, a research analyst for The New Teacher Project, teases me for being
the only quilter she knows who treats each quilt as a project. (Maybe that’s why I get
so many done!) After her colleagues at The Minnesota Evaluation Studies Institute at
the University of Minnesota heard about my work and books, they hired me to teach
a workshop on project management to evaluators, which was sold out. Our two sons
are working as software developers in Texas and Oregon and may become IT project
managers soon. Our children understand the main reason I write—I have a passion
for educating future leaders of the world, including them.
As always, I am eager to receive your feedback on this book. Please send
comments to me at schwalbe@augsburg.edu.
Kathy Schwalbe, Ph.D., PMP
Professor Emeritus, Department of Business Administration
Augsburg College
A B O U T T H E A U T H O R
Kathy Schwalbe, Professor Emeritus in the Department
of Business Administration at Augsburg College in
Minneapolis, taught courses in project management,
problem solving for business, systems analysis and
design, information systems projects, and electronic
commerce until her retirement in May 2015. She
retired from teaching to focus on writing, traveling, and
enjoying life. Kathy was also an adjunct faculty member
at the University of Minnesota, where she taught a
graduate-level course in project management in the
engineering department. She also provides training and
consulting services to several organizations and speaks at numerous conferences.
Kathy’s first job out of college was as a project manager in the Air Force. She worked
for 10 years in industry before entering academia in 1991. She was an Air Force
officer, project manager, systems analyst, senior engineer, and information technology
consultant. Kathy is an active member of PMI, having served as the Student Chapter
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Prefacexxviii
Liaison for the Minnesota chapter, VP of Education for the Minnesota chapter,
Editor of the ISSIG Review, Director of Communications for PMI’s Information Sys-
tems Specific Interest Group, member of PMI’s test-writing team, and writer for the
community posts. Kathy earned her Ph.D. in Higher Education at the University of
Minnesota, her MBA at Northeastern University’s High Technology MBA program, and
her B.S. in mathematics at the University of Notre Dame. She was named Educator of
the Year in 2011 by the Association of Information Technology Professionals (AITP)
Education Special Interest Group (EDSIG). Kathy lives in Minnesota with her hus-
band. Visit her personal website at www.kathyschwalbe.com or www.pmtexts.com.
Other books by Kathy Schwalbe:
An Introduction to Project Management, Fifth Edition (Minneapolis: Schwalbe
Publishing, 2015).
Healthcare Project Management, co-authored with Dan Furlong (Minneapolis:
Schwalbe Publishing, 2013).
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R 1
INTRODUCTION TO
PROJECT MANAGEMENT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:



Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

2
1.1 INTRODUCTION
Many people and organizations today have a new—or renewed—interest in project
management. Until the 1980s, project management primarily focused on providing
schedule and resource data to top management in the military, computer, and construc-
tion industries. Today’s project management involves much more, and people in every
industry and every country manage projects. Project management is a distinct profession
with degree programs, certifications, and excellent career opportunities.
New technologies have become a significant factor in many businesses. Computer
hardware, software, networks, and the use of interdisciplinary and global work teams have
radically changed the work environment. The following statistics demonstrate the
significance of project management in today’s society, especially for projects involving
information technology (IT):
Worldwide IT spending was $3.8 trillion in 2014, a 3.2 percent increase from
2013 spending. Telecom services accounted for 45 percent of the spending.1
The Project Management Institute estimates demand for 15.7 million project
management jobs from 2010 to 2020, with 6.2 million of those jobs in the
United States.2
O P E N I N G C A S E
Anne Roberts, the director of the Project Management Office for a large retail chain,
stood in front of 500 people in the large corporate auditorium to explain the company’s
new strategies during a monthly all-hands meeting. She was also streaming live video to
thousands of other employees at other locations, suppliers, and stockholders through-
out the world. The company had come a long way in implementing new information
systems to improve inventory control, sell products online, streamline the sales and
distribution processes, and improve customer service. However, a recent security breach
had alarmed investors and the stock price plummeted. People were anxious to hear about
the company’s new strategies.
Anne began to address the audience, “Good morning. As many of you know, we have
completed many projects successfully, including the advanced data networks project.
That project enabled us to provide persistent broadband between headquarters and our
retail stores throughout the world, allowing us to make timely decisions and continue
our growth strategy. Our customers love that they can return items to any store, and any
sales clerk can look up past sales information. Local store managers can make timely
decisions using up-to-date information. Of course, we’ve had some failures, and we need
to continually assess our portfolio of projects to meet business needs.
Two big IT initiatives this coming year include providing the best computer security
possible and providing enhanced online collaboration tools for our employees, suppliers,
and customers. Our challenge is to work even smarter to decide what projects will most
benefit the company, how we can continue to leverage the power of information technol-
ogy to support our business, and how we can exploit our human capital to successfully
plan and execute those projects. If we succeed, we’ll continue to be a world-class
corporation.”
“And if we fail?” someone asked from the audience.
“Let’s just say that failure is not an option,” Anne replied.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

3
The unemployment rate for IT professionals is generally half the rate of the
overall labor market in the United States. Between 2011 and 2014, and dur-
ing the recession, the average unemployment rate for workers not in science,
technology, engineering, and mathematics (STEM) was 7.4 percent, as
opposed to just above 3 percent for STEM workers.3
In 2013 (the most recent year of PMI’s salary survey), the average salary in
U.S. dollars for someone in the project management profession was $108,000
per year in the United States; $134,658 in Australia, (the highest-paid coun-
try); and $24,201 in Egypt (the lowest-paid country). Of the 11,150 people
from the United States who responded to PMI’s salary survey, 80 percent had
the Project Management Professional (PMP) credential, and their salary was
over 20 percent higher than professionals without it.4
The top skills employers look for in new college graduates are all related to
project management: team-work, decision-making, problem-solving, and
verbal communications. The three degrees most in demand are business,
engineering, and computer and information sciences.5
Organizations waste $109 million for every $1 billion spent on projects,
according to PMI’s Pulse of the Profession® report. Excelling at project man-
agement definitely affects the bottom line.6
The complexity and importance of IT projects, which involve using hardware, soft-
ware, and networks to create a product, service, or result, have evolved dramatically.
Today’s companies, governments, and nonprofit organizations are recognizing that to
be successful, they need to use modern project management techniques, especially
for IT projects. Individuals are realizing that to remain competitive in the workplace,
they must develop skills to become good project team members and project managers.
They also realize that many of the concepts of project management will help them in
their everyday lives as they work with people and technology on a day-to-day basis.
W H A T W E N T W R O N G ?
In 1995, the Standish Group published an often-quoted study titled “The CHAOS
Report.” This consulting firm surveyed 365 IT executive managers in the United States
who managed more than 8,380 IT application projects. As the title of the study suggests,
the projects were in a state of chaos. U.S. companies spent more than $250 billion each
year in the early 1990s on approximately 175,000 IT application development projects.
Examples of these projects included creating a new database for a state department
of motor vehicles, developing a new system for car rental and hotel reservations, and
implementing a client-server architecture for the banking industry. The study reported
that the overall success rate of IT projects was only 16.2 percent. The surveyors defined
success as meeting project goals on time and on budget. The study also found that more
than 31 percent of IT projects were canceled before completion, costing U.S. compa-
nies and government agencies more than $81 billion. The study authors were adamant
about the need for better project management in the IT industry. They explained,
“Software development projects are in chaos, and we can no longer imitate the three
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

4
monkeys—hear no failures, see no failures, speak no failures.”7 Although this study was
done 20 years ago, it was significant in making senior executives pay attention to the
importance of IT project management.
In another large study, PricewaterhouseCoopers surveyed 200 companies from 30
different countries about their project management maturity and found that over half
of all projects fail. The study also found that only 2.5 percent of corporations consis-
tently meet their targets for scope, time, and cost goals for all types of projects.8
Although several researchers question the methodology of such studies, the results
have prompted managers throughout the world to examine ways to improve their prac-
tices in managing projects. Many organizations assert that using project management
techniques provides advantages, such as:
Better control of financial, physical, and human resources
Improved customer relations
Shorter development times
Lower costs and improved productivity
Higher quality and increased reliability
Higher profit margins
Better internal coordination
Positive impact on meeting strategic goals
Higher worker morale
This chapter introduces projects and project management, explains how projects fit
into programs and portfolio management, discusses the role of the project manager, and
provides important background information on this growing profession. Although project
management applies to many different industries and types of projects, this text focuses
on applying project management to IT projects.
1.2 WHAT IS A PROJECT?
To discuss project management, it is important to understand the concept of a project.
A project is “a temporary endeavor undertaken to create a unique product, service, or
result.”9 Operations, on the other hand, is work done in organizations to sustain the busi-
ness. Projects are different from operations in that they end when their objectives have
been reached or the project has been terminated.
1.2a Examples of IT Projects
Projects can be large or small and involve one person or thousands of people. They can be
done in one day or take years to complete. As described earlier, IT projects involve using
hardware, software, and networks to create a product, service, or result. Examples of IT
projects include the following:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

5
A large network of healthcare providers updates its information systems and
procedures to reduce hospital acquired diseases.
A team of students creates a smartphone application and sells it online.
A company develops a driverless car.
A college upgrades its technology infrastructure to provide wireless Internet
access across the whole campus as well as online access to all academic and
student service information.
A company develops a new system to increase sales force productivity and
customer relationship management that will work on various laptops, smart-
phones, and tablets.
A television network implements a system to allow viewers to vote for contes-
tants and provide other feedback on programs via social media sites.
A government group develops a system to track child immunizations.
A large group of volunteers from organizations throughout the world develops
standards for environmentally friendly or green IT.
A global bank acquires other financial institutions and needs to consolidate
systems and procedures.
Government regulations require monitoring of pollutants in the air and
water.
A multinational firm decides to consolidate its information systems into an
integrated enterprise resource management approach.
Gartner, Inc., a prestigious consulting firm, identified the top 10 strategic technologies
for 2015. A few of these technologies include the following:
Computing everywhere: The needs of mobile users in diverse contexts and
environments will continue to drive companies to develop new products and
services.
The Internet of things: Expanding digitization and connectivity will
continue to enable companies to combine information from people,
places, and things to extend services, improve how assets or machines
operate, or create new sources of revenue. One example, according to
Gartner, is that “the pay-per-use model can be applied to assets (such as
. . . equipment), services (such as pay-as-you-drive insurance), people
(such as movers), places (such as parking spots), and systems (such as
cloud services).”
3D printing: Worldwide shipments of 3D printers are expected to nearly
double in 2015 compared to 2014 and double again in 2016. New applications
continue to be found for producing items at lower costs through improved
designs, streamlined prototyping, and short-run manufacturing.
Advanced, pervasive, and invisible analytics: Analytics continues to grow in
importance as the volume of data generated by embedded systems increases.
The challenge is analyzing data to provide “the right information to the right
person at the right time.”10
As you can see, a wide variety of projects use information technologies, and organiza-
tions rely on them for success.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

6
M E D I A S N A P S H O T
One of Gartner’s top 10 strategic technologies for 2012 included application stores and
marketplaces for smartphones and tablets. Gartner predicted that by 2014 there would
be more than 70 billion mobile application downloads every year, but the actual number
was almost double!11 Facebook is by far the most downloaded app, and the most popular
category of all apps continues to be games.
There are over 1.3 million apps in Apple’s App store and another 1.3 million in
Google’s Play Store. Of course, business professionals use phone applications for produc-
tive purposes. The challenge is to develop useful apps and get workers to focus on them
instead of the many distracting options available. Business Insider, Forbes, PC Magazine,
and website Lifehacker.com provide lists of top productivity apps “to keep you focused
and get things done.”12
1.2b Project Attributes
Projects come in all shapes and sizes. The following attributes help define a project
further:
A project has a unique purpose. Every project should have a well-defined
objective. For example, Anne Roberts, the director of the Project Manage-
ment Office in the chapter’s opening case, might sponsor an IT collaboration
project to develop a list and initial analysis of potential IT projects that might
improve operations for the company. The unique purpose of this project
would be to create a collaborative report with ideas from people throughout
the company. The results would provide the basis for further discussions and
selecting projects to implement. As you can see from this example, projects
result in a unique product, service, or result.
A project is temporary. A project has a definite beginning and end. In the IT
collaboration project, Anne might form a team of people to work immediately
on the project, and then expect a report and an executive presentation of the
results in one month.
A project is developed using progressive elaboration. Projects are often
defined broadly when they begin, and as time passes, the specific details of
the project become clearer. Therefore, projects should be developed in incre-
ments. A project team should develop initial plans and then update them with
more detail based on new information. For example, suppose that a few peo-
ple submitted ideas for the IT collaboration project, but they did not clearly
address how the ideas would support the business strategy of improving op-
erations. The project team might decide to prepare a questionnaire for people
to fill in as they submit their ideas to improve the quality of the inputs.
A project requires resources, often from various areas. Resources include
people, hardware, software, and other assets. Many projects cross depart-
mental or other boundaries to achieve their unique purposes. For the IT
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

7
collaboration project, people from IT, marketing, sales, distribution, and
other areas of the company would need to work together to develop ideas.
The company might also hire outside consultants to provide input. Once the
collaboration project team has selected key projects for implementation,
each of those will probably require additional resources. To meet objectives
of these new projects, people from other companies—product suppliers
and consulting companies—may be added to the team. Resources, however,
are limited and must be used effectively to meet project and other
corporate goals.
A project should have a primary customer or sponsor. Most projects have
many interested parties or stakeholders, but for a project to succeed someone
must take the primary role of sponsorship. The project sponsor usually pro-
vides the direction and funding for the project. Executive support is crucial
to project success, as described in later chapters. Anne Roberts would be
the sponsor for the IT collaboration project. Once further IT projects are
selected, however, the sponsors for those projects would be senior manag-
ers in charge of the main parts of the company affected by the projects. For
example, the sponsor of a project to improve online product sales would be
the vice president of sales. In this situation, Anne might become part of a
project steering committee, helping other managers understand different
project objectives, resolve priorities, research issues, or alter constraints
within a given project or across multiple projects.
A project involves uncertainty. Because every project is unique, it is some-
times difficult to define its objectives clearly, estimate how long it will take
to complete, or determine how much it will cost. External factors also cause
uncertainty, such as a supplier going out of business or a project team mem-
ber needing unplanned time off. This uncertainty is one of the main reasons
project management is so challenging, especially on projects involving
new technologies.
An effective project manager is crucial to a project’s success. Project managers work
with the project sponsors, team, and the other people involved to achieve project goals.
1.2c Project Constraints
Every project is constrained in different ways, often by its scope, time, and cost goals.
These limitations are sometimes referred to in project management as the triple
constraint. To create a successful project, a project manager must consider scope,
time, and cost and balance these three often-competing goals:
Scope: What work will be done as part of the project? What unique product,
service, or result does the customer or sponsor expect from the project? How
will the scope be verified?
Time: How long should it take to complete the project? What is the project’s
schedule? How will the team track actual schedule performance? Who can
approve changes to the schedule?
Cost: What should it cost to complete the project? What is the project’s bud-
get? How will costs be tracked? Who can authorize changes to the budget?
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

8
Figure 1-1 illustrates the three dimensions of the triple constraint. Each area—scope,
time, and cost—has a target at the beginning of the project. For example, the IT collaboration
project might have an initial scope of producing a 40- to 50-page report and a one-hour pre-
sentation on about 30 potential IT projects. The project manager might further define project
scope to include providing a description of each potential project, an investigation of what
other companies have implemented for similar projects, a rough time and cost estimate, and
assessments of the risk and potential payoff as high, medium, or low. The initial time esti-
mate for this project might be one month, and the cost estimate might be $45,000–$50,000.
These expectations provide targets for the scope, time, and cost dimensions of the project.
Note that the scope and cost goals in this example include ranges—the report can be
40 to 50 pages long and the project can cost between $45,000 and $50,000. Because proj-
ects involve uncertainty and limited resources, projects rarely finish according to their
original scope, time, and cost goals. Instead of discrete target goals, it is often more real-
istic to set a range for goals, such as spending between $45,000 and $50,000 and having a
40- to 50-page report. These goals might require hitting the target, but not the bull’s eye.
Successful project
management means
meeting all three
goals (scope, time,
and cost)—and
satisfying the project’s
sponsor!
Target
FIGURE 1-1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

9
Managing the triple constraint involves making trade-offs between scope, time,
and cost goals for a project. For example, you might need to increase the budget for
a project to meet scope and time goals. Alternatively, you might have to reduce the
scope of a project to meet time and cost goals. Experienced project managers know
that you must decide which aspect of the triple constraint is most important. If time
is most important, you must often change the initial scope and cost goals to meet the
schedule. If scope goals are most important, you may need to adjust time and
cost goals.
To generate project ideas for the IT collaboration project, suppose that the project
manager sent an e-mail survey to all employees, as planned. The initial time and cost
estimate may have been one week and $5,000 to collect ideas using this e-mail survey.
Now, suppose that the e-mail survey generated only a few good project ideas, but the
scope goal was to collect at least 30 good ideas. Should the project team use a different
method like focus groups or interviews to collect ideas? Even though it was not in the
initial scope, time, or cost estimates, it would really help the project. Because good ideas
are crucial to project success, it would make sense to inform the project sponsor that
adjustments are needed.
Although the triple constraint describes how the basic elements of a project inter-
relate, other elements can also play significant roles. Quality is often a key factor in proj-
ects, as is customer or sponsor satisfaction. Some people, in fact, refer to the quadruple
constraint of project management, which includes quality as well as scope, time, and cost.
A project team may meet scope, time, and cost goals but might fail to meet quality stan-
dards and satisfy the sponsor. For example, Anne Roberts may receive a 50-page report
describing 30 potential IT projects and hear a presentation that summarizes the report.
The project team may have completed the work on time and within the cost constraint,
but the quality may have been unacceptable.
Other factors might also be crucial to a particular project. On some projects,
resources are the main concern. For example, the entertainment industry often needs
particular actors for movies or television shows. Project goals must be adjusted based on
when particular people are available. Risk can also affect major project decisions. A com-
pany might wait to start a project until the risks are at an acceptable level. The project
manager should be communicating with the sponsor throughout the project to make
sure it is meeting expectations. Chapter 10, Project Communications Management, and
Chapter 13, Project Stakeholder Management, address communicating with stakeholders
and understanding their expectations in greater detail.
How can you avoid the problems that occur when you meet scope, time, and cost
goals, but lose sight of customer satisfaction? The answer is good project management,
which includes more than managing project constraints.
1.3 WHAT IS PROJECT MANAGEMENT?
Project management is “the application of knowledge, skills, tools, and techniques to proj-
ect activities to meet project requirements.”13 Project managers must strive not only to
meet specific scope, time, cost, and quality goals of projects, they must also facilitate the
entire process to meet the needs and expectations of people involved in project activities
or affected by them.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Figure 1-2 illustrates a framework to help you understand project management. Key
elements of this framework include the project stakeholders, project management knowl-
edge areas, project management tools and techniques, and the contribution of successful
projects to the enterprise.
10 Knowledge areas Tools and
techniques
Project 1
Project 2
Project 3
Project 4
Project portfolio
Enterprise
success
Stakeholders’
needs and
expectations
Time
management
Cost
management
Quality
management
Scope
management
Human
resource
management
Communications
management
Risk
management
Procurement
management
Stakeholder
management
Project
successProject integration management
FIGURE 1-2
1.3a Project Stakeholders
Stakeholders are the people involved in or affected by project activities, and include the
project sponsor, project team, support staff, customers, users, suppliers, and even oppo-
nents of the project. These stakeholders often have very different needs and expectations.
A familiar example of a project is building a new house. There are several stakeholders in
a home construction project.
The project sponsors would be the potential new homeowners who would be
paying for the house. They could be on a very tight budget, so would expect the
contractor to provide a realistic idea of what type of home they could afford
given their budget constraints. They would also need a realistic idea of when
they could move in. Regardless of budget, they would expect the contractor to
provide accurate estimates for the building costs. The new homeowners would
have to make important decisions to keep the costs of the house within their
budget. Can they afford to finish the basement right away? If they can afford to
finish the basement, will it affect the projected move-in date? In this example,
the project sponsors are also the customers and users of the product, which is
the house.
The house may require financing by a bank or other financial institution like
a credit union, which will secure a legal interest (lien) in the property and
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

the finished home. This institution is an example of a legal stakeholder who
must be informed of any changes to the plans or schedule because the proj-
ect is part of a legal contract.
The project manager in this example would normally be the general contrac-
tor responsible for building the house. The project manager needs to work
with all the project stakeholders to meet their needs and expectations.
The project team for building the house would include several construc-
tion workers, electricians, and carpenters. These stakeholders would need
to know exactly what work they must do and when they need to do it. They
would need to know if the required materials and equipment will be at the
construction site or if they are expected to provide the materials and equip-
ment. Their work would need to be coordinated because many interrelated
factors are involved. For example, the carpenter cannot put in kitchen cabi-
nets until the walls are completed.
Support staff might include the buyers’ employers, the general contractor’s
administrative assistant, and people who support other stakeholders. The
buyers’ employers might expect their employees to complete their work but
allow some flexibility so they can visit the building site or take phone calls
related to building the house. The contractor’s administrative assistant would
support the project by coordinating meetings between the buyers, the con-
tractor, suppliers, and other parties.
Building a house requires many suppliers. The suppliers would provide the
wood, windows, flooring, appliances, and other materials. Suppliers would
expect exact details on the items they need to provide, and where and when
to deliver those items.
A project might have opponents. In this example, a neighbor might oppose
the project because the workers make so much noise that she cannot con-
centrate on her work at home, or the noise might wake her sleeping children.
She might interrupt the workers to voice her complaints or even file a formal
complaint. Or, the neighborhood might have association rules concerning
new home design and construction. If the homeowners do not follow these
rules, they might have to halt construction due to legal issues. Even without
such complaints, the home must comply with certain building codes and
other restrictions; these considerations may also result in changes to the
project’s requirements, making the local government a stakeholder in
the project.
As you can see from this example, projects have many different stakeholders, and they
often have different interests. Stakeholders’ needs and expectations are important in the
beginning and throughout the life of a project. Successful project managers develop good
relationships with project stakeholders to understand and meet their needs and
expectations.
1.3b Project Management Knowledge Areas
Project management knowledge areas describe the key competencies that project
managers must develop. The center of Figure 1-2 shows the 10 knowledge areas of project
management.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

1. Project scope management involves defining and managing all the work
required to complete the project successfully.
2. Project time management includes estimating how long it will take to
complete the work, developing an acceptable project schedule, and ensuring
timely completion of the project.
3. Project cost management consists of preparing and managing the budget for
the project.
4. Project quality management ensures that the project will satisfy the stated or
implied needs for which it was undertaken.
5. Project human resource management is concerned with making effective use
of the people involved with the project.
6. Project communications management involves generating, collecting,
disseminating, and storing project information.
7. Project risk management includes identifying, analyzing, and responding to
risks related to the project.
8. Project procurement management involves acquiring or procuring goods and
services for a project from outside the performing organization.
9. Project stakeholder management includes identifying and analyzing stake-
holder needs while managing and controlling their engagement throughout
the life of the project.
10. Project integration management is an overarching function that affects and is
affected by all of the other knowledge areas.
Project managers must have knowledge and skills in all 10 of these areas. This text
includes an entire chapter on each of these knowledge areas because all of them are
crucial to project success.
1.3c Project Management Tools and Techniques
Thomas Carlyle, a famous historian and author, stated, “Man is a tool-using animal.
Without tools he is nothing, with tools he is all.” As the world continues to become more
complex, it is even more important for people to develop and use tools, especially for man-
aging important projects. Project management tools and techniques assist project man-
agers and their teams in carrying out work in all 10 knowledge areas. For example, some
popular time-management tools and techniques include Gantt charts, project network
diagrams, and critical path analysis. Table 1-1 lists some commonly used tools and tech-
niques by knowledge area. You will learn more about these and other tools and techniques
throughout this text.
A survey of 753 project and program managers was conducted to rate several project
management tools. Respondents rated tools on a scale of 1–5 (low to high) based on the
extent of their use and the potential of the tools to help improve project success. “Super
tools” were defined as those that had high use and high potential for improving project
success. These super tools included software for task scheduling (such as project manage-
ment software), scope statements, requirement analyses, and lessons-learned reports.
Tools that are already used extensively and have been found to improve project perfor-
mance include progress reports, kick-off meetings, Gantt charts, and change requests.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

These super tools appear in column 3 of Table 1-1.14 Note that project stakeholder man-
agement was not a separate knowledge area at the time of this survey. Of course,
different tools can be more effective in different situations. It is crucial for project
managers and their team members to determine which tools will be most useful for
their particular projects.
TABLE 1-1
Knowledge Area/Category Tools and Techniques Super Tools
Integration management Project selection methods
Project management methodologies
Stakeholder analyses
Work requests
Project charters
Project management plans
Change control boards
Project review meetings
Project management software
Change requests
Lessons-learned reports
Scope management Statements of work
Scope management plans
Scope verification techniques
Scope change controls
Scope statements
Work breakdown structures
Requirements analyses
Time management Project network diagrams
Critical path analysis
Crashing
Fast tracking
Schedule performance
measurements
Gantt charts
Cost management Project budgets
Net present value
Return on investment
Payback analysis
Earned value management
Project portfolio management
Cost estimates
Cost management plans
Cost baselines
Quality management Quality metrics
Checklists
Quality control charts
Pareto diagrams
Fishbone diagrams
Maturity models
Statistical methods
Test plans
Human resource management Motivation techniques
Empathic listening
Responsibility assignment matrices
Project organizational charts
Resource histograms
Team building exercises
(continued)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Knowledge Area/Category Tools and Techniques Super Tools
Communications management Communications management plans
Conflict management
Communications media selection
Status reports
Virtual communications
Templates
Project websites
Kick-off meetings
Progress reports
Risk management Risk management plans
Risk registers
Probability/impact matrices
Risk rankings
Procurement management Make-or-buy analyses
Contracts
Requests for proposals or quotes
Source selections
Supplier evaluation matrices
© Cengage Learning 2016
W H A T W E N T R I G H T ?
Follow-up studies by the Standish Group (publisher of the annual CHAOS study; see
“What Went Wrong?”) have shown some improvement in the success rates of IT projects:
The number of successful IT projects more than doubled, from 16 percent in 1994 to
39 percent in 2012.
The number of failed projects decreased from 31 percent in 1994 to 18
percent in 2012.
“This year’s results represent a high watermark for success rates in the history of
CHAOS research. The increase in success is a result of several factors, including looking at
the entire project environment of processes, methods, skills, costs, tools, decisions, optimi-
zation, internal and external influences, and team chemistry. Advances in the understand-
ing of the skills needed to be a good executive sponsor have proved to be very valuable
for increasing success rates. Increases in project management as a profession and trained
project management professionals can be tied directly to increases in success rates.”15
The 2013 CHAOS study also compared small projects (under $1 million) with large
projects (over $10 million). Not surprisingly, the success rate for small projects was
much higher than for large projects—76 percent versus 10 percent. It is easier to manage
smaller projects, and researchers suggest that organizations strive to break large projects
into a sequence of smaller ones in a process they call optimization.16
Despite its advantages, project management is not a silver bullet that guarantees
success on all projects. Project management is a very broad, often complex discipline.
What works on one project may not work on another, so it is essential for project
TABLE 1-1 continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

managers to continue to develop their knowledge and skills in managing projects. It is also
important to learn from the mistakes and successes of others.
1.3d Project Success
How do you define the success or failure of a project? The list that follows outlines a few
common criteria for measuring the success of a project, illustrating each with an example
of upgrading 500 desktop computers within three months for $300,000:
1. The project met scope, time, and cost goals. If all 500 computers were
upgraded and met other scope requirements, the work was completed in
three months or less, and the cost was $300,000 or less, you could consider
the project successful. The Standish Group studies used this definition of
success, but several people question this simple definition of project success
and the methods used for collecting the data. (Search for articles by Robert L.
Glass to read more about this debate.)
2. The project satisfied the customer/sponsor. Even if the project met initial
scope, time, and cost goals, the users of the computers or their managers
might not be satisfied. Perhaps the project manager or team members never
returned calls or were rude. Perhaps users had their daily work disrupted
during the upgrades or had to work extra hours due to the upgrades. If the
customers were not happy with important aspects of the project, it would be
deemed a failure. Conversely, a project might not meet initial scope, time,
and cost goals, but the customer could still be very satisfied. Perhaps the
project team took longer and spent more money than planned, but they were
very polite and helped the users and managers solve several work-related
problems. Many organizations implement a customer satisfaction rating sys-
tem to measure project success instead of tracking only scope, time, and cost
performance.
3. The results of the project met its main objective, such as making or saving a
certain amount of money, providing a good return on investment, or simply
making the sponsors happy. Even if the project cost more than estimated,
it took longer to complete, and the project team was hard to work with, the
project would be successful if users were happy with the upgraded comput-
ers, based on this criterion. As another example, suppose that the sponsor
approved the upgrade project to provide a good return on investment by
speeding up work and therefore generating more profits. If those goals were
met, the sponsor would deem the project a success, regardless of other fac-
tors involved.
Why do some IT projects succeed and others fail? Table 1-2 summarizes the results of
the 2013 CHAOS study. The factors that contribute most to the success of IT projects are
listed in order of importance. Executive support is the most important factor, followed by
user involvement. A few of the top success factors relate to good scope management, such
as having clear business objectives and optimizing scope. Project management expertise
continues to be a key success factor. In fact, experienced project managers, who can often
help influence all of these factors to improve the probability of project success, led 97 per-
cent of successful projects, based on an earlier CHAOS study in 2001.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

TABLE 1-2
1. Executive support
2. User involvement
3. Clear business objectives
4. Emotional maturity
5. Optimizing scope
6. Agile process
7. Project management expertise
8. Skilled resources
9. Execution
10. Tools and infrastructure
Source: The Standish Group, “CHAOS Manifesto 2013: Think Big, Act Small” (2013).
A 2011 U.S. government report listed the top three reasons why federal technology
projects succeed:
1. Adequate funding
2. Staff expertise
3. Engagement from all stakeholders
Notice that the CHAOS study list does not include adequate funding. Most nongov-
ernment companies must either find adequate funds for important projects or cancel
projects if they cannot be funded or get an adequate return. Government projects often
require that funds be allocated a year or more before they even start, and estimates often
fall short. “The government has struggled when acquiring technology thanks to the con-
voluted nature of the federal contracting process and the shortage of qualified contracting
officers and technical personnel. Critics argue that federal agencies get little return for
the $80 billion the government spends annually on IT. . . . ‘History has shown that gov-
ernment IT projects frequently face challenges of meeting cost, schedule or performance
goals,’ said Sen. Susan Collins (R-Maine) in a statement.”17
It is interesting to compare success factors for IT projects in the United States
with those in other countries. A 2004 study summarizes the results of a survey of 247
information systems project practitioners in mainland China. One of the study’s key find-
ings was that relationship management is viewed as a top success factor for information
systems in China, while it is not mentioned in U.S. studies. The study also suggested that
having competent team members is less important in China than in the United States.
The Chinese, like the Americans, included top management support, user involvement,
and a competent project manager as vital to project success.18
It is also important to look beyond individual project success rates and focus on how
organizations as a whole can improve project performance. Research comparing compa-
nies that excel in project delivery—the “winners”—from those that do not found four sig-
nificant best practices:
1. Use an integrated toolbox. Companies that consistently succeed in managing
projects clearly define what needs to be done in a project, by whom, when,
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

and how. They use an integrated toolbox, including project management
tools, methods, and techniques. They carefully select tools, align them with
project and business goals, link them to metrics, and provide them to project
managers to deliver positive results.
2. Grow project leaders. The winners know that strong project managers—
referred to as project leaders—are crucial to project success. They also know
that a good project leader needs to be a business leader as well, with strong
interpersonal and intrapersonal skills. Companies that excel in project man-
agement often grow or develop their project leaders internally, providing
them with career opportunities, training, and mentoring.
3. Develop a streamlined project delivery process. Winning companies have
examined every step in the project delivery process, analyzed fluctuations in
workloads, searched for ways to reduce variation, and eliminated bottlenecks
to create a repeatable delivery process. All projects go through clear stages
and clearly define key milestones. All project leaders use a shared road map,
focusing on key business aspects of their projects while integrating goals
across all parts of the organization.
4. Measure project health using metrics. Companies that excel in project
delivery use performance metrics to quantify progress. They focus on a
handful of important measurements and apply them to all projects. Metrics
often include customer satisfaction, return on investment, and percentage
of schedule buffer consumed.19
Project managers play an important role in making projects, and therefore organi-
zations, successful. Project managers work with the project sponsors, the project team,
and other stakeholders to meet project goals. They also work with sponsors to define
success for particular projects. Good project managers do not assume that their defini-
tion of success is the same as the sponsors’. They take the time to understand their
sponsors’ expectations and then track project performance based on important
success criteria.
1.4 PROGRAM AND PROJECT PORTFOLIO MANAGEMENT
As mentioned earlier, about one-quarter of the world’s gross domestic product is spent on
projects. Projects make up a significant portion of work in most business organizations or
enterprises, and managing those projects successfully is crucial to enterprise success. Two
important concepts that help projects meet enterprise goals are the use of programs and
project portfolio management.
1.4a Programs
A program is “a group of related projects, subprograms, and program activities managed
in a coordinated way to obtain benefits and control not available from managing them
individually.”20 As you can imagine, it is often more economical to group projects together
to help streamline management, staffing, purchasing, and other work. The following are
examples of common programs in the IT field.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Infrastructure: An IT department often has a program for IT infrastructure
projects. This program could encompass several projects, such as providing
more wireless Internet access, upgrading hardware and software,
enhancing computer security, and developing and maintaining corporate
standards for IT.
Applications development: This program could include several projects, such
as updating an enterprise resource planning (ERP) system, purchasing a new
off-the-shelf billing system, or developing a new capability for a customer
relationship management system.
User support: In addition to the many operational tasks related to user sup-
port, many IT departments have several projects to support users. For ex-
ample, a project might provide a better e-mail system or develop technical
training for users.
A program manager provides leadership and direction for the project managers
heading the projects within a program. Program managers also coordinate the efforts
of project teams, functional groups, suppliers, and operations staff supporting the
projects to ensure that products and processes are implemented to maximize benefits.
Program managers are responsible for more than the delivery of project results; they
are change agents responsible for the success of products and processes developed by
those projects. For example, the NASA International Space Station Program is
led by a program manager who oversees all U.S. projects involved with the station
and is accountable for achieving their objectives, funding, and contribution to
scientific knowledge.
Program managers often have review meetings with all their project managers to
share important information and coordinate important aspects of each project. Many pro-
gram managers worked as project managers earlier in their careers, and they enjoy shar-
ing their wisdom and expertise with their project managers. Effective program managers
recognize that managing a program is much more complex than managing a single project.
They recognize that technical and project management skills are not enough—program
managers must also possess strong business knowledge, leadership capabilities, and com-
munication skills.
1.4b Project Portfolio Management
In many organizations, project managers also support an emerging business strategy of
project portfolio management or portfolio management, as called in this text, in which
organizations group and manage projects and programs as a portfolio of investments
that contribute to the entire enterprise’s success. Portfolio managers help their organi-
zations make wise investment decisions by helping to select and analyze projects from
a strategic perspective. Portfolio managers may or may not have previous experience as
project or program managers. It is most important that they have strong financial and
analytical skills and understand how projects and programs can contribute to meeting
strategic goals.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Figure 1-3 illustrates the differences between project management and project
portfolio management. Notice that the main distinction is a focus on meeting tactical or
strategic goals. Tactical goals are generally more specific and short-term than strategic
goals, which emphasize long-term goals for an organization. Individual projects often
address tactical goals, whereas portfolio management addresses strategic goals. Project
management addresses questions like “Are we carrying out projects well?”, “Are proj-
ects on time and on budget?”, and “Do project stakeholders know what they should
be doing?”
Portfolio management addresses questions like “Are we working on the right proj-
ects?”, “Are we investing in the right areas?”, and “Do we have the right resources to be
competitive?” Pacific Edge Software’s product manager, Eric Burke, defines project portfo-
lio management as “the continuous process of selecting and managing the optimum set of
project initiatives that deliver maximum business value.”21
Many organizations use a more disciplined approach to portfolio management
by developing guidelines and software tools to assist in it. The Project Management
Institute (described later in this chapter) first published the Organizational Project
Management Maturity Model (OPM3) Knowledge Foundation in 2003.22 OPM3
describes the importance not only of managing individual projects or programs well
but the importance of following organizational project management to align proj-
ects, programs, and portfolios with strategic goals. OPM3 is a standard that organiza-
tions can use to measure their organizational project management maturity against a
comprehensive set of best practices.
Tactical
goals
Strategic goals
Project management
Project portfolio management
FIGURE 1-3
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

B E S T P R A C T I C E
A best practice is “an optimal way recognized by industry to achieve a stated goal or
objective.”23 Rosabeth Moss Kanter, a professor at Harvard Business School and well-known
author and consultant, says that visionary leaders know “the best practice secret: Stretch-
ing to learn from the best of the best in any sector can make a big vision more likely to
succeed.”24 Kanter also emphasizes the need to have measurable standards for best prac-
tices. An organization can measure performance against its own past, against peers, and,
even better, against potential. Kanter suggests that organizations need to continue to reach
for higher standards. She suggests the following exercise regimen for business leaders who
want to adapt best practices in an intelligent way to help their own organizations:
Reach high. Stretch. Raise standards and aspirations. Find the best of the best and
then use it as inspiration for reaching full potential.
Help everyone in your organization become a professional. Empower people to
manage themselves through benchmarks and standards based on best practice
exchange.
Look everywhere. Go far afield. Think of the whole world as your laboratory for
learning.
Robert Butrick, author of The Project Workout, wrote an article on best practices in
project management for the Ultimate Business Library’s Best Practice book. He suggests
that organizations need to follow basic principles of project management, including these
two mentioned earlier in this chapter:
Make sure your projects are driven by your strategy. Be able to demonstrate how
each project you undertake fits your business strategy, and screen out unwanted
projects as soon as possible.
Engage your stakeholders. Ignoring stakeholders often leads to project failure. Be
sure to engage stakeholders at all stages of a project, and encourage teamwork
and commitment at all times.25
As you can imagine, project portfolio management is not an easy task. Figure 1-4
illustrates one approach for project portfolio management in which one large portfolio
exists for the entire organization. This allows top management to view and manage all
projects at an enterprise level. Sections of the portfolio are then broken down to improve
the management of projects in each sector. For example, a company might have the main
portfolio categories shown in the left part of Figure 1-4—marketing, materials, IT, and
human resources (HR)—and divide each of those categories further to address its unique
concerns. The right part of this figure shows how the IT projects could be categorized in
more detail to assist in their management. In this example, there are three basic IT
project portfolio categories:
Venture: Projects in this category help transform the business. For example,
the large retail chain described in the opening case might have an IT project to
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

provide kiosks in stores and similar functionality on the Internet where custom-
ers and suppliers could quickly provide feedback on products or services. This
project could help transform the business by developing closer partnerships with
customers and suppliers.
Growth: Projects in this category would help the company increase its rev-
enues. For example, a company might have an IT project to provide informa-
tion on its corporate website in a new language, such as Chinese or Japanese.
This capability could help the company grow its business in those countries.
Core: Projects in this category must be accomplished to run the business. For
example, an IT project to provide computers for new employees would fall
under this category.
In Figure 1-4, the costs of Core IT projects are nondiscretionary, which means that
the company has no choice in whether to fund them. Core IT Projects must be funded
for the company to stay in business. Projects in the Venture or Growth category are
discretionary costs because the company can use its own discretion or judgment in decid-
ing whether to fund them; these projects are not critical to the company fulfilling its mis-
sion. The arrow in the center of Figure 1-4 indicates that the risks and value of projects
normally increase as you move from Core to Growth to Venture projects. In addition,
timeliness becomes increasingly important; growth and venture projects, more than core
projects, must be done within a certain time frame to be effective. However, some core
projects can also be high risk, have high value, and require good timing. As you can see,
many factors are involved in portfolio management.
Many organizations use specialized software to organize and analyze all types of proj-
ect data into project portfolios. Enterprise project management software or project and
portfolio management software integrates information from multiple projects to show the
Overall project portfolio categories IT project portfolio categories
Ri
sk
s,
V
al
ue
, T
im
in
g
Nondiscretionary
costs
Discretionary
costs
Venture:
Transform
the business
Growth:
Grow the
business
Core:
Run the
business
Marketing
Materials
IT
HR
FIGURE 1-4
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

22
status of active, approved, and future projects across an entire organization. It also helps
organizations prioritize project portfolio investment to deliver results with the best busi-
ness value. In 2014, Capterra published an infographic listing the top 20 project manage-
ment software tools. Microsoft Project continues to lead the market with over 880,000
customers and 22 million users.26 Figure 1-5 summarizes the capabilities of the Microsoft
Project Portfolio Management solution.
1.5 THE ROLE OF THE PROJECT MANAGER
You have already read that project managers must work closely with the other stakehold-
ers on a project, especially the sponsor and project team. They are also more effective if
they are familiar with the 10 project management knowledge areas and the various tools
and techniques related to project management. Experienced project managers help proj-
ects succeed. But what do project managers do, exactly? What skills do they really need
to do a good job? The next section provides brief answers to these questions, and the rest
of this book gives more insight into the role of the project manager. Even if you never
become a project manager, you will probably be part of a project team, and it is important
for team members to help their project managers.
1.5a Project Manager Job Description
A project manager can have many different job descriptions, which can vary tremendously
based on the organization and the project. In fact, PMI includes a page on their website to
FIGURE 1-5
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

23
answer the question, “Who are project managers?” In addition to saying that project man-
agers are organized, passionate, and goal-oriented individuals who drive business results
by leading projects, PMI emphasizes that they are also change agents who work well under
pressure and enjoy challenging work environments.
Project management jobs can be found in every country and every industry. Sites like
indeed.com listed hundreds of thousands of job openings in 2015. Monster.com has a job
category for project management, and their site says that project managers “smoothly
link management, clients and staff to keep projects rolling. To be successful in a project
management job, you’ll need people skills, business acumen and technical competence.”27
Here are a few edited postings:
Project manager for a consulting firm: Plans, schedules, and controls activi-
ties to fulfill identified objectives applying technical, theoretical, and mana-
gerial skills to satisfy project requirements. Coordinates and integrates team
and individual efforts and builds positive professional relationships with cli-
ents and associates.
Project manager for a computer systems firm: Works independently within
established practices to assist in the development and implementation
process of projects involving departmental, vendor relationships, and/or
cross-functional teams. Coordinates with internal/external clients to gather
business requirements and coordinate project plans. Monitor projects from
initiation through delivery ensuring completion of the project on schedule.
IT project manager for a nonprofit consulting firm: Responsibilities include
business analysis, requirements gathering, project planning, budget estimat-
ing, development, testing, and implementation. Responsible for working with
various resource providers to ensure development is completed in a timely,
high-quality, and cost-effective manner.
The job description for a project manager can vary by industry and by organization,
but most project managers perform similar tasks regardless of these differences. In fact,
project management is a skill needed in every major IT field, from database administra-
tor to network specialist to technical writer. Because demand for project managers is
high, some organizations have hired new college graduates to fill positions normally held
by experienced professionals. For example, Boom Lab, a consulting company, is growing
quickly by finding, training, and placing talented people as project coordinators. As new
project coordinators gain experience and credentials, they often continue their careers by
managing larger projects, becoming program managers, or transitioning into other man-
agement positions.
1.5b Suggested Skills for Project Managers
Project managers need to have a wide variety of skills and be able to decide which skills
are more important in different situations. A Guide to the Project Management Body of
Knowledge—the PMBOK® Guide—recommends that the project management team un-
derstand and use expertise in the following areas:
The Project Management Body of Knowledge
Application area knowledge, standards, and regulations
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

24
Project environment knowledge
General management knowledge and skills
Soft skills or human relations skills
This chapter introduced the 10 project management knowledge areas, as well as some
general tools and techniques project managers use. The following section focuses on the
IT application area, including skills required in the project environment, general manage-
ment, and soft skills. Note that the PMBOK® Guide, Fifth Edition describes three dimen-
sions of project management competency: project management knowledge (knowing
about project management), performance competency (being able to apply project man-
agement knowledge), and personal competency (attitudes and personality characteristics).
Consult PMI’s website at www.pmi.org for further information on skills for project manag-
ers and PMI’s Career Framework for Practitioners.
The project environment differs from organization to organization and project to
project, but some skills will help in almost all project environments. These skills include
understanding change and understanding how organizations work within their social,
political, and physical environments. Project managers must be comfortable leading and
handling change, because most projects introduce changes in organizations and involve
changes within the projects themselves. Project managers need to understand the orga-
nization in which they work and how that organization develops products and provides
services. The skills and behavior needed to manage a project for a Fortune 100 company
in the United States may differ greatly from those needed to manage a government project
in Poland. Chapter 2, The Project Management and Information Technology Context, pro-
vides detailed information on these topics.
Project managers should also possess general management knowledge and skills. They
should understand important topics related to financial management, accounting, pro-
curement, sales, marketing, contracts, manufacturing, distribution, logistics, the supply
chain, strategic planning, tactical planning, operations management, organizational struc-
tures and behavior, personnel administration, compensation, benefits, career paths, and
health and safety practices. On some projects, it will be critical for the project manager
to have a lot of experience in one or several of these general management areas. On other
projects, the project manager can delegate detailed responsibility for some of these areas
to a team member, support staff, or even a supplier. Even so, the project manager must be
intelligent and experienced enough to know which of these areas are most important and
who is qualified to do the work. The project manager must make all key project decisions
and take responsibility for them.
Achieving high performance on projects requires soft skills, otherwise called
human relations skills. Some of these soft skills include effective communication,
influencing the organization to get things done, leadership, motivation, negotiation,
conflict management, and problem solving. Why do project managers need good soft
skills? One reason is that to understand, navigate, and meet stakeholders’ needs and
expectations, project managers need to lead, communicate, negotiate, solve problems,
and influence the organization at large. They need to be able to listen actively to what
others are saying, help develop new approaches for solving problems, and then per-
suade others to work toward achieving project goals. Project managers must lead their
project teams by providing vision, delegating work, creating an energetic and positive
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

25
environment, and setting an example of appropriate and effective behavior. Project
managers must focus on teamwork skills to employ people effectively. They need to be
able to motivate different types of people and develop esprit de corps within the proj-
ect team and with other project stakeholders. Because most projects involve changes
and trade-offs between competing goals, it is important for project managers to have
strong coping skills as well. Project managers need to be able to cope with criticism
and constant change. Project managers must be flexible, creative, and sometimes pa-
tient in working toward project goals; they must also be persistent in making project
needs known.
Finally, project managers, especially those managing IT projects, must be able to
make effective use of technology as it relates to the specific project. Making effective use
of technology often includes special product knowledge or experience with a particular
industry.
Project managers must make many decisions and deal with people in a wide variety
of disciplines, so it helps tremendously to have a project manager who is confident in
using the special tools or technologies that are the most effective in particular settings.
Project managers do not normally have to be experts on any specific technology, but
they have to know enough to build a strong team and ask the right questions to keep
things on track. For example, project managers for large IT projects do not have to be
experts in the field of IT, but they must have working knowledge of various technolo-
gies and understand how the project would enhance the business. Many companies
have found good business managers can be very good IT project managers because they
focus on meeting business needs and rely on key project members to handle the
technical details.
A 2013 survey by CIO.com listed seven skills project managers need in order to be
effective and successful in leading IT projects:
1. Be highly organized.
2. Take charge and know how to lead.
3. Be an effective communicator.
4. Know how and when to negotiate.
5. Be detail-oriented.
6. Recognize and solve problems quickly.
7. Possess the necessary technical skills.28
All project managers should continue to develop their knowledge and experience in
project management, general management, soft skills, and the industries they support. IT
project managers must be willing to develop more than their technical skills to be produc-
tive team members and successful project managers. Everyone, no matter how technical
they are, should develop business and soft skills.
1.5c Importance of People Skills and Leadership Skills
Project management experts from various industries were asked to identify the 10 most
important skills and competencies for effective project managers. Table 1-3 shows the
results.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

26
TABLE 1-3
1. People skills
2. Leadership
3. Listening
4. Integrity, ethical behavior, consistency
5. Strength at building trust
6. Verbal communication
7. Strength at building teams
8. Conflict resolution, conflict management
9. Critical thinking, problem solving
10. Understanding and balancing of priorities
Source: Jennifer Krahn, “Effective Project Leadership: A Combination of Project Manager Skills and
Competencies in Context,” PMI Research Conference Proceedings (July 2006).
Respondents were also asked what skills and competencies were most important in
various project situations:
Large projects: Leadership, relevant experience, planning, people skills, verbal
communication, and team-building skills were most important.
High-uncertainty projects: Risk management, expectation management,
leadership, people skills, and planning skills were most important.
Innovative projects: Leadership, people skills, vision- and goal-setting,
self-confidence, expectations management, and listening skills were most
important.29
Notice that a few skills and competencies not cited in the top 10 list were mentioned
when people thought about the context of a project. To be most effective, project manag-
ers require a changing mix of skills and competencies depending on the project being
delivered.
Also notice the general emphasis on people and leadership skills. As mentioned
earlier, all project managers, especially those working on technical projects, need to
demonstrate leadership and management skills. Leadership and management are terms
often used interchangeably, although there are differences. Generally, a leader focuses
on long-term goals and big-picture objectives while inspiring people to reach those goals.
A manager often deals with the day-to-day details of meeting specific goals. Some people
say: “Managers do things right, and leaders do the right things.” “Leaders determine the
vision, and managers achieve the vision.” “You lead people and manage things.”
However, project managers often take on the role of both leader and manager. Good
project managers know that people make or break projects, so they must set a good example
to lead their team to success. They are aware of the greater needs of their stakeholders
and organizations, so they are visionary in guiding their current projects and in suggesting
future ones. As mentioned earlier, companies that excel in project management grow proj-
ect “leaders,” emphasizing development of business and communication skills. Yet, good
project managers must also focus on getting the job done by paying attention to the details
and daily operations of each task. Instead of thinking of leaders and managers as specific
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

27
people, it is better to think of people as having leadership skills, such as being visionary and
inspiring, and management skills, such as being organized and effective. Therefore, the best
project managers have leadership and management characteristics; they are visionary yet
focused on the bottom line. Above all else, good project managers focus on achieving posi-
tive results!
1.5d Careers for IT Project Managers
As shown earlier, the IT industry continues to grow, and the need for people to lead
IT projects has remained solid. In fact, every IT worker needs some skills in project
management.
Computerworld’s 2014 annual forecast survey supports this career projection. Forty-
three percent of the 194 respondents said that they expect their IT budgets to increase,
and overall IT budgets are expected to increase by 4.3 percent. The top five priorities
include spending on:
1. security technologies,
2. cloud computing,
3. business analytics,
4. application development,
5. wireless/mobile.30
IT executives listed the “ten hottest skills” they planned to hire for in 2015. Program-
ming and application development remained in first place, mainly due to the increased
need for programmers with mobile development expertise and experience building secure
applications. Project management skills continue to make the list, as these skills are
crucial to prioritizing business needs and implementing effective solutions. Table 1-4
shows the results of the latest survey, as well as the percentage of respondents who listed
the skill as being in demand. Even if you choose to stay in a technical role, you still
need project management knowledge and skills to help your team and your organization
succeed.
TABLE 1-4
Skill Percentage of Respondents
Programming and application development 48
Project management 35
Help desk/technical support 30
Security/compliance governance 28
Web development 28
Database administration 26
Business intelligence/analytics 24
Mobile application and device management 24
Networking 22
Big data 20
Source: Mary K. Pratt, “10 Hottest IT Skills for 2015,” Computerworld, November 18, 2014.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

28 1.6 THE PROJECT MANAGEMENT PROFESSION
The project management profession is growing at a very rapid pace. To understand this
line of work, it is helpful to briefly review the history of project management, learn about
the Project Management Institute (PMI) and some of its services (such as certification),
and examine the growth in project management software.
1.6a History of Project Management
Most people think that project management is a 20th century invention. But Mark Kozak-
Holland, certified PMP and author of books that mine history for insight about project man-
agement, says that’s wrong. He notes that major historical projects closely resemble today’s
project management best practices. About his 2011 book The History of Project Manage-
ment, he said, “The general perception of most people is that project management started in
the mid-20th century, or started earlier with Henry Gantt and his charts. . . . Yet, how were
all the great projects of the past delivered? Think about the Giza Pyramid, the Parthenon, the
Coliseum, the Gothic Cathedrals of Medieval Europe, the great voyages of exploration, the Taj
Mahal, and the mega projects of the industrial revolutions. Was project management used on
these projects? Were the concepts of project management even understood? Can we connect
modern and ancient project management?” Kozak-Holland’s answer to these questions is
“yes.” You can see the PMBOK process groups and techniques from the knowledge areas in all
of these historical projects. Project management has been around since 2550 B.C.E.31
Although people have worked on projects for centuries, most agree that the modern con-
cept of project management began with the Manhattan Project, which the U.S. military led to
develop the atomic bomb in World War II. The Manhattan Project involved many people with
different skills at several different locations. It also clearly separated the overall manage-
ment of the project’s mission, schedule, and budget under General Leslie R. Groves and the
technical management of the project under the lead scientist, Dr. Robert Oppenheimer. The
Manhattan Project lasted about three years and cost almost $2 billion in 1946.
In developing the project, the military realized that scientists and other technical
specialists often did not have the desire or the necessary skills to manage large projects.
For example, after being asked several times for each team member’s responsibilities at
the new Los Alamos laboratory in 1943, Dr. Oppenheimer tossed the project organization
chart at his director and said, “Here’s your damn organization chart.”32 Project manage-
ment was recognized as a distinct discipline requiring people with special skills and, more
importantly, the desire to lead project teams.
In 1917, long before the Manhattan project, Henry Gantt developed the famous Gantt
chart for scheduling work in factories. A Gantt chart is a standard format for displaying
project schedule information by listing project activities and their corresponding start
and finish dates in calendar form. Initially, managers drew Gantt charts by hand to
show project tasks and schedule information. This tool provided a standard format for
planning and reviewing all the work on early military projects.
Today’s project managers still use the Gantt chart as the primary tool to communicate
project schedule information, but with the aid of computers, it is no longer necessary to draw
the charts by hand, and they are easier to share and disseminate to project stakeholders.
Figure 1-6 displays a Gantt chart created with Project 2013, the most widely used project
management software today. You will learn more about using Project 2013 in Appendix A.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

29
FIGURE 1-6
During the Cold War years of the 1950s and ‘60s, the military continued to play an
important role in refining several project management techniques. Members of the U.S.
Navy Polaris missile/submarine project first used network diagrams in 1958. These dia-
grams helped managers model the relationships among project tasks, which allowed them
to create schedules that were more realistic. Figure 1-7 displays a network diagram cre-
ated using Project 2013. Note that the diagram includes arrows that show which tasks
are related and the sequence in which team members must perform the tasks. The con-
cept of determining relationships among tasks is essential in helping to improve project
scheduling. This concept allows you to find and monitor the critical path—the longest
path through a network diagram that determines the earliest completion of a project. It
shows you which tasks affect the target completion date of a project, and it can change as
work proceeds and more information becomes available. You will learn more about Gantt
charts, network diagrams, critical path analysis, and other time management concepts in
Chapter 6, Project Time Management.
By the 1970s, the U.S. military and its civilian suppliers had developed software to
assist in managing large projects. Early project management software was very expensive
to purchase, and it ran exclusively on mainframe computers. For example, Artemis was an
early project management software product that helped managers analyze complex sched-
ules for designing aircraft. A full-time employee was often required to run the complicated
software, and expensive pen plotters were used to draw network diagrams and Gantt
charts.
As computer hardware became smaller and more affordable and software companies
developed graphical, easy-to-use interfaces, project management software became less
expensive and more widely used. This made it possible—and affordable—for many indus-
tries worldwide to use project management software on all types and sizes of projects. New
software makes basic tools such as Gantt charts and network diagrams inexpensive, easy
to create, and available for anyone to update. See the section later in this chapter on proj-
ect management software for more information.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

FIGURE 1-7
In the 1990s, many companies began creating Project Management Offices to help
them handle the increasing number and complexity of projects. A Project Management
Office (PMO) is an organizational group responsible for coordinating the project manage-
ment function throughout an organization. A 2014 study found that 80 percent of U.S.
companies reported having PMOs. Figure 1-8 shows the percentage of companies with
PMOs based on past surveys.33 For large organizations, 90 percent reported having PMOs
in 2014, while 61 percent of small organizations did. The percentage of large organiza-
tions with PMOs was about the same in 2010, but only 48 percent of small organizations
had PMOs in 2010. This increase shows the growing importance of using standard project
management processes in organizations of all sizes.
There are different ways to structure a PMO, and they can have various roles and
responsibilities. Organizations continue to modify their PMOs to ensure they add
value to their unique situations. For some organizations with very mature project
management processes and experienced managers, a small PMO focusing on organiz-
ing all project data might be all that is needed. For an organization new to project
management, a larger PMO might be needed focusing on training and standards. PM
Solutions identified three key factors that are playing major roles in the growth
of PMOs:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Percentage of Companies with PMOs
47
77
84
80
0
20
40
60
80
100
2010 201420062000
Year
Pe
rc
en
ta
ge
FIGURE 1-8
1. The growing strategic value of the PMO
2. The increased role of the PMO in training
3. The ever-present challenge of resource management
Below are possible goals of a PMO:
Collect, organize, and integrate project data for the entire organization.
Ensure that the organization’s approaches for project management include
accepted and validated best practices.
Audit project documentation and offer feedback on project managers’
approaches and compliance with standards.
Develop and maintain templates, tools, and standards for project documents
and project methodologies to be used.
Develop or coordinate training in various project management topics.
Provide a formal career path for project managers.
Provide project management consulting services.
Provide a structure or department that project managers belong to while they
are assigned to a project or are between projects.
By the end of the 20th century, people in virtually every industry around the globe
began to investigate and apply different aspects of project management to their projects.
The sophistication and effectiveness with which project management tools are being
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

32
applied and used today is enabling companies to do business, use resources, and respond
to market requirements with greater speed and accuracy.
Many colleges, universities, and companies around the world now offer courses
related to different aspects of project management. You can even earn bachelor’s, master’s,
and doctoral degrees in project management. In late 2014, a gradschools.com search for
“project management” found 370 campus and online accredited graduate, certificate, and
doctoral programs from all types of institutions. PMI reported in 2015 that formal educa-
tion programs in project management continue to grow, especially in China and India,
where many infrastructure projects are needed. “In China, for example, the 104 institu-
tions offering project management programs receive more than 20,000 applications each
year.” As projects become more global and teams are no longer stationed in the same city
or even country, students are learning a common project management language no matter
where they seek their education.34
The problems organizations have in managing projects, increasing education in proj-
ect management, and the belief that it can make a difference continue to contribute to the
growth of this field.
1.6b The Project Management Institute
Although many professional societies suffer from declining membership, the Project
Management Institute (PMI), an international professional society for project manag-
ers founded in 1969, has continued to attract and retain members, reporting more than
449,000 members worldwide by late 2014. Because so many people work on projects in
different industries across the globe (51 million total according to PMI), PMI has created
communities of practice that enable members to share ideas about project management in
their particular application areas, such as information systems. PMI also has communities
G L O B A L I S S U E S
Based on a survey of more than 1,000 project management leaders across a variety of
experience levels and industries, several global dynamics are forcing organizations to
rethink their practices:
Talent development for project and program managers is a top concern. Seventy per-
cent of organizations have a career path for project and program management, but
most are still informal and not documented.
Basic project management techniques are core competencies. Seventy percent of
organizations said that they always or often use basic practices like change man-
agement and risk management on their projects.
Organizations want to use more agile approaches to project management. One-
quarter of survey respondents said they now use agile techniques, and agile proj-
ect management was the most requested article topic.
Benefits realization of projects is a key metric. Organizations know that they
need to align projects and programs with the organization’s business strategy.35
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

33P M I S T U D E N T M E M B E R S H I P
As a student, you can join PMI for a reduced fee ($32 versus $139 in 2015). Consult
PMI’s website (www.pmi.org) for more information. With student membership, you can
network with other project management students by joining a local PMI chapter. Many
welcome students to attend free events, including talks and job networking. You can vol-
unteer your services to help develop your skills and serve your community. You can also
qualify for the Certified Associate in Project Management (CAPM) certification with just
a bachelor’s degree and a course in project management.
for aerospace/defense, financial services, government, healthcare, and agile techniques, to
name a few. Note that there are other project management professional societies, such as
the International Project Management Association (IPMA) and the Association for Project
Management (APM).
1.6c Project Management Certification
Professional certification is an important factor in recognizing and ensuring quality in
a profession. PMI provides certification as a Project Management Professional (PMP)
— someone who has documented sufficient project experience and education, agreed to fol-
low the PMI code of professional conduct, and demonstrated knowledge of project manage-
ment by passing a comprehensive examination. Note that you do not need work experience
to qualify for CompTIA’s Project+ certification or PMI’s CAPM certification, so college gradu-
ates just entering the workforce can earn these certifications and become more marketable.
The number of people earning PMP certification continues to increase. In 1993, there
were about 1,000 certified project management professionals. At the end of April 2015,
there were 658,523 active PMPs.36 Figure 1-9 shows the rapid growth in the number of
people earning project management professional certification from 1993 to 2014.
Several studies show that organizations supporting technical certification programs
tend to operate in more complex IT environments and are more efficient than organiza-
tions that do not support certification. Likewise, organizations that support PMP certifi-
cation see the value of investing in programs to improve their employees’ knowledge in
project management. Many employers today require specific certifications to ensure that
their workers have current skills, and job seekers find that they often have an advantage
when they earn and maintain marketable certifications. Global Knowledge listed PMP certi-
fication as number 5 in their list of top-paying certifications for 2014.37
As IT projects become more complex and global in nature, the need for people with
demonstrated knowledge and skills in project management will continue. Just as passing
the CPA exam is a standard for accountants, passing the PMP exam is becoming a stan-
dard for project managers. Some companies require that all project managers be PMP cer-
tified. Project management certification is also enabling professionals in the field to share
a common base of knowledge. For example, any person with PMP certification can list,
describe, and use the 10 project management knowledge areas. Sharing a common base of
knowledge is important because it helps advance the theory and practice of project man-
agement. PMI also offers additional certifications, including agile techniques, scheduling,
risk, and program management.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter 1
34
1,000 1,900 2,800 4,400 6,41510,086
18,184
27,052
40,343
52,443
76,550
102,047
175,194
221,144
267,367
318,289
361,238
412,503
467,390
510,434
594,603
626,205
658,523
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
19
93
19
94
19
95
19
96
19
97
19
98
19
99
20
00
20
01
20
02
20
03
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
20
13
20
14
20
15
Year
N
um
be
r
of
P
M
Ps
© Cengage Learning 2016
FIGURE 1-9 Growth in PMP Certification, 1993–2014
1.6d Ethics in Project Management
Ethics, loosely defined, is a set of principles that guides decision making based on personal
values of what is considered right and wrong. Making ethical decisions is an important part
of project managers’ personal and professional lives because it generates trust and respect
with other people. Project managers often face ethical dilemmas. If project managers can
make more money by taking bribes, should they? No! Should project managers accept
subpar work to meet a deadline? No! Ethics guide us in making these types of decisions.
PMI approved a Code of Ethics and Professional Conduct that took effect in January
2007. This code applies not only to PMPs but to all PMI members who hold a PMI certifica-
tion, apply for a PMI certification, or serve PMI in a volunteer capacity.
It is vital for project management practitioners to conduct their work in an ethical
manner. Even if you are not affiliated with PMI, these guidelines can help you conduct
your work in an ethical manner, which helps the profession earn the confidence of the
public, employers, employees, and all project stakeholders. The PMI Code of Ethics and
Professional Conduct includes short chapters addressing vision and applicability,
responsibility, respect, fairness, and honesty. A few excerpts from this document
include the following:
“As practitioners in the global project management community:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

35
2.2.1 We make decisions and take actions based on the best interests of society,
public safety, and the environment.
2.2.2 We accept only those assignments that are consistent with our background,
experience, skills, and qualifications.
2.2.3 We fulfill the commitments that we undertake—we do what we say we will do.
3.2.1 We inform ourselves about the norms and customs of others and avoid engag-
ing in behaviors they might consider disrespectful.
3.2.2 We listen to others’ points of view, seeking to understand them.
3.2.3 We approach directly those persons with whom we have a conflict or
disagreement.
4.2.1 We demonstrate transparency in our decision-making process.
4.2.2 We constantly reexamine our impartiality and objectivity, taking corrective
action as appropriate.
4.3.1 We proactively and fully disclose any real or potential conflicts of interest to
appropriate stakeholders.
5.2.1 We earnestly seek to understand the truth.
5.2.2 We are truthful in our communications and in our
conduct.”38
In addition, PMI added a new series of questions to the PMP certification exam in
March 2002 and continues to include this topic to emphasize the importance of ethics and
professional responsibility.
1.6e Project Management Software
Unlike the tale of the cobbler who neglected to make shoes for his own children, the proj-
ect management and software development communities have definitely responded to the
need to provide more software to help manage projects. As mentioned earlier, Microsoft
Project continues to lead the market with over 880,000 customers and 22 million users.
See Appendix A for details on the various configurations available for Microsoft Project
and detailed instructions for using Project Professional 2013, the product available for
a free trial. TopTenReviews.com has a category for online project management software
and listed Clarizen, GeniusProject, and AtTask as the top three products in 2014. There
are also several smartphone and tablet apps for project management. There are enough
options that deciding which project management software to use has become a project in
itself. This section summarizes the basic types of project management software available
and provides references for finding more information.
Many people still use basic productivity software such as Microsoft Word and Excel to
perform many project management functions, including determining project scope, time,
and cost, assigning resources, and preparing project documentation. People often use
productivity software instead of specialized project management software because they
M I C R O S O F T P R O J E C T 2 0 1 3
Appendix A includes a Guide to Using Microsoft Project 2013, which will help you
develop hands-on skills for using this popular project management software.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

36
already have it and know how to use it. However, hundreds of project management soft-
ware tools provide specific functionality for managing projects and performing portfolio
management. These software tools can be divided into three general categories based on
functionality and price:
Low-end tools: These tools provide basic project management features and gen-
erally cost less than $200 per user. Smartphone and tablet apps are available
for much less, but they often have limited functionality. Low-end tools are often
recommended for small projects and single users. Most of these tools allow users
to create Gantt charts, which cannot be done easily using current productivity
software.
Midrange tools: A step up from low-end tools, midrange tools are designed to
handle larger projects, multiple users, and multiple projects. All of these tools
can produce Gantt charts and network diagrams, and can assist in critical path
analysis, resource allocation, project tracking, and status reporting. Prices
range from about $200 to $1,000 per user, or less per month for online tools.
Several tools require additional server software for using workgroup features.
High-end tools: These tools are sometimes referred to as enterprise project
management software. They provide robust capabilities to handle very large
projects and dispersed workgroups, and they have enterprise and portfolio
management functions that summarize and combine individual project infor-
mation to provide an enterprise view of all projects. These products are gen-
erally licensed on a per-user basis, can be integrated with enterprise database
management software, and are accessible via the Internet.
Several free or open-source tools are also available. For example, Basecamp, Trello,
and Asana offer free online tools that may work for some projects and offer paid products
to meet more complex needs. Most companies, including Microsoft, offer free trials of their
project management software. ProjectLibre, LibrePlan, and OpenProject are all free open-
source project management tools. Remember, however, that open-source tools are devel-
oped, managed, and maintained by volunteers and may not be well supported.
There are many reasons to study project management, particularly as it relates to IT
projects. The number of IT projects continues to grow in almost every industry the com-
plexity of these projects continues to increase, and the profession of project management
continues to expand and mature. As more people study and work in this important field,
the success rate of IT projects should continue to improve.
C A S E W R A P – U P
Anne Roberts worked with the VPs and the CEO to form teams to help identify potential
IT projects that would support their business strategies. They formed a project team to
implement a portfolio project management software tool across the organization. They
formed another team to develop project-based reward systems for all employees. They
also authorized funds for a project to educate all employees in project management, to
help people earn PMP and related certifications, and to develop a mentoring program.
Anne had successfully convinced everyone that effectively managing projects was crucial
to their company’s future.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

37Chapter Summary





Quick Quiz
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

38

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

39
Quick Quiz Answers
Discussion Questions


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Exercises


www.pmi.org
®

www.microsoft.com

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Key Terms
best practice p. 20
critical path p. 29
enterprise project
management software p. 21
ethics p. 34
Gantt chart p. 28
leader p. 26
manager p. 26
program p. 17
program manager p. 18
project p. 4
project and portfolio
management software p. 21
project management p. 9
Project Management Institute (PMI) p. 32
project management knowledge areas p. 11
Project Management Office (PMO) p. 30
Project Management Professional (PMP) p. 33
project management tools and
techniques p. 12
project manager p. 7
project portfolio management or portfolio
management p. 18
project sponsor p. 7
stakeholders p. 10
triple constraint p. 7
End Notes
vitalsigns.changetheequation.org/#us-United%20
States-Demand (2014).
Project Management Salary Survey
Forbes
® –
www.standishgroup.com
Application Development
Trends
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide)
Forbes
Business Insider
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

42
PMI Research Conference Proceedings
The Hill
Proceedings of PMI Research Conference, London
Proceedings
of the Project Management Institute Annual Seminars & Symposium
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide)
PMI Houston Chapter Meeting
Organizational Project Management Maturity Model (OPM3)
Knowledge Foundation
Best Practice: Ideas and Insights from the World’s Foremost
Business Thinkers
jobs.monster.com/v-project
-management.aspx
CIO.com
PMI Research Conference Proceedings
Computerworld
youtube/dYgMT57I7UI.
PMI’s Pulse of the Profession: Driving Success in Challeng-
ing Times
PMI Today
PMP Credential Handbook
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R 2
THE PROJECT
MANAGEMENT AND
INFORMATION TECHNOLOGY
CONTEXT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

44
Many of the theories and concepts of project management are not difficult to understand.
What is difficult is implementing them in various environments. Project managers must
consider many different issues when managing projects. Just as each project is unique, so
is its environment. This chapter discusses some of the concepts involved in understanding
the project environment, such as using a systems approach, understanding organizations,
managing stakeholders, matching product life cycles to the project environment, under-
standing the context of IT projects, and reviewing recent trends that affect IT project
management.
O P E N I N G C A S E
Tom Walters recently accepted a new position at his college as the Director of Informa-
tion Technology. Tom had been a respected faculty member at the college for the past
15 years. The college—a small, private institution in the Southwest—offers a variety
of programs in the liberal arts and professional areas. Enrollment includes 1,500 full-
time traditional students and about 1,000 working adults who attend evening programs.
Many instructors supplement their courses with information on the Internet and course
websites, but the college does not offer distance-learning programs. The college’s niche is
serving students in the region who like the setting of a small liberal arts college and want
to make connections with each other and their community.
Like other institutions of higher learning, the use of IT at the college has grown
tremendously in the past 10 years. Wi-Fi is available everywhere on campus. But only a
few classrooms on campus have computers for the instructors and students, and most
other classrooms have only instructor stations and projection systems. Tom knew that sev-
eral colleges throughout the country require that all students lease or own laptops or tab-
lets and that these colleges incorporate technology into most courses. This idea fascinated
him. He and two other members of the IT department visited a local college that had re-
quired all students to lease laptops for the past three years, and they were very impressed
with what they saw and heard. Because tablets were becoming more popular, they thought
it would make more sense to require tablets instead of laptops. Tom had heard how easy it
was for faculty members to create interactive course materials that would run on tablets;
these materials also could help reduce the cost of textbooks, a concern expressed by many
students. Tom and his staff developed plans to start requiring students either to lease or
purchase tablets at their college starting the next academic year.
Tom sent an e-mail to all faculty and staff in September, and briefly described his
plans. He did not get much response, however, until the February faculty meeting. As he
described some of the details of his plan, the chairs of the History, English, Philosophy,
and Economics departments all voiced opposition to the idea. They eloquently stated
that the college was not a technical training school and that they did not have time
to write their own course materials to run on tablets. They liked the books they used,
and students could already buy books in an electronic format, but most preferred the
print versions. Members of the Computer Science department voiced their concern that
almost all of their students already had state-of-the art laptops and would not want to
pay a mandatory fee to lease less-powerful tablets. The director of the adult education
program expressed her concern that many adult-education students would balk at
an increase in fees or required technology. Tom was in shock to hear his colleagues’
responses, especially after he and his staff had spent a lot of time planning how to
implement tablets at their campus. Now what should he do?
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

45
2.1 A SYSTEMS VIEW OF PROJECT MANAGEMENT
Even though projects are temporary and intended to provide a unique product or service,
you cannot run projects in isolation. If project managers lead projects in isolation, it is
unlikely that they will ever truly serve the needs of the organization. Therefore, projects
must operate in a broad organizational environment, and project managers need to con-
sider projects within the greater organizational context. To handle complex situations
effectively, project managers need to take a holistic view of a project and understand how
it relates to the larger organization. Systems thinking describes this holistic view of carry-
ing out projects within the context of the organization.
2.1a What Is a Systems Approach?
The term systems approach emerged in the 1950s to describe a holistic and analytical
approach to solving complex problems that includes using a systems philosophy, systems
analysis, and systems management. Systems are sets of interacting components that
work within an environment to fulfill some purpose. For example, the human body is
a system composed of many subsystems, including the nervous system, the skeletal
system, the circulatory system, and the digestive system. Organizations are also systems,
with people in various roles working together to design, develop, deliver, and sell vari-
ous products and services. A systems philosophy is an overall model for thinking about
things as systems.
Systems analysis is a problem-solving approach that requires defining the scope of
the system, dividing it into components, and then identifying and evaluating its prob-
lems, opportunities, constraints, and needs. Once this is completed, the systems ana-
lyst then examines alternative solutions for improving the current situation; identifies
an optimum, or at least satisfactory, solution or action plan; and examines that plan
against the entire system. Systems management addresses the business, technological,
and organizational issues associated with creating, maintaining, and modifying
a system.
Using a systems approach is critical to successful project management. If top manage-
ment and project managers are to understand how projects relate to the whole organization,
they must follow a systems philosophy. They must use systems analysis to address needs
with a problem-solving approach. They must use systems management to identify key issues
in business, technological, and organizational spheres related to each project in order to
identify and satisfy key stakeholders and do what is best for the entire organization.
In the chapter’s opening case, Tom Walters planned the tablet project without using
a systems approach. Members of his IT department did all of the planning. Even though
Tom sent an e-mail describing the tablet project to all faculty and staff, he did not ad-
dress many of the organizational issues involved in such a complex project. Most faculty
and staff are very busy at the beginning of the fall term, and many may not have read the
entire message. Others may have been too busy to communicate their concerns to the IT
department. Tom was unaware of the effects the tablet project would have on other parts
of the college. He did not clearly define the business, technological, and organizational
issues associated with the project. Tom and the IT department began work on the tablet
project in isolation. If they had taken a systems approach, considering other dimensions
of the project and involving key stakeholders, they could have identified and addressed
many of the issues raised at the February faculty meeting before the meeting.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

46
2.1b The Three-Sphere Model for Systems Management
Many business and IT students understand the concepts of systems and performing a
systems analysis. At the same time, they often overlook systems management. However,
addressing the three spheres of systems management—business, organization, and tech-
nology—can have a huge impact on selecting and managing projects successfully.
Figure 2-1 provides a sample of business, organizational, and technological issues that
could be factors in the tablet project. In this case, technological issues, though not simple by
any means, are probably the least difficult to identify and resolve. However, projects must
address issues in all three spheres of the systems management model. Although it is easier
to focus on the immediate and sometimes narrow concerns of a particular project, project
managers and other staff must recognize the effects of any project on the interests and
needs of the entire system or organization. The college president and senior administrators,
in particular, will focus on whether the tablet project adds value to the college as a whole.
Business
Organization Technology
e
FIGURE 2-1
Many IT professionals become captivated with the technology and day-to-day problem
solving involved in working with information systems. They tend to become frustrated
with many of the “people problems” or politics involved in most organizations. In addi-
tion, many IT professionals ignore important business questions, such as “Does it make
financial sense to pursue this new technology?” or “Should the company develop this soft-
ware in-house or purchase it off the shelf?” Using a more holistic approach helps project
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

47
managers integrate business and organizational issues into their planning. It also helps
them look at projects as a series of interrelated phases. When you integrate business and
organizational issues into project management planning and look at projects as a series of
interrelated phases, you do a better job of ensuring project success.
2.2 UNDERSTANDING ORGANIZATIONS
The systems approach requires that project managers always view their projects in the con-
text of the larger organization. Organizational issues are often the most difficult part of work-
ing on and managing projects. In fact, many people believe that most projects fail because
of organizational issues like company politics. Project managers often do not spend enough
time identifying all the stakeholders involved in projects, especially the people opposed to
the projects. Also, project managers often do not spend enough time considering the politi-
cal context of a project or the culture of the organization. To improve the success rate of IT
projects, it is important for project managers to develop a better understanding of people as
well as organizations.
2.2a The Four Frames of Organizations
As shown in Figure 2-2, you can try to understand organizations better by focusing on
different perspectives. Organizations can be viewed as having four different frames:
structural, human resources, political, and symbolic.1
The structural frame deals with how the organization is structured (usually
depicted in an organizational chart) and focuses on different groups’ roles and
responsibilities to meet the goals and policies set by top management. This
frame is very rational and focuses on coordination and control. For example,
within the structural frame, a key IT issue is whether a company should central-
ize the IT personnel in one department or decentralize across several depart-
ments. You will learn more about organizational structures in the next section.
The human resources (HR) frame focuses on producing harmony between
the needs of the organization and the needs of people. It recognizes that
mismatches can occur between the needs of the organization and those
of individuals and groups, and works to resolve any potential problems.
For example, many projects might be more efficient for the organization if
employees worked 80 or more hours a week for several months. However,
this work schedule would conflict with the personal lives and health of many
FIGURE 2-2
Structural frame: Roles
and responsibilities,
coordination, and control.
Organizational charts help
describe this frame.
Human resources frame:
Providing harmony
between needs of the
organization and needs
of people.
Political frame: Coalitions
composed of varied
individuals and interest
groups. Conflict and
power are key issues.
Symbolic frame: Symbols
and meanings related to
events. Culture, language,
traditions, and image are
all parts of this frame.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

48
employees. Important IT issues related to the human resources frame are the
shortage of skilled IT workers within the organization and unrealistic sched-
ules imposed on many projects.
The political frame addresses organizational and personal politics. Politics in
organizations take the form of competition among groups or individuals for
power, resources, and leadership. The political frame emphasizes that orga-
nizations are coalitions composed of varied individuals and interest groups.
Often, important decisions need to be made about the allocation of scarce
resources. Competition for resources makes conflict a central issue in orga-
nizations, and power improves the ability to obtain those resources. Project
managers must pay attention to politics and power if they are to be effective.
It is important to know who opposes your projects as well as who supports
them. Important IT issues related to the political frame are the differences in
power between central functions and operating units or between functional
managers and project managers.
The symbolic frame focuses on symbols and meanings. In this frame, the
most important aspect of any event in an organization is not what actually
happened, but what it means. Was it a good sign that the CEO came to a
kick-off meeting for a project, or was it a threat? The symbolic frame also
relates to the company’s culture. How do people dress? How many hours do
they work? How do they run meetings? Many IT projects are international
and include stakeholders from various cultures. Understanding those cultures
is also a crucial part of the symbolic frame.
Project managers must learn to work within all four frames to function well in organi-
zations. Organizational issues are discussed further in Chapter 9, Project Human Resource
Management, Chapter 10, Project Communications Management, and Chapter 13, Project
Stakeholder Management. The following sections on organizational structures, organiza-
tional culture, stakeholder management, and the need for top management commitment
provide additional information related to the structural and political frames.
W H A T W E N T W R O N G ?
In a paper titled “A Study in Project Failure,” two researchers examined the success and
failure of 214 IT projects over an eight-year period in several European countries. The
researchers found that only one in eight (12.5 percent) were considered successful in
terms of meeting scope, time, and cost goals. The authors made the following conclusions
about factors that contribute to a project’s failure:
“Our evidence suggests that the culture within many organisations is often such that
leadership, stakeholder and risk management issues are not factored into projects early
on and in many instances cannot formally be written down for political reasons and are
rarely discussed openly at project board or steering group meetings although they may be
discussed at length behind closed doors. … Despite attempts to make software develop-
ment and project delivery more rigorous, a considerable proportion of delivery effort re-
sults in systems that do not meet user expectations and are subsequently cancelled. In our
view this is attributed to the fact that very few organisations have the infrastructure, edu-
cation, training, or management discipline to bring projects to successful completion.”3
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

49
2.2b Organizational Structures
Many discussions of organizations focus on their structure. Three general classifications of
organizational structures are functional, project, and matrix. Many companies today use all
three structures somewhere in the organization, but using one is most common. Figure 2-3
portrays the three organizational structures. A functional organizational structure is the
hierarchy most people think of when picturing an organizational chart. Functional manag-
ers or vice presidents in specialties such as engineering, manufacturing, IT, and human
resources report to the chief executive officer (CEO). Their staffs have specialized skills in
their respective disciplines. For example, most colleges and universities have very strong
functional organizations. Only faculty members in the business department teach busi-
ness courses; faculty in the history department teach history; faculty in the art department
teach art, and so on.
VP Engineering VP Manufacturing VP IT VP HR
CEO
Staff Staff Staff Staff
Functional
Program Manager A
CEO
Staff Staff Staff
Project
Program Managers
CEO
Staff Staff Staff
Matrix
VP Engineering VP HR
Staff
VP Manufacturing
Staff
VP IT
Project Manager A: 2 engineering 1/2 HR1 manufacturing 31/2 IT
Project Manager B: 5 engineering 1 HR3 manufacturing 10 IT
Project Manager C: 1 engineering 1/10 HR0 manufacturing 4 IT
Program Manager B Program Manager C
FIGURE 2-3
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

A project organizational structure also is hierarchical, but instead of functional man-
agers or vice presidents reporting to the CEO, program managers report to the CEO. Their
staffs have a variety of skills needed to complete the projects within their programs. An
organization that uses this structure earns its revenue primarily from performing projects
for other groups under contract. For example, many defense, architectural, engineering,
and consulting companies use a project organizational structure. These companies often
hire people specifically to work on particular projects.
A matrix organizational structure represents the middle ground between functional
and project structures. Personnel often report both to a functional manager and one or more
project managers. For example, IT personnel at many companies often split their time be-
tween two or more projects, but they report to their manager in the IT department. Project
managers in matrix organizations have staff from various functional areas working on their
projects, as shown in Figure 2-3. Matrix organizational structures can be strong, weak, or bal-
anced, based on the amount of control exerted by the project managers. Problems can occur
if project team members are assigned to several projects in a matrix structure and the project
manager does not have adequate control of their time.
Table 2-1 summarizes how organizational structures influence projects and project
managers, based on information from several versions of the PMBOK® Guide. Project
managers have the most authority in a pure project organizational structure and the least
amount of authority in a pure functional organizational structure. It is important that proj-
ect managers understand their current organizational structure. For example, if someone in
a functional organization is asked to lead a project that requires strong support from several
different functional areas, he or she should ask for top management sponsorship. This spon-
sor should solicit support from all relevant functional managers to ensure that they cooper-
ate on the project and that qualified people are available to work as needed. The project
manager might also ask for a separate budget to pay for project-related trips, meetings, and
training or to provide financial incentives to the people supporting the project.
TABLE 2-1
Project
Characteristics
Organizational Structure Type
Functional Matrix Project
Weak
Matrix
Balanced
Matrix
Strong
Matrix
Project manager’s
authority
Little or
none
Limited Low to
moderate
Moderate to
high
High to
almost total
Percent of organization’s
personnel assigned full-
time to project work
Virtually
none
0–25% 15–60% 50–95% 85–100%
Who controls the project
budget
Functional
manager
Functional
manager
Mixed Project
manager
Project
manager
Project manager’s role Part-time Part-time Full-time Full-time Full-time
Common title for project
manager’s role
Project
coordinator/
project
leader
Project
coordinator/
project
leader
Project
manager/
project
officer
Project
manager/
program
manager
Project
manager/
program
manager
Project management
administrative staff
Part-time Part-time Part-time Full-time Full-time
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Even though project managers have the most authority in the project organizational
structure, this type of organization is often inefficient for the company as a whole. Assign-
ing staff full-time to the project often creates underutilization and misallocation of staff
resources. For example, if a technical writer is assigned full-time to a project, but has no
project work on a particular day, the organization is wasting money by paying that person
a full-time wage. Project organizations may also miss economies of scale that are available
through pooling requests for materials with other projects.
Disadvantages such as these illustrate the benefit of using a systems approach to
managing projects. For example, the project manager might suggest hiring an independent
contractor to do the technical writing work instead of using a full-time employee. This
approach would save the organization money while still meeting the needs of the project.
When project managers use a systems approach, they are better able to make decisions
that address the needs of the entire organization.
2.2c Organizational Culture
Just as an organization’s structure affects its ability to manage projects, so does its culture.
Organizational culture is a set of shared assumptions, values, and behaviors that char-
acterize the functioning of an organization. It often includes elements of all four frames
described previously. Organizational culture is very powerful, and many people believe the
underlying causes of many companies’ problems are not in the organizational structure or
staff; they are in the culture. It is also important to note that the same organization can
have different subcultures. The IT department may have a different organizational culture
than the finance department, for example. Some organizational cultures make it easier to
manage projects.
According to Stephen P. Robbins and Timothy Judge, authors of a popular textbook on
organizational behavior, there are 10 characteristics of organizational culture:
1. Member identity: The degree to which employees identify with the organiza-
tion as a whole rather than with their type of job or profession. For example,
project managers or team members might feel more dedicated to their com-
pany or project team than to their job or profession, or they might not have
any loyalty to a particular company or team. As you can guess, an organiza-
tional culture in which employees identify more with the whole organization
are more conducive to a good project culture.
2. Group emphasis: The degree to which work activities are organized around
groups or teams, rather than individuals. An organizational culture that em-
phasizes group work is best for managing projects.
3. People focus: The degree to which management’s decisions take into account
the effect of outcomes on people within the organization. A project manager
might assign tasks to certain people without considering their individual
needs, or the project manager might know each person very well and focus
on individual needs when assigning work or making other decisions. Good
project managers often balance the needs of individuals and the organization.
4. Unit integration: The degree to which units or departments within an organi-
zation are encouraged to coordinate with each other. Most project managers
strive for strong unit integration to deliver a successful product, service, or
result. An organizational culture with strong unit integration makes the proj-
ect manager’s job easier.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

5. Control: The degree to which rules, policies, and direct supervision are used to
oversee and control employee behavior. Experienced project managers know it
is often best to balance the degree of control to get good project results.
6. Risk tolerance: The degree to which employees are encouraged to be aggres-
sive, innovative, and risk seeking. An organizational culture with a higher risk
tolerance is often best for project management because projects often involve
new technologies, ideas, and processes.
7. Reward criteria: The degree to which rewards, such as promotions and salary
increases, are allocated according to employee performance rather than senior-
ity, favoritism, or other nonperformance factors. Project managers and their
teams often perform best when rewards are based mostly on performance.
8. Conflict tolerance: The degree to which employees are encouraged to air
conflicts and criticism openly. It is very important for all project stakeholders
to have good communications, so it is best to work in an organization where
people feel comfortable discussing differences openly.
9. Means-ends orientation: The degree to which management focuses on out-
comes rather than on techniques and processes used to achieve results. An
organization with a balanced approach in this area is often best for
project work.
10. Open-systems focus: The degree to which the organization monitors and
responds to changes in the external environment. As you learned earlier in
this chapter, projects are part of a larger organizational environment, so it is
best to have a strong open-systems focus.4
As you can see, there is a definite relationship between organizational culture and
successful project management. Project work is most successful in an organizational
culture where employees identify more with the organization, where work activities
emphasize groups, and where there is strong unit integration, high risk tolerance,
performance-based rewards, high conflict tolerance, an open-systems focus, and a
balanced focus on people, control, and means orientation.
2.3 FOCUSING ON STAKEHOLDER NEEDS
Recall from Chapter 1 that project stakeholders are the people involved in or affected by
project activities. Stakeholders can be internal or external to the organization, directly in-
volved in the project, or simply affected by the project. Internal project stakeholders include
the project sponsor, project team, support staff, and internal customers of the project. Other
internal stakeholders include top management, other functional managers, and other project
managers. Projects affect these additional internal stakeholders because they use the organi-
zation’s limited resources. Thus, while additional internal stakeholders may not be directly
involved in the project, they are still stakeholders because the project affects them in some
way. External project stakeholders include the project’s customers (if they are external to
the organization), competitors, suppliers, and other external groups potentially involved in
the project or affected by it, such as government officials or concerned citizens.
Because the purpose of project management is to meet project requirements and
satisfy stakeholders, it is critical that project managers take adequate time to identify,
understand, and manage relationships with all project stakeholders. Using the four frames
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

53
of organizations to think about project stakeholders can help you meet their expectations.
See Chapter 13, Project Stakeholder Management, for more information.
Consider again the tablet project from the opening case. Tom Walters seemed to focus
on just a few internal project stakeholders. He viewed only part of the structural frame of
the college. Because his department would do most of the work in administering the tablet
project, he concentrated on those stakeholders. He did not even involve the main custom-
ers for this project—the students at the college. Even though Tom sent an e-mail to faculty
and staff, he did not hold meetings with senior administrators or faculty at the college.
Tom’s view of the project stakeholders was very limited.
During the faculty meeting, it became evident that the tablet project had many stake-
holders in addition to the IT department and students. If Tom had expanded his view of the
structural frame of his organization by reviewing an organizational chart for the entire college,
he could have identified other key stakeholders. He would have been able to see that the proj-
ect would affect academic department heads and members of different administrative areas,
especially if he wanted faculty members to develop customized course materials themselves.
If Tom had focused on the human resources frame, he would have been able to tap into his
knowledge of the school and identify people who would most support or oppose requiring
tablets. By using the political frame, Tom could have considered the main interest groups that
would be most affected by the project’s outcome. Had he used the symbolic frame, Tom could
have tried to address what moving to a tablet environment would really mean for the college.
He then could have anticipated some of the opposition from people who were not in favor of
increasing the use of technology on campus. He also could have solicited a strong endorse-
ment from the college president or dean before talking at the faculty meeting.
Tom Walters, like many new project managers, learned the hard way that technical
and analytical skills were not enough to guarantee success in project management. To
be more effective, he had to identify and address the needs of different stakeholders and
understand how his project related to the entire organization.
M E D I A S N A P S H O T
The media have often reported on mismanaged IT projects. One that really stands out
was the high profile website created for U.S. citizens to sign up for healthcare under the
Obama administration. When the new site opened on October 1, 2013, only about 3 in
10 people could successfully log in and even after they logged in, many were kicked off
due to numerous bugs. An article in Forbes put its finger on the source of the problems:
“HealthCare.gov Diagnosis: The Government Broke Every Rule of Project Management.”
The Centers for Medicare & Medicaid Services (CMS) was in charge of overseeing the
project, which suffered from several classic mistakes: unrealistic requirements, technical
complexity, poor integration, fragmented authority, loose metrics, an aggressive schedule,
and not reporting problems to senior management. The author of the Forbes article sug-
gests that CMS should have let more competent people run the project from the start.5
What happened soon after the disastrous launch? President Obama asked White
House chief of staff Denis McDonough to determine if the site could be fixed or if it
should be totally scrapped. McDonough asked Jeff Zients, a highly regarded business-
man slated to be director of the National Economic Council, and Todd Park, the White
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

54
House chief technology officer, to work full-time to fix HealthCare.gov. They assembled
a team of elite technologists from several firms, dubbed the “Obama Trauma Team,”
including Gabriel Burt, CTO of Civis Analytics; Mikey Dickerson, site-reliability engi-
neer at Google; Paul Smith, deputy director of the Democratic National Committee’s
tech operation; Marty Abbott, former CTO of eBay; Jini Kim, former Google employee
turned CEO of her own healthcare data-analytics service; and key engineers from QSSI
and CGI (the companies that developed the site). The team realized there was no dash-
board to measure what was really going on with the site, and in only five hours they
coded one.
Burt soon recruited Mike Abbot, a partner at Kleiner Perkins Caufield & Byers ven-
ture capital firm, to lead the team of technologists. Abbot had successfully led projects
at Twitter, Microsoft, and Palm, and people loved his low-key, results-driven leadership
style. Abbot successfully led the new team in fixing the site. They quickly implemented
solutions, like caching key data to speed up the site, and in about two months, the
website was remarkably stable and much faster than before. “In about a tenth of the time
that a crew of usual-suspect, Washington contractors had spent over $300 million build-
ing a site that didn’t work, this ad hoc team rescued it and, arguably, Obama’s chance at a
health-reform legacy.”6
2.3a The Importance of Top Management Commitment
A very important factor in helping project managers successfully lead projects is the level
of commitment and support they receive from top management. Without this commitment,
many projects will fail. Some projects have a senior manager called a champion who acts
as a key advocate for a project. The sponsor can serve as the champion, but often another
manager can more successfully take on this role. As described earlier, projects are part of
the larger organizational environment, and many factors that might affect a project are out
of the project manager’s control. Several studies cite executive support as one of the key
factors associated with virtually all project success.
Top management commitment is crucial to project managers for the following reasons:
Project managers need adequate resources. The best way to kill a project is to
withhold the required money, human resources, and visibility. If project manag-
ers have top management commitment, they will also have adequate resources
and not be distracted by events that do not affect their specific projects.
Project managers often require approval for unique project needs in a timely
manner. For example, on large IT projects, top management must understand
that unexpected problems may result from the nature of the products being
developed and the specific skills of people on the project team. The team
might need additional hardware and software halfway through the project for
proper testing, or the project manager might need to offer special pay and
benefits to attract and retain key project personnel. With top management
commitment, project managers can meet these needs.
Project managers must have cooperation from people in other parts of the
organization. Because most IT projects cut across functional areas, top man-
agement must help project managers deal with the political issues that often
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

55
arise. If certain functional managers are not responding to project managers’
requests for necessary information, top management must step in to encour-
age the functional managers to cooperate.
Project managers often need someone to mentor and coach them on leader-
ship issues. Many IT project managers come from technical positions and are
inexperienced as managers. Senior managers should take the time to give ad-
vice on how to be good leaders. They should encourage new project managers
to take classes to develop leadership skills and allocate the time and funds for
managers to do so.
IT project managers work best in an environment in which top management values IT.
Working in an organization that values good project management and sets standards for its
use also helps project managers succeed.
2.3b The Need for Organizational Commitment to Information Technology
Another factor that affects the success of IT projects is the organization’s commitment
to IT in general. It is very difficult for an IT project to be successful if the organization
itself does not value IT. Many companies have realized that IT is integral to their business
and have created a vice president or equivalent position for the head of IT, often called
B E S T P R A C T I C E
A major element of good practice concerns IT governance, which addresses the authority
for and control of key IT activities in organizations, including IT infrastructure, IT use,
and project management. (The term project governance can also be used to describe a
uniform method of controlling all types of projects.) The IT Governance Institute (ITGI)
was established in 1998 to advance international thinking and standards in directing and
controlling an organization’s use of technology. Effective IT governance helps ensure that
IT supports business goals, maximizes investment in IT, and addresses IT-related risks
and opportunities. A 2004 book by Peter Weill and Jeanne Ross titled IT Governance:
How Top Performers Manage IT Decision Rights for Superior Results7 includes research
indicating that firms with superior IT governance systems have 20 percent higher profits
than firms with poor governance.
A lack of IT governance can be dangerous, as evidenced by three well-publicized IT
project failures in Australia: Sydney Water’s customer relationship management system,
the Royal Melbourne Institute of Technology’s academic management system, and One.
Tel’s billing system. Researchers explained how these projects were catastrophic for their
organizations, primarily due to a severe lack of IT governance, which the researchers
dubbed managerial IT unconsciousness in a subsequent article:
“All three projects suffered from poor IT governance. Senior management in all
three organizations had not ensured that prudent checks and balances were in place to
enable them to monitor either the progress of the projects or the alignment and impact
of the new systems on their business. Proper governance, particularly with respect to fi-
nancial matters, auditing, and contract management, was not evident. Also, project-level
planning and control were notably absent or inadequate—with the result that project
status reports to management were unrealistic, inaccurate, and misleading.”8
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

56
the Chief Information Officer (CIO). Some companies assign people from non-IT areas to
work full-time on large projects and increase involvement from end users of the systems.
Some CEOs even take a strong leadership role in promoting the use of IT in their organi-
zations and empower employees to use IT effectively.
The leadership style of the CIO plays a crucial role in gaining organizational commit-
ment to IT as well as motivation and support for IT workers. A 2014 survey found that
76 percent of CIOs in companies in Europe, the Middle East, and Africa (EMEA) need
to adapt their leadership style to fully embrace digital business. “Command-and-control
leadership doesn’t suit this digital world,” said Dave Aron, vice president and Gartner
Fellow. “In fact, it can be an obstacle. Vision and inspiration are typically the most power-
ful attributes of digital leaders. CIOs must accept to flip from ‘control first’ to vision first.
In EMEA, 65 percent of CIOs said that they need to decrease their time on commanding
IT, while 45 percent of them said they need to increase their visionary leadership.”9
Empowering employees at all levels to effectively use IT is also crucial. For example,
Hilton Worldwide won a prestigious Customer Relationship Management (CRM) award
by enabling its employees to create their own solution for improving customer service
and loyalty. In addition to using the company’s Satisfaction and Loyalty Tracking (SALT)
customer analytics software to deliver key information in a timely manner, team members
created a more personal process to focus on using data to improve the guest experience
called HEART: Hear the Guest; Empathize with the Guest; Apologize to the Guest; Resolve
the Issue; and Thank the Guest. By following this process along with timely data, Hilton
Worldwide dramatically increased their customer loyalty score, which leads to higher
profits.10
2.3c The Need for Organizational Standards
Another problem in most organizations is a lack of standards or guidelines to follow when
performing project management. These standards or guidelines might be as simple as provid-
ing standard forms or templates for common project documents, examples of good project
management plans, or guidelines for how project managers should provide status information
to top management. The content of a project management plan and instructions for provid-
ing status information might seem like common sense to senior managers, but many new
IT project managers have never created plans or created a nontechnical status report. Top
management must support the development of these standards and guidelines, and encour-
age or even enforce their use. For example, an organization might require all potential project
information to be reported in a standard format to make project portfolio management deci-
sions. If a project manager does not submit a potential project in the proper format, it could
be rejected.
As you saw in Chapter 1, some organizations invest heavily in project management
by creating a project management office or center of excellence, which assists project
managers in achieving project goals and maintaining project governance. Rachel Hollstadt,
founder and retired CEO of a project management consulting firm, suggests that organiza-
tions consider adding a new position, a Chief Project Officer (CPO). Some organizations
develop career paths for project managers; some require that all project managers have
Project Management Professional (PMP) certification and that all employees have some
type of project management training. The implementation of such standards demonstrates
an organization’s commitment to project management.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

57
2.4 PROJECT PHASES AND THE PROJECT LIFE CYCLE
Because projects operate as part of a system and involve uncertainty, it is good practice to
divide projects into several phases. General phases in traditional project management are often
called the concept, development, implementation, and close-out phases. The PMBOK® Guide,
Fifth Edition calls these phases starting the project, organizing and preparing, carrying out the
project work, and finishing the project. (These phases should not be confused with the project
management process groups of initiating, planning, executing, monitoring and controlling, and
closing, which are described in Chapter 3.) Project phases vary by project or industry.
A project life cycle is a collection of phases. Phases break projects down into smaller,
more manageable pieces, which will reduce uncertainty. Some organizations specify a set of
life cycles for use in all of their projects, while others follow common industry practices based
on the types of projects involved. Project life cycles define what work will be performed in
each phase, what deliverables will be produced and when, who is involved in each phase, and
how management will control and approve work produced in each phase. A deliverable is a
product or service, such as a technical report, a training session, a piece of hardware, or a
segment of software code, produced or provided as part of a project. (See Chapter 5, Project
Scope Management, for detailed information on deliverables.)
In early phases of a project life cycle, resource needs are usually lowest and the level of
uncertainty is highest. Project stakeholders have the greatest opportunity to influence the
final characteristics of the project’s products, services, or results during the early phases of
a project life cycle. It is much more expensive to make major changes to a project during
later phases. During the middle phases of a project life cycle, the certainty of completing
the project improves as it continues and as more information is known about the project
requirements and objectives. Also, more resources are usually needed than during the
initial or final phase. The final phase of a project focuses on ensuring that project require-
ments were met and that the project sponsor approves completion of the project.
The first two traditional project phases (concept and development) focus on planning,
and are often referred to as project feasibility. The last two phases (implementation and close-
out) focus on delivering the actual work, and are often referred to as project acquisition. Each
phase of a project should be successfully completed before the team moves on to the next
phase. This project life cycle approach provides better management control and appropriate
links to the ongoing operations of the organization.
Figure 2-4 provides a summary of the general phases of the traditional project life
cycle. In the concept phase, managers usually develop a business case, which describes the
need for the project and basic underlying concepts. A preliminary or rough cost estimate is
developed in this first phase, and an overview of the required work is created.
One tool for creating an overview of the required work is a work breakdown structure
(WBS). A WBS outlines project work by decomposing the work activities into different
levels of tasks. The WBS is a deliverable-oriented document that defines the total scope of
the project. In the concept phase, a WBS usually has only two levels. (You will learn more
about the WBS in Chapter 5, Project Scope Management.)
In the opening case, Tom Walters could have followed the project life cycle instead of
moving full steam ahead with the tablet project. He could have initiated a concept phase
and created a committee of faculty and staff to study the concept of increasing the use of
technology on campus. This committee might have developed a business case and plan
that included an initial, smaller project to investigate alternative ways of increasing the
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Taurus

Taurus

58
use of technology. The committee might have estimated that it would take six months
and $20,000 to conduct a detailed technology study. The WBS at this phase of the study
might have three levels and partition the work to include a competitive analysis of what
five similar campuses were doing; a survey of local students, staff, and faculty; and a rough
assessment of how using more technology would affect costs and enrollments. At the end
of the concept phase, the committee would be able to deliver a report and presentation on
its findings. The report and presentation would be examples of deliverables.
Project feasibility Project acquisition
Business
case
Preliminary
cost estimate
2-level WBS
Project
management
plan
Budgetary cost
estimate
3+-level WBS
Execution of work
packages
Definitive cost
estimate
Performance
reports
Completed work
Lessons learned
Customer
acceptance
Concept Development Implementation Close-out
Sample
deliverables
for each
phase
FIGURE 2-4
After the concept phase is completed, the next project phase—development—begins.
In the development phase, the project team creates more detailed project management
plans, a more accurate cost estimate, and a more thorough WBS. In the example under
discussion, suppose the concept phase report suggested that requiring students to have
tablets was one means of increasing the use of technology on campus. The project team
could then further expand this idea in the development phase. The team would have to
decide if students would purchase or lease the tablets, what type of hardware and soft-
ware the tablets would require, how much to charge students, how to handle training and
maintenance, and how to integrate the use of the new technology with current courses.
However, if the concept phase report showed that tablets were not a good idea for the col-
lege, then the project team would no longer consider increasing the use of technology by
requiring tablets and would cancel the project before development. This phased approach
minimizes the time and money spent developing inappropriate projects. A project idea
must pass the concept phase before evolving into the development phase.
The third phase of the traditional project life cycle is implementation. In this phase,
the project team creates a definitive or very accurate cost estimate, delivers the required
work, and provides performance reports to stakeholders. Suppose Tom Walters’ college took
the idea of requiring students to have tablets through the development phase. During the
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

59
implementation phase, the project team would need to obtain the required hardware and
software, install the necessary network equipment, deliver the tablets to the students, create
a process for collecting fees, and provide training to students, faculty, and staff. Other people
on campus would also be involved in the implementation phase. Faculty would need to
consider how best to take advantage of the new technology. The recruiting staff would have
to update their materials to reflect this new feature of the college. Security would need to
address new problems that might result from students carrying around expensive equipment.
The project team usually spends the bulk of its efforts and money during the implementation
phase of projects.
The last phase of the traditional project life cycle is the close-out phase. In it, all of the
work is completed, and customers should accept the entire project. The project team should
document its experiences on the project in a lessons-learned report. If the tablet idea made
it all the way through the implementation phase and all students received tablets, the proj-
ect team would then complete the project by closing out any related activities. Team mem-
bers might administer a survey to students, faculty, and staff to gather opinions on how the
project fared. They would ensure that any contracts with suppliers were completed and that
appropriate payments were made. They would transition future work related to the tablet
project to other parts of the organization. The project team could also share its lessons-
learned report with other colleges that are considering a similar program.
Many projects, however, do not follow this traditional project life cycle. They still have
general phases with some similar characteristics, but they are much more flexible. For
example, a project might have just three phases—the initial, intermediate, and final
phases. Or, there may be multiple intermediate phases. A separate project might be
needed just to complete a feasibility study. Regardless of the project life cycle’s specific
phases, it is good practice to think of projects as having phases that connect the beginning
and end of the process. This way, people can measure progress toward achieving project
goals during each phase and the project is more likely to be successful.
2.4a Product Life Cycles
Creating a product like a new automobile or a new operating system is a complicated
endeavor. For example, developing just the engine for a new electric or hybrid car is a full-
fledged project. Companies often use a program—a coordinated group of projects—to develop
products and bring them to market. And just like a project has a life cycle, so does a product.
All products—cars, buildings, even amusement parks—follow some type of life cycle.
The Walt Disney Company, for example, follows a rigorous process to design, build, and
test new products. Project managers oversee the development of all new products, such as
rides, parks, and cruise lines.
IT projects are used to develop products and services such as new software, hardware,
networks, research reports, and training on new systems. Most IT professionals are famil-
iar with the concept of a product life cycle, especially for developing software.
Software development projects are one subset of IT projects. Many IT projects involve
researching, analyzing, and then purchasing and installing new hardware and software
with little or no actual software development required. Other projects involve minor
modifications to enhance existing software or to integrate one application with another.
Still other projects involve a major amount of software development. Many argue that
developing software requires project managers to modify traditional project management
methods, depending on a particular product’s life cycle.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

A systems development life cycle (SDLC) is a framework for describing the phases
of developing information systems. Some popular models of an SDLC include the water-
fall model, the spiral model, the incremental build model, the prototyping model, and
the Rapid application development (RAD) model. These life cycle models are examples
of a predictive life cycle, meaning that the scope of the project can be articulated
clearly and the schedule and cost can be predicted accurately. The project team spends
a large portion of the project attempting to clarify the requirements of the entire system
and then producing a design. Users are often unable to see any tangible results in terms
of working software for an extended period. Below are brief descriptions of several
predictive SDLC models:11
The waterfall life cycle model has well-defined, linear stages of systems analysis,
design, construction, testing, and support. This life cycle model assumes that
requirements will remain stable after they are defined. The waterfall life cycle
model is used when risk must be tightly controlled and when changes must be
restricted after the requirements are defined. The waterfall approach is used in
many large-scale systems projects where complexity and cost are so high that
the more rigid steps of the approach help to ensure careful completion of all
deliverables.
The spiral life cycle model was developed based on refinements of the
waterfall model as applied to large government software projects. It recog-
nizes the fact that most software is developed using an iterative or spiral
approach rather than a linear approach. The project team is open to changes
and revisions later in the project life cycle, and returns to the requirements
phase to more carefully clarify and design the revisions. This approach is
suitable for projects in which changes can be incorporated with reasonable
cost increases or with acceptable time delays. Figure 2-5 illustrates the differ-
ences between the waterfall and spiral life cycle models.
Implementation Design
AnalysisTesting
Waterfall model Spiral model
Analysis
Design
Construction
Testing
Support
FIGURE 2-5
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Taurus

Taurus

Taurus

The incremental build life cycle model provides for progressive development
of operational software, with each release providing added capabilities. This
type of approach is often used by organizations like Microsoft, which issues a
specific release of a software package while working on future revisions that
will be distributed later in another release with a higher “build” or version
number. This approach helps to stage the priorities of the features and func-
tions with user priorities or the costs, time, and scope of the revisions.
The prototyping life cycle model is used for developing software prototypes
to clarify user requirements for operational software. It requires heavy user
involvement, and developers use a model to generate functional require-
ments and physical design specifications simultaneously. Developers can
throw away or keep prototypes, depending on the project. This approach is
often used in systems that involve a great deal of user interface design, such
as website projects, in systems that automate previously manual functions, or
in systems that change the nature of how something is done, such as mobile
applications.
The RAD life cycle model uses an approach in which developers work with an
evolving prototype. This life cycle model also requires heavy user involvement
and helps produce systems quickly without sacrificing quality. Developers use
RAD tools such as computer-aided software engineering (CASE), joint require-
ments planning (JRP), and joint application design (JAD) to facilitate rapid
prototyping and code generation. These tools are often used in reporting sys-
tems in which programmers enter parameters into software to generate reports
for user approval. When approved, the same parameters will generate the final
production system without further modification by the programmer.
In contrast to the predictive models, the adaptive software development (ASD) life
cycle model assumes that software requirements cannot be clearly expressed early in the
life cycle, so software is developed using a less structured, flexible approach. Software de-
velopers focus on the rapid creation of working code and an evolution of the entire software
system. Instead of planning in detail what the software should do, developers have a basic
idea of user needs and work to create code that will meet those needs. If some of the code
needs to change, a developer changes it. The software is never really finished; there are
stable periods between new releases. ASD grew out of RAD, but RAD allows for a time period
when the software is finished, while ASD does not.
ASD was first described in a 1974 paper written by Dr. Ernest A. Edmonds, where he
stated,
The aim of the paper is to describe the process of software development as it often
occurs unintentionally, in a way that might make it easier to recognize what is hap-
pening. An approach to the problem of controlling the process is indicated, as are the
areas where detailed investigation would be necessary in any particular case. The non-
technical users that concern us are people who do not write their own programs and
do not wish to use the computer for a technical, well defined process. The develop-
ment of software for such users is often made difficult because one cannot predict just
which facilities are the best ones to provide. There may not be an existing system to
analyse, and the analyst may not be able to invent one. It is suggested that the solution
proposed may also allow users to adapt their methods at the same rate as the develop-
ment of the software, giving a smooth and well understood change in the system.12
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Taurus

Taurus

Taurus

Taurus

Examples of ASD include extreme programming, feature driven development, dynamic
systems development model, and scrum. Today ASD approaches are collectively referred to
as agile software development, named after the Agile Manifesto published in 2001. The last
section of this chapter provides more information on agile as it applies to project manage-
ment, and Chapter 3 includes a brief case study of an agile project.
Whether predictive or agile, all of these models are examples of SDLCs. The type of software
and complexity of the information system in development determines which life cycle models to
use. Most important, to meet the needs of the project environment, the project manager needs
to understand the product life cycle. (For more information, you can find detailed descriptions
of each model on many websites and in management information systems textbooks.)
Most large IT products are developed as a series of projects or as part of a program.
For example, the systems planning phase for a new information system can include a
project to hire an outside consulting firm to help identify and evaluate potential strategies
for developing a particular business application, such as a new order processing system or
general ledger system. The planning phase can also include a project to develop,
administer, and evaluate a survey of users to get their opinions on the current informa-
tion systems used in the organization. The systems analysis phase might include a project
to create process models for certain business functions in the organization. This phase
can also include a project to create data models of existing company databases related to
the business function and application. The implementation phase might include a project
to hire contract programmers to code a part of the system. The close-out phase might
include a project to develop and run several training sessions for users of the new applica-
tion. It is often good practice to view large projects as a series of smaller, more manage-
able ones, especially when extensive uncertainty is involved. Successfully completing one
small project at a time will help the project team succeed in completing the larger project.
Some aspects of project management need to occur during each phase of the product
life cycle. Therefore, it is critical for IT professionals to understand and practice good
project management throughout the product life cycle.
2.4b The Importance of Project Phases and Management Reviews
Due to the complexity and importance of many IT projects and their resulting products, it
is important to take time to review the status of a project at each phase. A project should
successfully pass through each of the main project phases before continuing to the next.
Because the organization usually commits more money as a project continues, a manage-
ment review should occur after each phase to evaluate progress, potential success, and
continued compatibility with organizational goals.
Management reviews, called phase exits or kill points, are very important for keeping
projects on track and determining if they should be continued, redirected, or terminated.
Recall that projects are just one part of the entire system of an organization. Changes in
other parts of the organization might affect a project’s status, and a project’s status might
likewise affect events in other parts of the organization. By breaking projects into phases,
top management can make sure that the projects are still compatible with other needs of
the organization.
Take another look at the opening case. Suppose Tom Walters’ college conducted a
study sponsored by the college president on increasing the use of technology. At the end
of the concept phase, the project team could have presented information to the president,
faculty, and other staff members that described different options for increasing the use of
technology, an analysis of what competing colleges were doing, and results of a survey of
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Taurus

63
local stakeholders’ opinions on the subject. This presentation at the end of the concept
phase represents one form of a management review. Suppose the study reported that
90 percent of surveyed students, faculty, and staff strongly opposed the idea of requiring
all students to have tablets, and that many adult students said they would attend other
colleges if they were required to pay for the additional technology. The college would
probably decide not to pursue the idea any further. Had Tom taken a phased approach,
he and his staff would not have wasted time and money developing detailed plans.
In addition to formal management reviews, it is important to have top management
involvement throughout the life cycle of most projects. It is unwise to wait until the end of
project or product phases to have management inputs. Many projects are reviewed by man-
agement on a regular basis, such as weekly or even daily, to make sure they are progressing
well. Everyone wants to be successful in accomplishing goals at work, and having management
involvement ensures that a company can accomplish its project and organizational goals.
W H A T W E N T R I G H T ?
Having specific deliverables and kill points at the end of project or product phases helps
managers make better decisions about whether to proceed, redefine, or kill a project.
Improvement in IT project success rates reported by the Standish Group has been due
in part to an increased ability to know when to cancel failing projects. Standish Group
Chairman Jim Johnson made the following observation: “The real improvement that I
saw was in our ability to—in the words of Thomas Edison—know when to stop beating
a dead horse. … Edison’s key to success was that he failed fairly often; but as he said, he
could recognize a dead horse before it started to smell. … In information technology we
ride dead horses—failing projects—a long time before we give up. But what we are see-
ing now is that we are able to get off them; able to reduce cost overrun and time overrun.
That’s where the major impact came on the success rate”13
Another example of the power of management oversight comes from Huntington
Bancshares, Inc. This company, like many others, has an executive steering committee,
a group of senior executives from various parts of the organization who regularly review
important corporate projects and issues. The Ohio-based, $26 billion bank holding com-
pany completed a year-long website redesign using XML technology to give its online
customers access to real-time account information as well as other banking services. The
CIO, Joe Gottron, said there were “four or five very intense moments” when the whole
project was almost stopped due to its complexity. The executive steering committee met
weekly to review the project’s progress and discuss work planned for the following week.
Gottron said the meetings ensured that “if we were missing a beat on the project, no
matter which company [was responsible], we were on top of it and adding additional re-
sources to make up for it.”14
Some projects still go on for a long time before being killed. Blizzard, producer of the
popular massive multiplayer online (MMO) game World of Warcraft, decided to cancel
their Titan game project after spending over seven years in development. According
to Blizzard co-founder and CEO Mike Morhaime, “We set out to make the most ambi-
tious thing that you could possibly imagine. And it didn’t come together. We didn’t find
the fun. We didn’t find the passion. … We’d rather cut out a game we put a lot of time
and resources into than put out something that might ….” Chris Metzen, Blizzard’s
senior vice president of story and franchise development, finished Morhaime’s sentence:
“Damage the relationship. Smash the trust.”15
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

64
2.5 THE CONTEXT OF INFORMATION TECHNOLOGY PROJECTS
The project context has a critical impact on which product development life cycle will
be most effective for a particular software development project. Likewise, several issues
unique to the IT industry have a critical impact on managing IT projects. These include
the nature of projects, the characteristics of project team members, and the diverse
nature of technologies involved.
2.5a The Nature of IT Projects
Unlike projects in many other industries, IT projects are diverse. Some involve a small
number of people installing off-the-shelf hardware and associated software. Others involve
hundreds of people analyzing several organizations’ business processes and then devel-
oping new software in a collaborative effort with users to meet business needs. Even for
small hardware-oriented projects, a wide diversity of hardware types can be involved—
personal computers, mainframe computers, network equipment, kiosks, laptops, tablets,
or smartphones. The network equipment might be wireless, cellular based, or cable-based,
or might require a satellite connection. The nature of software development projects is
even more diverse than hardware-oriented projects. A software development project might
include creating a simple, stand-alone Microsoft Excel or Access application or a sophis-
ticated, global e-commerce system that uses state-of-the-art programming languages and
runs on multiple platforms.
IT projects also support every possible industry and business function. Managing an
IT project for a film company’s animation department requires different knowledge and
skills than a project to improve a federal tax collection system or to install a communica-
tion infrastructure in a third-world country. Because of the diversity of IT projects and the
newness of the field, it is important to develop and follow best practices in managing these
varied projects. Developing best practices gives IT project managers a common starting
point and method to follow with every project.
2.5b Characteristics of IT Project Team Members
Because IT projects are diverse, the people involved come from diverse backgrounds and
possess different skills. The resulting diverse project teams provide a significant advan-
tage because they can analyze project requirements from a more robust systems view.
Many companies purposely hire graduates with degrees in other fields such as business,
mathematics, or the liberal arts to provide different perspectives on IT projects. Even with
these different educational backgrounds, however, there are common job titles for people
working on most IT projects, such as business analyst, programmer, network specialist,
database analyst, quality assurance expert, technical writer, security specialist, hardware
engineer, software engineer, and system architect. Within the category of programmer,
several other job titles describe the specific technologies used, such as Java programmer,
PHP programmer, and C/C++/C# programmer.
Some IT projects require the skills of people in just a few job functions, but some
require inputs from many or all of them. Occasionally, IT professionals move between
these job functions, but more often people become technical experts in one area or they
decide to move into a management position. It is also rare for technical specialists or proj-
ect managers to remain with the same company for a long time. In fact, many IT projects
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

65
include a large number of contract workers. Working with this “army of free agents,” as
author Rob Thomsett calls them, creates special challenges.
2.5c Diverse Technologies
Many of the job titles for IT professionals reflect the different technologies required
to hold those positions. Differences in technical knowledge can make communication
between professionals challenging. Hardware specialists might not understand the
language of database analysts, and vice versa. Security specialists may have a hard time
communicating with business analysts. People within the same IT job function often
do not understand each other because they use different technology. For example,
someone with the title of programmer can often use several different programming
languages. However, if programmers are limited in their ability to work in multiple
languages, project managers might find it more difficult to form and lead more versatile
project teams.
Another problem with diverse technologies is that many of them change rapidly. A
project team might be close to finishing a project when it discovers a new technology that
can greatly enhance the project and better meet long-term business needs. New technolo-
gies have also shortened the time frame many businesses have to develop, produce, and
distribute new products and services. This fast-paced environment requires equally fast-
paced processes to manage and produce IT projects and products.
2.6 RECENT TRENDS AFFECTING INFORMATION TECHNOLOGY
PROJECT MANAGEMENT
Recent trends such as increased globalization, outsourcing, virtual teams, and agile project
management are creating additional challenges and opportunities for IT project managers
and their teams. Each of these trends and suggestions for addressing them are discussed in
this section.
2.6a Globalization
In his popular book The World Is Flat, Thomas L. Friedman describes the effects of
globalization, which has created a “flat” world where everyone is connected and the
“playing field” is level for many more participants.16 Lower trade and political barriers
and the digital revolution have made it possible to interact almost instantaneously with
billions of other people across the planet, and for individuals and small companies to
compete with large corporations. Friedman also discusses the increase in “uploading,” in
which people share information through blogging, podcasts, and open-source software.
IT is a key enabler of globalization. In 2014, more than 1.3 billion people were us-
ing Facebook, spending an average of 21 minutes a day.17 Other social networks, such as
Twitter and LinkedIn, also continue to grow. In 2014, there were over 284 million Twitter
users and 332 million LinkedIn users. According to LinkedIn’s website, in the third quarter
of 2014, 75 percent of new members came from outside the United States. Globalization
has significantly affected the field of IT. Even though major IT companies such as Apple,
IBM, and Microsoft started in the United States, much of their business is global—indeed,
companies and individuals throughout the world contribute to the growth of information
technologies, and work and collaborate on various IT projects.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

66
It is important for project managers to address several key issues when working on
global projects:
Communications: Because people work in different time zones, speak different
languages, have different cultural backgrounds, and celebrate different holidays,
it is important to address how people will communicate in an efficient and timely
manner. A communications management plan is vital. For details, see the plan
described in Chapter 10, Project Communications Management.
Trust: Trust is an important issue for all teams, especially when they are
global teams. It is important to start building trust immediately by recogniz-
ing and respecting others’ differences and the value they add to the project.
Common work practices: It is important to align work processes and develop
a modus operandi with which everyone agrees and is comfortable. Project
managers must allow time for the team to develop these common work prac-
tices. Using special tools, as described next, can facilitate this process.
Tools: IT plays a vital role in globalization, especially in enhancing communi-
cations and work practices. Many people use free tools such as Skype, Google
Docs, or social media to communicate. Many project management software
tools include their own communications and collaboration features in an
integrated package. IBM continues to be the leader in providing collaboration
tools to businesses in over 175 companies, followed by Oracle in 145 coun-
tries, SAP in 130 countries, and Microsoft in 113 countries.18 Work groups
must investigate options and decide which tools will work best for their proj-
ects. Security is often a key factor in deciding which tools to use.
After researching over 600 global organizations, KPMG International summarized
several suggestions for managing global project teams:
Employ greater project discipline for global projects; otherwise, weaknesses
within the traditional project disciplines may be amplified by geographical
differences.
Think globally but act locally to align and integrate stakeholders at all project
levels.
Consider collaboration over standardization to help balance the goals and
project approach.
Keep momentum going for projects, which will typically have a long duration.
Consider the use of newer, perhaps more innovative, tools and technology.19
2.6b Outsourcing
As described in detail in Chapter 12, Project Procurement Management, outsourcing
is an organization’s acquisition of goods and services from an outside source. The term
offshoring is sometimes used to describe outsourcing from another country. Offshoring
is a natural outgrowth of globalization. IT projects continue to rely more and more on
outsourcing, both within and outside their country boundaries.
Some organizations remain competitive by using outsourcing to their advantage.
Many organizations have found ways to reduce costs by outsourcing, even though the
practice can be unpopular in their home countries. For example, outsourcing was an
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

67
important topic in the 2012 U.S. Republican presidential debates, as candidates discussed
why Apple hires half a million low-paid workers in the Far East to assemble its products.
A New York Times article explained that outsourcing is not just about low costs. “One
former executive described how [Apple] relied upon a Chinese factory to revamp iPhone
manufacturing just weeks before the device was due on shelves. Apple had redesigned the
iPhone’s screen at the last minute, forcing an assembly line overhaul. New screens began
arriving at the plant near midnight. A foreman immediately roused 8,000 workers inside
the company’s dormitories, according to the executive. Each employee was given a bis-
cuit and a cup of tea, guided to a workstation and within half an hour started a 12-hour
shift fitting glass screens into beveled frames. Within 96 hours, the plant was producing
over 10,000 iPhones a day. ‘The speed and flexibility is breathtaking,’ the executive said.
‘There’s no American plant that can match that.’ ”20
Because of the increased use of outsourcing for IT projects, project managers need
to become more familiar with many global and procurement issues, including working on
and managing virtual teams.
2.6c Virtual Teams
Several factors, such as the cost and time required for travel or employee relocation, the
ability to communicate and work across vast distances, the advantages of hiring people
in locations that have a lower cost of living, and worker preferences for flexible work
hours, have contributed to a significant increase in virtual project teams. A virtual team
is a group of people who work together despite time and space boundaries using commu-
nication technologies. Team members might all work for the same company in the same
country, or they might include employees as well as independent consultants, suppliers,
or even volunteers providing their expertise from around the globe.
The main advantages of virtual teams include:
Lowering costs because many virtual workers do not require office space or
support beyond their home offices.
Providing more expertise and flexibility or increasing competitiveness and
responsiveness by having team members across the globe working any time
of day or night.
G L O B A L I S S U E S
Outsourcing also has disadvantages. For example, Apple benefits from manufacturing
products in China, but it had big problems there after its iPhone 4S launch in January
2012 caused fighting between migrant workers who were hired by scalpers to stand in
line to buy the phones. When Apple said it would not open its store in Beijing, riots re-
sulted and people attacked security guards. The Beijing Apple Store has had problems
before. In May 2011, four people were injured when a crowd waiting to buy the iPad 2
turned ugly. Market analysts blamed Apple for not marketing or distributing its products
well in China.21
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

68
Improving the balance between work and life for team members by
eliminating fixed office hours and the need to travel to work.
Disadvantages of virtual teams include:
Isolating team members who may not adjust well to working in a virtual
environment.
Increasing the potential for communications problems because team mem-
bers cannot use body language or other nonverbal communications to under-
stand each other and build relationships and trust.
Reducing the ability for team members to network and transfer information
informally.
Increasing the dependence on technology to accomplish work.
Like any team, a virtual team should focus on achieving a common goal.
Research on virtual teams reveals a growing list of factors that influence their success:
Team processes: It is important to define how the virtual team will operate. For
example, teams must agree on how and when work will be done, what tech-
nologies will be used, how decisions will be made, and other important process
issues.
Leadership style: The project manager’s leadership style affects all teams,
especially virtual ones.
Trust and relationships: Many virtual teams fail because of a lack of trust.
It is difficult to build relationships and trust from a distance. Some project
managers like to have a face-to-face meeting so team members can get to
know each other and build trust. If such a meeting is not possible, phone or
video conferences can help.
Team member selection and role preferences: Dr. Meredith Belbin defined a
team role as “a tendency to behave, contribute and interrelate with others in
a particular way.”22 It is important to select team members carefully and to
form a team in which all roles are covered. All virtual team members must
also understand their roles on the team. (Visit www.belbin.com for more
information on this topic.)
Task-technology fit: IT is more likely to have a positive impact on individual
performance if the capabilities of the technologies match the tasks that the
user must perform.
Cultural differences: It is important to address cultural differences, including
how people with authority are viewed, how decisions are made, how requests
or questions are communicated, and how workers prefer to operate (in col-
laboration or individually). These cultural differences vary from location to
location and affect many aspects of the team.
Computer-mediated communication: It is crucial to provide reliable and
appropriate computer-mediated communication to virtual team members,
including e-mail, instant messaging, text messaging, and chat rooms. If you
rely on these technologies to bring the virtual team together, you need to
ensure that they actually work, or you risk increasing the distance that can
exist across virtual boundaries.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

69
Team life cycles: Just as projects and products have life cycles, so do teams.
Project managers must address the team life cycle, especially when assigning
team members and determining deliverable schedules.
Incentives: Virtual teams may require different types of incentives to ac-
complish high-quality work on time. They do not have the benefit of physical
contact with their project managers or other team members, so it is impor-
tant to provide frequent positive incentives, such as a thank-you via e-mail
or phone, or even a bonus on occasion. Negative incentives, such as fines or
withholding payment, can also be effective if virtual team members are not
being productive.
Conflict management: Even though they might never physically meet, virtual
teams still have conflicts. It is important to address conflict management, as
described in more detail in Chapter 9, Project Human Resource Management.
Several studies have tried to determine factors that are correlated positively to the
effectiveness of virtual teams. Research suggests that team processes, trusting relation-
ships, leadership style, and team member selection provide the strongest correlations to
team performance and team member satisfaction.23
2.6d Agile Project Management
Earlier the agile approach to product development was discussed. Agile means being able
to move quickly and easily, but some people feel that project management, as they have
seen it used, does not allow people to work quickly or easily. Early software development
projects often used a waterfall approach, but as technology and businesses became more
complex, the approach often became difficult to use because requirements were unknown
or continuously changing. Agile today means using a method based on iterative and incre-
mental development, in which requirements and solutions evolve through collaboration.
Agile can be used for software development or in any environment in which the require-
ments are unknown or change quickly. In terms of the triple constraint, an agile approach
sets time and cost goals but leaves scope goals flexible so the project sponsors or product
owners can prioritize and reprioritize the work they want done. An agile approach makes
sense for some projects, but not all of them.
Many seasoned experts in project management warn people not to fall for the hype
associated with agile. For example, J. Leroy Ward, Executive Vice President at ESI In-
ternational, said that “Agile will be seen for what it is … and isn’t.” According to Ward,
“Project management organizations embracing Agile software and product development
approaches will continue to grow while being faced with the challenge of demonstrating
ROI through Agile adoption. In addition, they will need to disabuse their stakeholders and
executives of the expectations set by IT consultants, the media and the vendor commu-
nity that Agile is the next ‘silver bullet.’ Organizations that do it right—including selecting
the right projects for Agile—will reap significant rewards.”24
2.6e The Manifesto for Agile Software Development
In the business world, the term agile was first applied to software development projects.
In February 2001, a group of 17 people that called itself the Agile Alliance developed and
agreed on the Manifesto for Agile Software Development, as follows:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

We are uncovering better ways of developing software by doing it and helping others
do it. Through this work we have come to value:
Individuals and interactions over processes and tools
Working software over comprehensive documentation
Customer collaboration over contract negotiation
Responding to change over following a plan25
The person or organization that implements Agile is responsible for interpreting and
applying the preceding values.
Some people associate Agile with specific techniques such as Scrum.
2.6f Scrum
According to the Scrum Alliance, Scrum is the leading agile development method for com-
pleting projects with a complex, innovative scope of work. The term was coined in 1986 in
a Harvard Business Review study that compared high-performing, cross-functional teams
to the scrum formation used by rugby teams. The basic Scrum framework is summarized
in the following list and illustrated in Figure 2-6:
A product owner creates a prioritized wish list called a product backlog.
During sprint planning, the team pulls a small chunk from the top of that
wish list, a sprint backlog, and decides how to implement those pieces.
The team has a certain amount of time, a sprint, to complete its work—
usually two to four weeks—but meets each day to assess its progress (daily
Scrum).
Along the way, the ScrumMaster keeps the team focused on its goal.
FIGURE 2-6
1. Product owner
creates
prioritized wish
list or backlog
Product
backlog
2. Project team
creates sprint
backlog
3. Teams have daily
Scrum meetings
during each 2–4
week sprint
4. Sprint results
in a useful
product
1.
2.
3.
4.
5.
6.
etc. Sprint
review
Repeat steps 1–4
until complete
1.
2.
Sprint
backlog
Potentially
shippable
product
increment
Daily Scrum
Sprint
2–4
weeks
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

At the end of the sprint, the work should be potentially shippable, as in
ready to hand to a customer, put on a store shelf, or show to a stakeholder.
The sprint ends with a sprint review and retrospective.
As the next sprint begins, the team chooses another chunk of the product
backlog and begins working again.
The cycle repeats until enough items in the product backlog have been completed, the
budget is depleted, or a deadline arrives. Which of these milestones marks the end of
the work is entirely specific to the project. No matter which of these reasons stops work,
Scrum ensures that the most valuable work has been completed when the project ends.26
In the Axosoft video “Scrum in 10 Minutes,” Hamid Shojaee, an experienced software
developer who has worked with several major corporations, briefly explains key concepts
like product backlogs, team roles, sprints, and burndown charts.27 Techniques from the
just-in-time inventory control method Kanban can be used in conjunction with Scrum.
Kanban was developed in Japan by Toyota Motor Corporation. It uses visual cues to guide
workflow. For example, teams can place cards on boards to show the status of work in
the backlog, such as new, in progress, and complete. Cards on the board are moved to the
right to show progress in completing work. Kanban also helps limit work in progress by
making a bottleneck visible so people can collaborate to solve problems that created the
bottleneck. Kanban helps improve day-to-day workflow, while Scrum provides the struc-
ture for improving the organization of projects.28 Scrum was initially applied to software
development projects, but today other types of projects use this technique to help focus
on teamwork, complete the most important work first, and add business value. Chapter 3
includes a case study that illustrates an agile approach to project management.
2.6g Agile, the PMBOK® Guide, and a New Certification
The PMBOK® Guide describes best practices for what should be done to manage projects.
Agile is a methodology that describes how to manage projects. One could view Agile and the
Scrum framework as methods that break down a big project into several smaller projects,
defining the scope for each one. Project teams can have brief meetings each day to decide
how to get the most important work done first without calling the meetings “scrums.”
As stated earlier in the chapter, several different methods are related to developing
information systems and other products. Because projects are unique, someone must
decide what processes are needed and how they should be performed. Project teams can
follow one specific process, a hybrid of several, or their own customized approach.
The Project Management Institute (PMI) recognized the increased interest in Agile,
and introduced a new certification in 2011 called Agile Certified Practitioner (ACP). As
stated on the PMI website, “The use of agile as an approach to managing projects has been
increasing dramatically over the last several years. Gartner predicts that by the end of
2012, agile development methods will be used on 80 percent of all software development
projects. PMI’s research has shown that the use of agile has tripled from December 2008
to May 2011. Furthermore, research demonstrates the value that agile can have in de-
creasing product defects, improving team productivity, and increasing delivery of business
value. The PMI-ACP is positioned to recognize and validate knowledge of this important
approach.”29. At the end of April 2015, there were 8,255 people who earned the Agile Cer-
tified Practitioner Certification.30
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

One reason for increased interest in Agile is the hope that it will somehow make
project management easier. Many books, courses, and consultants are capitalizing on this
“new” approach. However, seasoned project managers understand that they have always
had the option of customizing how they run projects. They also know that project man-
agement is not easy, even when using Agile.
As you can see, working as an IT project manager or team member is an exciting and
challenging job. The excitement and challenge come from the focus on successfully com-
pleting projects that will have a positive impact on the organization as a whole.
C A S E W R A P – U P
After several people voiced concerns about the tablet idea at the faculty meeting, the
president of the college directed that a committee be created to formally review the con-
cept of requiring students to have tablets. Because the college was dealing with several
important enrollment-related issues, the president named the vice president of enroll-
ment to head the committee. Other people soon volunteered or were assigned to the
committee, including Tom Walters as head of Information Technology, the director of the
adult education program, the chair of the Computer Science department, and the chair of
the History department. The president also insisted that the committee include at least
two members of the student body. The president knew everyone was busy, and he ques-
tioned whether the tablet idea was a high-priority issue for the college. He directed the
committee to present a proposal at next month’s faculty meeting, either to recommend
creating a formal project team to fully investigate requiring tablets or to recommend ter-
minating the concept. At the next faculty meeting, few people were surprised to hear the
recommendation to terminate the concept. Tom Walters learned that he had to pay much
more attention to the needs of the entire college before proceeding with detailed IT plans.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

73
Chapter Summary







Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

74
Quick Quiz
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Quick Quiz Answers
Discussion Questions
75
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

76
Exercises


www.agilealliance.org

www.belbin.com


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

77
Key Terms
adaptive software development
(ASD) p. 61
agile p. 69
agile software development p. 62
champion p. 54
deliverable p. 57
executive steering committee p. 63
functional organizational structure p. 49
human resources (HR) frame p. 47
IT governance p. 55
kanban p. 71
kill point p. 62
matrix organizational structure p. 50
offshoring p. 66
organizational culture p. 51
outsourcing p. 66
phase exit p. 62
political frame p. 48
politics p. 48
predictive life cycle p. 60
project acquisition p. 57
project feasibility p. 57
project life cycle p. 57
project organizational structure p. 50
scrum p. 70
structural frame p. 47
symbolic frame p. 48
systems analysis p. 45
systems approach p. 45
systems development life cycle
(SDLC) p. 60
systems management p. 45
systems philosophy p. 45
systems thinking p. 45
virtual team p. 67
End Notes
Reframing Organizations
BCS
Organizational Behavior
Forbes www.forbes.com/sites/lorenthompson/2013/12/03/healthcare-gov
-diagnosis-the-government-broke-every-rule-of-project-management/
Time time.com/10228/obamas-trauma-team/
IT Governance: How Top Performers Manage IT Decision
Rights for Superior Results
Communications of the ACM
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

78
Proceedings of the Project Management Institute
Annual Seminars & Symposium
General Systems

PM Network
Computerworld
Polygon
The World Is Flat: A Brief History of the Twenty-First Century
DMR Digital Marketing Ramblings
The New York
Times www.nytimes.com/2012/01/22/business/apple-america-and-a-squeezed-middle
-class.html?_r=0
The New York
Times www.nytimes.com/2012/01/14/technology/apple-suspends-iphone-4s-sales
-in-mainland-china-stores.html
®
Information & Management
projecttimes.com
Axosoft
YouTube www.youtube
.com/watch?v=R8dYLbJiTUE.
®
PMI Today
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R3
THE PROJECT
MANAGEMENT PROCESS
GROUPS: A CASE STUDY
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

80
Recall from Chapter 1 that project management consists of 10 knowledge areas:
integration, scope, time, cost, quality, human resources, communications, risk,
procurement, and stakeholder management. Another important concept to understand
is that projects involve five project management process groups: initiating, planning,
executing, monitoring and controlling, and closing. Tailoring these process groups to
meet individual project needs increases the chance of success in managing projects.
This chapter describes each project management process group in detail through a
simulated case study based on JWD Consulting. It also includes samples of typical
project documents applied to this case. You can download templates for these and other
project documents from the companion website for this text. Although you will learn
more about each knowledge area in Chapters 4 through 13, it is important first to learn
how they fit into the big picture of managing a project. Understanding how the knowl-
edge areas and project management process groups function together will lend context
to the remaining chapters.
3.1 PROJECT MANAGEMENT PROCESS GROUPS
Project management is an integrative endeavor. Decisions and actions taken in one knowl-
edge area at a certain time usually affect other knowledge areas. Managing these interac-
tions often requires making trade-offs among the project’s scope, time, and cost—the
triple constraint of project management described in Chapter 1. A project manager may
also need to make trade-offs between knowledge areas, such as between managing risk and
human resources. Consequently, you can view project management as a number of related
processes.
O P E N I N G C A S E
Erica Bell is in charge of the Project Management Office (PMO) for her consulting firm,
JWD Consulting, which has grown to include more than 200 full-time consultants and
even more part-time consultants. JWD Consulting provides a variety of consulting
services to assist organizations in selecting and managing IT projects. The firm focuses
on finding and managing high-payoff projects and developing strong metrics to measure
project performance and benefits to the organization after the project is implemented.
The firm’s emphasis on metrics and working collaboratively with its customers gives it
an edge over many competitors.
Joe Fleming, the CEO, wanted his company to continue to grow and become a world-
class consulting organization. Because the core of the business is helping other organi-
zations with project management, he felt it was crucial for JWD Consulting to have an
exemplary process for managing its own projects. He asked Erica to work with her team
and other consultants in the firm to develop several intranet site applications that would
allow them to share their project management knowledge. He also thought that the firm
should make some of the information available to the firm’s clients. For example, the
firm could provide project management templates, tools, articles, links to other sites,
and an Ask the Expert feature to help build relationships with current and future clients.
Because JWD Consulting emphasizes the importance of high-payoff projects, Joe also
wanted to see a business case for this project before proceeding.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

81
A process is a series of actions directed toward a particular result. Project management
process groups progress from initiating activities to planning activities, executing activities,
monitoring and controlling activities, and closing activities. Recall that a project can have
different combinations of phases. One project might have concept, development, implemen-
tation, and close-out phases, and another might have initial, intermediate, and final phases.
But all projects and all project phases need to include all five process groups. You cannot
equate process groups with project phases. For example, project managers and teams need
to reexamine the business need for the project, part of monitoring and controlling activities,
during every phase of the project life cycle to determine if the project is worth continuing.
Initiating processes include defining and authorizing a project or project
phase. Initiating processes take place during each phase of a project. For
example, in the close-out phase, initiating processes are used to ensure that
the project team completes all the work, that someone documents lessons
learned, and that the customer accepts the work.
Planning processes include devising and maintaining a workable scheme to
ensure that the project addresses the organization’s needs. Projects include
several plans, such as the scope management plan, schedule management
plan, cost management plan, and procurement management plan. These
plans define each knowledge area as it relates to the project at a particular
point in time. For example, a project team must develop a plan to define
the work needed for the project, to schedule activities related to that work,
to estimate costs for performing the work, and to decide what resources
to procure to accomplish the work. To account for changing conditions on
the project and in the organization, project teams often revise plans during
each phase of the project life cycle. The project management plan, which is
described in Chapter 4, coordinates and encompasses information from all
other plans.
Executing processes include coordinating people and other resources to
carry out the various plans and create the products, services, or results of
the project or phase. Examples of executing processes include acquiring and
developing the project team, performing quality assurance, distributing infor-
mation, managing stakeholder expectations, and conducting procurements.
Monitoring and controlling processes include regularly measuring and moni-
toring progress to ensure that the project team meets the project objectives.
The project manager and staff monitor and measure progress against the plans
and take corrective action when necessary. A common monitoring and control-
ling process is reporting performance, where project stakeholders can identify
any necessary changes that may be required to keep the project on track.
Closing processes include formalizing acceptance of the project or project
phase and ending it efficiently. Administrative activities are often involved in
this process group, such as archiving project files, closing out contracts, doc-
umenting lessons learned, and receiving formal acceptance of the delivered
work as part of the phase or project.
The process groups are not mutually exclusive. For example, project managers
must perform monitoring and controlling processes throughout the project’s life span.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

82
2%Closing
Other Project Managers Alpha Project Managers
Monitoring and Controlling
Executing
Planning
Initiating
3%
4%
5%
82%
69%
11%
21%
1%
2%
Spending more time
on planning should
pay off in execution
That is, monitoring and controlling processes occur concurrently throughout a project
with initiating, planning, executing, and closing processes. Initiating and planning
processes can occur concurrently with executing processes, and so on for each
process group.
The level of activity and length of each process group varies for every project. Nor-
mally, executing tasks require the most resources and time, followed by planning tasks.
Initiating and closing tasks are usually the shortest (at the beginning and end of a project
or phase, respectively), and they require the least resources and time. However, every
project is unique, so exceptions are possible.
You can apply the process groups for each major phase or iteration of a project, or
you can apply the process groups to an entire project. The first example of the JWD Con-
sulting case study applies the process groups to the entire project. The second example
shows how you can use a more agile approach to manage the same project; several process
groups are repeated for each iteration of the project.
Many people ask for guidelines on how much time to spend in each process group.
In his book Alpha Project Managers: What the Top 2% Know That Everyone Else Does
Not, Andy Crowe collected data from 860 project managers in various companies and in-
dustries in the United States. He found that the best—the alpha—project managers spent
more time on every process group, except executing, than their counterparts as shown in
Figure 3-1. Notice that the alpha project managers spent almost twice as much time on
planning (21 percent versus 11 percent) as other project managers. Spending more time
on planning should lead to less time spent on execution, which should reduce the time
and money spent on projects. The best project managers know and practice this impor-
tant concept—do a good job of planning.1
FIGURE 3-1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

W H A T W E N T W R O N G ?
Many readers of CIO magazine commented on its cover story about problems with infor-
mation systems at the U.S. Internal Revenue Service (IRS). The article described serious
problems the IRS has had in managing IT projects. Philip A. Pell, PMP, believes that
having a good project manager and following a good project management process would
help the IRS and many organizations tremendously. Pell provided the following feedback
to the article:
Pure and simple, good, methodology-centric, predictable, and repeatable project
management is the SINGLE greatest factor in the success (or in this case failure)
of any project. When a key stakeholder says, ‘I didn’t know how bad things were,’
it is a direct indictment of the project manager’s communications management
plan. When a critical deliverable like the middleware infrastructure that makes
the whole thing work is left without assigned resources and progress tracking, the
project manager has failed in his duty to the stakeholders. When key stakeholders
(people and organizations that will be affected by the project, not just people who
are directly working on the project) are not informed and their feedback incorpo-
rated into the project plan, disaster is sure to ensue. The project manager is ulti-
mately responsible for the success or failure of the project.2
The IRS continues to have problems managing IT projects. A 2014 U.S. Government
Accountability Office (GAO) report stated that the IRS had significant cost and schedule
variances in over 68 percent (13 of 19) of its major IT projects that auditors evaluated
between June 2013 and April 2014. “The IRS is in the midst of several high-profile, long-
term, high-dollar IT projects to improve electronic tax filing, prepare the systems to man-
age subsidy calculations and penalties under the 2010 health care law, and modernize its
central taxpayer database and processing system. The success or failure of those projects
will affect the government’s ability to collect taxes and distribute refunds efficiently and
accurately.”3
Each of the five project management process groups is characterized by the comple-
tion of certain tasks. While initiating processes for a new project, the organization recog-
nizes that a new project exists and completes a project charter as part of this recognition.
(See Chapter 4 for more information on project charters.) Tables are provided later in this
chapter with detailed lists of possible outputs for each process group by knowledge area.
For example, Tables 3-3 through 3-7 list potential outputs for the initiating and planning
process groups. Samples of some outputs are provided for each process group in a case
study of JWD Consulting’s project management intranet site project. Project managers and
their teams must decide which outputs are required for their particular projects.
Outputs of the planning process group include completing the project scope state-
ment, the work breakdown structure, the project schedule, and many other items. Plan-
ning processes are especially important for IT projects. Anyone who has ever worked on a
large IT project that involves new technology knows the saying, “A dollar spent up front in
planning is worth one hundred dollars spent after the system is implemented.” Planning is
crucial in IT projects because once a project team implements a new system, considerable
effort is needed to change it. Research suggests that companies working to implement best
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

84
practices should spend at least 20 percent of project time in initiating and planning.4 This
percentage is backed up by evidence from Alpha project managers, as described earlier.
The executing process group takes the actions necessary to complete the work de-
scribed in the planning activities. The main outcome of this process group is delivering
the actual work of the project. For example, if an IT project involves providing new hard-
ware, software, and training, the executing processes would include leading the project
team and other stakeholders to purchase the hardware, develop and test the software, and
deliver and participate in the training. The executing process group should overlap the
other process groups, and generally requires the most resources.
Monitoring and controlling processes measure progress toward the project objectives,
monitor deviation from the plan, and take corrective action to match progress with the
plan. Performance reports are common outputs of monitoring and controlling. The project
manager should be monitoring progress closely to ensure that deliverables are being com-
pleted and objectives are being met. The project manager must work closely with the proj-
ect team and other stakeholders and take appropriate actions to keep the project running
smoothly. The ideal outcome of the monitoring and controlling process group is to com-
plete a project successfully by delivering the agreed-upon project scope within time, cost,
and quality constraints. If changes to project objectives or plans are required, monitoring
and controlling processes ensure that these changes are made efficiently and effectively to
meet stakeholder needs and expectations. Monitoring and controlling processes overlap all
of the other project management process groups because changes can occur at any time.
During the closing processes, the project team works to gain acceptance of the end
products, services, or results and bring the phase or project to an orderly end. Key out-
comes of this process group are formal acceptance of the work and creation of closing
documents, such as a final project report and lessons-learned report.
M E D I A S N A P S H O T
Just as IT projects need to follow the project management process groups, so do other
projects, such as the production of a movie. Processes involved in making movies might
include screenwriting (initiating), producing (planning), acting and directing (executing),
editing (monitoring and controlling), and releasing the movie to theaters (closing). Many
people enjoy watching the extra features on a DVD that describe how these processes
lead to the creation of a movie. For example, the DVD for Lord of the Rings: The Two
Towers Extended Edition includes detailed descriptions of how the script was created,
how huge structures were built, how special effects were made, and how talented profes-
sionals overcame numerous obstacles to complete the project. This material acted “not
as promotional filler but as a serious and meticulously detailed examination of the entire
filmmaking process.”5 New Line Cinema made history by shooting all three Lord of the
Rings films consecutively during one massive production. It took three years of prepara-
tion to build the sets, find the locations, write the scripts, and cast the actors. Director
Peter Jackson said that the amount of early planning they did made it easier than he
imagined to produce the films. Project managers in any field know how important it is to
have good plans and to follow a good process. Jackson continued his movie making suc-
cess by directing The Hobbit, produced as a film trilogy, with movies released in 2012,
2013, and 2014.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

85
3.2 MAPPING THE PROCESS GROUPS
TO THE KNOWLEDGE AREAS
You can map the main activities of each project management process group into the
10 project management knowledge areas. Table 3-1 provides a big-picture view of
the relationships among the 47 project management activities, the process groups in
which they are typically completed, and the knowledge areas into which they fit. The
activities listed in the table are the main processes for each knowledge area listed in
the PMBOK® Guide, Fifth Edition. This text includes additional activities not listed
in the PMBOK® Guide, such as creating a business case and team contract, which
can also assist in managing projects. Note that the PMBOK® Guide can serve as a guide
for all types of projects that use all types of methods, including Agile. It is up to
each project team to decide what processes and outputs are required based on their
specific needs.
Several organizations use PMI’s PMBOK® Guide information as a foundation for
developing their own project management methodologies, as described in the next sec-
tion. Notice in Table 3-1 that many of the project management activities occur as part of
the planning process group. Because each project is unique, project teams are always try-
ing to do something that has not been done before. To succeed at unique and new activi-
ties, project teams must do a fair amount of planning. Recall, however, that the most time
and money is normally spent on executing. It is good practice for organizations to deter-
mine how project management will work best in their own organizations.
TABLE 3-1
Project Management Process Groups
Knowledge Area Initiating Planning Executing
Monitoring and
Controlling Closing
Project
Integration
Management
Develop
project
charter
Develop project
management plan
Direct and
manage project
work
Monitor and
control project
work, perform
integrated
change control
Close project
or phase
Project Scope
Management
Plan scope
management,
collect
requirements,
define scope,
create WBS
Validate scope,
control scope
Project Time
Management
Plan schedule
management,
define activities,
sequence activities,
estimate activities
resources, estimate
activity durations,
develop schedule
Control schedule
(continued)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

86
Project Management Process Groups
Knowledge Area Initiating Planning Executing
Monitoring and
Controlling Closing
Project Cost
Management
Plan cost
management,
estimate costs,
determine budget
Control costs
Project Quality
Management
Plan quality
management
Perform quality
assurance
Control quality
Project
Human
Resource
Management
Plan human
resource
management
Acquire project
team, develop
project team,
manage project
team
Project
Communications
Management
Plan
communications
management
Manage
communications
Control
communications
Project Risk
Management
Plan risk
management,
identify risks,
perform
qualitative risk
analysis, perform
quantitative risk
analysis, plan risk
responses
Control risks
Project
Procurement
Management
Plan procurement
management
Conduct
procurements
Control
procurements
Close
procurements
Project
Stakeholder
Management
Identify
stake-
holders
Plan stakeholder
management
Manage
stakeholder
engagement
Control
stakeholder
engagement
Source: Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK®
Guide)—Fifth Edition, Project Management Institute, Inc., (2013). Copyright and all rights reserved.
Material from this publication has been reproduced with the permission of PMI.
3.3 DEVELOPING AN IT PROJECT MANAGEMENT METHODOLOGY
Some organizations spend a great deal of time and money on training efforts for general
project management skills, but after the training, project managers may still not know
how to tailor their project management skills to the organization’s particular needs. Be-
cause of this problem, some organizations develop their own internal IT project manage-
ment methodologies. The PMBOK® Guide is a standard that describes best practices for
what should be done to manage a project. A methodology describes how things should be
done, and different organizations often have different ways of doing things.
In addition to using the PMBOK® Guide as a basis for project management methodol-
ogy, many organizations use other guides or methods, such as the following:
TABLE 3-1 continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

87
PRojects IN Controlled Environments (PRINCE2): Originally developed for
IT projects, PRINCE2 was released in 1996 as a generic project management
methodology by the U.K. Office of Government Commerce (OCG). It is the
de facto standard in the United Kingdom and is used in over 50 countries.
(See www.prince2.com for more information.) PRINCE2 defines 45 sepa-
rate subprocesses and organizes them into eight process groups as follows:
1. Starting up a project
2. Planning
3. Initiating a project
4. Directing a project
5. Controlling a stage
6. Managing product delivery
7. Managing stage boundaries
8. Closing a project
Agile methods: As described in Chapter 2, agile software development is
a form of adaptive software development. All agile methods include an it-
erative workflow and incremental delivery of software in short iterations.
Popular agile methods include extreme programming, Scrum, feature-
driven development, lean software development, Agile Unified Process
(AUP), Crystal, and Dynamic Systems Development Method (DSDM). See
websites like www.agilealliance.org for more information. The second
case in this chapter provides an example of using Scrum.
G L O B A L I S S U E S
The first study on the state of agile methods in India was published in 2011. The survey
included feedback from 770 respondents from 330 organizations across India that are
already using Agile, piloting Agile, or planning for Agile. The study was undertaken to
understand the progress, challenges, and opportunities that firms face in evaluating and
implementing Agile. Only 14 percent of respondents reported having expert experience in
Agile methods, 39 percent considered themselves intermediate users, 35 percent were be-
ginners, and 12 percent had no experience. A summary of findings included the following:
Two-thirds of organizations in some stage of Agile adoption are realizing key
software and business benefits in terms of faster delivery of products to the
customer, an improved ability to manage changing requirements, and higher
quality and productivity in IT.
Organizations struggle with the magnitude of the cultural shift required for
Agile, opposition to change, a lack of coaching and help in the Agile adoption
process, and a lack of qualified people.
The daily stand-up, iteration planning, and release planning are the most
commonly used practices, while paired programming and open workspaces
are not popular.
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

88
Sudhir Tiwari, managing director of ThoughtWorks India, which sponsored the
study, noted that some organizations “are approaching the holy grail of Continuous
Delivery.” He said, “We live in an age where Flickr releases 40 patches a week into pro-
duction. The overall Agile suite is built to cater to teams which are looking at agility and
going into production very rapidly.”6 A 2014 survey conducted by VersionOne found
that 88 percent of survey respondents were knowledgeable about agile software develop-
ment techniques. Executive sponsorship was the main success factor when scaling agile
beyond a single team. The main barriers to further adoption of agile were an inability to
change organizational culture and resistance to change.7
Rational Unified Process (RUP) framework: RUP is an iterative software
development process that focuses on team productivity and enables all team
members to deliver software best practices to the organization. According to
RUP expert Bill Cottrell, “RUP embodies industry-standard management and
technical methods and techniques to provide a software engineering process
particularly suited to creating and maintaining component-based software
system solutions.”8 Cottrell explained that you can tailor RUP to include the
PMBOK process groups because several customers asked for that capability.
Several other project management methodologies are used specifically for soft-
ware development projects, such as Joint Application Development (JAD) and
Rapid Application Development (RAD). See websites such as www.ibm.com
/software/awdtools/rup for more information.
Six Sigma methodologies: Many organizations have projects that use Six
Sigma methodologies. The work of many project quality experts contributed
to the development of today’s Six Sigma principles. Two main methodolo-
gies are used on Six Sigma projects: Define, Measure, Analyze, Improve, and
Control (DMAIC) is used to improve an existing business process, and Define,
Measure, Analyze, Design, and Verify (DMADV) is used to create new prod-
uct or process designs to achieve predictable, defect-free performance. (See
Chapter 8, Project Quality Management, for more information on Six Sigma.)
Many organizations tailor a standard or methodology to meet their unique needs.
Even if organizations use the PMBOK® Guide as the basis for their project management
methodology, they still have to do a fair amount of work to adapt it to their unique work
environment.
W H A T W E N T R I G H T ?
Organizations that excel in project management complete 89 percent of their projects
successfully compared to only 36 percent of organizations that do not have good project
management processes. PMI estimates that poor project performance costs over $109
million for every $1 billion invested in projects and programs.9
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

89
Very large, complex projects often benefit the most from using proven project man-
agement methodologies. Several well-respected companies are teaming up to bid on an
$11 billion military health-record contract in 2015. IBM and Epic announced that they
were preparing to work on the project by running an instance of the Epic health-record
system (the most popular system on the market) on a secure, IBM-operated data center.
PriceWaterhouseCoopers (PWC) plans to work with Google to provide a solution based on
an open-source version of the Vista health-record system used by the Department of
Veterans Affairs.10 If this huge contract is managed well, it will save taxpayers over
$1.2 billion in potential wasted dollars.
The following sections present two examples of applying the project management process
groups to a project at JWD Consulting. Both examples use some of the ideas from the PMBOK®
Guide, Fifth Edition, some ideas from other methodologies, and some new ideas to meet
unique project needs. The first case study follows a more predictive or waterfall approach,
while the second case study follows a more adaptive approach using Scrum. Even though they
are tailored for JWD Consulting’s organizational needs, they both still use the project manage-
ment process groups and several outputs or deliverables described in the PMBOK® Guide.
3.4 CASE STUDY 1: JWD CONSULTING’S
PROJECT MANAGEMENT INTRANET SITE PROJECT
(PREDICTIVE APPROACH)
The following fictitious case provides an example of the elements involved in managing a
project from start to finish. This example also uses Microsoft Project to demonstrate how
project management software can assist in several aspects of managing a project. Several
templates illustrate how project teams prepare various project management documents.
Files for these and other templates are available on the companion website for this text.
Details on creating many of the documents shown are provided in later chapters, so do not
worry if you do not understand everything right now. These two cases are provided to give
you a sense of the big picture of IT project management. You might want to read this sec-
tion again later to enhance your learning.
3.4a Project Pre-Initiation and Initiation
In project management, initiating includes recognizing and starting a new project. An orga-
nization should put considerable thought into project selection to ensure that it initiates the
right kinds of projects for the right reasons. It is better to have a moderate or even small
amount of success on an important project than huge success on a project that is unim-
portant. The selection of projects for initiation is therefore crucial, as is the selection of proj-
ect managers. Ideally, the project manager would be involved in initiating a project, but often
the project manager is selected after many initiation decisions have already been made. You
will learn more about project selection in Chapter 4, Project Integration Management.
It is important to remember that strategic planning should serve as the foundation for
deciding which projects to pursue. The organization’s strategic plan expresses the vision,
mission, goals, objectives, and strategies of the organization. It also provides the basis for
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

90
IT project planning. IT is usually a support function in an organization, so the people who
initiate IT projects must understand how those projects relate to current and future needs
of the organization. For example, JWD Consulting’s main business is providing consulting
services to other organizations, not developing its own intranet site applications. Informa-
tion systems, therefore, must support the firm’s business goals, such as providing consult-
ing services more effectively and efficiently.
An organization may initiate IT projects for several reasons, but the most impor-
tant reason is to support business objectives. As mentioned in the chapter’s opening
case, JWD Consulting wants to follow an exemplary process for managing its projects
because its core business is helping other organizations manage projects. Developing
an intranet to share its project management knowledge could help JWD Consulting
reduce internal costs by working more effectively, and by allowing existing and po-
tential customers to access some of the firm’s information. JWD Consulting could also
increase revenues by bringing in more business. Therefore, the firm will use these
metrics—reducing internal costs and increasing revenues—to measure its performance
on this project.
3.4b Pre-Initiation Tasks
It is good practice to lay the groundwork for a project before it officially starts. Senior
managers often perform several tasks to lay the groundwork, sometimes called pre-
initiation tasks, including the following:
Determine the scope, time, and cost constraints for the project.
Identify the project sponsor.
Select the project manager.
Develop a business case for a project.
Meet with the project manager to review the process and expectations for
managing the project.
Determine if the project should be divided into two or more smaller projects.
As described in the opening case, the CEO of JWD Consulting, Joe Fleming, defined
the high-level scope of the project. He wanted to sponsor the project himself because it
was his idea and it was strategically important to the business. He wanted Erica Bell, the
PMO Director, to manage the project after proving there was a strong business case for
it. If there was a strong business case for pursuing the project, then Joe and Erica would
meet to review the process and expectations for managing the project. If there was not a
strong business case, the project would not continue.
As for the necessity of the last pre-initiation task, many people know from experience
that it is easier to successfully complete a small project than a large one, especially for IT
projects. It often makes sense to break large projects down into two or more smaller ones
to help increase the odds of success. In this case, however, Joe and Erica decided that the
work could be done in one project that would last about six months.
To justify investing in this project, Erica drafted a business case for it, getting input
and feedback from Joe, from one of her senior staff members in the PMO, and from a
member of the Finance department. She also used a corporate template and sample busi-
ness cases from past projects as a guide. Table 3-2 provides the business case. (Note that
this example and others are abbreviated.) Notice that the following information is in-
cluded in this business case:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

91
Introduction/background
Business objective
Current situation and problem/opportunity statement
Critical assumptions and constraints
Analysis of options and recommendation
Preliminary project requirements
Budget estimate and financial analysis
Schedule estimate
Potential risks
Exhibits
Because this project is relatively small and is for an internal sponsor, the business
case is not as long as many other business cases. Erica reviewed the business case with
Joe, and he agreed that the project was definitely worth pursuing. He was quite pleased to
see that payback was estimated within a year and that the return on investment was pro-
jected to be 112 percent. He told Erica to proceed with the formal initiation tasks for this
project, which are described in the next section.
(continued)
TABLE 3-2
1.0 Introduction/Background
JWD Consulting’s core business goal is to provide world-class project management consulting services
to various organizations. The firm can streamline operations and increase business by providing
information related to project management on its intranet site, making some information and services
accessible to current and potential clients.
2.0 Business Objective
JWD Consulting’s strategic goals include continuing growth and profitability. The project management
intranet site project will support these goals by increasing visibility of the firm’s expertise to current and
potential clients by allowing client and public access to some sections of the intranet. The project will
also improve profitability by reducing internal costs by providing standard tools, techniques, templates,
and project management knowledge to all internal consultants.
3.0 Current Situation and Problem/Opportunity Statement
JWD Consulting has a corporate website as well as an intranet. The firm currently uses the website for
marketing information. The primary use of the intranet is for consultant human resource information,
such as entering hours on projects, changing and viewing benefits information, and accessing an online
directory and Web-based e-mail system. The firm also uses an enterprise-wide project management
system to track all project information, focusing on the status of deliverables and meeting scope, time,
and cost goals. There is an opportunity to provide a new section on the intranet dedicated to sharing
consultants’ project management knowledge across the organization. JWD Consulting only hires
experienced consultants and gives them freedom to manage projects as they see fit. However, as the
business grows and projects become more complex, even experienced project managers are looking for
suggestions on how to work more effectively.
4.0 Critical Assumptions and Constraints
The proposed intranet site must be a valuable asset for JWD Consulting. Current consultants and clients must
actively support the project, and it must pay for itself within one year by reducing internal operating costs and
generating new business. The Project Management Office manager must lead the effort, and the project team
must include participants from several parts of the company, as well as from current client organizations. The
new system must run on existing hardware and software, and it should require minimal technical support. It
must be easily accessible by consultants and clients and be secure from unauthorized users.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

92
5.0 Analysis of Options and Recommendation
There are three options for addressing this opportunity:
1. Do nothing. The business is doing well, and we can continue to operate without this new project.
2. Purchase access to specialized software to support this new capability with little in-house development.
3. Design and implement the new intranet capabilities in-house, using mostly existing hardware and
software.
Based on discussions with stakeholders, we believe that option 3 is the best option.
6.0 Preliminary Project Requirements
The main features of the project management intranet site include the following:
1. Access to several project management templates and tools. Users must be able to search for
templates and tools, read instructions for using these templates and tools, and see examples of how
to apply them to real projects. Users must also be able to submit new templates and tools, which
should first be screened or edited by the Project Management Office.
2. Access to relevant project management articles. Many consultants sense an information overload
when they research project management information. They often waste time they should be
spending with their clients. The new intranet should include access to important articles on project
management topics, which are searchable by topic, and should allow users to ask the Project
Management Office staff to find additional articles to meet their needs.
3. Links to other, up-to-date websites, with brief descriptions of the main features of the external
sites.
4. An Ask the Expert feature to help build relationships with current and future clients and share
knowledge with internal consultants.
5. Appropriate security to make the entire intranet site accessible to internal consultants and certain
sections accessible to others.
6. The ability to charge money for access to some information. Some of the information and features
of the intranet site should prompt external users to pay for the information or service. Payment
options should include credit card or similar online payment transactions. After the system verifies
payment, the user should be able to access or download the desired information.
7. Other features suggested by users, if they add value to the business.
7.0 Budget Estimate and Financial Analysis
A preliminary estimate of costs for the entire project is $140,000. This estimate is based on the project
manager working about 20 hours per week for six months and other internal staff working a total of
about 60 hours per week for six months. The customer representatives would not be paid for their
assistance. A staff project manager would earn $50 per hour. The hourly rate for the other project team
members would be $70 per hour, because some hours normally billed to clients may be needed for
this project. The initial cost estimate also includes $10,000 for purchasing software and services from
suppliers. After the project is completed, maintenance costs of $40,000 are included for each year,
primarily to update the information and coordinate the Ask the Expert feature and online articles.
Projected benefits are based on a reduction in hours that consultants spend researching project
management information, appropriate tools, and templates. Projected benefits are also based on a small
increase in profits due to new business generated by this project. If each of 400 consultants saved just
40 hours each year (less than one hour per week) and could bill that time to projects that generate a
conservative estimate of $10 per hour in profits, then the projected benefit would be $160,000 per year.
If the new intranet increased business by just 1 percent, using past profit information, increased profits
due to new business would be at least $40,000 each year. Total projected benefits, therefore, are about
$200,000 per year. Exhibit A summarizes the projected costs and benefits and shows the estimated
net present value (NPV), return on investment (ROI), and year in which payback occurs. It also lists
assumptions made in performing this preliminary financial analysis. All of the financial estimates are
very encouraging. The estimated payback is within one year, as requested by the sponsor. The NPV is
$272,800, and the discounted ROI based on a three-year system life is excellent at 112 percent.
(continued)
TABLE 3-2 continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

8.0 Schedule Estimate
The sponsor would like to see the project completed within six months, but there is some flexibility in
the schedule. We also assume that the new system will have a useful life of at least three years.
9.0 Potential Risks
This project carries several risks. The foremost risk is a lack of interest in the new system by our
internal consultants and external clients. User inputs are crucial for populating information into this
system and realizing the potential benefits from using the system. There are some technical risks in
choosing the type of software used to search the system, implement security, process payments, and so
on, but the features of this system all use proven technologies. The main business risk is investing the
time and money into this project and not realizing the projected benefits.
10.0 Exhibits
Exhibit A: Financial Analysis for Project Management Intranet Site Project
Discount rate 8%
Assume the project is done in about 6 months
0 1 2 3 Total
Costs
Discount factor
Discounted costs 243,084
Benefits
Discount factor
Discounted benefits 515,419
Discounted benefits – costs
Cumulative benefits – costs
40,000
0.93
37,037
200,000
0.93
186,185
148,148
8,148
40,000
0.86
34,294
200,000
0.86
171,468
137,174
145,322
40,000
0.79
31,753
200,000
0.79
158,766
127,013
272,336 NPV
Payback in Year 1
Discounted life cycle ROI————>
Assumptions
Costs
PM (500 hours, $50/hour)
Staff (1500 hours, $70/hour)
Outsourced software and services
Total project costs (all applied in year 0)
Benefits
# consultants
Hours saved
$/hour profit
Benefits from saving time
Benefits from 1% increase in profits
Total annual projected benefits
Year
140,000
1
140,000
(140,000)
(140,000)
112%
# hours
25,000
105,000
10,000
400
40
10
160,000
40,000
200,000
140,000
0
0
1
© Cengage Learning 2016
3.4c Initiating
To officially initiate the project management intranet site project, Erica knew that the main tasks
were to identify all of the project stakeholders and to develop the project charter. Table 3-3
shows these processes and their outputs, based on the PMBOK® Guide, Fifth Edition. The
main outputs are a project charter and a stakeholder register. Additional outputs that Erica
found very useful for initiating projects were a stakeholder management strategy and a formal
project kick-off meeting. Descriptions of how these outputs were created and sample docu-
ments related to each of them are provided for this project. Recall that every project and
every organization is unique, so not all project charters, stakeholder registers, and other out-
puts will look the same. You will see examples of several of these documents in later chapters.
TABLE 3-2 continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

94
TABLE 3-3
Knowledge Area Initiating Process Outputs
Project Integration Management Develop project charter Project charter
Project Stakeholder Management Identify stakeholders Stakeholder register
Source: PMBOK® Guide, Fifth Edition, 2013.
Identifying Project Stakeholders Erica met with Joe Fleming, the project’s sponsor,
to help identify key stakeholders. Recall from Chapter 1 that stakeholders are people in-
volved in project activities or affected by them, and include the project sponsor, project
team, support staff, customers, users, suppliers, and even opponents to the project. Joe,
the project sponsor, knew it would be important to assemble a strong project team, and
he was confident in Erica’s ability to lead that team. They decided that key team mem-
bers should include one of their full-time consultants with an outstanding record, Michael
Chen; one part-time consultant, Jessie Faue, who was new to the company and supported
the Project Management Office; and two members of the IT department who supported
the current intranet, Kevin Dodge and Cindy Dawson. They also knew that client inputs
would be important, so Joe agreed to ask the CEOs of two of the firm’s largest clients if
they would be willing to provide representatives to work on this project at their own ex-
pense. All of the internal staff Joe and Erica recommended agreed to work on the project,
and the two client representatives were Kim Phuong and Page Miller. Because many other
people would be affected by this project as future users of the new intranet, Joe and Erica
also identified other key stakeholders, including their directors of IT, Human Resources
(HR), and Public Relations (PR), as well as Erica’s administrative assistant.
After Joe and Erica made the preliminary contacts, Erica documented the stakehold-
ers’ roles, names, organizations, and contact information in a stakeholder register, a
document that includes details related to the identified project stakeholders. Table 3-4
provides an example of part of the initial stakeholder register. Because this document
would be public, Erica was careful not to include information that might be sensitive, such
as how strongly the stakeholders supported the project and their potential influence on
the project. She would keep these issues in mind discreetly and use them in developing
the stakeholder management strategy.
TABLE 3-4
Name Position
Internal/
External Project Role Contact Information
Joe Fleming CEO Internal Sponsor joe_fleming@jwdconsulting.com
Erica Bell PMO Director Internal Project
manager
erica_bell@jwdconsulting.com
Michael Chen Senior
Consultant
Internal Team
member
michael_chen@jwdconsulting.com
Kim Phuong Business
Analyst
External Advisor kim_phuong@client1.com
Louise Mills PR Director Internal Advisor louise_mills@jwdconsulting.com
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

95
A stakeholder analysis is a technique that project managers can use to help under-
stand and increase the support of stakeholders throughout the project. Results of the
stakeholder analysis can be documented in a stakeholder register or in a separate stake-
holder management strategy. This strategy includes basic information such as stakeholder
names, level of interest in the project, level of influence on the project, and potential
management strategies for gaining support or reducing obstacles from each stakeholder.
Because much of this information can be sensitive, it should be considered confidential.
Some project managers do not even write down this information, but they do consider
it because stakeholder management is a crucial part of their jobs. Table 3-5 provides an
example of part of Erica’s stakeholder management strategy for the project management
intranet site project. You will see other examples of documenting stakeholder information
in later chapters.
Drafting the Project Charter Erica drafted a project charter and had the project
team members review it before showing it to Joe. Joe made a few minor changes, which
Erica incorporated. Table 3-6 shows the final project charter. (Charters can include
more details than are shown in this example. See Chapter 4 for more information on
project charters.) Note the items included in the project charter and its short length.
JWD Consulting believes that project charters should be one or two pages long, and they
may refer to other documents, such as a business case, as needed. Erica felt the most
important parts of the project charter were the signatures of key stakeholders (not in-
cluded for brevity) and their individual comments. It is hard to get stakeholders to agree
on even a one-page project charter, so everyone has a chance to make their concerns
known in the comments section. Note that Michael Chen, the senior consultant asked
to work on the project, was concerned about participating when he felt that his other
assignments with external clients might have a higher priority. He offered to have an
assistant help as needed. The IT staff members mentioned their concerns about testing
and security issues. Erica knew that she would have to address these concerns when
managing the project.
TABLE 3-5
Name
Level of
Interest
Level of
Influence Potential Management Strategies
Joe Fleming High High Joe likes to stay on top of key projects and make
money. Have a lot of short, face-to-face meetings
and focus on achieving the financial benefits of the
project.
Louise Mills Low High Louise has a lot of things on her plate, and she
does not seem excited about this project. She may
be looking at other job opportunities. Show her
how this project will help the company and her
resume.
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

96
TABLE 3-6
Project Title: Project Management Intranet Site Project
Project Start Date: May 2 Projected Finish Date: November 4
Budget Information: The firm has allocated $140,000 for this project. The majority of costs for this
project will be internal labor. An initial estimate provides a total of 80 hours per week.
Project Manager: Erica Bell, (310) 555-5896, erica_bell@jwdconsulting.com
Project Objectives: Develop a new capability accessible on JWD Consulting’s intranet site to help internal
consultants and external customers manage projects more effectively. The intranet site will include
several templates and tools that users can download, examples of completed templates and related project
management documents used on real projects, important articles related to recent project management
topics, an article retrieval service, links to other sites with useful information, and an Ask the Expert
feature, where users can post questions about their projects and receive advice from experts in the field.
Some parts of the intranet site will be accessible free to the public, other parts will only be accessible to
current customers and internal consultants, and other parts will be accessible for a fee.
Main Project Success Criterion: The project should pay for itself within one year of completion.
Approach:
Develop a survey to determine critical features of the new intranet site and solicit input from
consultants and customers.
Review internal and external templates and examples of project management documents.
Research software to provide security, manage user inputs, and facilitate the article retrieval and
Ask the Expert features.
Develop the intranet site using an iterative approach, soliciting a great deal of user feedback.
Develop a way to measure the value of the intranet site in terms of reduced costs and new
revenues, both during the project and one year after project completion.
ROLES AND RESPONSIBILITIES (PARTIAL LIST)
Name Role Position Contact Information
Joe Fleming Sponsor JWD Consulting, CEO joe_fleming@jwdconsulting.com
Erica Bell Project
Manager
JWD Consulting,
manager
erica_bell@jwdconsulting.com
Michael Chen Team
Member
JWD Consulting,
senior consultant
michael_chen@jwdconsulting.com
Jessie Faue Team
Member
JWD Consulting,
consultant
jessie_faue@jwdconsulting.com
Kevin Dodge Team
Member
JWD Consulting, IT
department
kevin_dodge@jwdconsulting.com
Cindy Dawson Team
Member
JWD Consulting, IT
department
cindy_dawson@jwdconsulting.com
Kim Phuong Advisor Client representative kim_phuong@client1.com
Page Miller Advisor Client representative page_miller@client2.com
Sign-Off: (Signatures of all the above stakeholders)
Comments: (Handwritten or typed comments from above stakeholders, if applicable)
“I will support this project as time allows, but I believe my client projects take priority. I will have one of my
assistants support the project as needed.”—Michael Chen
“We need to be extremely careful testing this new system, especially the
security in giving access to parts of the intranet site to the public and
clients.”—Kevin Dodge and Cindy Dawson
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

97
Holding a Project Kick-Off Meeting Experienced project managers like Erica know
that it is crucial to get projects off to a great start. Holding a good kick-off meeting is an
excellent way to do this. A kick-off meeting is a meeting held at the beginning of a project
so that stakeholders can meet each other, review the goals of the project, and discuss fu-
ture plans. The kick-off meeting is often held after the business case and project charter
are completed, but it could be held sooner, as needed. Even if some or all project stake-
holders must meet virtually, it is still important to have a kick-off meeting.
Erica also knows that all project meetings with major stakeholders should include an
agenda. Figure 3-2 shows the agenda that Erica provided for the project management
intranet site project kick-off meeting. Notice the main topics in an agenda:
Meeting objective
Agenda (lists in order the topics to be discussed)
A section for documenting action items, who they are assigned to, and when
each person will complete the action
A section to document the date and time of the next meeting
[Date of Meeting]
Project Management Intranet Site Project
FIGURE 3-2
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

98
It is good practice to focus on results of meetings, which is why a good agenda has sec-
tions for documenting action items and deciding on the next meeting date and time.
It is also good practice to document meeting minutes, focusing on key decisions and ac-
tion items. Erica planned to send the meeting minutes to all meeting participants and
other appropriate stakeholders within a day or two after the meeting.
3.4d Project Planning
Planning is often the most difficult and unappreciated process in project management.
Because planning is not always used to facilitate action, many people view planning
negatively. The main purpose of project plans, however, is to guide project execution. To
guide execution, plans must be realistic and useful, so a fair amount of time and effort
must go into the planning process. People who are knowledgeable about the work need to
plan the work. Chapter 4, Project Integration Management, provides detailed information
on preparing a project management plan, and Chapters 5 through 13 describe planning
processes for each of the other knowledge areas.
Table 3-7 lists the project management knowledge areas, processes, and outputs of
project planning according to the PMBOK® Guide, Fifth Edition. If you plan to earn PMP
or CAPM certification, it will be helpful to study this table and similar ones found in this
chapter to understand the potential outputs of each process group. There are many
potential outputs from the planning process group, and every knowledge area is included.
Just a few planning documents from JWD Consulting’s project management intranet site
project are provided in this chapter as examples, and later chapters include many more
examples.
Recall that the PMBOK® Guide is only a guide, so many organizations may have
different planning outputs based on their particular needs, as is the case in this example.
You can also use many templates for planning; several are listed in the last section of
this chapter.
TABLE 3-7
Knowledge Area Planning Process Outputs
Project Integration
Management
Develop project
management plan
Project management plan
Project Scope
Management
Plan scope management Scope management plan
Requirements management plan
Collect requirements Requirements documentation
Requirements traceability matrix
Define scope Project scope statement
Project documents updates
Create WBS Scope baseline
Project documents updates
Project Time
Management
Plan schedule management Schedule management plan
Define activities Activity list
Activity attributes
Milestone list
Project management plan updates
(continued)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

99
Knowledge Area Planning Process Outputs
Sequence activities Project schedule network diagrams
Project documents updates
Estimate activity resources Activity resource requirements
Resource breakdown structure
Project documents updates
Estimate activity durations Activity duration estimates
Project documents updates
Develop schedule Schedule baseline
Project schedule
Schedule data
Project calendars
Project management plan updates
Project documents updates
Project Cost
Management
Plan cost management Cost management plan
Estimate costs Activity cost estimates
Basis of estimates
Project documents updates
Determine budget Cost baseline
Project funding requirements
Project documents updates
Project Quality
Management
Plan quality management Quality management plan
Process improvement plan
Quality metrics
Quality checklists
Project documents updates
Project Human
Resource Management
Plan human resource management Human resource plan
Project
Communications
Management
Plan communications management Communications management
plan
Project documents updates
Project Risk
Management
Plan risk management Risk management plan
Identify risks Risk register
Perform qualitative risk analysis Project documents updates
Perform quantitative risk analysis Project documents updates
Plan risk responses Project management plan updates
Project documents updates
Project Procurement
Management
Plan procurement management Procurement management plan
Procurement statement of work
Procurement documents
Source selection criteria
Make-or-buy decisions
Change requests
Project Stakeholder
Management
Plan stakeholder management Stakeholder management plan
Project documents updates
Source: PMBOK® Guide, Fifth Edition, 2013.
TABLE 3-7 continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

100
Because the project management intranet site project is relatively small, Erica
believes some of the most important planning documents to focus on are the following:
A team contract (not listed in Table 3-7, which is based only on the PMBOK®
Guide)
A project scope statement
A work breakdown structure (WBS), a key part of the scope baseline
A project schedule, in the form of a Gantt chart with all dependencies and
resources entered
A list of prioritized risks (part of a risk register)
All of these documents, as well as other project-related information, will be avail-
able to all team members on a project website. JWD Consulting has used project websites
for several years, and has found that they help facilitate communications and document
project information. For larger projects, JWD Consulting also creates many of the other
outputs listed in Table 3-7. (You will learn more about these documents by knowledge area
in the following chapters.)
Soon after the project team signed the project charter, Erica organized a team-building
meeting. An important goal of the meeting was helping the project team members get to
know each other. Erica had met and talked to each member separately, but this was the
first time the project team would spend much time together. Jessie Faue worked in the
Project Management Office with Erica, so they knew each other well, but Jessie was new to
the company and did not know any of the other team members. Michael Chen was a senior
consultant and often worked on the highest-priority projects for external clients. He at-
tended the meeting with his assistant, Jill Anderson, who would support the project when
Michael was too busy. Everyone valued Michael’s expertise, and he was extremely straight-
forward in dealing with people. He also knew both of the client representatives from past
projects. Kevin Dodge was JWD Consulting’s intranet guru, who tended to focus on techni-
cal details. Cindy Dawson was also from the IT department and had experience working as
a business consultant and negotiating with outside suppliers. Kim Phuong and Page Miller,
the two client representatives, were excited about the project, but they were wary of shar-
ing sensitive information about their companies.
Erica knew that it was important to build a strong team and have everyone work well
together. She had all participants introduce themselves, and then she led an icebreaking
activity so everyone would be more relaxed. She asked all participants to describe their
dream vacations, assuming that cost was no issue. This activity helped everyone get to
know each other and show different aspects of their personalities.
Erica then explained the importance of the project, again reviewing the signed proj-
ect charter. She explained that an important tool to help a project team work together
was to have members develop a team contract that everyone felt comfortable sign-
ing. JWD Consulting believed in using team contracts for all projects to help promote
teamwork and clarify team communications. She explained the main topics covered
in a team contract and showed them a team contract template. She then had the team
members form two smaller groups, with one consultant, one IT department member,
and one client representative in each group. These smaller groups made it easier for
everyone to contribute ideas. Each group shared its ideas for what should go into
the contract, and then everyone worked together to form one project team contract.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

101
Table 3-8 shows the resulting team contract, which took about 90 minutes to create.
Erica could see that there were different personalities on this team, but she felt they
all could work together well.
Erica wanted to keep the team-building meeting to its two-hour time limit. The next
task would be to clarify the scope of the project by developing a project scope statement
and WBS. She knew it would take time and several future meetings to develop these docu-
ments, but she wanted to get a feel for what everyone thought were the main deliverables
for this project, their roles in producing those deliverables, and what areas of the project
scope needed clarification. She reminded everyone what their budget and schedule goals
were so they would keep the goals in mind as they discussed the scope of the project.
TABLE 3-8
Code of Conduct: As a project team, we will:
Work proactively, anticipating potential problems and working to prevent them.
Keep other team members informed of information related to the project.
Focus on what is best for the entire project team.
Participation: We will:
Be honest and open during all project activities.
Encourage diversity in team work.
Provide the opportunity for equal participation.
Be open to new approaches and consider new ideas.
Have one discussion at a time.
Let the project manager know well in advance if a team member has to miss a meeting or may
have trouble meeting a deadline for a given task.
Communication: We will:
Decide as a team on the best way to communicate. Because a few team members cannot
often meet face to face, we will use e-mail, a project website, and other technology to assist in
communicating.
Have the project manager facilitate all meetings and arrange for phone and video conferences,
as needed.
Work together to create the project schedule and enter actuals into the enterprise-wide project
management system by 4 p.m. every Friday.
Present ideas clearly and concisely.
Keep discussions on track.
Problem Solving: We will:
Encourage everyone to participate in solving problems.
Only use constructive criticism and focus on solving problems, not blaming people.
Strive to build on each other’s ideas.
Meeting Guidelines: We will:
Have a face-to-face meeting the first and third Tuesday morning of every month.
Meet more frequently the first month.
Hold other meetings as needed.
Record meeting minutes and send them via e-mail within 24 hours of all project meetings,
focusing on decisions made and action items from each meeting.
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

102
She also asked each person to provide the number of hours he or she would be available to
work on this project each month for the next six months. She then had each person write
answers to the following questions:
1. List one item that is most unclear to you about the scope of this project.
2. What other questions do you have or issues do you foresee about the scope of
the project?
3. List what you believe to be the main deliverables for this project.
4. Which deliverables do you think you will help create or review?
Erica collected everyone’s inputs. She explained that she would take this information
and work with Jessie to develop the first draft of the scope statement that she would e-mail
to everyone by the end of the week. She also suggested that they all meet again in one week
to develop the scope statement further and to start creating the WBS for the project.
Erica and Jessie reviewed all the information and created the first draft of the scope
statement. At their next team meeting, they discussed the scope statement and got a good
start on the WBS. Table 3-9 shows a portion of the scope statement that Erica created
after a few more e-mails and another team meeting. Note that the scope statement lists
the product characteristics and requirements, summarizes the deliverables, and describes
project success criteria in detail.
TABLE 3-9
Project Title: Project Management Intranet Site Project
Date: May 18 Prepared by: Erica Bell, Project Manager, erica_bell@jwdconsulting.com
Project Summary and Justification: Joe Fleming, CEO of JWD Consulting, requested this project to
assist the company in meeting its strategic goals. The new intranet site will increase visibility of the
company’s expertise to current and potential clients. It will also help reduce internal costs and improve
profitability by providing standard tools, techniques, templates, and project management knowledge to
all internal consultants. The budget for the project is $140,000. An additional $40,000 per year will be
required for operational expenses after the project is completed. Estimated benefits are $200,000 each
year. It is important to focus on the system paying for itself within one year of its completion.
Product Characteristics and Requirements:
1. Templates and tools: The intranet site will allow authorized users to download files they can use to
create project management documents and to help them use project management tools. These files
will be in Microsoft Word, Excel, Access, Project, or in HTML or PDF format, as appropriate.
2. User submissions: Users will be encouraged to e-mail files with sample templates and tools to the
Webmaster. The Webmaster will forward the files to the appropriate person for review and then
post the files to the intranet site, if desired.
3. Articles: Articles posted on the intranet site will have appropriate copyright permission. The
preferred format for articles will be PDF. The project manager may approve other formats.
4. Requests for articles: The intranet site will include a section for users to ask someone from the
Project Management Office (PMO) at JWD Consulting to research appropriate articles for them.
The PMO manager must first approve the request and negotiate payments, if appropriate.
5. Links: All links to external sites will be tested on a weekly basis. Broken links will be fixed or
removed within five working days of discovery.
6. The Ask the Expert feature must be user-friendly and capable of soliciting questions and
immediately acknowledging that the question has been received in the proper format. The feature
must also be capable of forwarding the question to the appropriate expert (as maintained in the
system’s expert database) and capable of providing the status of questions that are answered. The
system must also allow for payment for advice, if appropriate.
(continued)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

7. Security: The intranet site must provide several levels of security. All internal employees will have
access to the entire intranet site when they enter their security information to access the main,
corporate intranet. Part of the intranet will be available to the public from the corporate website.
Other portions of the intranet will be available to current clients based on verification with the
current client database. Other portions of the intranet will be available after negotiating a fee or
entering a fixed payment using pre-authorized payment methods.
8. Search feature: The intranet site must include a search feature for users to search by topic and key
words.
9. The intranet site must be accessible using a company-approved Internet browser. Users must have
appropriate application software to open several of the templates and tools.
10. The intranet site must be available 24 hours a day, 7 days a week, with one hour per week for
system maintenance and other periodic maintenance, as appropriate.
Summary of Project Deliverables
Project management-related deliverables: Business case, charter, team contract, scope statement, WBS,
schedule, cost baseline, progress reports, final project presentation, final project report, lessons-learned
report, and any other documents required to manage the project.
Product-related deliverables:
1. Survey: Survey current consultants and clients to help determine desired content and features for
the intranet site.
2. Files for templates: The intranet site will include templates for at least 20 documents when the
system is first implemented, and it will have the capacity to store up to 100 documents. The project
team will decide on the initial 20 templates based on survey results.
3. Examples of completed templates: The intranet site will include examples of projects that have
used the templates available on the site. For example, if there is a template for a business case,
there will also be an example of a real business case that uses the template.
4. Instructions for using project management tools: The intranet site will include information
on how to use several project management tools, including the following as a minimum: work
breakdown structures, Gantt charts, network diagrams, cost estimates, and earned value
management. Where appropriate, sample files will be provided in the application software
appropriate for the tool. For example, Microsoft Project files will be available to show sample
work breakdown structures, Gantt charts, network diagrams, cost estimates, and applications of
earned value management. Excel files will be available for sample cost estimates and earned value
management charts.
5. Example applications of tools: The intranet site will include examples of real projects that have
applied the tools listed in number 4.
6. Articles: The intranet site will include at least 10 useful articles about relevant topics in project
management. The intranet site will have the capacity to store at least 1,000 articles in PDF format
with an average length of 10 pages each.
7. Links: The intranet site will include links with brief descriptions for at least 20 useful sites. The
links will be categorized into meaningful groups.
8. Expert database: In order to deliver an Ask the Expert feature, the system must include and access
a database of approved experts and their contact information. Users will be able to search for
experts by predefined topics.
9. User Requests feature: The intranet site will include an application to solicit and process requests
from users.
10. Intranet site design: An initial design of the new intranet site will include a site map, suggested
formats, and appropriate graphics. The final design will incorporate comments from users on the
initial design.
11. Intranet site content: The intranet site will include content for the templates and tools sections,
articles section, article retrieval section, links section, Ask the Expert section, User Requests
feature, security, and payment features.
12. Test plan: The test plan will document how the intranet site will be tested, who will do the testing,
and how bugs will be reported.
(continued)
TABLE 3-9 continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

104
13. Promotion: A plan for promoting the intranet site internally and externally will describe various
approaches for soliciting inputs during design. The promotion plan will also announce the
availability of the new intranet site.
14. Project benefit measurement plan: A project benefit plan will measure the financial value of the
intranet site.
Project Success Criteria: Our goal is to complete this project within six months for no more than
$140,000. The project sponsor, Joe Fleming, has emphasized the importance of the project paying for
itself within one year after the site is complete. To meet this financial goal, the intranet site must have
strong user inputs. We must also develop a method for capturing the benefits while the intranet site is
being developed and tested, and after it is rolled out. If the project takes a little longer to complete or
costs a little more than planned, the firm will still view it as a success if it has a good payback and helps
promote the firm’s image as an excellent consulting organization.
© Cengage Learning 2016
As the project team worked on the scope statement, it also developed the work
breakdown structure (WBS) for the project. The WBS is a very important tool in project
management because it provides the basis for deciding how to do the work. The WBS
also provides a basis for creating the project schedule and for measuring and forecasting
project performance. Erica and her team decided to use the project management pro-
cess groups as the main categories for the WBS, as shown in Figure 3-3. They included
completed work from the initiating process to provide a complete picture of the project’s
scope. The team members also wanted to list several milestones on their schedule, such as
the completion of key deliverables, so they prepared a separate list of milestones that they
would include on the Gantt chart. You will learn more about creating a WBS in Chapter 5,
Project Scope Management.
After preparing the WBS, the project team held another face-to-face meeting to de-
velop the project schedule, following the steps outlined in Section 2.5 of the WBS. Several
of the project schedule tasks are dependent on one another. For example, the intranet site
testing was dependent on the construction and completion of the content tasks. Everyone
participated in the development of the schedule, especially the tasks on which each mem-
ber would be working. Some of the tasks were broken down further so the team members
had a better understanding of what they had to do and when. They also kept their work-
loads and cost constraints in mind when developing the duration estimates. For example,
Erica was scheduled to work 20 hours per week on this project, and the other project
team members combined should not spend more than 60 hours per week on average for
the project. As team members provided duration estimates, they also estimated how many
work hours they would spend on each task.
After the meeting, Erica worked with Jessie to enter all of the information into
Microsoft Project. Erica was using the intranet site project to train Jessie in applying
several project management tools and templates. They entered all of the tasks, duration
estimates, and dependencies to develop the Gantt chart. Their initial inputs resulted in a
completion date that was a few weeks later than planned. Erica and Jessie reviewed the
critical path for the project, and Erica had to shorten the duration estimates for a few
critical tasks to meet their schedule goal of completing the project within six months. She
talked to the team members working on those tasks, and they agreed that they could plan
TABLE 3-9 continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

105
1.0 Initiating
1.2 Prepare project charter
1.3 Hold project kick-off meeting
2.0 Planning
2.1 Hold team planning meeting
2.2 Prepare team contract
2.3 Prepare scope statement
2.4 Prepare WBS
2.5 Prepare schedule and cost baseline
2.5.1 Determine task resources
2.5.2 Determine task durations
2.5.3 Determine task dependencies
2.5.4 Create draft Gantt chart
2.5.5 Review and finalize Gantt chart
2.6 Identify, discuss, and prioritize risks
3.0 Executing
3.1 Survey
3.2 User inputs
3.3 Intranet site content
3.3.1 Templates and tools
3.3.2 Articles
3.3.3 Links
3.3.4 Ask the Expert
3.3.5 User requests feature
3.4 Intranet site design
3.5 Intranet site construction
3.6 Intranet site testing
3.7 Intranet site promotion
3.8 Intranet site roll-out
3.9 Project benefits measurement
4.0 Monitoring and Controlling
4.1 Progress reports
4.2 Change requests
5.0 Closing
5.1 Prepare final project report
5.2 Prepare final project presentation
5.3 Lessons learned
1.1 Identify key stakeholders
FIGURE 3-3
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

106
to work more hours each week on those tasks, if required, to complete them on time.
Figure 3-4 shows the resulting Gantt chart created in Microsoft Project. Only the execut-
ing tasks are expanded to show the subtasks under that category. (You will learn how to
use Project 2013 in Appendix A. Chapter 6, Project Time Management, explains Gantt
charts and other time management tools.)
The baseline schedule projects a completion date of November 1. Also notice that
there is only one delivery of the software, shown as a milestone near the end of the proj-
ect, on October 17. The project charter had a planned completion date of November 4.
Erica wanted to complete the project on time, and although three extra days was not
much of a buffer, she felt the baseline schedule was realistic. She would do her best to
help everyone meet their deadlines.
Erica decided to enter the resource and cost information after reviewing the
schedule because the majority of the costs for this project were internal labor.
Aware of the connection between time spent and cost on the project, the team kept
its labor hour constraints in mind when developing task duration estimates. Erica
and Jessie entered each project team member’s name and labor rate in the resource
sheet for their Microsoft Project file. The client representatives were not being
paid for their time, so she left their labor rates at the default value of zero. Erica
had also included $10,000 for procurement in the financial analysis she prepared
for the business case. She showed Jessie how to enter that amount as a fixed cost
split equally between the Ask the Expert and User Requests features, because she
thought they would have to purchase external software and services for those. Erica
then helped Jessie assign resources to tasks, which involved entering the projected
number of hours everyone planned to work each week on each task. They then ran
several cost reports and made a few minor adjustments to resource assignments to
make their planned total cost meet their budget constraints. Their cost baseline was
very close to their planned budget of $140,000.
FIGURE 3-4
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

107
The last deliverable her team needed to create within the planning process group
was a list of prioritized risks. As the project progresses, this information will be up-
dated and expanded in a risk register, which also includes information on root causes
of the risks, warning signs that potential risks might occur, and response strategies for
the risks. (See Chapter 11, Project Risk Management, for more information on risk
registers.) Erica reviewed the risks she had mentioned in the business case as well as
the comments team members made on the project charter and in their team meetings.
She held a special meeting for everyone to brainstorm and discuss potential risks. They
listed all of the risks they identified and then categorized them to analyze how likely
(high, medium, or low probability) each was and how big an impact (high, medium, or
low) each could have. Only one risk was in the high probability and high impact cat-
egory, and several had medium impact. They chose not to list the low-probability and
low-impact risks. After some discussion, the team developed the list of prioritized risks
shown in Table 3-10.
3.4e Project Execution
Executing the project involves taking the necessary actions to complete the activities in
the project plan. The products of the project are created during project execution, and it
usually takes the most resources to accomplish this process. Table 3-11 lists the knowl-
edge areas, executing processes, and outputs of project execution from the PMBOK®
Guide, Fifth Edition.
Many project sponsors and customers focus on deliverables related to providing
the products, services, or results desired from the project. However, it is equally
important to document change requests and update planning documents as part of
execution. Templates related to this process group are listed later in this chapter.
TABLE 3-10
Ranking Potential Risk
1 Lack of inputs from internal consultants
2 Lack of inputs from client representatives
3 Security of new system
4 Outsourcing/purchasing for the article retrieval and Ask the Expert features
5 Outsourcing/purchasing for processing online payment transactions
6 Organizing the templates and examples in a useful fashion
7 Providing an efficient search feature
8 Getting good feedback from Michael Chen and other senior consultants
9 Effectively promoting the new system
10 Realizing the benefits of the new system within one year
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

108
TABLE 3-11
Knowledge Area Executing Process Outputs
Project Integration
Management
Direct and manage project
work
Deliverables
Work performance data
Change requests
Project management plan updates
Project documents updates
Project Quality
Management
Perform quality assurance Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
Project Human Resource
Management
Acquire project team Project staff assignments
Resource calendars
Project management plan updates
Develop project team Team performance assessments
Enterprise environmental factor updates
Manage project team Change requests
Project management plan updates
Project documents updates
Enterprise environmental factors updates
Organizational process assets updates
Project Communications
Management
Manage communications Project communications
Project documents updates
Project management plan updates
Organizational process assets updates
Project Procurement
Management
Conduct procurements Selected sellers
Agreements
Resource calendars
Change requests
Project management plan updates
Project documents updates
Project Stakeholder
Management
Manage stakeholder
engagement
Issue log
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
Source: PMBOK® Guide, Fifth Edition, 2013.
Erica knew that providing strong leadership and using good communication skills were
crucial to good project execution. For this relatively small project, she was able to work
closely with all the team members to make sure they were producing the desired work
results. She also used her networking skills to get input from other people in the firm and
from external sources at no additional cost to the project. She made sure that everyone who
would use the resulting intranet application understood what the team was producing as
part of the project and how the intranet application would help them in the future.
Erica also knew that working efficiently was critical for successful execution, regard-
less of the size of the project. Therefore, she used resources throughout the company
when they were available. For example, she used the firm’s formal change request form,
even though it had primarily been used for external projects. The firm also had contract
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

109
specialists and templates for several procurement documents that the project team mem-
bers would use for the portions of the project it planned to outsource.
Erica kept in mind that Joe, the CEO and project sponsor, liked to see progress on
projects through milestone reports. He also wanted Erica to alert him to any potential
issues or problems. Erica met with most of her project team members often, and she
talked to Joe about once a week to review progress on completing milestones and to
discuss any other project issues. Although Erica could have used project management
software to create milestone reports, she used word-processing software instead because
this project was small and she could more easily manipulate the report format. Table 3-12
shows a sample of a milestone report for the project management intranet site project that
Erica reviewed with Joe in mid-June.
TABLE 3-12
Milestone Date Status Responsible Issues/Comments
Initiating
Stakeholders identified May 2 Completed Erica and Joe
Project charter signed May 10 Completed Erica
Project kick-off meeting held May 13 Completed Erica Went very well
Planning
Team contract signed May 13 Completed Erica
Scope statement completed May 27 Completed Erica
WBS completed May 31 Completed Erica
List of prioritized risks
completed June 3 Completed Erica
Reviewed with
sponsor and team
Schedule and cost baseline
completed June 13 Completed Erica
Executing
Survey and analysis completed June 28 Erica
Poor response so far!
Intranet site design completed July 26 Kevin
Project benefits measurement
completed August 9 Erica
User inputs collected August 9 Jessie
Articles completed August 23 Jessie
Templates and tools
completed September 6 Erica
Ask the Expert completed September 6 Michael
User Requests feature
completed September 6 Cindy
Links completed September 13 Kevin
Intranet site construction
completed October 4 Kevin
Intranet site testing
completed October 18 Cindy
(continued)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

110
Milestone Date Status Responsible Issues/Comments
Intranet site promotion
completed October 25 Erica
Intranet site roll-out
completed October 25 Kevin
Monitoring and Controlling
Progress reports Every Friday All
Closing
Final project presentation
completed October 27 Erica
Sponsor sign-off on project
completed October 27 Joe
Final project report completed October 28 Erica
Lessons-learned reports
submitted November 1 All
© Cengage Learning 2016
Human resource issues often occur during project execution, especially conflicts. At
several of the team meetings, Erica could see that Michael seemed to be bored and often
left the room to make phone calls to clients. She talked to Michael about the situation,
and she discovered that Michael was supportive of the project, but he knew he could only
spend a minimal amount of time on it. He was much more productive outside of meetings,
so Erica agreed to have Michael attend a minimal number of project team meetings. She
could see that Michael was contributing to the team by the feedback he provided and his
leadership on the Ask the Expert feature for the intranet site. Erica adjusted her commu-
nication style to meet his specific needs.
Another problem occurred when Cindy was contacting potential suppliers for software
to help with the Ask the Expert and User Requests features. Kevin wanted to write all of
the software for the project himself, but Cindy knew it made better business sense to pur-
chase these new software capabilities from a reliable source. Cindy had to convince Kevin
that it was worth buying some software from other sources.
Cindy also discovered that their estimate of $10,000 was only about half the amount
they needed for software services. She discussed the problem with Erica, explaining the
need for some custom development no matter which supplier they chose. Erica agreed
that they should go with an outside source, and she asked their sponsor to approve the
additional funds. Joe agreed, but he stressed the importance of still having the system pay
for itself within a year.
Even near the beginning of the project, Erica had tapped Joe for help when the team
received a low response rate to their survey and requests for user inputs. Joe sent an
e-mail to all of JWD Consulting’s consultants describing the importance of the project. He
also offered five extra vacation days to the person who provided the best examples of how
they used tools and templates to manage their projects. Erica then received informative
input from the consultants. Having effective communication skills and strong top manage-
ment support are essential to good project execution.
TABLE 3-12 continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

111
B E S T P R A C T I C E
One way to learn about best practices in project management is by studying recipi-
ents of PMI’s Project of the Year award. The Quartier International de Montréal (QIM),
Montreal’s international district, was a 66-acre urban revitalization project in the
heart of downtown Montreal. This $90 million, five-year project turned a once un-
popular area into a thriving section of the city with a booming real estate market, and
has generated $770 million in related construction. Clement Demers, PMP, was the
director general for the QIM project. He said the team “took a unique project execu-
tion approach by dividing work into packages that allowed for smaller-scale testing of
management techniques and contract awards. Benefiting from experience gained in
each stage, managers could then adjust future work segments and management styles
accordingly.”11
Other strategies that helped the team succeed included the following:
The team identified champions in each stakeholder group to help inspire others to
achieve project goals.
The team’s communications plan included a website dedicated to public
concerns.
There were two-day reviews at the beginning of each project phase to discuss
problems and develop solutions to prevent conflict.
Financial investors were asked for input to increase their stake in the
project.
The team recognized the value of hiring high-quality experts, such as archi-
tects, engineers, lawyers, and urban planners. They paid all professionals a
fixed price for their services and paid their fees quickly.
Another Canadian firm won the Project of the Year award in 2014. The
CA $1.3 billion AP60 Phase 1 Project produced an upgraded aluminum
smelting facility in Jonquiere, Quebec. In 2013, the Adelaide desalination
project in Adelaide, Australia, won the award. This project, which supplies
water during times of drought, was completed early and within 1 percent of
its AU$1.4 billion budget.12 The 2012 award went to a high-risk chemical
agent disposal project in Hermiston, Oregon, which was completed ahead of
schedule, under budget, and with a low injury rate that was striking given
the deadly nature of the chemicals involved.13 See PMI’s website for more
information on award criteria and winners.
3.4f Project Monitoring and Controlling
Monitoring and controlling is the process of measuring progress toward project objec-
tives, monitoring deviation from the current plan, and taking corrective action to match
progress with the current plan. Monitoring and controlling is done throughout the life of
a project and involves 9 of the 10 project management knowledge areas. Table 3-13 lists
the knowledge areas, monitoring and controlling processes, and outputs, according to the
PMBOK® Guide, Fifth Edition. Templates related to this process group are listed later in
this chapter.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

112
TABLE 3-13
Knowledge Area
Monitoring and Controlling
Process Outputs
Project Integration
Management
Monitor and control project work Change requests
Work performance reports
Project management plan updates
Project documents updates
Perform integrated change
control
Approved change requests
Change log
Project management plan updates
Project documents updates
Project Scope
Management
Validate scope Accepted deliverables
Change requests
Work performance information
Project documents updates
Control scope Work performance information
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
Project Time
Management
Control schedule Work performance information
Schedule forecasts
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
Project Cost
Management
Control cost Work performance information
Cost forecasts
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
Project Quality
Management
Control quality Quality control measurements
Validated changes
Validated deliverables
Work performance information
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
Project Communications
Management
Control communications Work performance information Change
requests
Project documents updates
Organizational process assets updates
Project Risk
Management
Control risks Work performance information
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
(continued)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Knowledge Area
Monitoring and Controlling
Process Outputs
Project Procurement
Management
Control procurements Work performance information
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
Project Stakeholder
Management
Control stakeholder engagement Work performance information
Change requests
Project documents updates
Organizational process assets updates
Source: PMBOK® Guide, Fifth Edition, 2013.
On the project management intranet site project, several updates to the project
management plan were made to reflect changes made to the project scope, schedule, and
budget. Erica and other project team members took corrective action when necessary.
For example, when they were not getting many responses to their survey, Erica asked Joe
for help. When Cindy had trouble negotiating with a supplier, she got help from another
senior consultant who had worked with that supplier in the past. Erica also had to request
more funds for that part of the project.
Project team members submitted a brief progress report every Friday to show work per-
formance information. They were originally using a company template for progress reports,
but Erica found that by modifying the old template, she received better information, which
then helped her team work more effectively. She wanted team members not only to report
what they did but also to focus on what was going well or not going well, and why. This ex-
tra information helped team members reflect on the project’s progress and identify areas in
need of improvement. Table 3-14 is an example of one of Cindy’s progress reports.
TABLE 3-14
Project Name: Project Management Intranet Project
Team Member Name: Cindy Dawson, cindy_dawson@jwdconsulting.com
Date: August 5
Work completed this week:
–Worked with Kevin to start the intranet site construction
–Organized all the content files
–Started developing a file naming scheme for content files
–Continued work on Ask the Expert and User Requests features
–Met with preferred supplier
–Verified that their software would meet our needs
–Discovered the need for some customization
Work to complete next week:
–Continue work on intranet site construction
–Prepare draft contract for preferred supplier
–Develop new cost estimate for outsourced work
TABLE 3-13 continued
(continued)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

114
What’s going well and why:
The intranet site construction started well. The design was very clear and easy to follow. Kevin really
knows what he’s doing.
What’s not going well and why:
It is difficult to decide how to organize the templates and examples. Need more input from senior
consultants and clients.
Suggestions/Issues:
–Hold a special meeting to decide how to organize the templates and examples on the intranet site.
–Get some sample contracts and help in negotiating with the preferred supplier.
Project changes:
I think we can stay on schedule, but it looks like we’ll need about $10,000 more for outsourcing. That’s
doubling our budget in that area.
© Cengage Learning 2016
In addition to progress reports, an important tool for monitoring and controlling the
project was using project management software. All team members submitted their ac-
tual hours worked on tasks each Friday afternoon by 4 p.m. via the firm’s enterprise-wide
project management software. They were using the enterprise version of Microsoft Proj-
ect 2013, so they could easily update their task information via the Web. Erica worked
with Jessie to analyze the information, paying special attention to the critical path and
earned value data. (See Chapter 6, Project Time Management, for more information on
critical path analysis; Chapter 7, Project Cost Management, for a description of earned
value management; and Appendix A for more information on using Project 2013 to help
control projects.) Erica wanted to finish the project on time, even if it meant spending
more money. Joe agreed with that approach, and approved the additional funding Erica
projected they would need based on the earned value projections and the need to make
up a little time on critical tasks.
Joe again emphasized the importance of the new system paying for itself within a
year. Erica was confident that they could exceed the projected financial benefits, and she
decided to begin capturing benefits as soon as the project team began testing the system.
When she was not working on this project, Erica was managing JWD Consulting’s Project
Management Office (PMO), and she could already see how the intranet site would help
her staff save time and make their consultants more productive. One of her staff members
wanted to move into the consulting group, and she believed the PMO could continue to
provide its current services with one less person due to this new system—a benefit Erica
had not considered before. Several of the firm’s client contracts were based on perfor-
mance and not hours billed, so she was excited to start measuring the value of the new
intranet site to their consultants as well.
3.4g Project Closing
The closing process involves gaining stakeholder and customer acceptance of the final
products and services and then bringing the project or project phase to an orderly end.
It includes verifying that all of the deliverables are complete, and it often includes a
TABLE 3-14 continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

115
final project report and presentation. Even though many IT projects are canceled before
completion, it is still important to formally close any project and reflect on what can be
learned to improve future projects. As philosopher George Santayana said, “Those who
cannot remember the past are condemned to repeat it.”14
It is also important to plan for and execute a smooth transition of the project into
the normal operations of the company. Most projects produce results that are inte-
grated into the existing organizational structure. For example, JWD Consulting’s project
management intranet site project will require staff to support the intranet site after it
is operational. Erica included support costs of $40,000 per year for the projected three-
year life of the new system. She also created a transition plan as part of the final report
to provide for a smooth transition of the system into the firm’s operations. The plan in-
cluded a list of issues that had to be resolved before the firm could put the new intranet
site into production. For example, Michael Chen would not be available to work on the
intranet site after the six-month project was complete, so the team had to know who
would support the Ask the Expert feature and plan some time for Michael to work with
that person.
Table 3-15 lists the knowledge areas, processes, and outputs of project closing
based on the PMBOK® Guide, Fifth Edition. During the closing processes of any proj-
ect, project team members must deliver the final product, service, or result of the proj-
ect and update organizational process assets, such as project files and a lessons-learned
report. If project team members procured items during the project, they must formally
complete or close out all contracts. Templates related to project closing are listed later
in this chapter.
Erica and her team prepared a final report, final presentation, contract files,
and lessons-learned report in closing the project. Erica reviewed the confidential,
individual lessons-learned reports from each team member and wrote one summary
lessons-learned report to include in the final documentation, part of which is pro-
vided in Table 3-16. Notice the bulleted items in the fourth question, such as the
importance of having a good kick-off meeting, working together to develop a team
contract, using project management software, and communicating well with the
project team and sponsor.
Erica also had Joe sign a client acceptance form, one of the sample templates on the
new intranet site that the project team suggested all consultants use when closing their
projects. (You can find this and other templates on the companion website for this text.)
TABLE 3-15
Knowledge Area Closing Process Outputs
Project Integration
Management
Close project or phase Final product, service, or result transition
Organizational process assets updates
Project
Procurement
Management
Close procurements Closed procurements
Organizational process assets updates
Source: PMBOK® Guide, Fifth Edition, 2013.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

116
Table 3-17 provides the table of contents for the final project report. The cover
page included the project title, date, and team member names. Notice the inclusion of
a transition plan and a plan to analyze the benefits of the system each year in the final
report. Also, notice that the final report includes attachments for all the project manage-
ment and product-related documents. Erica knew how important it was to provide good
final documentation on projects. The project team produced a hard copy of the final
TABLE 3-16
Project Name: JWD Consulting Project Management Intranet Site Project
Project Sponsor: Joe Fleming
Project Manager: Erica Bell
Project Dates: May 2 – November 4
Final Budget: $150,000
1. Did the project meet scope, time, and cost goals?
We did meet scope and time goals, but we had to request an additional $10,000, which the
sponsor approved.
2. What were the success criteria listed in the project scope statement?
Below is what we put in our project scope statement under project success criteria:
“Our goal is to complete this project within six months for no more than $140,000. The project
sponsor, Joe Fleming, has emphasized the importance of the project paying for itself within one
year after the intranet site is complete. To meet this financial goal, the intranet site must have
strong user input. We must also develop a method for capturing the benefits while the intranet
site is being developed and tested, and after it is rolled out. If the project takes a little longer to
complete or costs a little more than planned, the firm will still view it as a success if it has a good
payback and helps promote the firm’s image as an excellent consulting organization.”
3. Reflect on whether you met the project success criteria.
As stated above, the sponsor was not too concerned about going over budget as long as the
system would have a good payback period and help promote our firm’s image. We have already
documented some financial and image benefits of the new intranet site. For example, we have
decided that we can staff the PMO with one less person, resulting in substantial cost savings. We
have also received excellent feedback from several of our clients about the new intranet site.
4. What were the main lessons your team learned from managing this project?
The main lessons we learned include the following:
Having a good project sponsor was instrumental to project success. We ran into a couple of
difficult situations, and Joe was very creative in helping us solve problems.
Teamwork was essential. It really helped to take time for everyone to get to know each other
at the kick-off meeting. It was also helpful to develop and follow a team contract.
Good planning paid off in execution. We spent a fair amount of time developing a good
project charter, scope statement, WBS, schedules, and so on. Everyone worked together to
develop these planning documents, and there was strong buy-in.
Project management software was very helpful throughout the project.
5. Describe one example of what went right on this project.
6. Describe one example of what went wrong on this project.
7. What will you do differently on the next project based on your experience working on this project?
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

117
documentation and an electronic copy to store on the new intranet site for other consul-
tants to use as desired.
Erica also organized a project closure luncheon for the project team right after the
final project presentation. She used the luncheon to share lessons learned and celebrate a
job well done.
3.5 CASE STUDY 2: JWD CONSULTING’S PROJECT MANAGE-
MENT INTRANET SITE PROJECT (AGILE APPROACH)
This section demonstrates an agile approach to managing JWD Consulting’s project
management intranet site project. Instead of repeating the sample documents shown in
the first, predictive case study, this section emphasizes the differences of using an agile
TABLE 3-17
1. Project Objectives
2. Summary of Project Results
3. Original and Actual Start and End Dates
4. Original and Actual Budget
5. Project Assessment (Why did you do this project? What did you produce? Was the project a success?
What went right and wrong on the project?)
6. Transition Plan
7. Annual Project Benefits Measurement Approach
Attachments:
A Project Management Documentation
Business case
Project charter
Team contract
Scope statement
WBS and WBS dictionary
Baseline and actual Gantt chart
List of prioritized risks
Milestone reports
Progress reports
Contract files
Lessons-learned reports
Final presentation
Client acceptance form
B Product-Related Documentation
Survey and results
Summary of user inputs
Intranet site content
Intranet site design documents
Test plans and reports
Intranet site promotion information
Intranet site roll-out information
Project benefits measurement information
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

118
approach in each process group. Recall that an agile approach is often used for projects in
which the business team cannot clearly express the scope early in the product life cycle,
but the team wants to provide a potentially shippable product earlier rather than later. An
agile project team typically uses several iterations or deliveries of software instead of wait-
ing until the end of the project to provide one product.
Note that teams do not normally make a snap decision about whether to manage a proj-
ect using an agile approach or not. Likewise, you don’t just decide whether to take a plane or
a car on a long trip without specific logic. If you need to get somewhere quickly, have little
concern for sightseeing along the way, and have no problems with flying, you will probably
take a plane. If you want to take your time getting somewhere, see sights along the way, and
enjoy driving, you will take a car. Likewise, organizations should use logic to decide when to
use a predictive approach or an agile approach to managing specific projects. Projects with
heavy constraints, inexperienced and dispersed teams, large risks, generally clear up-front
requirements, and a fairly rigid completion date are best done using a predictive approach.
In contrast, projects with less rigid constraints, experienced and preferably co-located
teams, smaller risks, unclear requirements, and more flexible scheduling would be more
compatible with an agile approach. The same project is used in this section to highlight the
main differences between the processes and outputs of these two approaches.
When using agile techniques and its most popular method, Scrum, a team uses
specific roles, artifacts, and ceremonies.
3.5a Scrum Roles, Artifacts, and Ceremonies
Recall from Chapter 2 that Scrum includes three main roles for project participants:
Product owner: The person responsible for the business value of the project and
for deciding what work to do and in what order, as documented in the product
backlog. In this case, Joe Fleming is the product owner. He is the CEO of JWD
Consulting and the person who suggested the project.
ScrumMaster: The person who ensures that the team is productive, facilitates
the daily Scrum, enables close cooperation across all roles and functions, and
removes barriers that prevent the team from being effective. ScrumMasters
have authority over the process but not the people on the team. They must
be comfortable surrendering control to the product owner and team. Some
experts suggest that traditional project managers do not make great Scrum-
Masters. In this case, Erica Bell will take on the challenge and serve as the
ScrumMaster.
Scrum team or development team: A cross-functional team of five to nine
people who organize themselves and the work to produce the desired results
for each sprint. A sprint normally lasts two to four weeks, during which
specific work must be completed and made ready for review. Large projects
might require teams of teams. In this case, Michael Chen, Jessie Faue, Kevin
Dodge, Cindy Dawson, Kim Phuong, and Page Miller are development team
members. Their positions are listed in the project charter shown earlier in
Table 3-6. Kim and Page are client representatives who do not work for JWD
Consulting, but they are key team members, especially for developing the
parts of the intranet that external clients would use.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

119
In Scrum, an artifact is a useful object created by people. An artifact can be called
a deliverable in other project management approaches. The following three artifacts are
created with Scrum:
Product backlog: A list of features prioritized by business value. The highest-
priority items should be broken down in enough detail for the team to estimate
the effort involved in developing them. Some experts suggest scheduling about
10 workdays for each item. Size and complexity of the work dictates the estimate.
Sprint backlog: The highest-priority items from the product backlog to be
completed within a sprint. The Scrum team breaks down the highest-priority
items into smaller tasks that take about 12 to 16 hours to complete. Exam-
ples of a sprint backlog and product backlog are provided later in this section
under Planning.
Burndown chart: Shows the cumulative work remaining in a sprint on a
day-by-day basis. An example burndown chart is provided later in this sec-
tion under Monitoring and Controlling.
The ScrumMaster facilitates four ceremonies or meetings when using Scrum methods:
Sprint planning session: A meeting with the team to select a set of work from the
product backlog to deliver during a sprint. This meeting takes about four hours
to a full day.
Daily Scrum: A short meeting for the development team to share progress
and challenges and plan work for the day. Ideally the team members are in
the same place, the meeting usually lasts no more than 15 minutes, and it
is held at the same time and place each day. If that is not possible, teams
can use videoconferencing to have short virtual meetings. The ScrumMaster
asks what work has been done since yesterday, what work is planned for
today, and what impediments or stumbling blocks might hamper the team’s
efforts. The ScrumMaster documents these stumbling blocks and works with
key stakeholders to resolve them after the daily Scrum. Many teams use
the term issues for items that do not have to be solved in the next 24 hours
and blockers for items that need to be addressed immediately. This allows a
ScrumMaster to maintain focus on highest-priority items (blockers) first and
then manage the resolution of other issues over the next day or so.
Sprint reviews: A meeting in which the team demonstrates to the product
owner what it has completed during the sprint.
Sprint retrospectives: A meeting in which the team looks for ways to improve
the product and the process based on a review of the actual performance of
the development team.
Figure 3-5 displays how you can view the Scrum framework shown in Chapter 2 in
terms of the project management process groups. Creating the product backlog, develop-
ing the sprint backlog, and discussing plans during the daily Scrum would fall under plan-
ning. Performing the daily work and sprint, and creating the potentially shippable product
increment would fit under executing. Holding the sprint review and discussing challenges
as part of the daily Scrum can be viewed as monitoring and controlling. Reflecting during
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

120
(continued)
1. Product owner
creates
prioritized wish
list or backlog
Planning
Product
backlog
2. Project team
creates sprint
backlog
3. Teams have daily
Scrum meetings
during each 2–4
week sprint
4. Sprint results
in a useful
product
1.
2.
3.
4.
5.
6.
etc.
Sprint
review
and
Sprint
retro-
spective
Repeat steps 1–4 until complete
1.
2.
Sprint
backlog
Potentially
shippable
product
increment
24
hours
Daily Scrum
Sprint
2–4
weeks
Executing Closing
Monitoring and
controlling
FIGURE 3-5
TABLE 3-18
Initiating:
Determine roles
Decide how many sprints will compose each release and the scope of software to deliver
Planning:
Create product backlog
Create sprint backlog
Create release backlog
Plan work each day in the daily Scrum
Document stumbling blocks in a list
Executing:
Complete tasks each day during sprints
Produce a shippable product at the end of each sprint
the sprint retrospective would fit under closing. Initiating the entire project is a phase that
falls outside the Scrum framework in this example.
Table 3-18 summarizes some of the unique Scrum activities by each process group.
The following sections provide more detail on these activities.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

121
3.5b Project Pre-Initiation and Initiation
The main differences between pre-initiation in this case and the first case would be deter-
mining roles and deciding what functionality would be delivered as part of each release, how
many sprints will be required to complete a release, and how many releases of software to
deliver. This is similar to dividing the project into several smaller projects. A project charter,
stakeholder register, stakeholder management strategy, and kick-off meeting would still be
created as part of initiation, just as they were in the predictive version of this case. Using the
Scrum roles, however, Joe Fleming would be the product owner, Erica Bell the ScrumMaster,
and the other people listed in the project charter would be team members.
Joe met with Erica to discuss what functionality would be delivered in each release,
how many sprints would be needed for each release, how many software releases would
be required, and the approach required to complete the project. They realized that before
they could pin down functionality, releases, and sprints, they needed to survey potential
users to collect requirements for the new software and determine a way to measure the
value of the intranet site after it was implemented. They estimated that collecting and
analyzing information from potential users would take about two months.
Working together, Joe and Erica would create a survey that specifically asks potential
users which features would provide the most value. For example, instead of listing general
ideas, they would list specific features and have respondents rank them in order of im-
portance. They would also ask survey respondents to submit sample templates, tools, and
other useful information to Cindy Dawson, a project team member in the IT department.
Collecting this information up front would streamline the software development process.
Joe and Erica decided that three software releases would be realistic, given the time
and cost constraints. Each sprint would be targeted to last four weeks, and reviews and
creation of the product and sprint backlogs would be an ongoing activity within each sprint.
Joe and Erica met with Cindy and other team members several times. Cindy had the
most experience working on agile projects. She discussed the importance of submitting
several graphical user interface designs to prospective users to gain their feedback. This
approach was extremely useful in the past, based on Cindy’s experience, and it would save a
lot of rework during development. For example, a team member would create one to four de-
signs of a particular interface for prospective users to review in sessions hosted by a market-
ing team. Cindy explained that the feedback would help lead to a better, more intuitive user
interface. Also, asking prospective users to rate the “look and feel” would be very beneficial.
Users may be distracted by a selected color scheme, for example, so team members should
craft the same interface in various color schemes to gauge which one has the greatest appeal
TABLE 3-18 continued
Monitoring and Controlling:
Resolve issues and blockers
Create and update burndown chart
Demonstrate the completed product during the sprint review meeting
Closing:
Reflect on how to improve the product and process during the sprint retrospective meeting
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

122
and generates the most positive usability score. Cindy explained that user interface designers
are not normally development team members, but organizations might use them to provide
detailed design specifications that provide a consistent user interface. Erica and Joe learned a
lot from Cindy and would incorporate her recommendations into future plans.
3.5c Planning
Instead of creating a team contract, WBS, Gantt chart, and list of prioritized risks for the
whole project, the team follows the Scrum method. A preliminary scope statement for
the entire project can still be a useful tool for planning, even though the team knows that
more details will be added and changes will be made. Because Scrum implies that team
members work as a self-directed group, coached by the ScrumMaster, a team contract
should not be necessary.
In place of a WBS, high-level descriptions of the work to be completed would be iden-
tified in the product and sprint backlogs. The team would develop a more detailed list of
technical stories and associated tasks to complete during each sprint. The team must also
establish a velocity (or capacity) estimate for each sprint based on team member availability
each day of the sprint. Estimates can be provided as hours of work, assuming that all devel-
opers are contractors who can code eight hours per day. Estimates can also be provided as
points, assuming that developers are employees who code less than eight hours per day. For
example, six hours per day would equal a point, so 36 hours of effort would equal 6 points.
A Gantt chart for the entire project could still be created, as shown in Figure 3-6.
Notice that the process groups do not follow a simple linear pattern. Several process groups
are repeated for each sprint, resulting in several releases of a usable software product,
as shown by the milestones. Recall that in the predictive version of this case, there was
only one release or delivery of software near the end of the project, on October 17. In
this case, two additional deliveries of software are scheduled, one on August 3 and one on
September 11. Some teams create a release road map, as described later in this section, for
each software release. The entire project is still scheduled for completion on November 1.
FIGURE 3-6
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

In addition to listing all of the preliminary project requirements in a scope state-
ment, as shown in section 6.0 of the business case (see Table 3-2), Joe, the product
owner, created a product backlog to prioritize the most important functions of the new
intranet software in terms of adding value to the business. Joe created the product back-
log after analyzing the survey results and discussing options with several people. He
included separate items for the most important templates and tools, instead of grouping
them in one item, and requested a point person from their firm’s pool of consultants to
contact for questions about each template or tool as well. Notice that this approach com-
bined a few items in the scope statement shown in the first case to focus on what would
add the most value. Having a point person would be useful before the team developed the
more complex Ask the Expert feature. After reviewing the product backlog, the Scrum
team would do its planning and update the sprint backlog based on the items the team
could complete in the first sprint. Table 3-19 provides an example of the product backlog
and a sprint backlog for the first sprint. The team would then have its first daily Scrum
meeting to plan the day.
The Scrum team breaks down the items in the sprint backlog into more specific work
items, often in the form of user stories, technical stories, and related tasks. User stories
are short descriptions written by customers of what they need a system to do for them.
These descriptions should be about three sentences long. They provide the basis for
time estimates for the sprint planning meeting. User stories should be testable and small
enough that programmers can complete and unit test their code in a timely manner.
Developers break down user stories into technical stories. Then they use technical sto-
ries to translate user requirements into the technical specifications necessary to create the
defined user functionality. The technical stories can contain one or more technical tasks that
developers use to chart progress on a sprint board as work is conducted throughout a sprint.
A task should fit within a day. One item in the sprint backlog may or may not be documented
TABLE 3-19
Product Backlog
1. User story templates, samples, and point
person
2. WBS templates, samples, and point person
3. Project schedule templates, samples, and point
person
4. Ability to charge customers for some intranet
products and services
5. Ability to collect user suggestions
6. Business case templates, samples, and point
person
7. Ask the Expert feature
8. Stakeholder management strategy templates,
samples, and point person
9. Risk register templates, samples, and point
person
10. Etc.
Sprint Backlog
1. User story templates, samples, and point person
2. WBS templates, samples, and point person
3. Project schedule templates, samples, and point
person
4. Ability to charge customers for some intranet
products and services
5. Ability to collect user suggestions
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

124
in one user story, one technical story, and one task, based on its complexity. There could be a
one-to-one relationship or a many-to-one relationship if the item is highly complex.
For example, someone in the finance area of the company could write a user story
called “Ability to charge customers for some intranet products and services.” It might
read as follows: “As a financial manager, I want our site to use Company B to process pay-
ments so that we save money on transaction and customer service costs.” User stories are
broken down into a detailed technical story and then into tasks, similar to tasks in a work
breakdown structure.
Some organizations use a release road map to lay out all the work for an entire release,
which can include more than one sprint. This road map is usually represented as a chart
consisting of several columns. The release road map provides a clear picture of what stories
(scope) will be contained in each sprint. This tool enables the Scrum team to easily review
and update velocity estimates versus actuals. A release road map should be derived from
data in the Project Management Information System (PMIS) or a related agile management
system, such as Microsoft’s Team Foundation Server, Rally, VersionOne, or JIRA.
3.5d Executing
As discussed earlier in this chapter, the most time and money should be spent on execut-
ing, when plans are implemented to create the desired product. The team would complete
tasks each day, as it would in the predictive version of this case. But by using an agile
approach, the team would produce several iterations of a potentially shippable product.
For example, at the end of the first sprint, JWD Consulting would have some functionality
available on its new project management intranet site. Users would be able to access tem-
plates, samples, and a point person for user stories, WBSs, and project schedules, as listed
in the first sprint backlog. Users would also be able to make suggestions for functionality
they would like to see in the intranet site as it was being developed. The first iteration of
the software would also provide the ability to charge customers for some products and ser-
vices. By using Scrum methods, the business could benefit from these new features a few
months earlier than they could using the predictive approach described in the first case.
Because Erica and some of the project team would be inexperienced in using Scrum,
they would have to work out several challenges. For example, communications are very
different because the project team meets every morning, physically or virtually. There
would also be communications issues with users of the new intranet site, who might be
confused by getting three iterations of the product instead of just one. See Chapters 10
and 13, Project Communications Management and Project Stakeholder Management, for
additional information.
3.5e Monitoring and Controlling
The two main tools for monitoring and controlling in the Scrum framework are the daily
Scrum and the sprint review. Daily Scrums are held each morning to plan and communi-
cate work for the day and discuss any risks, issues, or blockers. The daily Scrum includes
a brief discussion of any issues and blockers the team is facing. The ScrumMaster would
work with the appropriate stakeholders to address these problems as part of monitoring
and controlling. Removing obstacles so the team can perform well is one of the main job
duties of the ScrumMaster. The ScrumMaster documents issues and blockers, similar to a
list of prioritized risks.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

125
The work progress within a sprint can be represented on a sprint board maintained by
the ScrumMaster. The sprint board contains a card to represent each task to be worked on
during the sprint. Each task card contains the control number, task name, estimated time to
complete, rank or priority number, and team member assigned. As tasks are opened, worked
on, and closed, their cards are moved physically to the appropriate section on the board.
These sections include Not Started, In Progress, Ready to Test, Tested, and Closed. Develop-
ers update the status of tasks in the Not Started, In Progress, and Ready to Test sections.
Testers update the status for tasks in the Tested section. The product owner is responsible
for reviewing functionality, confirming that it is working as expected, and changing a task’s
status to Closed.
A burndown chart is an important artifact used to graphically display progress on
each sprint. The burndown chart in Figure 3-7 shows progress during the first sprint for
the JWD Consulting intranet project, which was scheduled to last four weeks and produce
five items or user stories listed in the sprint backlog. Remember that during planning,
each user story was broken down into specific tasks, and the team estimated how long it
would take to complete each task for each user story. During the daily Scrum meeting, the
work a team member claims should fit within a day. Each day, the team should again esti-
mate the number of hours or points remaining for each task. Some tasks might be added
and some might be dropped as the scope becomes clearer. It does not matter how many
hours have been spent; what matters is how many hours of work remain to complete the
user stories for that sprint.
The burndown chart plots each day’s sum of estimated hours or points remaining. It
also shows an idealized burndown line, as if the team were completing an equal amount
of work each day, or 10 tasks each day in this example. The chart then clearly shows
0
50
100
150
200
Remaining Ideal Velocity
Sprint 1 Burndown Chart
Days
W
or
k
to
C
om
pl
et
e
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
FIGURE 3-7
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

126
whether the team is doing well in that sprint or if there is potential for trouble. Burndown
charts help the team understand whether user stories might not be completed within that
sprint. The chart provides an indicator that stories are at risk and should be removed. If
progress is better than anticipated, the burndown chart can indicate that stories should be
added to the sprint.
At the end of each sprint, the ScrumMaster—Erica in this example—leads the sprint
demonstration review meeting. The team demonstrates to the product owner what it has
completed during the sprint. In this case, Joe would review the five features created dur-
ing the first sprint. After the sprint demonstration review, he would update the product
backlog based on the latest information and business needs, and the next sprint cycle
would begin.
3.5f Closing
After the sprint review, the ScrumMaster leads a sprint retrospective. During this short
meeting (about half an hour), the team reflects on what happened during the sprint. The
ScrumMaster normally solicits team member feedback via e-mail first and collates these
results before the meeting. This saves time and focuses the discussion on items that are
most important. The retrospective is similar to a lessons-learned report, but it focuses on
a shorter period of time. The sprint retrospective is intended to answer two fundamental
questions:
What went well during the last sprint that we should continue doing?
What could we do differently to improve the product or process?
The sprint retrospective meeting is usually led by the ScrumMaster, who documents
a list of action items for implementation. Those items may be added to the product back-
log if the product owner agrees with them. For example, after the first sprint for the JWD
project management intranet site project, the team might suggest that the site be mobile
enabled. This new requirement could be added to the product backlog and selected as an
item for the next sprint. Recall that an agile approach welcomes new requirements as long
as they focus on business value.
As demonstrated in the two cases on the same project, the agile approach and predic-
tive approach have similarities and differences. If done well, an agile method can produce
several releases of useful software. This approach allows the organization to work together
quickly to address changing business needs.
3.6 TEMPLATES BY PROCESS GROUP
As you can see, project teams prepare many documents throughout the life of a
project. Many people use templates to apply a standard format for preparing those
documents. Table 3-20 lists templates used to prepare the documents shown in this
chapter and later chapters. The table lists the template name, chapter number, pro-
cess group(s) in which you normally use the template, the application software used
to create it, and the file name for the template. You can download all of these tem-
plates in one compressed file from the companion website for this text or from the
author’s website at www.kathyschwalbe.com. Feel free to modify the templates to
meet your needs.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

127
TABLE 3-20
Template Name Process Group
Chapter(s)
Where
Used
Application
Software File Name
Business Case Pre-initiating 3 Word business_case
Business Case
Financial Analysis
Pre-initiating 3, 4 Excel business_case_ financials.xls
Stakeholder Register Initiating 3, 13 Word stakeholder_register
Stakeholder
Management Strategy
Initiating 3, 13 Word stakeholder_strategy
Kick-off Meeting Initiating 3 Word kick-off_meeting
Payback Chart Initiating 4 Excel payback.xls
Weighted Decision
Matrix
Initiating 4, 12 Excel wtd_decision_matrix.xls
Project Charter Initiating 3, 4, 5 Word charter
Team Contract Planning 3 Word team_contract
Requirements
Traceability Matrix
Planning 5 Word reqs_matrix
Scope Statement Planning 3, 4, 5 Word scope_ statement
Statement of Work Planning 12 Word statement_of_work
Request for Proposal Planning 12 Word rfp_outline
Software Project
Management Plan
Planning 4 Word sw_project_mgt_plan
Work Breakdown
Structure
Planning 3, 5, 6 Word wbs
Gantt Chart Planning, Executing 3, 5, 6 Project Gantt_chart.mpp
Network Diagram Planning, Executing 3, 6 Project network_ diagram.mpp
Project Cost Estimate Planning 7 Excel cost_estimate.xls
Earned Value Data and
Chart
Monitoring and
Controlling
7 Excel earned_value.xls
Burndown Chart Monitoring and
Controlling
3, 7 Excel burndownchart.xls
Quality Assurance Plan Executing 8 Word quality_assurance_ plan
Pareto Chart Monitoring and
Controlling
8 Excel pareto_chart.xls
Project Organizational
Chart
Planning, Executing 9 Power-Point project_org_chart.ppt
Responsibility
Assignment Matrix
Planning, Executing 9 Excel ram.xls
Resource Histogram Planning, Executing 9 Excel resource_histogram.xls
Communications
Management Plan
Planning 10 Word comm_plan
Project Description
(text)
Planning 10 Word project_desc_text
(continued)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

128
TABLE 3-20 continued
Template Name Process Group
Chapter(s)
Where
Used
Application
Software File Name
Project Description
(Gantt chart)
Planning 10 Project project_desc_Gantt.mpp
Milestone Report Executing 3, 6 Word milestone_report
Change Request Form Planning,
Monitoring and
Controlling
4 Word change_request
Progress Report Monitoring and
Controlling
3, 10 Word progress_report
Probability/Impact
Matrix
Planning, Executing,
Monitoring and
Controlling
11 Power-Point prob_impact_matrix.ppt
List of Prioritized Risks Planning, Executing,
Monitoring and
Controlling
3, 11 Word list_of_risks
Risk Register Planning,
Monitoring and
Controlling
11 Excel risk_register.xls
Top 10 Risk Item
Tracking
Planning,
Monitoring and
Controlling
11 Excel top_10.xls
Breakeven/Sensitivity
Analysis
Planning 11 Excel breakeven.xls
Expectations
Management Matrix
Monitoring and
Controlling
13 Word expectations
Issue Log Monitoring and
Controlling
13 Word issue_log
Client Acceptance
Form
Closing 10 Word client_acceptance
Lessons-Learned
Report
Closing 3, 10 Word lessons_learned_ report
Final Project
Documentation
Closing 3, 10 Word final_documentation
© Cengage Learning 2016
The project management process groups—initiating, planning, executing, monitor-
ing and controlling, and closing—provide a useful framework for understanding project
management. They apply to most projects, both IT and non-IT, and along with the project
management knowledge areas, help project managers see the big picture of managing a
project in their organization.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

129
C A S E W R A P – U P
Erica Bell and her team finished the project management intranet site project on
November 4, as planned in their project charter. They went over budget, but Joe had
approved Erica’s request for additional funds, primarily for purchasing external soft-
ware and customization. Like any project, they had a few challenges, but they worked
together as a team and used good project management to meet their sponsor’s and users’
needs. They received positive initial feedback from internal consultants and some of
their clients on the new intranet site. People were asking for templates, examples, and
expert advice even before the system was ready. (If they had used an agile approach,
these features could have been delivered earlier.) About a year after the project was com-
pleted, Erica worked with a member of the Finance department to review the benefits of
the new system. Although the Project Management Office lost one of its staff members, it
did not request a replacement because the new system helped reduce its workload. This
saved the firm about $70,000 a year for the salary and benefits of that staff position. The
team also had data to show that the firm saved more than $180,000 on contracts with
clients because of the new system, compared with their projection of $160,000. The firm
was breaking even with the Ask the Expert feature during the first year, and Erica esti-
mated that the system provided $30,000 in additional profits the first year by generating
new business, instead of the $40,000 the team had projected. However, savings from the
PMO staff position salary and the extra savings on contracts more than made up for the
$10,000 difference. Joe was proud of the project team and the system they produced to
help make JWD Consulting a world-class organization.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter Summary
PMBOK® Guide
Quick Quiz
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

PMBOK® Guide
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Quick Quiz Answers
Discussion Questions
PMBOK® Guide
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Exercises
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

www
.kathyschwalbe.com
Key Terms
agile methods
artifact
burndown chart
closing processes
daily Scrum
executing processes
initiating processes
kick-off meeting
methodology
monitoring and controlling
processes
planning processes
process
product backlog
product owner
project management process groups
PRojects IN Controlled Environments
(PRINCE2)
Rational Unified Process (RUP)
framework
ScrumMaster
Scrum team or development team
Six Sigma methodologies
sprint
sprint backlog
stakeholder register
standard
user stories
End Notes
Alpha Project Managers: What the Top 2% Know That Everyone Else Does
Not
CIO.com
FCW: The
Business of Federal Technology
Underground Online UGO.com
6
VersionOne.com
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

IBM Developer works
®
FWC:
The Business of Federal Technology
PM Network
www.youtube.com/watch?v=SIPleb0y0jg
www.youtube.com/watch?v=d0hSS_e7ABo&feature=share&list
=UUMA-ZzWeWAipboxxBRjzedg
The Life of Reason: Reason in Common Sense
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R 4
PROJECT INTEGRATION
MANAGEMENT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:



Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

138
O P E N I N G C A S E
Nick Carson recently became project manager of a critical biotech enterprise at his
Silicon Valley company. This project involved creating the hardware and software for
a next generation (next-gen) DNA-sequencing instrument used in assembling and ana-
lyzing the human genome. Several companies were competing to build smaller, faster
sequencing instruments that would reduce the costs and improve the quality of data
analysis in this rapidly changing field. The biotech project was the company’s largest
endeavor, and it had tremendous potential for future growth and revenue.
Unfortunately, there were problems managing this large project. It had been under
way for three years and had already gone through three different project managers. Nick
had been the lead software developer on the project before top management made him
the project manager. The CEO told him to do whatever it took to deliver the first version
of the product in four months and a production version in nine months. Negotiations for
a potential corporate buyout with a larger company influenced top management’s sense
of urgency to complete the project.
Highly energetic and intelligent, Nick had the technical background to make the
project a success. He delved into the technical problems and found some critical flaws
that kept the next-gen DNA-sequencing instrument from working. Nevertheless, he was
having difficulty in his new role as project manager. Although Nick and his team got the
product out on time, top management was upset because Nick did not focus on managing
all aspects of the project. He never provided them with accurate schedules or detailed
plans of what was happening on the project. Instead of performing the work of project
manager, Nick had taken on the role of software integrator and troubleshooter. Nick,
however, did not understand top management’s complaints—he delivered the product,
didn’t he? Didn’t they realize how valuable he was?
4.1 WHAT IS PROJECT INTEGRATION MANAGEMENT?
Project integration management involves coordinating all of the other project manage-
ment knowledge areas throughout a project’s life cycle. This integration ensures that all
the elements of a project come together at the right times to complete a project success-
fully. According to the PMBOK® Guide, Fifth Edition, six main processes are involved in
project integration management:
1. Developing the project charter involves working with stakeholders to create
the document that formally authorizes a project—the charter.
2. Developing the project management plan involves coordinating all planning ef-
forts to create a consistent, coherent document—the project management plan.
3. Directing and managing project work involves carrying out the project man-
agement plan by performing the activities included in it. The outputs of this
process are deliverables, work performance information, change requests,
project management plan updates, and project documents updates.
4. Monitoring and controlling project work involves overseeing activities to
meet the performance objectives of the project. The outputs of this process
are change requests, project management plan updates, and project docu-
ments updates.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

139
5. Performing integrated change control involves identifying, evaluating, and
managing changes throughout the project life cycle. The outputs of this pro-
cess include change request status updates, project management plan up-
dates, and project documents updates.
6. Closing the project or phase involves finalizing all activities to formally close the
project or phase. Outputs of this process include final product, service, or result
transition and organizational process assets updates. Figure 4-1 summarizes
these processes and outputs, and shows when they occur in a typical project.
Many people consider project integration management the key to overall project suc-
cess. Someone must take responsibility for coordinating all of the people, plans, and work
required to complete a project. Someone must focus on the big picture of the project and
steer the project team toward successful completion. Someone must make the final deci-
sions when conflicts occur among project goals or people. Someone must communicate key
project information to top management. These responsibilities belong to the project man-
ager, whose chief means for accomplishing all these tasks is project integration management.
FIGURE 4-1
Initiating
Process: Develop project charter
Output: Project charter
Planning
Process: Develop project management plan
Output: Project management plan
Executing
Process: Direct and manage project work
Outputs: Deliverables, work performance data, change requests,
project management plan updates, project documents
updates
Monitoring and Controlling
Process: Monitor and control project work
Outputs: Change requests, project management plan updates,
project documents updates
Process: Perform integrated change control
Outputs: Approved change requests, change log, project management
plan updates, project documents updates
Closing
Process: Close project or phase
Outputs: Final product, service, or result transition;
organizational process assets updates
Project Start Project Finish
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

Particularly on large projects, the project manager’s main job is project integration
management. To perform well in that role, it is important to understand the organiza-
tion’s needs and staff your project with skilled workers capable of making the project
a success.
Good project integration management is critical to providing stakeholder satisfaction.
Project integration management includes interface management, which involves identify-
ing and managing the points of interaction between various elements of a project. The
primary tools for interface management are communication and relationships. The num-
ber of interfaces can increase exponentially as the number of people involved in a project
increases. Thus, one of the most important jobs of a project manager is to establish and
maintain good communication and relationships across organizational interfaces. The
project manager must communicate well with all project stakeholders, including custom-
ers, the project team, top management, other project managers, and opponents of
the project.
What happens when a project manager does not communicate well with all stake-
holders? In the chapter’s opening case, Nick Carson seemed to ignore a key stakeholder
for the next-gen DNA-sequencing instrument project—his top management. Nick was
comfortable working with other members of the project team, but he was not familiar
with his new job as project manager or the needs of the company’s top management. Nick
continued to do his old job of software developer and took on the added role of software
integrator. He mistakenly thought project integration management meant software inte-
gration management and focused on the project’s technical problems. He totally ignored
what project integration management is really about—integrating the work of all of the
people involved in the project by focusing on good communication and relationship man-
agement. Recall that project management is applying knowledge, skills, tools, and tech-
niques to meet project requirements, while also meeting or exceeding stakeholder needs
and expectations. Nick did not take the time to find out what top management expected
W H A T W E N T W R O N G ?
Understanding an organization’s needs and making the right staffing decisions for a proj-
ect is much easier said than done, as senior British police officer Mark Rowley discovered
after failure of the Surrey Integrated Reporting Enterprise Network (Siren) project.
The Surrey police force began looking into replacing its criminal intelligence system
in 2005, and they awarded a contract to develop a new one in 2009. The police force
spent £14.8 million (over $22 million) on the project until it was canceled in 2013. It was
finally replaced with a much less expensive system used by thirteen other forces.
Surrey Police and Crime Commissioner Kevin Hurley said that Mark Rowley, chief
constable at the time and the person in charge of Siren, should take responsibility for the
project failure. Rowley was reassigned to the Metropolitan Police Service, and he insisted
that no misconduct occurred. An audit report by Grant Thornton said Siren was an
“ambitious project that was beyond the in-house capabilities and experience of the police
force and police authority.”1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

from him as the project manager; he assumed that completing the project on time and
within budget was sufficient to make them happy. Yes, top management should have
made its expectations more clear, but Nick should have taken the initiative to get the
guidance he needed.
In addition to not understanding project integration management, Nick did not use
holistic or systems thinking (see Chapter 2). He burrowed into the technical details of his
particular project. He did not stop to think about what it meant to be the project manager,
how this project related to other projects in the organization, or top management’s expec-
tations of him and his team.
Project integration management must occur within the context of the entire organiza-
tion, not just within a particular project. The project manager must integrate the work of
the project with the ongoing operations of the organization. In the opening case, Nick’s
company was negotiating a potential buyout with a larger company. Consequently, top
management needed to know when the next-gen DNA-sequencing instrument would be
ready, how big the market was for the product, and if the company had enough in-house
staff to continue to manage projects like this one in the future. Top management wanted
to see a project management plan and a schedule to help monitor the project’s progress
and show the potential buyer what was happening. When top managers tried to talk to
Nick about these issues, he soon returned to discussing the technical details of the proj-
ect. Even though Nick was very bright, he had no experience or real interest in many of
the company’s business aspects. Project managers must always view their projects in the
context of the changing needs of their organizations and respond to requests from top
management. Likewise, top management must keep project managers informed of major
issues that could affect their projects and strive to make processes consistent throughout
their organization.
Following a standard process for managing projects can help prevent some of the typi-
cal problems new and experienced project managers face, including communicating with
and managing stakeholders. Before organizations begin projects, however, they should go
through a formal process to decide what projects to pursue.
4.2 STRATEGIC PLANNING AND PROJECT SELECTION
Successful leaders look at the big picture or strategic plan of the organization to determine
what types of projects will provide the most value. Some may argue that project managers
should not be involved in strategic planning and project selection because top manage-
ment is usually responsible for these types of business decisions. But successful organiza-
tions know that project managers can provide valuable insight into the project selection
process.
4.2a Strategic Planning
Strategic planning involves determining long-term objectives by analyzing the strengths
and weaknesses of an organization, studying opportunities and threats in the business
environment, predicting future trends, and projecting the need for new products and ser-
vices. Strategic planning provides important information to help organizations identify
and then select potential projects.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Many people are familiar with SWOT analysis—analyzing Strengths, Weaknesses,
Opportunities, and Threats—which is one tool used in strategic planning. For example, a
group of four people who want to start a new business in the film industry could perform
a SWOT analysis to help identify potential projects. They might determine the following
based on a SWOT analysis:
Strengths:
As experienced professionals, we have numerous contacts in the film industry.
Two of us have strong sales and interpersonal skills.
Two of us have strong technical skills and are familiar with several filmmak-
ing software tools.
We all have impressive samples of completed projects.
Weaknesses:
None of us have accounting or financial experience.
We have no clear marketing strategy for products and services.
We have little money to invest in new projects.
We have no company Web site and limited use of technology to run the business.
Opportunities:
A potential client has mentioned a large project she would like us to bid on.
The film industry continues to grow.
There are two major conferences this year where we could promote our
company.
Threats:
Other individuals or companies can provide the services we can.
Customers might prefer working with more established individuals and
organizations.
There is high risk in the film business.
Based on their SWOT analysis, the four entrepreneurs outline potential projects as
follows:
Find an external accountant or firm to help run the business.
Hire someone to develop a company website, focusing on our experience and
past projects.
Develop a marketing plan.
Develop a strong proposal to get the large project the potential client
mentioned.
Plan to promote the company at two major conferences this year.
Some people like to perform a SWOT analysis by using mind mapping, a technique
that uses branches radiating from a core idea to structure thoughts and ideas. The
human brain does not work in a linear fashion. People come up with many unrelated
ideas. By capturing those ideas in a visual mind map format, you can often generate
more ideas than by creating lists. You can create mind maps by hand, using sticky
notes, using presentation software such as Microsoft PowerPoint, or by using mind
mapping software.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Figure 4-2 shows a sample mind map for the new film industry business SWOT analysis.
This diagram was created using MindView Business Edition software by MatchWare. Notice
that this map has four main branches representing strengths, weaknesses, opportunities,
and threats. Ideas in each category are added to the appropriate branch, and sub-branches
are shown for some ideas under those categories. Notice that several branches end with
a project idea, such as Project proposal, Conference promotions, Accountant, Marketing
plan, and Website. You can easily format the project ideas to make them stand out, as
shown in Figure 4-2. From this example, you can see that no project ideas are identified to
address strengths or threats, so these areas should be discussed further.
4.2b Identifying Potential Projects
The first step in project management is deciding what projects to do in the first place.
Therefore, project initiation starts with identifying potential projects, using realistic meth-
ods to select which projects to work on, and then formalizing their initiation by issuing
some sort of project charter.
In addition to using a SWOT analysis, organizations often follow a detailed process for
project selection. Figure 4-3 shows a four-stage process for selecting IT projects. Note the
hierarchical structure of this model and the results produced from each stage.
In the first stage of the selection process, starting at the top of the hierarchy, a steer-
ing committee develops an IT strategic plan that is tied to the organization’s overall
strategic plan. In many organizations, this steering committee consists of managers from
departments throughout the company to ensure that all projects are selected in the best
interests of the entire organization. The head of the Project Management Office (PMO)
would be part of this committee because the PMO acts as the central location for keeping
track of all project activities. It is very important to have managers from outside the IT
department assist in developing the IT strategic plan, as they can help IT personnel under-
stand organizational strategies and identify the business areas that support them. At the
end of this stage, the organization should have a well-defined list of IT strategic goals.
After identifying strategic goals, the next stage in the process for selecting IT proj-
ects is to perform a business area analysis. This analysis outlines business processes that
are central to achieving strategic goals and helps determine which processes could most
benefit from IT. In the next stage, the organization starts defining the scope, benefits, and
constraints of potential IT projects. The last stage in the process for selecting IT projects
is choosing which projects to do and assigning resources for working on them.
FIGURE 4-2
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Tie information technology strategy
to mission and vision of organization.
Identify key business areas.
Information
Technology
Strategy Planning
Business Area Analysis
Project Planning
Resource Allocation
Information Technology
Planning Stages
Select information
technology projects.
Assign resources.
Results Produced
Document key business
processes that could benefit
from information technology.
Define potential projects.
Define project scope,
benefits, and constraints.
FIGURE 4-3
4.2c Aligning IT with Business Strategy
Notice that aligning IT projects with business strategy is at the heart of selecting IT proj-
ects. This is consistently a top concern for CIOs. It is often difficult to educate line man-
agers on technology’s possibilities and limitations and keep IT professionals in tune with
changing business needs. Most organizations face thousands of problems and opportuni-
ties for improvement. To get the most value from technology, an organization’s strategic
plan should guide the IT project selection process. Recall from Chapter 2’s Best Practice
feature that IT governance is an important part of ensuring that IT supports business
goals. IT governance helps organizations maximize their investments in IT and address
IT-related risks and opportunities.
An organization must develop a strategy for using IT to define how it will support
the organization’s objectives. This IT strategy must align with the organization’s strategic
plans. In fact, research shows that supporting explicit business objectives is the top rea-
son cited for why organizations invest in IT projects. Other top criteria for investing in IT
projects include supporting implicit business objectives and providing financial incentives,
such as a good internal rate of return (IRR) or net present value (NPV).2 In a 2014 survey,
responses from 178 CIOs suggested that the majority of organizations (87 percent) are
planning to maintain or increase IT budgets with an average budget increase of 4.9 per-
cent. Investments in core technologies, such as infrastructure, networks, and storage, re-
ceived the largest budget allocation. Annual spending increased by 5 percent to 32 percent
on edge technologies, such as mobile, social, customer relationship management (CRM),
and marketing automation. The focus of new IT projects continues to be revenue growth,
a strategic objective of many organizations.3
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Information systems often are central to business strategy. Author Michael Porter,
who developed the concept of the strategic value of competitive advantage, and many
other experts have emphasized the importance of using IT to support strategic plans and
provide a competitive advantage. Many information systems are classified as strategic
because they directly support key business strategies. For example, information systems
can support an organizational strategy of being a low-cost producer. As one of the largest
retailers in the United States, Walmart’s inventory control system is a classic example of
such a strategic system. Information systems can support a strategy of providing special-
ized products or services that set a company apart from others in the industry. Consider
the classic example of Federal Express’s introduction of online package tracking systems.
FedEx was the first company to provide this type of service, which gave it a competitive
advantage until others developed similar systems. Information systems can also support
a strategy of selling to a particular market or occupying a specific product niche. Owens
Corning developed a strategic information system that boosted the sales of its home-
insulation products by providing its customers with a system for evaluating the energy
efficiency of building designs. In 2012, the editor in chief of CIO magazine stated, “The
smart use of technology is always a key component in driving innovation and creating a
competitive edge. We see IT value proving itself across the board in many organizations.”4
B E S T P R A C T I C E
In a 2013 survey, CEOs and senior executives identified the companies they most ad-
mired for their ability to apply IT-related business capabilities for competitive advan-
tage. The executives identified the best practices of 21 companies, as follows:
Customer-driven IT is essential. The best organizations excel at managing
complex e-commerce systems and platforms, supporting multichannel man-
agement, and innovating quickly to meet customer needs.
IT can enable branding and customer recruitment. Many of the top companies
use customer success stories to show how IT helped them create new markets
and solve customer problems. These testimonials drive recruitment efforts for
analytics, cloud computing, and systems integration work.
Keep improving. Successful organizations did not get complacent with their
use of IT. For example, many leveraged the disruptive power of cloud comput-
ing and mobility to improve their enterprise systems.5
The top companies admired for using IT as a competitive advantage, in alphabeti-
cal order, include:
Accenture Hospital Corporation of America Nestle
Amazon IBM Procter & Gamble
Apple Intermountain Healthcare Progressive Insurance
Cleveland Clinic JP Morgan Chase Schlumberger
General Electric Kaiser Permanente Target
Goldman Sachs Mayo Clinic Toyota
Google Microsoft Wells Fargo
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

4.3 METHODS FOR SELECTING PROJECTS
Organizations identify many potential projects as part of their strategic planning pro-
cesses, and they need to narrow down the list of potential projects to the ones that will be
of most benefit. They often rely on experienced project managers to help them make
project selection decisions. Selecting projects is not an exact science, and many methods
exist for selecting projects. Five common techniques are:
Focusing on broad organizational needs
Categorizing IT projects
Performing net present value or other financial analyses
Using a weighted scoring model
Implementing a balanced scorecard
In practice, many organizations use a combination of these approaches to select proj-
ects. Each approach has advantages and disadvantages, and it is up to management to de-
termine the best approach for selecting projects based on their particular organization.
4.3a Focusing on Broad Organizational Needs
Top managers must focus on meeting their organizations’ many needs when deciding what
projects to undertake, when to undertake them, and to what level. Projects that address
broad organizational needs are much more likely to be successful because they will be im-
portant to the organization. For example, a broad organizational need might be to improve
safety, increase morale, provide better communications, or improve customer service.
However, it is often difficult to provide a strong justification for many IT projects related to
these broad organizational needs. For example, estimating the financial value of such proj-
ects is often impossible, even though everyone agrees that they have a high value. As the
old proverb says, “It is better to measure gold roughly than to count pennies precisely.”
One method for selecting projects based on broad organizational needs is to deter-
mine whether they first meet three important criteria: need, funding, and will. Do people
in the organization agree that the project needs to be done? Does the organization have
the desire and capacity to provide adequate funds to perform the project? Is there a
strong will to make the project succeed? For example, many visionary CEOs can describe
a broad need to improve certain aspects of their organizations, such as communications.
Although they cannot specifically describe how to improve communications, they might
allocate funds to projects that address this need. As projects progress, the organization
must reevaluate the need, funding, and will for each project to determine if it should be
continued, redefined, or terminated.
4.3b Categorizing IT Projects
Another method for selecting projects is based on various categorizations, such as the
project’s impetus, time window, and general priority. The impetus for a project is often to
respond to a problem, an opportunity, or a directive.
Problems are undesirable situations that prevent an organization from achieving
its goals. These problems can be current or anticipated. For example, users of
an information system may be having trouble logging on to the system or getting
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

information in a timely manner because the system has reached its capacity. In
response, the company could initiate a project to enhance the current system
by adding more access lines or upgrading the hardware with a faster processor,
more memory, or more storage space.
Opportunities are chances to improve the organization. For example, the
project described in the chapter’s opening case involves creating a new prod-
uct that can make or break the entire company.
Directives are new requirements imposed by management, government, or
some external influence. For example, many projects that involve medical
technologies must meet rigorous government requirements.
Organizations select projects for any of these reasons. It is often easier to get ap-
proval and funding for projects that address problems or directives because the organiza-
tion must respond to these categories to avoid hurting their business. Many problems and
directives must be resolved quickly, but managers must also apply systems thinking and
seek opportunities for improving the organization through IT projects.
Another categorization for IT projects is based on timing: How long will it take to
complete a project and what is the deadline for completing it? For example, some poten-
tial projects must be finished within a specific time window; otherwise, they are no longer
valid projects. Some projects can be completed very quickly—within a few weeks, days, or
even minutes. Many organizations have an end-user support function to handle very small
projects that can be completed quickly. However, even though many IT projects can be
completed quickly, it is still important to prioritize them.
Organizations can also categorize IT projects as having high, medium, or low priority
based on the current business environment. For example, if it is crucial to cut operating
costs quickly, projects that have the most potential to do so would be given a high prior-
ity. An organization should always complete high-priority projects first, even if a low- or
medium-priority project could be finished in less time. Usually an organization has many
more potential IT projects than it can undertake at one time, so it is crucial to work on
the most important projects first.
4.3c Performing Financial Analyses
Financial considerations are an important aspect of the project selection process, whether
economic times are tough or the economy is growing. As authors Dennis Cohen and
Robert Graham put it, “Projects are never ends in themselves. Financially they are always
a means to an end, cash.”6 Many organizations require an approved business case before
pursuing projects, and financial projections are a critical component of the business case.
(See Chapter 3 for a sample business case.) Three primary methods for projecting the
financial value of projects include net present value analysis, return on investment, and
payback analysis. Because project managers often deal with business executives, they
must understand how to speak business language, which often boils down to the following
important financial concepts.
Net Present Value Analysis
Most people know that a dollar earned today is worth more than a dollar earned five
years from now—a principle called the time value of money. Many projects have financial
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

implications that extend into the future. In order to evaluate potential projects equally,
you need to consider their net present value.
Net present value (NPV) analysis is a method of calculating the expected net mon-
etary gain or loss from a project by calculating the value of all expected future cash in-
flows and outflows at the present time. An organization should consider only projects
with a positive NPV if financial value is a key criterion for project selection. A positive
NPV means that the return from a project exceeds the cost of capital—the return avail-
able from investing the capital elsewhere. In other words, the cost of capital is the rate of
return that could have been earned by putting the same money into a different investment
with equal risk. Projects with higher NPVs are preferred to projects with lower NPVs, if all
other factors are equal.
To calculate NPV, you must assume a certain discount rate. The discount rate is the
interest rate used to discount cash flows. It takes into account not just the time value of
money but also the risk or uncertainty of future cash flows. The greater the uncertainty of
future cash flows, the higher the discount rate. It is also called the capitalization rate or
the opportunity cost of capital.
Figure 4-4 illustrates this concept in Microsoft Excel for two different projects. Note
that this example starts discounting immediately in Year 1 and uses a 10 percent discount
rate. You can use the NPV function in Excel to calculate the NPV quickly. Detailed steps
for performing this calculation manually are presented later.
Figure 4-4 lists the projected benefits first, followed by the costs, and then the cal-
culated cash flow amount. Note that the sum of the cash flow—benefits minus costs or
income minus expenses—is the same for both projects at $5,000. The net present values
are different, however, because they account for the time value of money. Project 1 has
A
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
B C D E F
17
G
Discount rate 10%
PROJECT 1
PROJECT 2
YEAR 1
YEAR 1
YEAR 2 YEAR 3 YEAR 4 YEAR 5
YEAR 2 YEAR 3 YEAR 4 YEAR 5
TOTAL
TOTAL
Benefits
Costs
Cash flow
NPV
$0 $2,000 $3,000 $4,000 $5,000
$5,000 $1,000 $1,000 $1,000 $1,000
$1,000 $2,000 $3,000 $4,000($5,000)
$14,000
$9,000
$5,000
$2,316
Formula =npv(b1,b6:f6)
Formula =npv(b1,b13:f13)
Benefits
Costs
Cash flow
NPV
$1,000
$2,000
($1,000)
$2,000
$2,000
$0
$4,000
$2,000
$2,000
$4,000
$2,000
$2,000
$4,000
$2,000
$2,000
$15,000
$10,000
$5,000
$3,201
Note that totals are
equal, but NPVs are
not because of the
time value of money
FIGURE 4-4
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Project Integration Management
149
a negative cash flow of $5,000 in the first year, while Project 2 has a negative cash flow
of only $1,000 in the first year. Although both projects have the same total cash flows
without discounting, they are not of comparable financial value. Project 2’s NPV of $3,201
is better than Project 1’s NPV of $2,316. NPV analysis, therefore, is a method for making
equal comparisons between cash flows for multiyear projects.
To determine NPV, follow these steps:
1. Determine the estimated costs and benefits for the life of the project and the
products it creates. For example, JWD Consulting assumed its project would
produce a system in about six months that would be used for three years, so
costs are included in Year 0, when the system is developed. Ongoing system
costs and projected benefits are included for Years 1, 2, and 3.
2. Determine the discount rate. In Figure 4-4, the discount rate is 10 percent
per year.
3. Calculate the net present value. Most spreadsheet software has a built-in
function to calculate NPV. For example, Figure 4-4 shows the formula that
Microsoft Excel uses: 5npv(discount rate, range of cash flows), where the
discount rate is in cell B1 and the range of cash flows for Project 1 are in cells
B6 through F6. (See Chapter 7, Project Cost Management, for more informa-
tion on cash flow and other cost-related terms.) To use the NPV function, you
must have a row or column in the spreadsheet for the cash flow each year,
which is the benefit amount for that year minus the cost amount.
The result of the formula yields an NPV of $2,316 for Project 1 and $3,201 for Project 2.
Because both projects have positive NPVs, they are good candidates for selection. How-
ever, because Project 2 has an NPV that is 38 percent higher than Project 1, it would be
the better choice. If the two numbers are close, then other methods should be used to
help decide which project to select.
The mathematical formula for calculating NPV is:
NPV 5 a
t50 . . . n
At/(1 1 r)
t
where t equals the year of the cash flow, n is the last year of the cash flow, A is the amount
of cash flow each year, and r is the discount rate.
If you cannot enter the data into spreadsheet software, you can perform the calcula-
tions by hand or with a calculator. First, determine the annual discount factor—a mul-
tiplier for each year based on the discount rate and year—and then apply it to the costs
and benefits for each year. The formula for the discount factor is 1/(1 1 r)t, where r is the
discount rate, such as 8 percent, and t is the year. For example, the discount factors used
in Figure 4-5 are calculated as follows:
Year 0 :  discount factor  5 1/(1 1 0.08)0 5 1
Year 1 :  discount factor  5 1/(1 1 0.08)1 5 0.93
Year 2 :  discount factor  5 1/(1 1 0.08)2 5 0.86
Year 3 :  discount factor  5 1/(1 1 0.08)3 5 0.79
After determining the discount factor for each year, multiply the costs and benefits
each year by the appropriate discount factor. (Note discount factor in this case is rounded
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

to two decimal places). For example, in Figure 4-5, the discounted cost for Year 1 is
$40,000 3 0.93 5 $37,200. Next, sum all of the discounted costs and benefits each year
to get a total. The total discounted costs in Figure 4-5 are $243,200. To calculate the NPV,
subtract the total discounted costs from the total discounted benefits. In this example, the
NPV is $516,000 2 $243,200 5 $272,800.
When calculating NPV, some organizations refer to the investment year or years for
project costs as Year 0 and do not discount costs in Year 0. Other organizations start dis-
counting immediately based on their financial procedures; it’s simply a matter of prefer-
ence for the organization.
The discount rate can also vary, often based on the prime rate and other economic consid-
erations. Some people consider it to be the rate at which the organization could borrow money
for the project. Financial experts in your organization can tell you what discount rate to use.
When calculating NPV, you can enter costs as negative numbers instead of positive num-
bers, and you can list costs first and then benefits. For example, Figure 4-5 shows the financial
calculations used in the JWD Consulting business case for the project management intranet
site project described in Chapter 3. Note that the discount rate is 8 percent, costs are not dis-
counted in Year 0, the discount factors are rounded to two decimal places, costs are listed first,
and costs are entered as positive numbers. Also note that costs and benefits are discounted
before they are summed. The NPV and other calculations are the same; only the format is dif-
ferent. A project manager needs to check with the organization to learn its guidelines for when
discounting starts, what discount rate to use, and what format the organization prefers.
Return on Investment
Another important financial consideration is return on investment. Return on investment
(ROI) is the result of subtracting the project costs from the benefits and then dividing by
FIGURE 4-5
Discount rate 8%
Assume the project is completed in Year 0 Year
Costs
Discount factor
Discounted costs
Benefits
Discount factor
Discounted benefits
Discounted benefits – costs
Cumulative benefits – costs
ROI
0 1 2 3 Total
140,000
1 0.93 0.86 0.79
140,000 37,200
40,000 40,000 40,000
243,20034,400 31,600
0 200,000 200,000 200,000
1 0.93 0.86 0.79
0 186,000 516,000172,000 158,000
(140,000) 148,800 137,600 126,400
8,800 146,400 272,800
112%
Payback In Year 1
(140,000)
272,800 NPV
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

the costs. For example, if you invest $100 today and next year it is worth $110, your ROI
is ($110 – 100)/100 or 0.10 (10 percent). Note that the ROI is always a percentage. It can
be positive or negative. For multiyear projects, it is best to use discounted costs and ben-
efits when calculating ROI. Figure 4-5 shows an ROI of 112 percent, which you calculate
as follows:
ROI 5 (total discounted benefits – total discounted costs)/discounted costs
ROI 5 (516,000 – 243,200)/243,200 5 112%
The higher the ROI is, the better. An ROI of 112 percent is outstanding.
Many organizations have a required rate of return for projects. The required rate of
return is the minimum acceptable rate of return on an investment. For example, an organi-
zation might have a required rate of return of at least 10 percent for projects. The organiza-
tion bases the required rate of return on what it could expect to receive elsewhere for an
investment of comparable risk. You can also determine a project’s internal rate of return
(IRR) by finding what discount rate results in an NPV of zero for the project. You can use
the Goal Seek function in Excel to set the cell that contains the formula for NPV to the
value 0 by changing the cell that contains the discount rate. The resulting discount rate is
the IRR. For example, in Figure 4-4, you could set cell b7 to zero while changing cell b1 to
find that the IRR for Project 1 is 27 percent.
Payback Analysis
Payback analysis is another important financial tool when selecting projects. Payback
period is the amount of time it will take to recoup the total dollars invested in a project,
in terms of net cash inflows. In other words, payback analysis determines how much time
will elapse before accrued benefits overtake accrued and continuing costs. Payback occurs
when the net cumulative benefits equal the net cumulative costs or when the net cumula-
tive benefits minus costs equal zero. Figure 4-5 shows how to find the payback period. The
cumulative benefits minus costs for Year 0 are ($140,000). Adding that number to the dis-
counted benefits minus costs for Year 1 results in $8,800. Because that number is positive,
the payback occurs in Year 1.
Creating a chart helps illustrate more precisely when the payback period occurs.
Figure 4-6 charts the cumulative discounted costs and cumulative discounted benefits
each year using the numbers from Figure 4-5. Note that the lines cross around Year 1. This
is the point where the cumulative discounted benefits equal the cumulative discounted
costs, so that the cumulative discounted benefits minus costs are zero. Beyond this point,
discounted benefits exceed discounted costs and the project shows a profit. Because this
project started in Year 0, a payback in Year 1 actually means the project reached payback
in its second year. An early payback period, such as in the first or second year, is consid-
ered very good.
Many organizations have requirements for the length of the payback period of an
investment. They might require all IT projects to have a payback period of less than two
years or even one year, regardless of the estimated NPV or ROI. Dan Hoover, vice president
and area director of Ciber Inc., an international systems integration consultancy, suggests
that organizations, especially small firms, should focus on payback period when making IT
investment decisions. “If your costs are recovered in the first year,” Hoover said, “the proj-
ect is worthy of serious consideration, especially if the benefits are high. If the payback
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

period is more than a year, it may be best to look elsewhere.”7 However, organizations
must also consider long-range goals when making technology investments. Many crucial
projects cannot achieve a payback so quickly or be completed in such a short time period.
To aid in project selection, project managers must understand the organization’s
financial expectations for projects. Top management must also understand the limita-
tions of financial estimates, particularly for IT projects. For example, it is very difficult
to develop good estimates of projected costs and benefits for IT projects. You will learn
more about estimating costs and benefits in Chapter 7, Project Cost Management.
4.3d Using a Weighted Scoring Model
A weighted scoring model is a tool that provides a systematic process for selecting proj-
ects based on many criteria. These criteria can include factors such as meeting broad or-
ganizational needs; addressing problems, opportunities, or directives; the amount of time
needed to complete the project; the overall priority of the project; and projected financial
performance of the project.
The first step in creating a weighted scoring model is to identify criteria that are im-
portant to the project selection process. It often takes time to develop and reach agreement
on these criteria. Holding facilitated brainstorming sessions or using groupware to ex-
change ideas can aid in developing these criteria. Possible criteria for IT projects include:
Supports key business objectives or strategies
Has strong internal sponsor
600,000
Year
400,000
300,000
200,000
100,000
0
0 1 2 3
500,000
Payback
$
Cumulative costs Cumulative benefits
Payback
FIGURE 4-6
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Has strong customer support
Uses realistic level of technology
Can be implemented in one year or less
Provides positive NPV
Has low risk in meeting scope, time, and cost goals
Next, you assign a weight to each criterion based on its importance. Once again, deter-
mining weights requires consultation and final agreement. You can assign weights based on
percentages; the weights of the criteria must total 100 percent. You then assign numerical
scores to each criterion (for example, 0 to 100) for each project. The scores indicate how
much each project meets each criterion. At this point, you can use a spreadsheet applica-
tion to create a matrix of projects, criteria, weights, and scores. Figure 4-7 provides an ex-
ample of a weighted scoring model to evaluate four different projects. After assigning weights
for the criteria and scores for each project, you calculate a weighted score for each project
by multiplying the weight for each criterion by its score and adding the resulting values.
A
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
B C D E F
Weighted Project Scores
Weight
17
18
19
20
21
22
23
24
25
26
Criteria Project 1 Project 2 Project 3 Project 4
Supports key business objectives
Has strong internal sponsor
Has strong customer support
Uses realistic level of technology
Can be implemented in one year or less
Provides positive NPV
Has low risk in meeting scope, time, and cost goals
25% 90 90 50 20
15% 70 90 50 20
15% 50 90 50 20
10% 25 90 50 70
5% 20 20 50 90
20% 50 70 50 50
10% 20 50 50 90
100% 56 78.5 50 41.5
Weighted Score by Project
0
Project 4
Project 3
Project 2
Project 1
20 40 60 10080
FIGURE 4-7
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

For example, you calculate the weighted score for Project 1 in Figure 4-7 as:
25% * 90 1 15% * 70 1 15% * 50 1 10% * 25 1 5% * 20 1 20% * 50 1 10% * 20 5 56
Note that in this example, Project 2 would be the obvious choice for selection because
it has the highest weighted score. Creating a bar chart to graph the weighted scores for
each project allows you to see the results at a glance.
If you create the weighted scoring model in a spreadsheet, you can enter the data,
create and copy formulas, and perform a “what-if” analysis. For example, suppose that
you want to change the weights for the criteria. By having the weighted scoring model in a
spreadsheet, you can easily change the weights and update the weighted scores and charts
automatically. This capability allows you to investigate various options for different stake-
holders quickly. Ideally, the result should reflect the group’s consensus, and any major
disagreements should be documented.
You can also establish how well projects meet criteria by assigning points. For ex-
ample, a project might receive 10 points if it definitely supports key business objectives,
5 points if it somewhat supports them, and 0 points if it is totally unrelated to key busi-
ness objectives. With a point model, you can simply add all the points to determine the
best projects for selection, without having to multiply weights and scores and sum the
results.
You can also determine minimum scores or thresholds for specific criteria in a
weighted scoring model. For example, suppose that an organization should not consider
a project if it does not score at least 50 out of 100 on every criterion. You can build this
type of threshold into the weighted scoring model to reject projects that do not meet these
minimum standards. As you can see, weighted scoring models can aid in project selection
decisions.
4.3e Implementing a Balanced Scorecard
Drs. Robert Kaplan and David Norton developed another approach to help select and
manage projects that align with business strategy. A balanced scorecard is a strategic
planning and management system that helps organizations align business activities to
strategy, improve communications, and monitor performance against strategic goals.
The Gartner Group estimates that over half of large U.S. organizations use this approach.
The balanced scorecard has evolved over time. “The ‘new’ balanced scorecard trans-
forms an organization’s strategic plan from an attractive but passive document into the
‘marching orders’ for the organization on a daily basis. It provides a framework that not
only provides performance measurements but helps planners identify what should be
done and measured.”8 You can find several examples of balanced scorecards from manu-
facturing companies like Shat-R-Shield to non-profits like the Kenya Red Cross at
www.balancedscorecard.org.
As you can see, organizations can use many approaches to select projects. Many
project managers have some say in which projects their organizations select for imple-
mentation. Even if they do not, they need to understand the motives and overall business
strategies for the projects they are managing. Project managers and team members are
often called upon to explain the importance of their projects, and understanding project
selection methods can help them represent the project effectively.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

4.4 DEVELOPING A PROJECT CHARTER
After top management decides which projects to pursue, it is important to let the rest of the
organization know about these projects. Management needs to create and distribute docu-
mentation to authorize project initiation. This documentation can take many different forms,
but one common form is a project charter. A project charter is a document that formally
recognizes the existence of a project and provides direction on the project’s objectives and
management. It authorizes the project manager to use organizational resources to complete
the project. Ideally, the project manager plays a major role in developing the project charter.
Instead of project charters, some organizations initiate projects using a simple letter
of agreement, while others use much longer documents or formal contracts. Key project
stakeholders should sign a project charter to acknowledge agreement on the need for and
intent of the project. A project charter is a key output of the initiation process, as de-
scribed in Chapter 3.
The PMBOK® Guide, Fifth Edition lists inputs, tools, techniques, and outputs of the
six project integration management processes. The following inputs are helpful in develop-
ing a project charter:
A project statement of work: A statement of work is a document that describes
the products or services to be created by the project team. It usually includes a
description of the business need for the project, a summary of the requirements
and characteristics of the products or services, and organizational information,
such as appropriate parts of the strategic plan, showing the alignment of the proj-
ect with strategic goals.
A business case: As explained in Chapter 3, many projects require a busi-
ness case to justify their investment. Information in the business case, such
as the project objective, high-level requirements, and time and cost goals, is
included in the project charter.
Agreements: If you are working on a project under contract for an external
customer, the contract or agreement should include much of the information
needed for creating a good project charter. Some people might use a contract
or agreement in place of a charter. However, many contracts are difficult to
read and can often change, so it is still a good idea to create a project charter.
Enterprise environmental factors: These factors include relevant govern-
ment or industry standards, the organization’s infrastructure, and market-
place conditions. Managers should review these factors when developing
a project charter.
Organizational process assets: Organizational process assets include formal
and informal plans, policies, procedures, guidelines, information systems,
financial systems, management systems, lessons learned, and historical infor-
mation that can influence a project’s success.
The main tools and techniques for developing a project charter are expert judgment
and facilitation techniques, such as brainstorming and meeting management. Experts
from inside and outside the organization should be consulted when creating a project
charter to make sure it is useful and realistic. Facilitators often make it easier for experts
to collaborate and provide useful information.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

The only output of the process to develop a project charter is the charter itself.
Although the format of project charters can vary tremendously, they should include at
least the following basic information:
The project’s title and date of authorization
The project manager’s name and contact information
A summary schedule, including the planned start and finish dates; if a
summary milestone schedule is available, it should also be included or
referenced
A summary of the project’s budget or reference to budgetary documents
A brief description of the project objectives, including the business need or
other justification for authorizing the project
Project success criteria, including project approval requirements and who
signs off on the project
A summary of the planned approach for managing the project, which should
describe stakeholder needs and expectations, important assumptions, and
constraints, and should refer to related documents, such as a communica-
tions management plan, as available
A roles and responsibilities matrix
A sign-off section for signatures of key project stakeholders
A comments section in which stakeholders can provide important comments
related to the project
Unfortunately, many internal projects, like the one described in the opening case of
this chapter, do not have project charters. They often have a budget and general guide-
lines, but no formal, signed documentation. If Nick had a project charter to refer to—
especially if it included information for managing the project—top management would
have received the business information it needed, and managing the project might have
been easier. Project charters are usually not difficult to write. The difficult part is getting
people with the proper knowledge and authority to write and sign the project charter. Top
management should have reviewed the charter with Nick because he was the project man-
ager. In their initial meeting, they should have discussed roles and responsibilities, as well
as their expectations of how Nick should work with them. If there is no project charter,
the project manager should work with key stakeholders, including top management, to
create one. Table 4-1 shows a possible charter that Nick could have created for completing
the next-gen DNA-sequencing instrument project.
Many projects fail because of unclear requirements and expectations, so starting
with a project charter makes a lot of sense. If project managers are having difficulty ob-
taining support from project stakeholders, for example, they can refer to the agreements
listed in the project charter. Note that the sample project charter in Table 4-1 includes
several items under the Approach section to help Nick in managing the project and the
sponsor in overseeing it. To help Nick make the transition to project manager, the char-
ter said that the company would hire a technical replacement and part-time assistant for
Nick as soon as possible. To help Ahmed, the project sponsor, feel more comfortable with
how the project was being managed, items were included to ensure proper planning and
communications. Recall from Chapter 2 that executive support contributes the most to
successful IT projects. Because Nick was the fourth project manager on this project,
top management at his company obviously had problems choosing and working with
project managers.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

TABLE 4-1
Project Title: Next-gen DNA-Sequencing Instrument Completion Project
Date of Authorization: February 1
Project Start Date: February 1 Projected Finish Date: November 1
Key Schedule Milestones:
Complete first version of the software by June 1
Complete production version of the software by November 1
Budget Information: The firm has allocated $1.5 million for this project, and more funds are available if
needed. The majority of costs for this project will be internal labor. All hardware will be outsourced.
Project Manager: Nick Carson, (650) 949-0707, ncarson@dnaconsulting.com
Project Objectives: The Next-gen DNA-sequencing instrument project has been under way for three years.
It is a crucial project for our company. This is the first charter for the project; the objective is to complete
the first version of the instrument software in four months and a production version in nine months.
Main Project Success Criteria: The software must meet all written specifications, be thoroughly tested,
and be completed on time. The CEO will formally approve the project with advice from other key
stakeholders.
Approach:
Hire a technical replacement for Nick Carson and a part-time assistant as soon as possible.
Within one month, develop a clear work breakdown structure, scope statement, and Gantt chart
detailing the work required to complete the Next-gen DNA-sequencing instrument.
Purchase all required hardware upgrades within two months.
Hold weekly progress review meetings with the core project team and the sponsor.
Conduct thorough software testing per the approved test plans.
ROLES AND RESPONSIBILITIES
Name Role Position Contact Information
Ahmed Abrams Sponsor CEO aabrams@dnaconsulting.com
Nick Carson Project Manager Manager ncarson@dnaconsulting.com
Susan Johnson Team Member DNA expert sjohnson@dnaconsulting.com
Renyong Chi Team Member Testing expert rchi@dnaconsulting.com
Erik Haus Team Member Programmer ehaus@dnaconsulting.com
Bill Strom Team Member Programmer bstrom@dnaconsulting.com
Maggie Elliot Team Member Programmer melliot@dnaconsulting.com
Sign-off: (Signatures of all the above stakeholders)
Ahmed Abrams Nick Carson
Susan Johnson Renyong Chi
Erik Haus Bill Strom
Maggie Elliot
Comments: (Handwritten or typed comments from above stakeholders, if applicable)
“I want to be heavily involved in this project. It is crucial to our company’s success, and I expect
everyone to help make it succeed.”—ahmed abrams
“The software test plans are complete and well documented. If anyone has
questions, do not hesitate to contact me.”—Renyong Chi
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Taking the time to discuss, develop, and sign off on a simple project charter could
have prevented several problems in this case.
After creating a project charter, the next step in project integration management is
preparing a project management plan.
4.5 DEVELOPING A PROJECT MANAGEMENT PLAN
To coordinate and integrate information across project management knowledge areas and
across the organization, there must be a good project management plan. A project manage-
ment plan is a document used to coordinate all project planning documents and help guide
a project’s execution and control. Plans created in the other knowledge areas are consid-
ered subsidiary parts of the overall project management plan. Project management plans
also document project planning assumptions and decisions regarding choices, facilitate
communication among stakeholders, define the content, extent, and timing of key man-
agement reviews, and provide a baseline for progress measurement and project control.
Project management plans should be dynamic, flexible, and subject to change when the
environment or project changes. These plans should greatly assist the project manager in
leading the project team and assessing project status.
To create and assemble a good project management plan, the project manager must
practice the art of project integration management, because information is required from
all of the project management knowledge areas. Working with the project team and other
stakeholders to create a project management plan will help the project manager guide the
project’s execution and understand the overall project.
The main inputs for developing a project management plan include the project char-
ter, outputs from planning processes, enterprise environment factors, and organizational
process assets. The main tool and technique is expert judgment, and the output is a proj-
ect management plan.
4.5a Project Management Plan Contents
Just as projects are unique, so are project management plans. A small project that in-
volves a few people working over a couple of months might have a project management
plan consisting of only a project charter, scope statement, and Gantt chart. A large project
that involves 100 people working over three years would have a much more detailed proj-
ect management plan. It is important to tailor project management plans to fit the needs
of specific projects. The project management plans should guide the work, so they should
be only as detailed as needed for each project.
Most project management plans have common elements. A project management plan
includes an introduction or overview of the project, a description of how the project is
organized, the management and technical processes used on the project, and sections de-
scribing the work to be performed, the schedule, and the budget.
The introduction or overview of the project should include the following information
at a minimum:
The project name: Every project should have a unique name, which helps distin-
guish each project and avoids confusion among related projects.
A brief description of the project and the need it addresses: This description
should clearly outline the goals of the project and strategic reason for it. The
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

description should be written in layperson’s terms, avoid technical jargon,
and include a rough time and cost estimate.
The sponsor’s name: Every project needs a sponsor. Include the name, title,
and contact information of the sponsor in the introduction.
The names of the project manager and key team members: The project man-
ager should always be the contact for project information. Depending on the
size and nature of the project, names of key team members may also
be included.
Deliverables of the project: This section should briefly list and describe
the products that will be created as part of the project. Software packages,
pieces of hardware, technical reports, and training materials are examples
of deliverables.
A list of important reference materials: Many projects have a history that
precedes them. Listing important documents or meetings related to a
project helps project stakeholders understand that history. This section
should reference the plans produced for other knowledge areas. Recall from
Chapter 3 that every knowledge area includes some planning processes.
Therefore, the project management plan should reference and summarize
important parts of the scope management, schedule management, cost
management, quality management, human resource management, commu-
nications management, risk management, procurement management, and
stakeholder management plans.
A list of definitions and acronyms, if appropriate: Many projects, especially
IT projects, involve terminology that is unique to a particular industry or
technology. Providing a list of definitions and acronyms will help avoid
confusion.
The description of how the project is organized should include the following
information:
Organizational charts: The description should include an organizational
chart for the company sponsoring the project and for the customer’s com-
pany, if the project is for an external customer. The description should also
include a project organizational chart to show the lines of authority, respon-
sibilities, and communication for the project. For example, the Manhattan
Project introduced in Chapter 1 had a very detailed organizational chart of all
participants.
Project responsibilities: This section of the project plan should describe the
major project functions and activities and identify the people responsible for
them. A responsibility assignment matrix (described in Chapter 9) is often
used to display this information.
Other organizational or process-related information: Depending on the
nature of the project, the team might need to document major
processes they follow on the project. For example, if the project  
involves releasing a major software upgrade, team members might
benefit from having a diagram or timeline of the major steps involved
in the process.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

The section of the project management plan that describes management and techni-
cal approaches should include the following information:
Management objectives: It is important to understand top management’s view
of the project, the priorities for the project, and any major assumptions or
constraints.
Project controls: This section describes how to monitor project progress and
handle changes. Will there be monthly status reviews and quarterly progress
reviews? Will there be specific forms or charts to monitor progress? Will the
project use earned value management (described in Chapter 7) to assess
and track performance? What is the process for change control? What level
of management is required to approve different types of changes? (You will
learn more about change control later in this chapter.)
Risk management: This section briefly addresses how the project team will
identify, manage, and control risks. This section should refer to the risk man-
agement plan, if one is required for the project.
Project staffing: This section describes the number and types of people re-
quired for the project. It should refer to the human resource plan, if one is
required for the project.
Technical processes: This section describes specific methodologies a project
might use and explains how to document information. For example, many IT
projects follow specific software development methodologies or use particular
Computer Aided Software Engineering (CASE) tools. Many companies or cus-
tomers also have specific formats for technical documentation. It is impor-
tant to clarify these technical processes in the project management plan.
The next section of the project management plan should describe the work that needs
to be performed and reference the scope management plan. It should summarize the
following:
Major work packages: A project manager usually organizes the project work
into several work packages using a work breakdown structure (WBS) and
produces a scope statement to describe the work in more detail. This section
should briefly summarize the main work packages for the project and refer to
appropriate sections of the scope management plan.
Key deliverables: This section lists and describes the key products created
as part of the project. It should also describe the quality expectations for the
product deliverables.
Other work-related information: This section highlights key information re-
lated to the work performed on the project. For example, it might list specific
hardware or software to use on the project or certain specifications to follow.
It should document major assumptions made in defining the project work.
The project schedule information section should include the following:
Summary schedule: It is helpful to have a one-page summary of the overall
project schedule. Depending on the project’s size and complexity, the sum-
mary schedule might list only key deliverables and their planned completion
dates. For smaller projects, it might include all of the work and associated
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

dates for the entire project in a Gantt chart. For example, the Gantt chart
and milestone schedule provided in Chapter 3 for JWD Consulting were fairly
short and simple.
Detailed schedule: This section provides more detailed information about
the project schedule. It should reference the schedule management plan
and discuss dependencies among project activities that could affect the
project schedule. For example, this section might explain that a major part
of the work cannot start until an external agency provides funding. A net-
work diagram can show these dependencies (see Chapter 6, Project Time
Management).
Other schedule-related information: Many assumptions are often made
when preparing project schedules. This section should document major as-
sumptions and highlight other important information related to the project
schedule.
The budget section of the project management plan should include the following:
Summary budget: The summary budget includes the total estimate of the
overall project’s budget. It could also include the budget estimate for each
month or year by certain budget categories. It is important to provide some
explanation of what these numbers mean. For example, is the total budget es-
timate a firm number that cannot change, or is it a rough estimate based on
projected costs over the next three years?
Detailed budget: This section summarizes the contents of the cost manage-
ment plan and includes more detailed budget information. For example, what
are the fixed and recurring cost estimates for the project each year? What are
the projected financial benefits of the project? What types of people are needed
to do the work, and how are the labor costs calculated? (See Chapter 7, Proj-
ect Cost Management, for more information on creating cost estimates and
budgets.)
Other budget-related information: This section documents major assump-
tions and highlights other important information related to financial aspects
of the project.
4.5b Using Guidelines to Create Project Management Plans
Many organizations use guidelines to create project management plans. Microsoft Project
2013 and other project management software packages come with several template files to
use as guidelines. However, do not confuse a project management plan with a Gantt chart.
The project management plan is much more than a Gantt chart, as described earlier.
Many government agencies also provide guidelines for creating project management
plans. For example, the U.S. Department of Defense (DOD) Standard 2167, Software
Development Plan, describes the format for contractors to use when creating a software
development plan for DOD projects. The Institute of Electrical and Electronics Engineers
(IEEE) Standard 1058–1998 describes the contents of its Software Project Management
Plan (SPMP). Table 4-2 provides some of the categories for the IEEE SPMP. Companies
that work on software development projects for the Department of Defense must follow
this standard or a similar standard.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

TABLE 4-2
Major Section Headings Section Topics
Overview Purpose, scope, and objectives; assumptions and constraints; project
deliverables; schedule and budget summary; evolution of the plan
Project Organization External interfaces; internal structure; roles and responsibilities
Managerial Process Plan Start-up plans (estimation, staffing, resource acquisition, and project
staff training plans); work plan (work activities, schedule, resource, and
budget allocation); control plan; risk management plan; closeout plan
Technical Process Plans Process model; methods, tools, and techniques; infrastructure plan;
product acceptance plan
Supporting Process Plans Configuration management plan; verification and validation plan;
documentation plan; quality assurance plan; reviews and audits;
problem resolution plan; subcontractor management plan; process
improvement plan
Source: IEEE Standard 1058–1998
In many private organizations, specific documentation standards are not as rigorous;
however, there are usually guidelines for developing project management plans. It is good
practice to follow the organization’s standards or guidelines for developing project man-
agement plans to facilitate their execution. The organization can work more efficiently if
all project management plans follow a similar format. Recall from Chapter 1 that compa-
nies that excel in project management develop and deploy standardized project delivery
systems.
The winners clearly spell out what needs to be done in a project, by whom, when, and
how. For this they use an integrated toolbox, including PM tools, methods, and tech-
niques. … If a scheduling template is developed and used over and over, it becomes a
repeatable action that leads to higher productivity and lower uncertainty. Sure, using
scheduling templates is neither a breakthrough nor a feat. But laggards exhibited al-
most no use of the templates. Rather, in constructing schedules their project manag-
ers started with a clean sheet, a clear waste of time.9
In the chapter’s opening case, Nick Carson’s top managers were disappointed because
he did not provide the project planning information they needed to make important busi-
ness decisions. They wanted to see detailed project management plans, including sched-
ules and a means for tracking progress. Nick had never created a project management plan
or even a simple progress report before, and the organization did not provide templates
or examples to follow. If it had, Nick might have been able to deliver the information top
management was expecting.
4.6 DIRECTING AND MANAGING PROJECT WORK
Directing and managing project work involves managing and performing the work de-
scribed in the project management plan, one of the main inputs for this process. Other
inputs include approved change requests, enterprise environmental factors, and organiza-
tional process assets. The majority of time on a project is usually spent on execution, as is
most of the project’s budget.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

The application area of the project directly affects project execution because products
are created during the execution phase. For example, the next-gen DNA-sequencing instru-
ment from the opening case and all associated software and documentation would be pro-
duced during project execution. The project team would need to use its expertise in biology,
hardware and software development, and testing to create the product successfully.
The project manager needs to focus on leading the project team and managing stake-
holder relationships to execute the project management plan successfully. Project human
resource management, communications management, and stakeholder management are
crucial to a project’s success. See Chapters 9, 10, and 13, respectively, for more infor-
mation on these knowledge areas. If the project involves a significant amount of risk or
outside resources, the project manager also needs to be well versed in project risk man-
agement and project procurement management. See Chapters 11 and 12 for details on
those knowledge areas. Many unique situations occur during project execution, so project
managers must be flexible and creative in dealing with them. Review the situation that
Erica Bell faced during project execution in Chapter 3. Also review the ResNet case study
(available on the companion website for this text) to understand the execution challenges
that project manager Peeter Kivestu and his project team faced.
4.6a Coordinating Planning and Execution
In project integration management, project planning and execution are intertwined and
inseparable activities. The main function of creating a project management plan is to
guide project execution. A good plan should help produce good products or work results
and should document what constitutes good work results. Updates to plans should reflect
knowledge gained from completing work earlier in the project. Anyone who has tried to
write a computer program from poor specifications appreciates the importance of a good
plan. Anyone who has had to document a poorly programmed system appreciates the im-
portance of good execution.
A common-sense approach to improving the coordination between project plan devel-
opment and execution is to follow this simple rule: Those who will do the work should plan
the work. All project personnel need to develop both planning and executing skills, and they
need experience in these areas. In IT projects, programmers who have to write detailed
specifications and then create the code from them become better at writing specifications.
Likewise, most systems analysts begin their careers as programmers, so they understand
what type of analysis and documentation they need to write good code. Although project
managers are responsible for developing the overall project management plan, they must so-
licit input from project team members who are developing plans in each knowledge area.
4.6b Providing Strong Leadership and a Supportive Culture
Strong leadership and a supportive organizational culture are crucial during project execu-
tion. Project managers must lead by example to demonstrate the importance of creating
good project plans and then following them in project execution. Project managers often
create plans for things they need to do themselves. If project managers follow through on
their own plans, their team members are more likely to do the same.
Good project execution also requires a supportive organizational culture. For exam-
ple, organizational procedures can help or hinder project execution. If an organization has
useful guidelines and templates for project management that everyone in the organization
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

follows, it will be easier for project managers and their teams to plan and do their work. If
the organization uses the project plans as the basis for performing work and monitoring
progress during execution, the culture will promote the relationship between good plan-
ning and execution. On the other hand, if organizations have confusing or bureaucratic
project management guidelines that hinder getting work done or measuring progress
against plans, project managers and their teams will be frustrated.
Even with a supportive organizational culture, project managers may sometimes
find it necessary to break the rules to produce project results in a timely manner. When
project managers break the rules, politics will play a role in the results. For example, if
a particular project requires use of nonstandard software, the project manager must use
political skills to convince concerned stakeholders that using standard software would be
inadequate. Breaking organizational rules—and getting away with it—requires excellent
leadership, communication, and political skills.
4.6c Capitalizing on Product, Business, and Application Area Knowledge
In addition to strong leadership, communication, and political skills, project managers
need to possess product, business, and application area knowledge to execute projects
successfully. It is often helpful for IT project managers to have prior technical experience
or at least a working knowledge of IT products. For example, if the project manager were
leading a team to help define user requirements, it would be helpful to understand the
language of the business and technical experts on the team. See Chapter 5, Project Scope
Management, for more information on collecting requirements.
Many IT projects are small, so project managers may be required to perform some
technical work or mentor team members to complete the project. For example, a three-
month project to develop a web-based application with only three team members would
benefit most from a project manager who can complete some of the technical work. On
larger projects, however, the project manager’s primary responsibility is to lead the team
W H A T W E N T R I G H T ?
Pulse of the Profession® Capturing the Value of Project Management 2015 –

improves their ability to execute strategy –
cultural changes
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

and communicate with key project stakeholders. The project manager does not have time
to do the technical work. In this case, it is usually best that the project manager under-
stand the business and application area of the project more than the technology involved.
On very large projects the project manager must understand the business and appli-
cation area of the project. For example, Northwest Airlines completed a series of projects
in recent years to develop and upgrade its reservation systems. The company spent mil-
lions of dollars and had more than 70 full-time people working on the projects at peak pe-
riods. The project manager, Peeter Kivestu, had never worked in an IT department, but he
had extensive knowledge of the airline industry and the reservations process. He carefully
picked his team leaders, making sure they had the required technical and product knowl-
edge. ResNet was the first large IT project at Northwest Airlines led by a business manager
instead of a technical expert, and it was a roaring success. Many organizations have found
that large IT projects require experienced general managers who understand the business
and application area of the technology, not the technology itself.
4.6d Project Execution Tools and Techniques
Directing and managing project work requires specialized tools and techniques, some of
which are unique to project management. Project managers can use specific tools and
techniques to perform activities that are part of execution processes. These include:
Expert judgment: Anyone who has worked on a large, complex project ap-
preciates the importance of expert judgment in making good decisions. Project
managers should not hesitate to consult experts on different topics, such as what
methodology to follow, what programming language to use, and what training
approach to follow.
Meetings: Meetings are crucial during project execution. Face-to-face meet-
ings with individuals or groups of people are important, as are phone and
virtual meetings. Meetings allow people to develop relationships, pick up on
important body language or tone of voice, and have a dialogue to help re-
solve problems. It is often helpful to establish set meeting times for various
stakeholders. For example, Nick could have scheduled a short meeting once
a week with senior managers. He could have also scheduled 10-minute stand-
up meetings every morning for the project team.
Project management information systems: As described in Chapter 1, hun-
dreds of project management software products are on the market today.
Many large organizations use powerful enterprise project management sys-
tems that are accessible via the Internet and tie into other systems, such as
financial systems. Even in smaller organizations, project managers or other
team members can create Gantt charts that include links to other planning
documents on an internal network. For example, Nick or his assistant could
have created a detailed Gantt chart for their project in Project 2013 and
created links to other key planning documents created in Word, Excel, or
PowerPoint. Nick could have shown the summary tasks during the progress
review meetings, and if top management had questions, Nick could have
shown them supporting details. Nick’s team could also have set baselines for
completing the project and tracked their progress toward achieving those
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

goals. See Appendix A for details on using Project 2013 to perform these
functions, and for samples of Gantt charts and other useful outputs from
project management software.
Although project management information systems can aid in project execution, proj-
ect managers must remember that positive leadership and strong teamwork are critical
to successful project management. Project managers should delegate the detailed work
involved in using these tools to other team members and focus on providing leadership
for the whole project to ensure project success. Stakeholders often focus on the most
important output of execution from their perspective: the deliverables. For example, a
production version of the next-gen DNA-sequencing instrument was the main deliverable
for the project in the opening case. Of course, many other deliverables were created along
the way, such as software modules, tests, and reports. Other outputs of project execution
include work performance information, change requests, and updates to the project man-
agement plan and project documents.
Project managers and their teams are most often remembered for how well they
executed a project and handled difficult situations. Likewise, sports teams around the
world know that the key to winning is good execution. Team coaches can be viewed as
project managers, with each game a separate project. Coaches are often judged on their
win-loss record, not on how well they planned for each game. On a humorous note,
when one losing coach was asked what he thought about his team’s execution, he
responded, “I’m all for it!”
4.7 MONITORING AND CONTROLLING PROJECT WORK
On large projects, many project managers say that 90 percent of the job is communicating
and managing changes. Changes are inevitable on most projects, so it’s important to de-
velop and follow a process to monitor and control changes.
Monitoring project work includes collecting, measuring, and disseminating perfor-
mance information. It also involves assessing measurements and analyzing trends to de-
termine what process improvements can be made. The project team should continuously
monitor project performance to assess the overall health of the project and identify areas
that require special attention.
The project management plan, schedule and cost forecasts, validated changes, work
performance information, enterprise environmental factors, and organizational process
assets are all important inputs for monitoring and controlling project work.
The project management plan provides the baseline for identifying and controlling
project changes. A baseline is the approved project management plan plus approved
changes. For example, the project management plan includes a section that describes the
work to perform on a project. This section of the plan describes the key deliverables for
the project, the products of the project, and quality requirements. The schedule section
of the project management plan lists the planned dates for completing key deliverables,
and the budget section of the plan provides the planned cost of these deliverables. The
project team must focus on delivering the work as planned. If the project team or someone
else causes changes during project execution, the team must revise the project manage-
ment plan and have it approved by the project sponsor. Many people refer to different
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

types of baselines, such as a cost baseline or schedule baseline, to describe different proj-
ect goals more clearly and performance toward meeting them.
Schedule and cost forecasts, validated changes, and work performance information
provide details on how project execution is going. The main purpose of this information
is to alert the project manager and project team about issues that are causing problems or
might cause problems in the future. The project manager and project team must continu-
ously monitor and control project work to decide if corrective or preventive actions are
needed, what the best course of action is, and when to act.
M E D I A S N A P S H O T
Few events get more media attention than the Olympic Games. Imagine all the work
involved in planning and executing an event that involves thousands of athletes from
around the world with millions of spectators. The 2002 Olympic Winter Games and
Paralympics took five years to plan and cost more than $1.9 billion. PMI presented the
Salt Lake Organizing Committee (SLOC) with the Project of the Year award for delivering
world-class games that, according to the International Olympic Committee, “made a pro-
found impact upon the people of the world.”11
Four years before the Games began, the SLOC used a Primavera software-based sys-
tem with a cascading color-coded WBS to integrate planning. A year before the Games,
the team added a Venue Integrated Planning Schedule to help integrate resource needs,
budgets, and plans. For example, this software helped the team coordinate different areas
involved in controlling access into and around a venue, such as roads, pedestrian path-
ways, seating and safety provisions, and hospitality areas, saving nearly $10 million.
When the team experienced a budget deficit three years before the Games, it sepa-
rated “must-have” items from “nice-to-have” items and implemented a rigorous expense
approval process. According to Matthew Lehman, SLOC managing director, using classic
project management tools turned a $400 million deficit into a $100 million surplus.
The SLOC also used an Executive Roadmap, a one-page list of the top 100 activi-
ties during the Games, to keep executives apprised of progress. Activities were tied to
detailed project information within each department’s schedule. A 90-day highlighter
showed which managers were accountable for each integrated activity. Fraser Bullock,
SLOC Chief Operating Officer and Chief, said, “We knew when we were on and off sched-
ule and where we had to apply additional resources. The interrelation of the functions
meant they could not run in isolation—it was a smoothly running machine.”12
Important outputs of monitoring and controlling project work include change requests
and work performance reports. Change requests include recommended corrective and
preventive actions and defect repairs. Corrective actions should result in improvements in
project performance. Preventive actions reduce the probability of negative consequences
associated with project risks. Defect repairs involve bringing defective deliverables into
conformance with requirements. For example, if project team members have not been
reporting hours that they worked, a corrective action would show them how to enter the
information and let them know that they need to do it. An example of a preventive action
might be modifying a time-tracking system screen to avoid common errors people have
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

矫正的调节的

一致性

made in the past. A defect repair might be having someone redo an incorrect entry. Many
organizations use a formal change request process and forms to keep track of project
changes, as described in the next section. Work performance reports include status re-
ports, progress reports, memos, and other documents used to communicate performance.
4.8 PERFORMING INTEGRATED CHANGE CONTROL
Integrated change control involves identifying, evaluating, and managing changes through-
out the project life cycle. The three main objectives of integrated change control are:
Influencing the factors that create changes to ensure that changes are benefi-
cial: To ensure that changes are beneficial and that a project is successful, proj-
ect managers and their teams must make trade-offs among key project
dimensions, such as scope, time, cost, and quality.
Determining that a change has occurred: To determine that a change has
occurred, the project manager must know the status of key project areas at
all times. In addition, the project manager must communicate significant
changes to top management and key stakeholders. Top management and
other key stakeholders do not like surprises, especially ones that mean the
project might produce less, take longer to complete, cost more than planned,
or create products of lower quality.
Managing actual changes as they occur: Managing change is a key role of
project managers and their teams. It is important that project managers
exercise discipline in managing the project to help minimize the number of
changes that occur.
Important inputs to the integrated change control process include the project man-
agement plan, work performance information, change requests, enterprise environmental
factors, and organizational process assets. Important outputs include approved change re-
quests, a change log, and updates to the project management plan and project documents.
Change requests are common on projects and occur in many different forms. They
can be oral or written, formal or informal. For example, a project team member responsi-
ble for installing a server might ask the project manager if it is acceptable to order a server
with a faster processor than planned. The server is from the same manufacturer and has
the same approximate cost. Because this change is positive and should have no negative
effects on the project, the project manager might give a verbal approval at the progress
review meeting. Nevertheless, it is still important that the project manager document this
change to avoid any potential problems. The appropriate team member should update the
scope statement to include the new server specifications.
Still, keep in mind that many change requests can have a major impact on a project.
For example, customers who change their minds about the number of hardware compo-
nents they want as part of a project will have a definite impact on its scope and cost. Such
a change might also affect the project’s schedule. The project team must present such
significant changes in written form to the project sponsor, and there should be a formal
review process for analyzing and deciding whether to approve these changes.
Change is unavoidable and often expected on most IT projects. Technologies change,
personnel change, organizational priorities change, and so on. A good change control sys-
tem is also important for project success.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

纪律

口头的 非书面的

4.8a Change Control on IT Projects
From the 1950s to the 1980s, IT was often referred to as data automation or data process-
ing. At that time, a widely held view of project management was that the project team
should strive to do exactly what it planned, on time and within budget. The problem with
this view was that project teams could rarely meet original project goals, especially for
projects that used new technologies. Stakeholders rarely agreed up front on the scope of
the project or what the finished product should look like. Time and cost estimates created
early in a project were rarely accurate.
Beginning in the 1990s, most project managers and top management realized that
project management is a process of constant communication and negotiation about
project objectives and stakeholder expectations. This view assumes that changes hap-
pen throughout the project life cycle and recognizes that changes are often beneficial
to some projects. For example, if a project team member discovers a new hardware
or software technology that could satisfy customers’ needs for less time and money,
the project team and key stakeholders should be open to making major changes in
the project.
All projects will have some changes, and managing them is a key issue in project
management, especially for IT projects. Many IT projects involve the use of hardware and
software that is updated frequently. To continue the example from earlier in this section,
the initial plan for ordering the server might have identified a model that used cutting-
edge technology at the time. If the actual server order occurred six months later, it is quite
possible that a more powerful server could be available at the same cost. This example
illustrates a positive change. On the other hand, the server manufacturer specified in the
project plan could go out of business, which would result in a negative change. IT project
managers should be accustomed to such changes and build some flexibility into their proj-
ect plans and execution. Customers for IT projects should also be open to meeting project
objectives in different ways.
Some changes might make sense but be too large to fit into a current project. Remem-
ber that projects have scope, time, cost, and other goals, and changes often affect those
goals. If the organization wants to meet time and cost goals, for example, it must control
changes to the project’s scope. Organizations often decide to document some change
requests and include them in an upgrade to the current project.
Even if project managers, project teams, and customers are flexible, it is important
that projects have a formal change control system. This formal system is necessary to plan
for managing change.
4.8b Change Control System
A change control system is a formal, documented process that describes when and how of-
ficial project documents may be changed. It also describes the people authorized to make
changes, the paperwork required for these changes, and any automated or manual track-
ing systems the project will use. A change control system often includes a change control
board, configuration management, and a process for communicating changes.
A change control board (CCB) is a formal group of people responsible for approving
or rejecting changes to a project. The primary functions of a CCB are to provide guidelines
for preparing change requests, evaluating change requests, and managing the implemen-
tation of approved changes. An organization could have key stakeholders for the entire
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

organization on this board, and a few members could rotate based on the unique needs
of each project. By creating a formal board and a process for managing changes, overall
change control should improve.
However, CCBs can have some drawbacks, such as the time it takes to make deci-
sions on proposed changes. CCBs often meet only once a week or once a month and may
not make decisions in one meeting. Some organizations have streamlined processes for
making quick decisions on smaller project changes. One company created a “48-hour
policy,” in which task leaders on a large IT project would reach agreements on key deci-
sions or changes within their expertise and authority. The person in the area most af-
fected by this decision or change then had 48 hours to go to top management and seek
approval. If the project team’s decision could not be implemented for some reason, the
top manager consulted would have 48 hours to reverse the decision; otherwise, the proj-
ect team’s decision was approved. This type of process is an effective way to deal with the
many time-sensitive decisions or changes that project teams must make on IT projects.
Configuration management is another important part of integrated change control.
Configuration management ensures that the descriptions of the project’s products are cor-
rect and complete. It involves identifying and controlling the functional and physical de-
sign characteristics of products and their support documentation. Members of the project
team, frequently called configuration management specialists, are often assigned to per-
form configuration management for large projects. Their job is to identify and document
the functional and physical characteristics of the project’s products, control any changes
to such characteristics, record and report the changes, and audit the products to verify
conformance to requirements. Visit the Institute of Configuration Management’s website
(www.icmhq.com) for more information on this topic.
G L O B A L I S S U E S
Rapid changes in technology, such as the increased use of mobile roaming for com-
munications, often cause governments around the world to take action. Incompatible
hardware, software, and networks can make communications difficult in some regions,
and a lack of competition can cause prices to soar. Fortunately, a group called the Or-
ganisation for Economic Co-operation and Development (OECD) promotes policies that
will improve the economic and social well-being of people around the world. In February
2012, the OECD called upon its members’ governments to boost competition in inter-
national mobile roaming markets. “The OECD has detailed a series of measures that, if
implemented would, it says: ‘encourage effective competition, raise consumer awareness
and protection and ensure fairer prices.’ If these fail to produce results it says: ‘Govern-
ments should consider price regulation for roaming services,’ and that ‘Wholesale roam-
ing services could be regulated by means of bilateral or multilateral wholesale agreements
with mutually established price caps.’”13
OECD also encourages expansion of other technologies. By the end of 2013, wireless
broadband penetration grew to 72.4 percent in the 34-country OECD area. Strong de-
mand for smartphones and tablets helped wireless broadband subscriptions grow by
14.6 percent.14
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Another critical factor in change control is communication. Project managers should
use written and oral performance reports to help identify and manage project changes.
For example, on software development projects, most programmers must make their
edits to a copy of the master file in a database; to ensure version control, programmers
must “check out” the file to edit it. If two programmers are allowed to check out the
same file, they must coordinate to merge their changes. In addition to written or formal
communication methods, oral and informal communications are also important. Some
project managers have stand-up meetings once a week or even every morning, depending
on the nature of the project. The goal of a stand-up meeting is to quickly communicate
what is most important for the project. For example, the project manager might have a
stand-up meeting every morning with all of the team leaders. There might be a stand-up
meeting every Monday morning with all interested stakeholders. Requiring participants
to stand keeps meetings short and forces everyone to focus on the most important proj-
ect events.
Why is good communication so critical to success? One of the most frustrating as-
pects of project change is not having everyone coordinated and informed about the latest
project information. Again, it is the project manager’s responsibility to integrate all project
changes so that the project stays on track. The project manager and staff members must
develop a system for notifying everyone affected by a change in a timely manner. E-mail,
real-time databases, cell phones, and the Web make it easy to disseminate the most cur-
rent project information. You will learn more about good communication in Chapter 10,
Project Communications Management.
Table 4-3 lists suggestions for performing integrated change control. As described ear-
lier, project management is a process of constant communication and negotiation. Project
managers should plan for changes and use appropriate tools and techniques, such as a
change control board, configuration management, and good communication. It is helpful
to define procedures for making timely decisions about small changes, use written and
oral performance reports to help identify and manage changes, and use software to assist
in planning, updating, and controlling projects.
Project managers must also provide strong leadership to steer the project to successful
completion. They must not get too involved in managing project changes. Project man-
agers should delegate much of the detailed work to project team members and focus on
TABLE 4-3
View project management as a process of constant communication and negotiation
Plan for change
Establish a formal change control system, including a change control board (CCB)
Use effective configuration management
Define procedures for making timely decisions about smaller changes
Use written and oral performance reports to help identify and manage change
Use project management software and other software to help manage and communicate changes
Focus on leading the project team and meeting overall project goals and expectations
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

providing overall leadership for the project in general. Remember, project managers must
focus on the big picture and perform project integration management well to lead their
team and organization to success.
4.9 CLOSING PROJECTS OR PHASES
The last process in project integration management is closing the project or phase, which
requires that you finalize all activities and transfer the completed or cancelled work to
the appropriate people. The main inputs to this process are the project management plan,
accepted deliverables, and organizational process assets. The main tool and technique is
again expert judgment. The outputs of closing projects are:
Final product, service, or result transition: Project sponsors are usually most
interested in making sure they receive delivery of the final products, services,
or results they expected when they authorized the project. For items produced
under contract, formal acceptance or handover includes a written statement that
the terms of the contract were met. Internal projects can also include some type
of project completion form.
Organizational process asset updates: The project team should provide
a list of project documentation, project closure documents, and historical
information produced by the project in a useful format. This information is
considered a process asset. Project teams normally produce a final project
report, which often includes a transition plan describing work to be done as
part of operations after the project is completed. Teams also often write a
lessons-learned report at the end of a project, and this information can be a
tremendous asset for future projects. (See Chapter 10, Project Communica-
tions Management, for more information on creating final project reports,
lessons-learned reports, and other project communications.) Several organi-
zations also conduct a post-implementation review to analyze whether the
project achieved what it set out to do. Information from this type of review
also becomes an organizational process asset for future projects.
4.10 USING SOFTWARE TO ASSIST IN PROJECT
INTEGRATION MANAGEMENT
As described throughout this chapter, project teams can use various types of software to
assist in project integration management. Project teams can create documents with word-
processing software, give presentations with presentation software, track information with
spreadsheets, databases, or customized software, and transmit information using various
types of communication software.
Project management software is also an important tool for developing and integrating
project planning documents, executing the project management plan and related project
plans, monitoring and controlling project activities, and performing integrated change
control. Small project teams can use low-end or midrange project management software
to coordinate their work. For large projects, such as the Olympic Games described in the
Media Snapshot earlier in this chapter, organizations may benefit most from high-end
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

FIGURE 4-8
tools that provide enterprise project management capabilities and integrate all aspects of
project management.
As you learned in Chapter 1, organizations can also use software to assist in project
portfolio management and optimization. Portfolio management software often provides
many types of charts or dashboards to help managers see the big picture in managing
portfolios of projects. For example, Figure 4-8 shows column charts, bar charts, pie charts,
and bubble charts from www.projectmanager.com. All projects can benefit from using
some type of project management information system to coordinate and communicate
project information.
In recent years, the growth of cloud computing has transformed how, when, and
where people work. Many project management software tools are now available in the
cloud, as are other tools and services. Most business professionals and students now store
their files using some type of cloud storage (Google Drive, Microsoft OneDrive, DropBox,
etc.). Many cloud tools are accessible via smartphones and tablets as well as laptops and
desktops. Cloud computing enables users to easily access and share information from any
location at any time. Project integration management is not easy, but the cloud has defi-
nitely helped provide easier access to important information and applications.
As you can see, a lot of work is involved in project integration management. Project
managers and their teams must focus on pulling all the elements of a project together to
successfully complete it.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

C A S E W R A P – U P
Without consulting Nick Carson or his team, Nick’s CEO hired a new person, Jim Lansing,
to act as a middle manager between himself and the people in Nick’s department. The
CEO and other top managers really liked Jim; he met with them often, shared ideas, and
had a great sense of humor. He started developing standards that the company could use
to help manage projects in the future. For example, he developed templates for creating
plans and progress reports and put them on the company’s intranet. However, Jim and
Nick did not get along, especially after Jim accidentally sent an e-mail to Nick that was
intended for the CEO. In the e-mail, Jim said that Nick was hard to work with and preoc-
cupied with the birth of his son.
Nick was furious when he read the e-mail, and stormed into the CEO’s office. The
CEO suggested that Nick move to another department, but Nick did not like that option.
Without considering the repercussions, the CEO offered Nick a severance package to
leave the company. Because of the planned corporate buyout, the CEO knew the com-
pany might have to let some people go anyway. Nick talked the CEO into giving him a
two-month sabbatical he had earned plus a higher percentage on his stock options. After
discussing the situation with his wife and realizing that he would get over $70,000 if he
resigned, Nick took the severance package. He had such a bad experience as a project
manager that he decided to stick with being a technical expert. Jim, however, thrived in
his position and helped the company improve its project management practices and
ensure success in a highly competitive market.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter Summary





Quick Quiz
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Quick Quiz Answers
Discussion Questions



Exercises
www.matchware.com
/itpm
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.






®

Running Case
Note:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.



Global Treps: Shark Tank



DonorsChoose.org


Change the Laws Campaign:

Wealthy Unite:

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Global Smart Shoppers:
Tasks





DonorsChoose.org


Key Terms
balanced scorecard
baseline
capitalization rate
cash flow
change control board (CCB)
change control system
configuration management
cost of capital
directives
discount factor
discount rate
integrated change control
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

181
interface management
internal rate of return (IRR)
mind mapping
net present value (NPV) analysis
opportunities
opportunity cost of capital
organizational process assets
payback period
problems
project charter
project integration management
project management plan
required rate of return
return on investment (ROI)
strategic planning
SWOT analysis
weighted scoring model
End Notes
MIS Quarterly
CIO
Forbes
The Project Manager’s MBA
Computerworld
balancedscorecard.org
/Resources/About-the-Balanced-Scorecard
Proceedings of
the Project Management Institute Annual Seminars & Symposium
2015 Pulse of the Profession®: Capturing the Value of Project
Management
PM Network
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R5
PROJECT SCOPE
MANAGEMENT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

xufen
打字机
范围

184
O P E N I N G C A S E
Kim Nguyen was leading a meeting to create the work breakdown structure (WBS) for her
company’s IT upgrade project. This project was necessary because of several high-priority,
Internet-based applications the company was developing. The IT upgrade project involved
creating and implementing a plan to make all employees’ IT assets meet new corporate
standards within nine months. These standards specified the minimum requirements for
each desktop or laptop computer, including the type of processor, amount of memory, hard
disk size, type of network connection, security features, and software. Kim knew that to
perform the upgrades, the project team would first have to create a detailed inventory of all
the current hardware, networks, and software in the entire company of 2,000 employees.
Kim had worked with other stakeholders to develop a project charter and initial
scope statement. The project charter included rough cost and schedule estimates for the
project and signatures of key stakeholders; the initial scope statement provided a start in
defining the hardware, software, and network requirements as well as other information
related to the project scope. Kim called a meeting with her project team and other stake-
holders to further define the scope of the project. She wanted to get everyone’s ideas on
what the project involved, who would do what, and how they could avoid scope creep.
The company’s new CEO, Walter Schmidt, was known for keeping a close eye on major
projects. The company had started using a new project management information system
that let everyone know the status of projects at a detailed and high level. Kim knew that
a good WBS was the foundation for scope, time, and cost performance, but she had never
led a team in creating one or allocating costs based on a WBS. Where should she begin?
5.1 WHAT IS PROJECT SCOPE MANAGEMENT?
Many of the factors associated with project success, such as user involvement, clear busi-
ness objectives, and optimized scope, are elements of project scope management.
A critically important and difficult aspect of project management is defining the scope
of a project. Scope refers to all the work involved in creating the products of the proj-
ect and the processes used to create them. Recall from Chapter 2 that a deliverable is a
product created as part of a project. Deliverables can be product-related, such as a piece
of hardware or software, or process-related, such as a planning document or meeting min-
utes. Project stakeholders must agree what the products of the project are and, to some
extent, how they should be produced to define all of the deliverables.
Project scope management includes the processes involved in defining and control-
ling what work is or is not included in a project. It ensures that the project team and
stakeholders have the same understanding of what products the project will produce and
what processes the project team will use to produce them. Six main processes are involved
in project scope management:
1. Planning scope management involves determining how the project’s scope and
requirements will be managed. The project team works with appropriate stake-
holders to create a scope management plan and requirements management plan.
2. Collecting requirements involves defining and documenting the features and
functions of the products as well as the processes used for creating them. The
project team creates requirements documentation and a requirements
traceability matrix as outputs of the requirements collection process.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo
利益相关者

lenovo

lenovo

lenovo

lenovo

lenovo

3. Defining scope involves reviewing the scope management plan, project char-
ter, requirements documents, and organizational process assets to create a
scope statement, adding more information as requirements are developed
and change requests are approved. Outputs of scope definition are the project
scope statement and updates to project documents.
4. Creating the WBS involves subdividing the major project deliverables into
smaller, more manageable components. Outputs include a scope baseline (which
includes a WBS and a WBS dictionary) and updates to project documents.
5. Validating scope involves formalizing acceptance of the project deliverables.
Key project stakeholders, such as the customer and sponsor for the project,
inspect and then formally accept the deliverables during this process. If the
deliverables are not acceptable, the customer or sponsor usually requests
changes. The outputs of this process are accepted deliverables, change re-
quests, work performance information, and updates to project documents.
6. Controlling scope involves controlling changes to project scope throughout the
life of the project—a challenge on many IT projects. Scope changes often influ-
ence the team’s ability to meet project time and cost goals, so project managers
must carefully weigh the costs and benefits of scope changes. The outputs of this
process are work performance information, change requests, and updates to the
project management plan, project documents, and organizational process assets.
Figure 5-1 summarizes these processes and outputs and shows when they occur in a
typical project.
Planning
Process: Plan scope management
Outputs: Scope management plan, requirements management plan
Process: Collect requirements
Outputs: Requirements documentation, requirements traceability matrix
Process: Define scope
Outputs: Project scope statement, project documents updates
Process: Create WBS
Outputs: Scope baseline, project documents updates
Monitoring and Controlling
Process: Validate scope
Outputs: Accepted deliverables, change requests, work performance
information, project documents updates
Process: Control scope
Outputs: Work performance information, change requests, project
management plan updates, project documents updates,
organizational process assets updates
Project Start Project Finish
FIGURE 5-1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo
validate : 确认生效

lenovo

5.2 PLANNING SCOPE MANAGEMENT
The first step in project scope management is planning how the scope will be managed
throughout the life of the project. After reviewing the project management plan, project
charter, enterprise environmental factors, and organizational process assets, the project
team uses expert judgment and meetings to develop two important outputs: the scope
management plan and the requirements management plan.
The scope management plan is a subsidiary part of the project management plan, as
described in Chapter 4, Project Integration Management. It can be informal and broad or
formal and detailed, based on the needs of the project. In fact, small projects may not need a
written scope management plan, but large projects or highly technical projects often benefit
from one. In general, a scope management plan includes the following information:
How to prepare a detailed project scope statement: For example, are there
templates or guidelines to follow? How much detail is needed to describe each
deliverable?
How to create a WBS: It is often difficult to create a good WBS. This section
of the scope management plan would provide suggestions, samples, and
resources for creating a WBS.
How to maintain and approve the WBS: The initial WBS often changes,
and project team members disagree on what should be included. The scope
management plan describes guidelines for maintaining the WBS and getting
approval for it.
How to obtain formal acceptance of the completed project deliverables: It is
extremely important to understand the process for obtaining formal accep-
tance of completed deliverables, especially for projects in which payments
are based on formal acceptance.
How to control requests for changes to the project scope: This process is
related to performing integrated change control, as described in Chapter 4.
Organizations often have guidelines for submitting, evaluating, and approv-
ing changes to scope, and this section of the scope management plan would
specify how to handle change requests for the project.
Another important output of planning scope management is the requirements
management plan. Before you learn about the contents of this document, it is important to
understand what requirements are. The 1990 IEEE Standard Glossary of Software
Engineering Terminology defines a requirement as follows:
“1. A condition or capability needed by a user to solve a problem or achieve an
objective.
2. A condition or capability that must be met or possessed by a
system or system component to satisfy a contract, standard, specification, or
other formally imposed document.
3. A documented representation of a condition or capability as in 1 or 2.”1
The PMBOK® Guide, Fifth Edition, describes requirements as “conditions or capabili-
ties that must be met by the project or present in the product, service, or result to satisfy
an agreement or other formally imposed specification.” It further explains that require-
ments “include the quantified and documented needs and expectations of the sponsor,
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

187
customer, and other stakeholders. These requirements need to be elicited, analyzed, and
recorded in enough detail to be included in the scope baseline and be measured once proj-
ect execution begins.”
For example, the chapter’s opening case describes a project for upgrading IT assets to
meet corporate standards. These standards specify the minimum requirements for each
laptop, such as the type of processor, amount of memory, and hard disk size. The docu-
mented requirements for this project, therefore, might state that all laptops include an
Intel processor, at least 16 GB of memory, and a 2-TB hard drive.
For some IT projects, it is helpful to divide requirements development into categories
called elicitation, analysis, specification, and validation. These categories include all the
activities involved in gathering, evaluating, and documenting requirements for a software
or software-containing product. It is also important to use an iterative approach to defin-
ing requirements because they are often unclear early in a project.
The requirements management plan documents how project requirements will be
analyzed, documented, and managed. A requirements management plan can include the
following information:
How to plan, track, and report requirements activities
How to perform configuration management activities
How to prioritize requirements
How to use product metrics
How to trace and capture attributes of requirements
W H A T W E N T R I G H T ?
Several studies cite how difficult it is to manage requirements. Finding qualified people—
business analysts—to do the job is equally difficult. The U.S. Bureau of Labor Statistics has
projected the number of jobs for business analysts to increase 19 percent by 2022.2 A 2014 PMI
survey found that only 49 percent of respondents had the resources in place to do requirements
management properly and 53 percent failed to use a formal process to validate requirements.3
Fortunately, several organizations have recognized this need and have developed
training and certification programs for business analysts.
The International Institute of Business Analysis (IIBA)® issues both the Certified
Business Analysis Professional (CBAP®) and Certification of Competency in
Business Analysis (CCBA®) certifications. This organization had about 28,000
members by the end of 2014 and recently published the third edition of the Guide
to Business Analysis Body of Knowledge (BABOK® Guide).
The International Requirements Engineering Board (IREB) provides certifica-
tion as a Certified Professional for Requirements Engineering (CPRE). Over
19,000 people in 55 countries held this certification by the end of 2014.
PMI began offering a new certification as a PMI Professional in Business Analysis
(PMI-PBA)® in 2014.
Several colleges and universities are offering majors and minors in business or
data analytics at the undergraduate and graduate levels.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

188
5.3 COLLECTING REQUIREMENTS
The second step in project scope management is often the most difficult: collecting
requirements. A major consequence of not defining requirements well is rework, which
can consume up to half of project costs, especially for software development projects. As
illustrated in Figure 5-2, it costs much more (up to 30 times more) to correct a software
defect in later development phases than to fix it in the requirements phase. Everyone
can cite examples in all types of industries of how important it is to understand require-
ments as early as possible. For example, if you are designing a house, it is much cheaper
to decide where windows and walls will be on paper or a computer screen than after the
entire house is framed. New processes and technologies are making it easier to define and
implement requirements, but it is still one of the most challenging aspects of project scope
management.
FIGURE 5-2
0
500
1000
1500
2000
2500
3000
3500
Design and
architecture
Implementation
Development Phase
Integration
testing
Customer
beta test
Postproduct
release
Re
la
ti
ve
C
os
t
100
500
1000
1500
3000
Source: IBM Software Group, “Minimizing code defects to improve software quality and lower development
costs,“ Rational Software (October 2008).
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

189
B E S T P R A C T I C E
Google continues to be among the most admired companies in the world, well-known for
being a great place to work and for being innovative in developing new products. James
Whittaker, former engineering director at Google, responsible for testing Chrome, maps,
and Google web apps, wrote a book with co-authors Jason Arbon and Jeff Carollo (also
former Google employees) called How Google Tests Software. Whittaker also worked for
Microsoft and as a professor and is one of the best-known names in testing software.
In How Google Tests Software, the authors explain that Google used to be like other
large companies: testing was not part of the mainstream, and people who did it were
underappreciated and overworked. It took Google a long time to develop the people, pro-
cesses, and technologies it uses today to develop software. A key part of success at Google
was changing the culture. Google has fewer dedicated testers than most of its competitors
have on a single product team. How is that possible? The authors explain that quality
rests on the shoulders of those writing the code. The employees at Google do things the
best, fastest way possible for them, knowing that coders are responsible for the quality of
their own work. They don’t rely on testers to ensure quality.
It is also interesting to note that Google does not believe in fads or buzzwords. In an
interview, InfoQ asked the authors how Google’s approach fits into the wider Agile com-
munity. Their response: “Google doesn’t try to be part of the Agile community. We don’t
use the terminology of scrums or bother with scrum masters and the like. We have crafted
our own process of moving fast. It’s a very Agile process that doesn’t get bogged down with
someone else’s idea of what it means to be Agile. When you have to stop and define what
it means to be Agile and argue what flavor of Agile you are, you just stopped being Agile.”4
Part of the difficulty is that people often do not have a good process for collecting and
documenting project requirements.
There are several ways to collect requirements. Interviewing stakeholders one on one is
often very effective, although it can be expensive and time-consuming. Holding focus groups
and facilitated workshops, and using group creativity and decision-making techniques to
collect requirements, are normally faster and less expensive than one-on-one interviews.
Questionnaires and surveys can be efficient ways to collect requirements as long as key
stakeholders provide honest and thorough information. Observation can also be a good
technique for collecting requirements, especially for projects that involve improving work
processes and procedures. For software development projects, prototyping and document
analysis are common techniques for collecting requirements, as are context diagrams, which
help to clarify the interfaces and boundaries of a project or process. On agile software devel-
opment projects, the product owner creates the prioritized product backlog for each sprint,
as shown in Chapter 3. Benchmarking, or generating ideas by comparing specific project
practices or product characteristics to those of other projects or products inside or outside
the performing organization, can also be used to collect requirements.
Even though there are many ways to collect requirements, people who work on soft-
ware projects in particular have considerable difficulty defining and managing require-
ments. A 2011 study revealed some interesting statistics:
Eighty-eight percent of the software projects involved enhancing existing
products instead of creating new ones.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Eighty-six percent of respondents said that customer satisfaction was
the most important metric for measuring the success of development
projects, 82 percent said that feedback from customers and partners was
the main source of product ideas and requirements, and 73 percent said the
most important challenge for their teams was gaining a clear understand-
ing of what customers wanted, followed by documenting and managing
requirements.
Seventy-five percent of respondents were managing projects with at least
100 requirements; 20 percent were managing projects with over 1,000
requirements.
Seventy percent of respondents spent at least 10 percent of their time man-
aging changes to requirements; 30 percent spent more than 25 percent of
their time on such changes.
The majority of software development teams used a hybrid methodology,
26 percent used waterfall or modified waterfall techniques, and 19 percent
used agile techniques.
Eighty-three percent of software development teams still use Microsoft
Office applications such as Word and Excel as their main tools to
communicate requirements.
The respondents listed “requirements collaboration and management
software” and “requirements modeling and visualization” as the top two
software tools on their wish list, followed by test management and project
management.5
The project’s size, complexity, importance, and other factors affect how much effort
is spent on collecting requirements. For example, a team working on a project to upgrade
the entire corporate accounting system for a multibillion-dollar company with more than
50 locations should spend a fair amount of time collecting requirements. On the other
hand, a project to upgrade the hardware and software for a small accounting firm with
only five employees would need a much smaller effort. In any case, it is important for a
project team to decide how it will collect and manage requirements. It is crucial to gather
inputs from key stakeholders and align the scope with business strategy, as described in
Chapter 4.
Just as a project team can collect requirements in several ways, there are several
ways to document the requirements. Project teams should first review the project char-
ter because it includes high-level requirements for the project, and they should refer to
the scope and requirements management plans. They should also review the stakeholder
register and stakeholder management plan to ensure that all key stakeholders have a say
in determining requirements. The format for documenting stakeholder requirements can
range from a listing of all requirements on a single piece of paper to a room full of note-
books. People who have worked on complex projects, such as building a new airplane,
know that the requirements documentation for a plane can weigh more than the plane
itself! Requirements documents are often generated by software and include text, images,
diagrams, videos, and other media. Requirements are often broken down into different
categories such as functional requirements, service requirements, performance require-
ments, quality requirements, and training requirements.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

191
In addition to preparing requirements documentation as an output of collecting
requirements, project teams often create a requirements traceability matrix. A require-
ments traceability matrix (RTM) is a table that lists requirements, their various at-
tributes, and the status of the requirements to ensure that all are addressed. Table 5-1
provides an example of an RTM entry for the IT upgrade project described in the chapter’s
opening case. An RTM can have many variations. For example, software requirements are
often documented in an RTM that cross-references each requirement with related ones
and lists specific tests to verify that they are met. Remember that the main purpose of an
RTM is to maintain the linkage from the source of each requirement through its decompo-
sition to implementation and validation. Search the Internet for more detailed examples
of an RTM.
5.4 DEFINING SCOPE
The next step in project scope management is to provide a detailed definition of the work
required for the project. Good scope definition is very important to project success
because it helps improve the accuracy of time, cost, and resource estimates, it defines a
baseline for performance measurement and project control, and it aids in communicating
clear work responsibilities. The main tools and techniques used in defining scope include
expert judgment, product analysis, alternatives generation, and facilitated workshops.
For example, a facilitator could have users, developers, and salespeople join a face-to-
face meeting or virtual meeting to exchange ideas about developing a new product. The
main outputs of scope definition are the project scope statement and project documents
updates.
Key inputs for preparing the project scope statement include the project charter,
scope management plan, requirements documentation, and organizational process assets
such as policies and procedures related to scope statements, as well as project files and
lessons learned from previous, similar projects. Table 5-2 shows the project charter for the
IT upgrade project described in the opening case. Notice how information from the project
charter provides a basis for further defining the project scope. The charter describes the
high-level scope, time, and cost goals for the project objectives and success criteria, a gen-
eral approach to accomplishing the project’s goals, and the main roles and responsibilities
of important project stakeholders.
Although contents vary, project scope statements should include at least a product
scope description, product user acceptance criteria, and detailed information on all project
deliverables. It is also helpful to document other scope-related information, such as the
project boundaries, constraints, and assumptions. The project scope statement should also
TABLE 5-1
Requirement No. Name Category Source Status
R32 Laptop
memory
Hardware Project charter and
corporate laptop
specifications
Complete. Laptops ordered meet
requirement by having 16 GB
of memory.
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

TABLE 5-2
Project Title: Information Technology (IT) Upgrade Project
Project Start Date: March 4 Projected Finish Date: December 4
Key Schedule Milestones:
Inventory update completed April 15
Hardware and software acquired August 1
Installation completed October 1
Testing completed November 15
Budget Information: Budgeted $1,000,000 for hardware and software costs and $500,000 for labor costs.
Project Manager: Kim Nguyen, (310) 555–2784, knguyen@course.com
Project Objectives: Upgrade hardware and software for all employees (approximately 2,000) within nine
months based on new corporate standards. See attached sheet describing the new standards. Upgrades
may affect servers as well as associated network hardware and software.
Main Project Success Criteria: The hardware, software, and network upgrades must meet all written
specifications, be thoroughly tested, and be completed in nine months. Employee work disruptions will
be minimal.
Approach:
Update the IT inventory database to determine upgrade needs
Develop detailed cost estimate for project and report to CIO
Issue a request for quote to obtain hardware and software
Use internal staff as much as possible for planning, analysis, and installation
Name Role Responsibility
Walter Schmidt CEO Project sponsor, monitor project
Mike Zwack CIO Monitor project, provide staff
Kim Nguyen Project Manager Plan and execute project
Jeff Johnson Director of IT Operations Mentor Kim
Nancy Reynolds VP, Human Resources Provide staff, issue memo to all employees
about project
Steve McCann Director of Purchasing Assist in purchasing hardware and software
Sign-off: (Signatures of all the above stakeholders)
Comments: (Handwritten or typed comments from above stakeholders, if applicable)
“This project must be done within 10 months at the absolute latest.” Mike Zwack, CIO
“We are assuming that adequate staff will be available and committed to supporting this project. Some
work must be done after hours to avoid work disruptions, and overtime will be provided.” Jeff Johnson
and Kim Nguyen, IT department
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

193
reference supporting documents, such as product specifications that will affect what prod-
ucts are created or purchased, or corporate policies, which might affect how products or
services are produced. Many IT projects require detailed functional and design specifications
for developing software, which also should be referenced in the detailed scope statement.
As time progresses, the scope of a project should become more clear and specific.
For example, the project charter for the IT upgrade project in Table 5-2 includes a short
statement about the servers and other computers and software that the project may affect.
Table 5-3 provides an example of how the scope becomes progressively more detailed in
scope statements labeled Version 1 and Version 2.
Notice in Table 5-3 that the project scope statements often refer to related documents,
which can be product specifications, product brochures, or other plans. As more informa-
tion becomes available and decisions are made related to project scope, such as specific
products that will be purchased or changes that have been approved, the project team
should update the project scope statement. The team might name different iterations
of the scope statement Version 1, Version 2, and so on. These updates may also require
changes to other project documents. For example, if the company must purchase serv-
ers from a supplier it has never worked with before, the procurement management plan
should include information on working with that new supplier.
An up-to-date project scope statement is an important document for developing and
confirming a common understanding of the project scope. It describes in detail the work
to be accomplished on the project and is an important tool for ensuring customer satisfac-
tion and preventing scope creep, as described later in this chapter.
Recall from Chapter 1 the importance of addressing the triple constraint of project
management—meeting scope, time, and cost goals for a project. Time and cost goals are
normally straightforward. For example, the time goal for the IT upgrade project is nine
months, and the cost goal is $1.5 million. It is much more difficult to describe, agree upon,
and meet the scope goal of many projects.
TABLE 5-3
Project Charter:
Upgrades may affect servers … (listed under Project Objectives)
Project Scope Statement, Version 1:
Servers: If additional servers are required to support this project, they must be compatible with existing
servers. If it is more economical to enhance existing servers, a detailed description of enhancements
must be submitted to the CIO for approval. See current server specifications provided in Attachment 6.
The CEO must approve a detailed plan describing the servers and their location at least two weeks
before installation.
Project Scope Statement, Version 2:
Servers: This project will require purchasing 10 new servers to support web, network, database,
application, and printing functions. Virtualization will be used to maximize efficiency. Detailed
descriptions of the servers are provided in a product brochure in Attachment 8, along with a plan
describing where they will be located.
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

194
M E D I A S N A P S H O T
Inaccurate requirements gathering continues to be one of the main causes of project
failure. Organizations lack the resources and maturity in requirements management,
which comes at a price. The authors of the 2014 PMI in-depth report on requirements
management state that “For every dollar spent on projects and programs, 5.1 percent is
wasted due to poor requirements management. Put in more striking terms, this amounts
to US$51 million wasted for every US$1billion spent. That’s a lot of potential value falling
through the cracks in the project-driven world.”6
The report provides the following survey results:
Forty-seven percent of organizations report that inaccurate requirements manage-
ment is the primary cause of projects not meeting their original goals and business
objectives.
Over half of organizations report not having adequate resources to perform require-
ments management well.
Only 24 percent of organizations report doing well in recognizing and developing
skills needed for effective management of requirements.
Only 46 percent of organizations report using a formal process to ensure unbiased
requirements validation for projects.
The report concludes by suggesting that organizations need to develop people, processes,
and culture to improve requirements management.
5.5 CREATING THE WORK BREAKDOWN STRUCTURE
After collecting requirements and defining scope, the next step in project scope manage-
ment is to create a work breakdown structure. A work breakdown structure (WBS) is a
deliverable-oriented grouping of the work involved in a project that defines its total scope.
Because most projects involve many people and many different deliverables, it is impor-
tant to organize and divide the work into logical parts based on how the work will be per-
formed. The WBS is a foundation document in project management because it provides
the basis for planning and managing project schedules, costs, resources, and changes.
Because the WBS defines the total scope of the project, some project management experts
believe that work should not be done on a project if it is not included in the WBS. There-
fore, it is crucial to develop a complete WBS.
The project scope management plan, scope statement, requirements documentation,
enterprise environmental factors, and organizational process assets are the primary inputs
for creating a WBS. The main tool or technique is decomposition—that is, subdividing
project deliverables into smaller pieces. The outputs of the process of creating the WBS
are the scope baseline and project documents updates. The scope baseline includes the
approved project scope statement and its associated WBS and WBS dictionary.
What does a WBS look like? A WBS is often depicted as a task-oriented tree of activi-
ties, similar to an organizational chart. A project team often organizes the WBS around
project products, project phases, or the project management process groups. Many people
like to create a WBS in chart form first to help them visualize the whole project and all of
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

its main parts. Figure 5-3 shows a WBS for an intranet project. Notice that product areas
provide the basis for its organization. In this case, there are main boxes or groupings on
the WBS for developing the website design, the home page for the intranet, the marketing
department’s pages, and the sales department’s pages.
In contrast, a WBS for the same intranet project can be organized around project
phases, as shown in Figure 5-4.7 Notice that project phases of concept, website design,
website development, rollout, and support provide the basis for its organization.
Also note the levels in Figure 5-4. The name of the entire project is in the top box,
called Level 1, and the main groupings for the work are listed in the second tier of boxes,
called Level 2. This level numbering is based on the Project Management Institute’s
Practice Standard for Work Breakdown Structures, Second Edition (2006). Each of the
boxes can be broken down into subsequent tiers of boxes to show the hierarchy of the
work. Many people and project management software tools use the term task to describe
each level of work in the WBS, although PMI does not use that term. For example, in
Figure 5-4 the following items can be referred to as tasks: the Level 2 item called
“Concept,” the Level 3 item called “Define requirements,” and the Level 4 item called
“Define user requirements.” Tasks that are decomposed into smaller tasks are called
summary tasks.
Figure 5-4 shows a sample WBS in both chart and tabular form. Notice that both of
these formats show the same information. Many documents, such as contracts, use the
tabular format. Project management software also uses this format. The WBS becomes
the contents of the Task Name column in Microsoft Project, and the hierarchy or level
of tasks is shown by indenting and numbering tasks within the software. The numbering
shown in the tabular form is based on the Practice Standard for Work Breakdown Struc-
tures, Second Edition. The automatic numbering feature in Microsoft Project 2013 uses
this standard, but not all software does. Be sure to check with your organization to see
which numbering scheme it prefers to use for work breakdown structures. To avoid con-
fusion, it is important to decide on a numbering scheme and then use it when referring to
WBS items.
FIGURE 5-3
Website design Home page design Marketing pages Sales pages
Intranet
Site map
Programs
Graphic design
Text
Hyperlinks
Images
Text
Hyperlinks
Images
Text
Hyperlinks
Images
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Also determine how you will name WBS items. Some organizations use only nouns to
focus on describing deliverables. For example, instead of Define requirements, the WBS
would say Requirements definition. Remember that the main purpose of the WBS is to
define all of the work required to complete a project, so focus on that while following your
organization’s structural guidelines.
In Figure 5-4, the lowest level of the WBS is Level 4. A work package is a task at the
lowest level of the WBS. In Figure 5-4, tasks 1.2.1, 1.2.2, 1.2.3, and 1.2.4 (based on the
numbering on the left) are work packages. The other tasks would be broken down further.
However, some tasks can remain at Level 2 or 3 in the WBS. Others might be broken down
to Level 5 or 6, depending on the complexity of the work.
FIGURE 5-4
Level 1 – Entire Project
Level 2
Level 3
Level 4
Website
development
Concept Website
design
Roll out Support
Intranet
project
Evaluate
current
systems
Define
risks & risk
management
approach
Develop
project plan
Define
specific
functionality
Brief web
development
team
Define content
requirements
Define user
requirements
Define system
requirements
Define server
owner
requirements
Define
requirements
Chart
form
Tabular form with PMI numbering
1.1 Concept
1.1.1 Evaluate current systems
1.1.2 Define requirements
1.1.2.1 Define user requirements
1.1.2.2 Define content requirements
1.1.2.3 Define system requirements
1.1.2.4 Define server owner requirements
1.1.3 Define specific functionality
1.1.4 Define risks and risk management
approach
1.1.5 Develop project plan
1.1.6 Brief web development team
1.2 Website design
1.3 Website development
1.4 Roll out
1.5 Support
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

197
A work package also represents the level of work that the project manager monitors
and controls. You can think of work packages in terms of accountability and reporting. If
a project has a relatively short time frame and requires weekly progress reports, a work
package might represent work completed in one week or less. If a project has a very long
time frame and requires quarterly progress reports, a work package might represent work
completed in one month or more. A work package might also be the procurement of a
specific product or products, such as an item or items purchased from an outside source.
A work package should be defined at the proper level so the project manager can clearly
establish an estimate of the effort needed to complete it, estimate the cost of all required
resources, and evaluate the quality of the results when the work package is finished.
When using project management software, estimates of work time should be entered
only at the work package level. The rest of the WBS items are just groupings or summary
tasks for the work packages. The software automatically calculates duration estimates for
various WBS levels based on data entered for each work package and the WBS hierarchy.
Figure 5-5 shows the phase-oriented intranet WBS, using the Microsoft Project number-
ing scheme from Figure 5-4, in the form of a Gantt chart created in Project 2013. You can see
from this figure that the WBS is the basis for project schedules. Notice that the WBS is in the
left part of the figure in the Task Name column. The resulting schedule is in the right part of
the figure. You will learn more about Gantt charts in Chapter 6, Project Time Management.
The example WBSs shown here are simplified so that they are somewhat easy to
understand and construct. Nevertheless, it is very difficult to create a good WBS. To cre-
ate a good WBS, you must understand the project and its scope and incorporate the needs
and knowledge of the stakeholders. The project manager and the project team must de-
cide as a group how to organize the work and how many levels to include in the WBS.
While many project managers have found that they should focus on doing the top
levels well before becoming bogged down in more detailed levels, it is also true that more
accurate estimates of scope, time, and cost are obtained when the project is defined ap-
propriately and in sufficient detail. Operating at too high a level increases project risk.
FIGURE 5-5
WBS Schedule
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

198
The act of defining the WBS is meant to offset that risk by considering the project’s details
in advance of their execution.
Many people confuse tasks on a WBS with specifications. Tasks on a WBS represent
work that needs to be done to complete the project. For example, if you are creating a
WBS to redesign a kitchen, you might have Level 2 categories called design, purchasing,
flooring, walls, cabinets, and appliances. Under flooring, you might have tasks to remove
the old flooring, install the new flooring, and install the trim. You would not have tasks like
“12 ft. by 14 ft. of light oak” or “flooring must be durable”; these are specifications.
Another concern when creating a WBS is how to organize it to provide the basis for
the project schedule. You should focus on what work needs to be done and how it will be
done, not when it will be done. In other words, the tasks do not have to be developed as
a sequential list of steps. If you want some time-based flow for the work, you can create a
WBS using the project management process groups of initiating, planning, executing, mon-
itoring and controlling, and closing as Level 2 in the WBS. By doing this, not only does the
project team follow good project management practice, the WBS tasks can also be mapped
more easily against time. For example, Figure 5-6 shows a WBS and Gantt chart for the
intranet project, organized by the five project management process groups. Tasks under
initiating include selecting a project manager, forming the project team, and developing
the project charter. Tasks under planning include developing a scope statement, creating
a WBS, and developing and refining other plans, which would be broken down in more
detail for a real project. The tasks of concept, website design, website development, and
rollout, which were WBS Level 2 items in Figure 5-4, now become WBS Level 3 items un-
der executing. The executing tasks vary the most from project to project, but many of the
tasks under the other project management process groups would be similar for all proj-
ects. If you do not use the project management process groups in the WBS, you can have
a Level 2 category called “project management” to make sure you account for all tasks
WBS Schedule
FIGURE 5-6
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

199
related to managing the project. Remember that all work should be included in the WBS,
including project management.
Some project teams like to list every deliverable they need to produce and then use
those as the basis for creating all or part of their WBS. In Chapter 3, JWD Consulting used
the project management process groups for the Level 2 items in its WBS for the project
management intranet site project. Then in breaking down the executing task, the project
team focused on the product deliverables it had to produce. Table 5-4 shows the categories
the team used for that part of the WBS. Recall that the scope statement should list and
describe all of the deliverables required for the project. It is very important to ensure con-
sistency between the project charter, scope statement, WBS, and Gantt chart to define the
scope of the project accurately.
It is also very important to involve the entire project team and the customer in creating
and reviewing the WBS. People who will do the work should help to plan the work by creat-
ing the WBS. Having group meetings to develop a WBS helps everyone understand what work
must be done for the entire project and how it should be done, given the people involved. It
also helps to identify where coordination between different work packages will be required.
5.5a Approaches to Developing Work Breakdown Structures
You can use several approaches to develop a work breakdown structure:
Using guidelines
The analogy approach
The top-down approach
The bottom-up approach
The mind-mapping approach
TABLE 5-4
3.0 Executing
3.1 Survey
3.2 User inputs
3.3 Intranet site content
3.3.1 Templates and tools
3.3.2 Articles
3.3.3 Links
3.3.4 Ask the Expert
3.3.5 User requests
3.4 Intranet site design
3.5 Intranet site construction
3.6 Site testing
3.7 Site promotion
3.8 Site rollout
3.9 Project benefits measurement
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Using Guidelines
If guidelines exist for developing a WBS, it is very important to follow them. Some organi-
zations—the U.S. Department of Defense (DOD), for example—
prescribe the form and content for WBSs for particular projects. Many DOD projects
require contractors to prepare their proposals based on the DOD-provided WBS. These
proposals must include cost estimates for each task in the WBS at a detailed and summary
level. The cost for the entire project must be calculated by summing the costs of all of the
lower-level WBS tasks. When DOD personnel evaluate cost proposals, they must compare
the contractors’ costs with the DOD’s estimates. A large variation in costs for a certain
WBS task often indicates confusion as to what work must be done.
Consider a large automation project for the U.S. Air Force. In the mid-1980s, the Air
Force developed a request for proposals for the Local On-Line Network System (LONS) to
automate 15 Air Force Systems Command bases. This $250 million project involved provid-
ing the hardware and developing software for sharing documents such as contracts, specifi-
cations, and requests for proposals. The Air Force proposal guidelines included a WBS that
contractors were required to follow in preparing their cost proposals. Level 2 WBS items
included hardware, software development, training, and project management. The hardware
item was composed of several Level 3 items, such as servers, workstations, printers, and net-
work hardware. Air Force personnel reviewed the contractors’ cost proposals against their
internal cost estimate, which was also based on this WBS. Having a prescribed WBS helped
contractors to prepare their cost proposals and helped the Air Force to evaluate them.
Many organizations provide guidelines and templates for developing WBSs, as well
as examples of WBSs from past projects. Microsoft Project 2013 comes with several
templates, and more are available on Microsoft’s website and other sites. At the request
of many of its members, PMI developed a WBS Practice Standard to provide guidance
for developing and applying the WBS to project management. The Practice Standard
includes sample WBSs for a wide variety of projects in various industries, including proj-
ects for web design, telecom, service industry outsourcing, and software implementation.
Project managers and their teams should review appropriate information to develop
their unique project WBSs more efficiently. For example, Kim Nguyen and key team mem-
bers from the opening case should review their company’s WBS guidelines, templates, and
other related information before and during the team meetings to create their WBS.
The Analogy Approach
Another method for constructing a WBS is the analogy approach. In the analogy
approach, you use a similar project’s WBS as a starting point. For example, Kim Nguyen
from the opening case might learn that one of her organization’s suppliers did a similar IT
upgrade project last year. She could ask them to share their WBS for that project to pro-
vide a starting point for her own project.
McDonnell Aircraft Company, now part of Boeing, provides an example of using an
analogy approach when creating WBSs. McDonnell Aircraft Company designed and manu-
factured several different fighter aircraft. When creating a WBS for a new aircraft design, it
started by using 74 predefined subsystems for building fighter aircraft based on past expe-
rience. There was a Level 2 WBS item for the airframe that was composed of Level 3 items
such as a forward fuselage, center fuselage, aft fuselage, and wings. This generic, product-
oriented WBS provided a starting point for defining the scope of new aircraft projects and
developing cost estimates for new aircraft designs.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Some organizations keep a repository of WBSs and other project documentation on
file to assist people working on projects. Project 2013 and many other software tools in-
clude sample files to assist users in creating a WBS and Gantt chart. Viewing examples of
WBSs from similar projects allows you to understand different ways to create a WBS.
The Top-Down and Bottom-Up Approaches
Two other methods of creating WBSs are the top-down and bottom-up approaches. Most
project managers consider the top-down approach of WBS construction to be conventional.
To use the top-down approach, start with the largest items of the project and break
them into subordinate items. This process involves refining the work into greater and
greater levels of detail. For example, Figure 5-4 shows how work was broken down to Level
4 for part of the intranet project. After finishing the process, all resources should be as-
signed at the work package level. The top-down approach is best suited to project manag-
ers who have vast technical insight and a big-picture perspective.
In the bottom-up approach, team members first identify as many specific tasks
related to the project as possible. They then aggregate the specific tasks and organize
them into summary activities, or higher levels in the WBS. For example, a group of people
might be responsible for creating a WBS to develop an e-commerce application. Instead of
looking for guidelines on how to create a WBS or viewing WBSs from similar projects, they
could begin by listing detailed tasks they think they would need to perform in order to cre-
ate the application. After listing these detailed tasks, they would group the tasks into cat-
egories. Then they would group these categories into higher-level categories. Some people
have found that writing all possible tasks as notes and then placing them on a wall helps
the team see all the work required for the project and develop logical groupings for per-
forming the work. For example, a business analyst on the project team might know that
it had to define user requirements and content requirements for the e-commerce applica-
tion. These tasks might be part of the requirements documents the team would have to
create as one of the project deliverables. A hardware specialist might know that the team
had to define system requirements and server requirements, which would also be part of
a requirements document. As a group, they might decide to put all four of these tasks un-
der a higher-level item called “define requirements” that would result in the delivery of a
requirements document. Later, they might realize that defining requirements should fall
under a broader category of concept design for the e-commerce application, along with
other groups of tasks related to the concept design. The bottom-up approach can be very
time-consuming, but it can also be a very effective way to create a WBS. Project managers
often use the bottom-up approach for projects that represent entirely new systems or ap-
proaches to doing a job, or to help create buy-in and synergy with a project team.
Mind Mapping
Some project managers like to use mind mapping to help develop WBSs. As described in
Chapter 4 during the discussion of SWOT analysis, mind mapping is a technique that uses
branches radiating from a core idea to structure thoughts and ideas. Instead of writing
down tasks in a list or immediately trying to create a structure for tasks, mind mapping
allows people to write and even draw pictures of ideas in a nonlinear format. This more
visual, less structured approach to defining and then grouping tasks can unlock creativity
among individuals and increase participation and morale among teams.8
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Source: MatchWare’s MindView 4 Business Edition
FIGURE 5-7
Figure 5-7 shows a diagram that uses mind mapping to create a WBS for the IT up-
grade project. The rectangle near the center represents the entire project. Each of the four
main branches radiating from the center represents the main tasks or Level 2 items for
the WBS. Different people at the meeting who are creating this mind map might have dif-
ferent roles in the project, which could help in deciding the tasks and WBS structure. For
example, Kim would want to focus on all of the project management tasks, and she might
also know that they will be tracked in a separate budget category. People who are familiar
with acquiring or installing hardware and software might focus on that work, and so on.
Branching off from the main task called “Upgrade inventory” are two subtasks, “Perform
physical inventory” and “Update database.” Branching off from the “Perform physical in-
ventory” subtask are three further subdivisions labeled Building A, Building B, and Build-
ing C. The team would continue to add branches and items until they exhausted ideas for
what work needs to be performed.
After discovering WBS items and their structure using the mind-mapping technique,
you could then translate the information into chart or tabular form, as described earlier.
A feature of MindView 4.0 Business Edition software is that you can click a single icon to
convert a mind map into a Gantt chart. The mind map provides the task list based on the
WBS. MindView also lets you enter information about tasks, such as dependencies and
durations, to generate a complete Gantt chart. You can also export your mind map into
Microsoft Project. The WBS is entered in the Task List column, and the structure is cre-
ated automatically based on the mind map. Figure 5-8 shows the resulting Gantt charts for
the IT upgrade project both in MindView 4.0 and Project 2013. See Appendix A for more
information on using Project 2013.
Mind mapping can be used for developing WBSs using the top-down or bottom-up
approach. For example, you could conduct mind mapping for an entire project by listing
the project in the center of a document, adding the main categories on branches radiat-
ing from the center, and then adding branches for appropriate subcategories. You could
also develop a separate mind-mapping diagram for each deliverable and then merge them
to create one large diagram for the entire project. You can also add items anywhere on
a mind-mapping document without following a strict top-down or bottom-up approach.
After the mind-mapping documents are complete, you can convert them into a chart or
tabular WBS form.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

5.5b The WBS Dictionary
Many of the items listed on the sample WBSs are rather vague. What exactly does
“Update database” mean, for example? The person responsible for this task might think
that it does not need to be broken down any further, which could be fine. However, the
task should be described in more detail so everyone has the same understanding of what
it involves. What if someone else has to perform the task? What would you tell that team
member to do? What will it cost to complete the task? More detailed information is
needed to answer these and other questions.
A WBS dictionary is a document that provides detailed information about each WBS
item. The term dictionary should not be confused with defining terms or acronyms in this
case; such definitions belong in a glossary that would be included elsewhere in the project
documentation. Instead, the WBS dictionary is a definition of the work involved in the
task—a clarification that makes the summary description in the WBS easier to understand
in terms of the approach taken to complete the work.
The format of the WBS dictionary can vary based on project needs. It might be appro-
priate to have a short paragraph describing each work package. For a more complex proj-
ect, an entire page or more might be needed for each of the work package descriptions.
Some projects might require that each WBS item describe the responsible organization,
resource requirements, estimated costs, dependencies with other activities, and other in-
formation. Project teams often review WBS dictionary entries from similar tasks to get a
better idea of how to create their entries.
FIGURE 5-8
MindView 4.0 Gantt Chart Project 2013 Gantt Chart
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

In the IT upgrade project described in the opening case, Kim should work with her
team and sponsor to determine the level of detail needed in the WBS dictionary. They
should also decide where this information will be entered and how it will be updated. Kim
and her team decided to enter all of the WBS dictionary information into their enterprise
project management system, following departmental guidelines. Table 5-5 is an example of
one entry.
The approved project scope statement and its associated WBS and WBS dictionary
form the scope baseline. Performance in meeting project scope goals is based on this
scope baseline.
5.5c Advice for Creating a WBS and WBS Dictionary
As stated previously, creating a good WBS is no easy task and usually requires several
iterations. Often, it is best to use a combination of approaches to create a project’s WBS.
Some basic principles, however, apply to creating any good WBS and its WBS dictionary.
A unit of work should appear in only one place in the WBS.
The work content of a WBS item is the sum of the WBS items below it.
A WBS item is the responsibility of only one person, even though many
people might be working on it.
The WBS must be consistent with the way work actually will be performed; it
should serve the project team first, and serve other purposes only if practical.
Project team members should be involved in developing the WBS to ensure
consistency and buy-in.
TABLE 5-5
WBS Dictionary Entry March 20
Project Title: Information Technology (IT) Upgrade Project
WBS Item Number: 2.2
WBS Item Name: Update Database
Description: The IT department maintains an online database of hardware and software on the
corporate intranet. We need to make sure that we know exactly what hardware and software employees
are currently using and if they have any unique needs before we decide what to order for the upgrade.
This task will involve reviewing information from the current database, producing reports that list each
department’s employees and location, and updating the data after performing the physical inventory and
receiving inputs from department managers. Our project sponsor will send a notice to all department
managers to communicate the importance of this project and this particular task. In addition to general
hardware and software upgrades, the project sponsors will ask the department managers to provide
information for any unique requirements they might have that could affect the upgrades. This task also
includes updating the inventory data for network hardware and software. After updating the inventory
database, we will send an e-mail to each department manager to verify the information and make
changes online as needed. Department managers will be responsible for ensuring that their people are
available and cooperative during the physical inventory. Completing this task is dependent on WBS Item
Number 2.1, Perform Physical Inventory, and must precede WBS Item Number 3.0, Acquire Hardware
and Software.
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Each WBS item must be documented in a WBS dictionary to ensure accurate
understanding of the scope of work included and not included in that item.
The WBS must be a flexible tool to accommodate inevitable changes while
properly maintaining control of the work content in the project according to
the scope statement.9
5.6 VALIDATING SCOPE
It is difficult to create a good project scope statement and WBS for a project. It is even
more difficult, especially on IT projects, to verify the project scope and minimize scope
changes. Some project teams know from the start that the scope is very unclear and that
they must work closely with the project customer to design and produce various deliver-
ables. In this case, the project team must develop a process for scope validation that meets
unique project needs. Careful procedures must be developed to ensure that customers are
getting what they want and that the project team has enough time and money to produce
the desired products and services.
Even when the project scope is fairly well defined, many IT projects suffer from scope
creep—the tendency for project scope to keep getting bigger and bigger. There are many
horror stories about IT projects failing due to problems such as scope creep, including a
few classic examples in the following What Went Wrong? feature. For this reason, it is very
important to verify the project scope with users throughout the life of the project and de-
velop a process for controlling scope changes.
Scope creep can also be a good thing, if managed well. Later in this chapter, you can
see how Northwest Airlines encouraged scope changes on its ResNet project and managed
them well.
W H A T W E N T W R O N G ?
A project scope that is too broad and grandiose can cause severe problems. Scope creep
and an overemphasis on technology for technology’s sake resulted in the bankruptcy of a
large pharmaceutical firm, Texas-based FoxMeyer Drug. In 1994, the CIO was pushing for
a $65 million system to manage the company’s critical operations. He did not believe in
keeping things simple, however. The company spent nearly $10 million on state-of-the-
art hardware and software and contracted the management of the project to a prestigious
(and expensive) consulting firm. The project included building an $18 million robotic
warehouse, which looked like something out of a science fiction movie, according to in-
siders. The scope of the project kept getting bigger and more impractical. The elaborate
warehouse was not ready on time, and the new system generated erroneous orders that
cost FoxMeyer Drug more than $15 million in unrecovered excess shipments. In July
1996, the company took a $34 million charge for its fourth fiscal quarter, and by August
of that year, FoxMeyer Drug filed for bankruptcy.10
Another classic example of scope creep comes from McDonald’s Restaurants. In
2001, the fast-food chain initiated a project to create an intranet that would connect
its headquarters with all of its restaurants and provide detailed operational information
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Scope validation involves formal acceptance of the completed project deliverables.
This acceptance is often achieved by a customer inspection and then sign-off on key deliv-
erables. To receive formal acceptance of the project scope, the project team must develop
clear documentation of the project’s products and procedures to evaluate whether they
were completed correctly and satisfactorily. Recall from Chapter 4 that configuration
management specialists identify and document the functional and physical characteristics
of the project’s products, record and report the changes, and audit the products to verify
conformance to requirements. To minimize scope changes, it is crucial to do a good job of
configuration management and validating project scope.
The scope management plan, scope baseline, requirements documentation, require-
ments traceability matrix, validated deliverables, and work performance data are the main
inputs for scope validation. The main tools for performing scope validation are inspection
and group decision-making techniques. The customer, sponsor, or user inspects the work
after it is delivered and decides if it meets requirements. The main outputs of scope vali-
dation are accepted deliverables, change requests, work performance information, and
project documents updates. For example, suppose that Kim’s team members deliver up-
graded computers to users as part of the IT upgrade project. Several users might complain
because the computers did not include special keyboards they need for medical reasons.
Appropriate people would review this change request and take appropriate corrective ac-
tion, such as getting sponsor approval for purchasing the special keyboards.
in real time. For example, headquarters would know if sales were slowing or if the grill
temperature was correct in every single store—all 30,000 of them in more than 120
countries. McDonald’s would not divulge detailed information, but they admitted that the
project was too large in scale and scope. After spending $170 million on consultants and
initial implementation planning, McDonald’s realized that the project was too much to
handle and terminated it.11
Another major scope problem on IT projects is a lack of user involvement. A prime
example occurred in the late 1980s at Northrop Grumman, which specializes in defense
electronics, IT, advanced aircraft, shipbuilding, and space technology. An IT project team
there became convinced that it should automate the review and approval process of gov-
ernment proposals. The team implemented a powerful workflow system to manage the
whole process. Unfortunately, the end users of the system were aerospace engineers who
preferred to work in a more casual, ad hoc fashion. They dubbed the system “Naziware”
and refused to use it. This example illustrates an IT project that wasted millions of dol-
lars developing a system that was not in touch with the way end users did their work.12
Failing to follow good project management processes and use off-the-shelf software also
results in scope problems. 21st Century Insurance Group in Woodland Hills, California,
paid Computer Sciences Corporation $100 million to develop a system for managing
business applications, including managing insurance policies, billing, claims, and cus-
tomer service. After five years, the system was still in development and supported less
than 2 percent of the company’s business. Joshua Greenbaum, an analyst at Enterprise
Applications Consulting, called the project a “huge disaster” and questioned the insur-
ance company’s ability “to manage a process that is pretty well known these days. … I’m
surprised that there wasn’t some way to build what they needed using off-the-shelf com-
ponents and lower their risk.”13
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

G L O B A L I S S U E S
Many countries have had difficulties controlling the scope of large projects, especially
those that involve advanced technologies and many different users. For example, the
state government of Victoria, Australia, introduced a public transportation smart card,
called myki, in 2010. Public Transport Victoria’s description of the card included the fol-
lowing information: “Many cities around the world have public transport smart cards.
myki has been designed to fit our State’s unique needs. myki users enjoy an integrated
ticketing system that works across the state on trains, trams and buses.”14
Unfortunately, there were many problems in developing and implementing the smart
cards. The $1.35 billion system became valid on all forms of Melbourne public transporta-
tion in July 2010, three years and five months after it was meant to replace the Metcard.
Users’ initial reactions to the myki smart card were mixed, with several reports of myki
readers not working on trams. Many skeptics said they would wait until problems were
fixed before trying the new system.15 Many articles described problems with the myki
card, revealing obvious difficulty in validating the scope of this high-visibility project. The
Public Transport Users Association (PTUA) compiled a long list of problems with the new
card and suggested that people stick to using the old card for a while. Clearly, the new
system did not meet user requirements and had major flaws. In January 2012, over
18 months after the myki rollout, 70 percent of users still used the old Metcard. The gov-
ernment decided to keep myki in June 2011 after estimating that it would cost taxpayers
more than $1 billion to scrap the troubled system. The Metcard was planned to be phased
out for good by the end of 2012. PTUA president Daniel Bowen was not certain that the
transition would go smoothly. “To a certain extent it makes sense to bring people across
(to myki) because you can’t have two systems running at the same time forever. … Once
you get the majority of people using myki though, they’d better make sure it’s humming,
otherwise there could be chaos.”16 Myki continued to make headlines in 2015, but not in
a good way. “Two years after myki became the only ticket in town, frustrated commuters
say the system is still riddled with issues.”17
5.7 CONTROLLING SCOPE
As you learned in Chapter 4 when you studied integrated change control, change is
inevitable on projects, especially changes to the scope of IT projects. Scope control
involves managing changes to the project scope while keeping project goals and business
strategy in mind. Users often are not sure how they want screens to look or what
functionality they will need to improve business performance. Developers are not ex-
actly sure how to interpret user requirements, and they also have to deal with constantly
changing technologies.
The goal of scope control is to influence the factors that cause scope changes, to en-
sure that changes are processed according to procedures developed as part of integrated
change control, and to manage changes when they occur. You cannot do a good job of
controlling scope if you do not first do a good job of collecting requirements, defining
scope, and validating scope. How can you prevent scope creep when you have not agreed
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

on the work to be performed and your sponsor has not validated that the proposed work
is acceptable? You also need to develop a process for soliciting and monitoring changes to
project scope. Stakeholders should be encouraged to suggest changes that will benefit the
overall project and discouraged from suggesting unnecessary changes.
The project management plan, requirements documentation, requirements traceabil-
ity matrix, work performance data, and organizational process assets are the main inputs
to scope control. An important tool for performing scope control is variance analysis.
Variance is the difference between planned and actual performance. For example, if a
supplier was supposed to deliver five special keyboards and you received only four, the
variance would be one keyboard. The outputs of scope control include work performance
information, change requests, project management plan updates, project documents up-
dates, and organizational process assets updates.
Table 1-2 in Chapter 1 lists the top 10 factors that help IT projects succeed. Four of
these 10 factors are related to scope validation and control: user involvement, executive
support, clear business objectives, and optimizing scope. To avoid project failures, there-
fore, it is crucial for IT project managers and their teams to improve user input and execu-
tive support and reduce incomplete and changing requirements.
The following sections provide more suggestions for improving scope management on
IT projects.
5.7a Suggestions for Improving User Input
Lack of user input leads to problems with managing scope creep and controlling change.
How can you manage this important issue? The following suggestions can help a project
team improve user input:
Develop a good project selection process for IT projects. Insist that all projects
have a sponsor from the user organization. The sponsor should not work in the IT
department, nor should the sponsor be the project manager. Project information,
including the project charter, project management plan, project scope statement,
WBS, and WBS dictionary, should be easily available in the organization. Making
basic project information available will help avoid duplication of effort and ensure
that the most important projects are the ones on which people are working.
Have users on the project team. Some organizations require project managers
to come from the business area of the project instead of the IT group. Some
organizations assign co-project managers to IT projects, one from IT and one
from the main business group. Users should be assigned full-time to large IT
projects and part-time to smaller projects. A key success factor in Northwest
Airlines’ ResNet project was training reservation agents—the users—how to
write programming code for their new reservation system. (See the compan-
ion website for this text to read the entire case study for the ResNet project.)
Because the sales agents had intimate knowledge of the business, they pro-
vided excellent input and actually created most of the software.
Have regular meetings with defined agendas. The idea of meeting regularly
sounds obvious, but many IT projects fail because the project team members
do not have regular interaction with users. They assume that they under-
stand what users need without getting direct feedback. To encourage this in-
teraction, users should sign off on key deliverables presented at meetings.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Deliver something to project users and sponsors on a regular basis. If the
delivered product is hardware or software, make sure it works first.
Do not promise to deliver what the team cannot deliver in a particular time
frame. Make sure the project schedule allows enough time to produce the
deliverables.
Locate users with the developers. People often get to know each other better
by being in close proximity. If the users cannot be physically moved to be
near developers during the entire project, they should set aside certain days
to work in the same location.
5.7b Suggestions for Reducing Incomplete and Changing Requirements
Some requirement changes are expected on IT projects, but many projects have too many
changes to their requirements, especially during later stages of the project life cycle when
it is more difficult to implement changes. The following suggestions can help improve the
requirements process:
Develop and follow a requirements management process that includes proce-
dures for determining initial requirements.
Employ techniques such as prototyping, use case modeling, and Joint
Application Design to understand user requirements thoroughly. Prototyping
involves developing a working replica of the system or some aspect of the sys-
tem. These working replicas may be throwaways or an incremental compo-
nent of the deliverable system. Prototyping is an effective tool for gaining an
understanding of requirements, determining the feasibility of requirements,
and resolving user interface uncertainties. Use case modeling is a process
for identifying and modeling business events, who initiated them, and how
the system should respond to them. It is an effective tool for understanding
requirements of information systems. Joint Application Design (JAD) uses
highly organized and intensive workshops to bring together project stake-
holders—the sponsor, users, business analysts, programmers, and so on—to
jointly define and design information systems. These techniques also help us-
ers become more active in defining system requirements. Consult a systems
analysis and design text for details on these techniques.
Put all requirements in writing and keep them current and readily available.
Several tools are available to automate this function. For example, a type
of software called a requirements management tool aids in capturing and
maintaining requirements information, provides immediate access to the
information, and assists in establishing necessary relationships between re-
quirements and information created by other tools.
Create a requirements management database for documenting and control-
ling requirements. Computer Aided Software Engineering (CASE) tools or
other technologies can assist in maintaining a repository for project data. A
CASE tool’s database can also be used to document and control requirements.
Provide adequate testing to verify that the project’s products perform as ex-
pected. Conduct testing throughout the project life cycle. Chapter 8, Project
Quality Management, includes more information on testing.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Use a process for reviewing requested requirements changes from a systems
perspective. For example, ensure that project scope changes include associ-
ated cost and schedule changes. Require approval via signatures of appropri-
ate stakeholders. It is crucial for the project manager to lead the team in its
focus on achieving approved scope goals and not getting sidetracked into
doing additional work. For example, in his book Alpha Project Managers,
Andy Crowe tried to uncover what the best or “alpha” project managers do
differently from other project managers. One of these alpha project managers
explained how he learned an important lesson about scope control:
Toward the end of some projects I’ve worked on, the managers made
their teams work these really long hours. After the second or third time
this happened, I just assumed that this was the way things worked. Then
I got to work with a manager who planned everything out really well and
ran the team at a good pace the whole time, and we kept on schedule.
When the customer found out that things were on schedule, he kept try-
ing to increase the scope, but we had a good manager this time, and she
wouldn’t let him do it without adjusting the baselines. That was the first
time I was on a project that finished everything on time and on budget,
and I was amazed at how easy she made it look.18
Emphasize completion dates. For example, a project manager at Farmland
Industries, Inc. in Kansas City, Missouri, kept her 15-month, $7 million integrated
supply-chain project on track by setting the project deadline. She said, “May 1
was the drop-dead date, and everything else was backed into it. Users would come
to us and say they wanted something, and we’d ask them what they wanted to
give up to get it. Sticking to the date is how we managed scope creep.”19
Allocate resources specifically for handling change requests. For example,
Peeter Kivestu and his ResNet team at Northwest Airlines knew that users
would request enhancements to the reservations system they were developing.
They provided a special function key on the ResNet screen for users to submit
their requests, and the project included three full-time programmers to handle
these requests. Users made over 11,000 enhancement requests. The managers
who sponsored the four main software applications had to prioritize the soft-
ware enhancement requests and decide as a group what changes to approve.
The three programmers then implemented as many items as they could, in
priority order, given the time they had. Although they only implemented
38 percent of the requested enhancements, they were the most important
ones, and the users were very satisfied with the system and process.
5.8 USING SOFTWARE TO ASSIST IN
PROJECT SCOPE MANAGEMENT
Project managers and their teams can use several types of software to assist in project
scope management. As shown in several of the figures and tables in this chapter, you
can use word-processing software to create scope-related documents, and most people
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

use spreadsheet or presentation software to develop various charts, graphs, and ma-
trixes related to scope management. Mind-mapping software can be useful in develop-
ing a WBS. Project stakeholders also transmit project scope management information
using various types of communication software such as e-mail and assorted web-based
applications.
Project management software helps you develop a WBS, which serves as a basis
for creating Gantt charts, assigning resources, allocating costs, and performing other
tasks. You can also use the templates that come with various project management
software products to help you create a WBS for your project. (See the section on proj-
ect scope management in Appendix A for detailed information on using Project 2013,
and see the companion website for information on templates related to project scope
management.)
You can also use many types of specialized software to assist in project scope
management. Many IT projects use special software for requirements management,
prototyping, modeling, and other scope-related work. Because scope is such a crucial
part of project management, many software products are available to assist in managing
project scope. For example, Gartner estimates that the market for requirements defini-
tion and management tools was $280 million in 2014 and growing over 3 percent annu-
ally. New tools focus on improving collaboration and speed to better address mass market
needs.20
Project scope management is very important, especially on IT projects. After selecting
projects, organizations must plan scope management, collect the requirements and define
the scope of the work, break down the work into manageable pieces, validate the scope
with project stakeholders, and manage changes to project scope. Using the basic project
management concepts, tools, and techniques discussed in this chapter can help you
manage project scope successfully.
C A S E W R A P – U P
Kim Nguyen reviewed guidelines for creating WBSs that were provided by her company
and other sources. She had a meeting with the three team leaders for her project to get
their input on how to proceed. They reviewed several sample documents and decided to
have major groupings for their project based on updating the inventory database, acquir-
ing the necessary hardware and software, installing the hardware and software, and per-
forming project management. After they decided on a basic approach, Kim led a meeting
with the entire project team of 12 people, with some attending virtually. She reviewed
the project charter and stakeholder register, described the basic approach they would
use to collect requirements and define the project scope, and reviewed sample WBSs.
Kim opened the floor for questions, which she answered confidently. She then let each
team leader work with his or her people to start writing the detailed scope statement and
their sections of the WBS and WBS dictionary. Everyone participated in the meeting,
sharing their expertise and openly asking questions. Kim could see that the project was
off to a good start.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

212
Chapter 5
Chapter Summary
Project scope management includes the processes to ensure that the project addresses all the work
required to complete the project successfully. The main processes include planning scope management,
collecting requirements, defining scope, creating the WBS, validating scope, and controlling scope.
The first step in project scope management is planning scope management. The project
team reviews information and uses expert judgment and meetings to help create a scope
management plan and requirements management plan.
The next step is collecting requirements, a crucial part of many IT projects. It is important to
review the project charter and meet with key stakeholders listed in the stakeholder register when
collecting requirements. The main outputs of this process are requirements documentation and a
requirements traceability matrix.
A project scope statement is created in the scope definition process. This document often
includes a product scope description, product user acceptance criteria, detailed information on all pro-
ject deliverables, and information on project boundaries, constraints, and assumptions. There are often
several versions of the project scope statement to keep scope information detailed and up to date.
A work breakdown structure (WBS) is a deliverable-oriented grouping of the work involved in
a project that defines its total scope. The WBS forms the basis for planning and managing project
schedules, costs, resources, and changes. You cannot use project management software without
first creating a good WBS. A WBS dictionary is a document that provides detailed information
about each WBS item. A good WBS is often difficult to create because of the complexity of the
project. There are several approaches for developing a WBS, including using guidelines, the
analogy approach, the top-down approach, the bottom-up approach, and mind mapping.
Validating scope involves formal acceptance of the completed project deliverables. Control-
ling scope involves controlling changes to the project scope.
Poor project scope management is one of the key reasons projects fail. For IT projects, it is
important for good project scope management to have strong user involvement, executive sup-
port, a clear statement of requirements, and a process for managing scope changes.
Many software products are available to assist in project scope management. The WBS is a key
concept in properly using project management software because it provides the basis for entering tasks.
Quick Quiz
1. _______ refer(s) to all the work involved in creating the products of the project and the pro-
cesses used to create them.
a. Deliverables
b. Milestones
c. Scope
d. Product development
2. Which tool or technique for collecting requirements is often the most expensive and time
consuming?
a. interviews
b. focus groups
c. surveys
d. observation
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

213
Project Scope Management
3. A _______ is a deliverable-oriented grouping of the work involved in a project that defines its
total scope.
a. scope statement
b. WBS
c. WBS dictionary
d. work package
4. What approach to developing a WBS involves writing down or drawing ideas in a nonlinear format?
a. top-down
b. bottom-up
c. analogy
d. mind mapping
5. Assume that you have a project with major categories called planning, analysis, design, and
testing. What level of the WBS would these items fall under?
a. 0
b. 1
c. 2
d. 3
6. Which of the following is not a best practice that can help in avoiding scope problems on
IT projects?
a. Keep the scope realistic.
b. Use off-the-shelf hardware and software whenever possible.
c. Follow good project management processes.
d. Don’t involve too many users in scope management.
7. Why did McDonald’s terminate a large project after spending $170 million on it?
a. The company found a better technology.
b. The company decided to outsource the work.
c. The scope was too much to handle.
d. The government requirement that prompted the project was repealed.
8. Scope _______ is often achieved by a customer inspection and then sign-off on key
deliverables.
a. acceptance
b. validation
c. completion
d. close-out
9. Which of the following is not a suggestion for improving user input?
a. Develop a good project selection process for IT projects.
b. Have users on the project team.
c. Co-locate users with developers.
d. Only have meetings as needed, not on a regular basis.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

214
Chapter 5
10. Project management software helps you develop a _______, which serves as a basis for
creating Gantt charts, assigning resources, and allocating costs.
a. project plan
b. schedule
c. WBS
d. deliverable
Quick Quiz Answers
1. c; 2. a; 3. b; 4. d; 5. c; 6. d; 7. c; 8. b; 9. d; 10. c
Discussion Questions
1. What is involved in project scope management, and why is good project scope management
so important on IT projects?
2. What is involved in collecting requirements for a project? Why is it often difficult to do?
3. Discuss the process of defining project scope in more detail as a project progresses,
going from information in a project charter to a project scope statement, WBS, and WBS
dictionary.
4. Describe different ways to develop a WBS and explain why it is often so difficult to do.
5. What is the main technique used for validating scope? Give an example of scope validation
on a project.
6. Using examples in this book or online, describe a project that suffered from scope creep.
Could it have been avoided? How? Can scope creep be a good thing? When? What can
organizations do to successfully manage inevitable changes in scope that are good for
business?
7. Why do you need a good WBS to use project management software? What other types of
software can you use to assist in project scope management?
Exercises
1. You are working on a project to develop a new or enhanced system to help people at your
college, university, or organization to find jobs. The system must be tailored to your student
or work population and be very easy to use. Write a short paper describing how you would
collect requirements for this system, and include at least five requirements in a requirements
traceability matrix.
2. Read the report cited in the chapter called PMI’s Pulse of the Profession: Requirements
Management—A Core Competency for Project and Program Success. Find one or two
other reports on requirements management written in the past year. Summarize the findings
of the reports and your opinion on the topic.
3. Use MindView Business software to develop a WBS in chart form by creating a new file or
map in Top Down view. You can download a 30-day trial of MindView Business from
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

215
Project Scope Management
www.matchware.com/itpm. (The chart should be similar to an organizational chart—see
the sample at the top of Figure 5-4). Assume that the Level 1 category is called Software
Project, and that the Level 2 categories are Initiating, Planning, Executing, Monitoring and
Controlling, and Closing. Under the Executing section, include Level 3 categories of Analy-
sis, Design, Prototyping, Testing, Implementation, and Support. Assume that the Support
category includes Level 4 items for Training, Documentation, User Support, and Enhance-
ments. Print the WBS in chart form. Show the same information in a Gantt chart by selecting
View from the menu bar in MindView Business, then Gantt. Widen the Task Name column
and select Number Scheme from the menu bar to add a numbering scheme. Save your file
and then print just the Task Name column of the Gantt chart view by taking a screen shot
and cropping the screen. Your results should resemble those in Figure 5-9.
4. Create the same WBS described in Exercise 3 using Microsoft Project 2013 and indenting
categories appropriately. Use the outline numbering feature to display the outline numbers,
or enter the numbers manually. Notice that Project 2013 uses PMI’s standard numbering
scheme, but MindView does not. You may want to enter the numbers to ensure that they ap-
pear as desired and are displayed in all reports. Microsoft Project does not include automatic
FIGURE 5-9 Top-down WBS and Gantt chart created in MindView Business Software
Source: MatchWare’s MindView 4 Business Edition
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

216
Chapter 5
numbers in reports. Do not enter any durations or dependencies. See Appendix A or Project
2013’s Help for instructions on creating a WBS. Print the resulting Gantt chart on one page,
and be sure to display the entire Task Name column.
5. Using the file you created in MindView for Exercise 3, export the WBS into Project 2013.
Open the file, select the MindView icon in the upper-left portion of the toolbar, select Export,
select Microsoft Project, and name the file. The file opens in Project 2013. Make adjustments
as needed and then print the Gantt chart from Project 2013.
6. Create a WBS for one of the following projects:
Introducing self-checkout registers at your school’s bookstore
Providing a new Internet cafe onsite at your organization
Developing an app that you and a friend will create and sell online within three months
Earning your CAPM or PMP certification
Decide on all of the Level 2 categories for the WBS. Use your choice of software to create a
WBS in chart form and as tasks in a Gantt chart. Do not enter any durations or dependen-
cies. Be sure to include all of the deliverables and work required for the project. Make notes
of questions you had while completing this exercise.
7. Review three different template files from Microsoft Project 2013, MindView, or any other
project management software tool. What do you think about the WBSs? Write a short pa-
per summarizing your analysis, and provide at least three suggestions for improving one of
the WBSs.
8. Research the benefits of and requirements for earning a certification in business analysis,
as described in the What Went Right feature in this chapter. Summarize your findings in a
short paper.
Running Case
You have been selected as the project manager for the Global Treps project. You helped to run
a local shark tank like event at your college last year as part of a class project, so you have a
general idea of what is involved. The schedule goal is six months, and the budget is $120,000.
Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your
strengths are your organizational and leadership skills.
You are a senior, live on-campus, and get free room and board by being a resident assis-
tant in your dorm. Bobby, a computer whiz who funded a lot of his college expenses by build-
ing websites, will be your main technical guy on the project. He goes to your college and lives
off-campus. Three other people will form your core project team: Kim, a new college grad now
working for a non-profit group in Vietnam; Ashok, a business student in India; and Alfreda, a
student in the U.S. planning to visit her home town in Ethiopia for two months in a few months.
You will hold most meetings virtually, but you can meet face-to-face with Bobby and Dr. K. as
needed. You have all known each other for at least a year and are excited to make this project a
success.
You and your team members will do the work part-time while you finish school or work at
other jobs, but you can use up to $50,000 total to pay yourselves. You estimate that you will need
another $30,000 for travel expenses, $20,000 for hardware and software, and the other $20,000
will go toward organizing events, consultants, legal/business fees, etc.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

217
Project Scope Management
Your goal is to develop a fully functioning website and test it by holding four events in four
different countries. You’ll make improvements to the site after those events, develop plans to
scale it up, and recommend how to transition the project results into a successful business.
Recall from Chapter 4 that this system would include the following capabilities:
Provide guidelines and templates for running a shark tank type event
Accept donations from potential investors targeted toward specific schools or organizations
wishing to host an event (similar to the popular DonorsChoose.org site, where people can
fund teachers’ requests)
Accept ideas for needed new products or services
Provide the ability for organizations to create their own custom site to solicit local partici-
pants and sharks, accept applications, and promote the winners as well as losers.
Note that you decided not to include the idea of providing an online version of the event as part
of the initial project as your sponsor and team decided that physical events would be most ef-
fective. You have also decided to limit the scope of this first project to provide the ability for 20
organizations to create their own custom websites. Your team members will screen the organiza-
tions and assist people in using the site to plan their events.
You plan to hold four shark tank like events within four months, using your team members
abroad to help organize and run those events, plus one at your college. Your semester has just
started, so you plan to hold your event at the end of the term. The project will fund refreshments
for the events and prizes for the winners, with a budget of $1,000 for each event. You don’t think
you’ll get any donations via the new website before these events, but you’ll try to have it set up to
accept donations by the last month.
You will create some short videos to show people how to use the site and provide sugges-
tions for holding the events.
After testing the site and getting customer feedback, you will make some changes and docu-
ment recommendations for a follow-on project. You will also create a business plan recommend-
ing how to transition this project into a real business that can make a profit after two years.
Assume that you would pay for a new website and account through an online provider. Bobby
would do most of the customization/programming for the site, but you would consider outsourcing
or purchasing services to provide some of the capabilities like accepting donations and developing
the short videos on the site. You would also buy a new laptop and Internet access for your three
team members abroad so that they could share information with their contacts in those countries.
You and Dr. K. want to attend all of the events as part of the project, and you might include a
full face-to-face meeting with the whole team if possible.
Tasks
1. Document your approach for collecting requirements for the project. Include at least five
technical requirements and five non-technical requirements in a requirements traceability
matrix. Also develop a list of at least five questions you would like to ask the project sponsor.
Let your instructor answer them for you, if applicable.
2. Develop a first version of a project scope statement for the project. Use the template pro-
vided on the companion website for this text and the example in Chapter 3 as guides. Be as
specific as possible in describing product characteristics and requirements, as well as all of
the project’s deliverables. Be sure to include the Global Treps website, four shark tank like
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

218
Chapter 5
events, a business plan, and outsourced items (laptops, donation acceptance, video cre-
ation, etc.) as part of the project scope.
3. Develop a work breakdown structure for the project. Break down the work to Level 3 or Level 4,
as appropriate. Use the template on the companion website and samples in this text as guides.
Print the WBS in list form. Be sure the WBS is based on the project charter (created for the
Chapter 4 Running Case), the project scope statement created in Task 2 above, and other
relevant information.
4. Use the WBS you developed in Task 3 to begin creating a Gantt chart using your choice of
software. Do not enter any durations or dependencies. Print the resulting Gantt chart on one
page, and be sure to display the entire Task Name column.
5. Develop a strategy for scope validation and change control for this project. Write a short
paper summarizing key points of the strategy.
Key Terms
analogy approach p.200
benchmarking p.189
bottom-up approach p.201
decomposition p.194
deliverable p.184
Joint Application Design (JAD) p.209
project scope management p.184
project scope statement p.191
prototyping p.209
requirement p.186
requirements management plan p.187
requirements traceability matrix (RTM) p.191
scope p.184
scope baseline p.194
scope creep p.205
scope validation p.206
top-down approach p.201
use case modeling p.209
variance p.208
WBS dictionary p.203
work breakdown structure (WBS) p.194
work package p.196
End Notes
1 Karl Wiegers, Software Requirements, Second edition (Redmond, WA: Microsoft Press, 2003), p. 7.
2 Amy Hillman, “The Rise in Business-Analytics Degrees,” Huffington Post (May 13, 2014).
3 Project Management Institute, Pulse of the Profession®: Requirements Management
( August 2014).
4 Craig Smith, “Interview and Book Review: How Google Tests Software,” InfoQ.com
(September 11, 2012).
5 John Simpson, “2011: The State of Requirements Management” (2011).
6 Project Management Institute, Pulse of the Profession: Requirements Management —
A Core Competency for Project and Program Success (August 2014).
7 This structure is based on a sample Project 98 file. See www.microsoft.com for additional
template files.
8 Mindjet Visual Thinking, “About Mind Maps,” Mindjet.com (2002).
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

219
Project Scope Management
9 David I. Cleland, Project Management: Strategic Design and Implementation, Second edition
(New York: McGraw-Hill, 1994).
10 Geoffrey James, “Information Technology Fiascoes … and How to Avoid Them,” Datamation
(November 1997).
11 Paul McDougall, “8 Expensive IT Blunders,” InformationWeek (October 16, 2006).
12 Geoffrey James, “Information Technology Fiascoes … and How to Avoid Them,” Datamation
(November 1997).
13 Marc L. Songini, “21st Century Insurance Apps in Limbo Despite $100M Investment,”
Computerworld (December 6, 2002).
14 www.myki.com.au/About-myki/What-is-myki (accessed March 1, 2012).
15 Megan Levy, “Peak-Hour Test for myki Smartcard System,” The Age (July 26, 2010).
16 Greg Thom, “When It Comes to myki, Like It or Lump It,” Herald Sun (January 20, 2012).
17 Alex White, “The $1.5 Billion myki Debacle Labor Doesn’t Want to Know About,” Herald Sun
(January 3, 2015).
18 Andy Crowe, Alpha Project Managers: What the Top 2% Know That Everyone Else Does
Not (Kennesaw, GA: Velociteach Press, 2006), pp. 46–47.
19 Julia King, “IS Reins in Runaway Projects,” Computerworld (September 24, 1997).
20 Thomas E. Murphy, “Market Guide for Software Requirements Definition and Management
Solutions,” Gartner (October 7, 2014).
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R 6
PROJECT TIME MANAGEMENT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

222
6.1 THE IMPORTANCE OF PROJECT SCHEDULES
Managers often cite the need to deliver projects on time as one of their biggest challenges
and the main cause of conflict. Perhaps part of the reason that schedule problems are so
common is that time is easily measured and remembered. You can debate scope and cost
overruns and make actual numbers appear closer to estimates, but once a project schedule
is set, people remember the projected completion date, and anyone can quickly estimate
schedule performance by subtracting the original time estimate from how long it really
took to complete the project. People often compare planned and actual project completion
times without taking into account the approved changes in the project. Time is the variable
that has the least amount of flexibility. Time passes no matter what happens on a project.
Individual work styles and cultural differences may also cause schedule conflicts. For
example, you will learn in Chapter 9, Project Human Resource Management, about the
Myers Briggs Type Indicator. One dimension of this team-building tool deals with attitudes
toward structure and deadlines. Some people prefer detailed schedules and emphasize task
completion. Others prefer to keep things open and flexible. Different cultures and even
entire countries have different attitudes about schedules. For example, in some countries
businesses close for several hours every afternoon to have siestas. Countries may have dif-
ferent holidays, which means not much work will be done at certain times of the year. Cul-
tures may also have different perceptions of work ethic—some may value hard work and
strict schedules while others may value the ability to remain relaxed and flexible.
With all the possibilities for schedule conflicts, it is important for project managers to
use good project time management. Project time management, simply defined, involves
O P E N I N G C A S E
Sue Johnson was the project manager for a consulting company contracted to provide
a new online registration system at a local college in nine months or less. This system
had to be operational by May 1 so students could use it to register for the fall semester.
Her company’s contract had a stiff penalty clause if the system was not ready by then,
and Sue and her team would get nice bonuses for doing a good job on this project and
meeting the schedule. Sue knew that it was her responsibility to meet the schedule and
manage scope, cost, and quality expectations. She and her team developed a detailed
schedule and network diagram to help organize the project.
Developing the schedule turned out to be the easy part; keeping the project on track
was more difficult. Managing personnel issues and resolving schedule conflicts were two
of the bigger challenges. Many of the college’s employees took unplanned vacations and
missed or rescheduled project review meetings. These changes made it difficult for the
project team to follow the planned schedule for the system because the team had to have
customer sign-off at various stages of the systems development life cycle. One senior
programmer on Sue’s project team quit, and she knew it would take extra time for a new
person to get up to speed, especially since the exiting programmer did a poor job docu-
menting how his code linked to other systems at the college. It was still early in the proj-
ect, but Sue knew they were falling behind. What could she do to meet the operational
date of May 1?
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Taurus

Taurus

Taurus

223
the processes required to ensure timely completion of a project. Seven main processes are
involved in project time management:
1. Planning schedule management involves determining the policies, proce-
dures, and documentation that will be used for planning, executing, and con-
trolling the project schedule. The main output of this process is a schedule
management plan.
2. Defining activities involves identifying the specific activities that the project
team members and stakeholders must perform to produce the project deliv-
erables. An activity or task is an element of work normally found on the work
breakdown structure (WBS) that has expected duration, cost, and resource
requirements. The main outputs of this process are an activity list, activity
attributes, a milestone list, and project management plan updates.
3. Sequencing activities involves identifying and documenting the relationships
between project activities. The main outputs of this process include project
schedule network diagrams and project documents updates.
M E D I A S N A P S H O T
In contrast to the 2002 Salt Lake City Winter Olympic Games (see Chapter 4’s Media
Snapshot), planning and scheduling were not well implemented for the 2004 Athens
Summer Olympic Games or the 2014 Sochi Winter Olympic Games.
Many articles written before the Athens opening ceremonies predicted that the facili-
ties would not be ready in time. “With just 162 days to go to the opening of the Athens
Olympics, the Greek capital is still not ready for the expected onslaught. … By now 22
of the 30 Olympic projects were supposed to be finished. This week the Athens Olympic
Committee proudly announced 19 venues would be finished by the end of next month.
That’s a long way off target.”1 However, many people were pleasantly surprised by the
amazing opening ceremonies, beautiful new buildings, and state-of-the-art security and
transportation systems in Athens. For example, traffic flow, considered a major pre-Games
hurdle, was superb. One spectator at the games commented on the prediction that the fa-
cilities would not be ready in time: “Athens proved them all wrong. … It has never looked
better.”2 The Greeks even made fun of critics by having construction workers pretend that
they were still working as the ceremonies began. Unfortunately, the Greek government suf-
fered a huge financial deficit because the games cost more than twice the planned budget.
The 2014 Winter Olympic Games in Sochi, Russia, suffered even greater financial
losses. Originally budgeted at US$12 billion, final costs reached over US$51 billion, mak-
ing it the most expensive games in history. Unlike Greece’s humorous response to chal-
lenges at the Athens games, Russian citizens were much more serious. Although in 2006,
86 percent of Sochi residents supported the games, by 2013 only 40 percent supported
them. Russian citizens, especially those in Sochi, understood the negative impacts of
hosting the games when they heard about the poor planning and huge cost overruns.
“… the Sochi Olympics will continue to be a burden for the Russian state, with expenses
for operation, maintenance and foregone interest and tax revenue in the order of USD
1.2 billion per year. The event also did not manage to improve the image of Russia in the
world and among the domestic population support dropped over the seven years of its
implementation, most notably among the local population.”3
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

224
4. Estimating activity resources involves estimating how many resources—
people, equipment, and materials—a project team should use to perform
project activities. The main outputs of this process are activity resource
requirements, a resource breakdown structure, and project documents updates.
5. Estimating activity durations involves estimating the number of work peri-
ods that are needed to complete individual activities. Outputs include activity
duration estimates and project documents updates.
6. Developing the schedule involves analyzing activity sequences, activity
resource estimates, and activity duration estimates to create the project sched-
ule. Outputs include a schedule baseline, project schedule, schedule data, project
calendars, project management plan updates, and project documents updates.
7. Controlling the schedule involves controlling and managing changes to the
project schedule. Outputs include work performance information, schedule
forecasts, change requests, project management plan updates, project docu-
ments updates, and organizational process assets updates.
Figure 6-1 summarizes these processes and outputs, showing when they occur in a
typical project.
Monitoring and Controlling
Process: Control schedule
Outputs: Work performance information, schedule forecasts, change
requests, project management plan updates, project documents
updates, organizational process assets updates
Project Start Project Finish
Planning
Process: Plan schedule management
Outputs: Schedule management plan
Process: Define activities
Outputs: Activity list, activity attributes, milestone list, project
management plan updates
Process: Sequence activities
Outputs: Project schedule network diagrams, project documents updates
Process: Estimate activity resources
Outputs: Activity resource requirements, resource breakdown structure,
project documents updates
Process: Estimate activity durations
Outputs: Activity duration estimates, project documents updates
Process: Develop schedule
Outputs: Schedule baseline, project schedule, schedule data, project calendars,
project management plan updates, project documents updates
FIGURE 6-1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

225
You can improve project time management by performing these processes and by
using some basic project management tools and techniques. Every manager is familiar
with some form of scheduling, but most managers have not used several of the tools and
techniques that are unique to project time management, such as Gantt charts, network
diagrams, and critical path analysis.
6.2 PLANNING SCHEDULE MANAGEMENT
The first step in project time management is planning how the schedule will be managed
throughout the life of the project. Project schedules grow out of the basic documents that
initiate a project. The project charter often mentions planned project start and end dates,
which serve as the starting points for a more detailed schedule. After reviewing the project
management plan, project charter, enterprise environmental factors, and organizational
process assets, the project team uses expert judgment, analytical techniques, and meet-
ings to develop the schedule management plan.
The schedule management plan, like the scope management plan, can be informal
and broad or formal and detailed, based on the needs of the project. In general, a schedule
management plan includes the following information:
Project schedule model development: Many projects include a schedule model,
which contains project activities with estimated durations, dependencies, and
other planning information that can be used to produce a project schedule. See
Appendix A for information on using Microsoft Project 2013 to create a schedule
model.
Level of accuracy and units of measure: This section discusses how accurate
schedule estimates should be and determines whether time is measured in
hours, days, or another unit.
Control thresholds: Variance thresholds, such as ±10%, are established for
monitoring schedule performance.
Rules of performance measurement: For example, if team members are
expected to track the percentage of work completed, this section specifies
how to determine the percentages.
Reporting formats: This section describes the format and frequency of sched-
ule reports required for the project.
Process descriptions: The schedule management plan also describes how all
of the schedule management processes will be performed.
6.3 DEFINING ACTIVITIES
You might think that all project work has been defined in enough detail after planning
scope management, but it is often necessary to describe activities in more detail as part
of schedule management. Defining activities involves identifying the specific actions that
will produce the project deliverables in enough detail to determine resource and schedule
estimates. The project team reviews the schedule management plan, scope baseline,
enterprise environmental factors, and organizational process assets to begin defining ac-
tivities. Outputs of this process include an activity list, activity attributes, a milestone list,
and project management plan updates.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

The activity list is a tabulation of activities to be included on a project schedule. The
list should include the activity name, an activity identifier or number, and a brief descrip-
tion of the activity. The activity attributes provide schedule-related information about
each activity, such as predecessors, successors, logical relationships, leads and lags, re-
source requirements, constraints, imposed dates, and assumptions related to the activity.
The activity list and activity attributes should agree with the WBS and WBS dictionary.
Information is added to the activity attributes as it becomes available; this information
includes logical relationships and resource requirements that are determined in later
processes. Many project teams use an automated system to keep track of activity-related
information.
A milestone on a project is a significant event that normally has no duration. It of-
ten takes several activities and a lot of work to complete a milestone, but the milestone
itself is a marker to help in identifying necessary activities. Milestones are also useful
tools for setting schedule goals and monitoring progress. For example, milestones on a
project like the one in the chapter’s opening case might include completion and cus-
tomer sign-off of documents, such as design documents and test plans; completion of
specific products, such as software modules or installation of new hardware; and comple-
tion of important process-related work, such as project review meetings and tests. Not
every deliverable or output created for a project is really a milestone. Milestones are the
most important and visible events. For example, in the context of child development,
parents and doctors check for milestones, such as a child first rolling over, sitting, crawl-
ing, walking, and talking. You will learn more about milestones later in this chapter.
Activity information is a required input to the other time management processes. You
cannot determine activity sequencing, resources, or durations, develop the schedule, or
control the schedule until you have a good understanding of project activities.
Recall the triple constraint of project management—balancing scope, time, and cost
goals—and note the order of these items. Ideally, the project team and key stakehold-
ers first define the project scope, then the time or schedule for the project, and then the
project’s cost. The order of these three items reflects the basic order of the processes in
project time management: defining activities (further defining the scope), sequencing
activities (further defining the time), and estimating activity resources and activity dura-
tions (further defining the time and cost). These project time management processes are
the basis for creating a project schedule.
The goal of defining activities is to ensure that the project team completely understands
all the work it must do as part of the project scope so they can start scheduling the work. For
example, a WBS item might be “Produce study report.” The project team must understand
what the item means before team members can make schedule-related decisions. How long
should the report be? Does it require a survey or extensive research to produce? What skill
level does the report writer need to have? Further defining the task will help the project team
determine how long it will take to do and who should do it.
The WBS is often dissected further as the project team members continue to define
the activities required for performing the work. For example, the task “Produce study
report” might be broken down into several subtasks describing the steps of producing the
report, such as developing a survey, administering the survey, analyzing the survey
results, performing research, writing a draft report, editing the report, and finally produc-
ing the report. This process of progressive elaboration, one of the project attributes listed
in Chapter 1, is sometimes called “rolling wave planning.”
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

227
As stated earlier, activities or tasks are elements of work performed during the course
of a project; they have expected durations, costs, and resource requirements. Defining
activities also results in supporting detail to document important product information as
well as assumptions and constraints related to specific activities. The project team should
review the activity list and activity attributes with project stakeholders before moving on
to the next step in project time management. If the team does not review these items with
project stakeholders, it could produce an unrealistic schedule and deliver unacceptable re-
sults. For example, if a project manager simply estimated that the “Produce study report”
task would take one day and then had an intern or trainee write a 10-page report to com-
plete that task, the result could be a furious customer who expected extensive research,
surveys, and a 100-page report. Clearly defining the work is crucial to all projects. If there
are misunderstandings about activities, requested changes may be required.
In the opening case of this chapter, Sue Johnson and her project team had a contract
and detailed specifications for the college’s new online registration system. They also had
to focus on meeting the May 1 date for delivering an operational system so the college
could start using the new system for the new semester’s registration. To develop a project
schedule, Sue and her team had to review the contract, detailed specifications, and de-
sired operational date, then create an activity list, activity attributes, and milestone list.
After developing more detailed definitions of project activities, Sue and her team would
review them with the customers to ensure that the team was on the right track.
W H A T W E N T W R O N G ?
At the U.S. Federal Bureau of Investigation (FBI), poor time management was one of the
reasons behind the failure of Trilogy, a “disastrous, unbelievably expensive piece of va-
porware, which was more than four years in the (un)making. The system was supposed
to enable FBI agents to integrate intelligence from isolated information silos within the
Bureau.”4 In May 2006, the Government Accounting Agency said that the Trilogy project
failed at its core mission of improving the FBI’s investigative abilities and was plagued
with missed milestones and escalating costs.
The FBI rushed to develop the new system beginning in 2001, in response to the
attacks on September 11. The need for new software was obvious to former FBI agent
David J. Williams, who recalls joining a roomful of agents shortly after 9/11 to help with
intelligence. Agents were wearing out the casters on their chairs by sliding back and forth
among 20 old computer terminals, many of which were attached to various databases
that contained different information.
Congressional hearings revealed numerous problems with the project. Its require-
ments were very loosely defined, there were many leadership changes throughout the
project, and several contracts had no scheduled milestones for completion or penalties if
work was late. The new system was finally completed in 2006 and cost more than $537
million—more than a year late and $200 million over budget.
The FBI replaced Trilogy with a new system called Sentinel and began training
employees to use it in May 2007.5 Unfortunately, history repeated itself as troubles
still loomed with Sentinel in 2012. According to the FBI’s original plan, Sentinel was
to be completed by December 2009 at an estimated cost of $425 million. The FBI later
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

228
increased the estimated cost to $451 million and extended the project completion date
twice, so that the project was now two years behind schedule. During a test exercise in
2011, the system experienced two outages, and the FBI determined that its current hard-
ware structure was inadequate. In 2014, several people complained that the system still
wasn’t working well. “You can’t find what you need most of the time, or you get junk you
don’t want, but other than that, the FBI’s long troubled, half-billion-dollar Sentinel com-
puterized file system is coming along just fine.”6
6.4 SEQUENCING ACTIVITIES
After defining project activities, the next step in project time management is sequencing
them or determining their dependencies. Inputs to the activity sequencing process include
the schedule management plan, activity list and attributes, project scope statement, mile-
stone list, and organizational process assets. The sequencing process involves evaluating
the reasons for dependencies and the different types of dependencies.
6.4a Dependencies
A dependency or relationship pertains to the sequencing of project activities or tasks.
For example, does a certain activity have to be finished before another can start? Can
the project team do several activities in parallel? Can some overlap? Determining these
relationships or dependencies among activities is crucial for developing and managing a
project schedule.
There are three basic reasons for identifying dependencies among project activities:
Mandatory dependencies are inherent in the nature of the work being per-
formed on a project. They are sometimes referred to as hard logic. For example,
you cannot test code until after the code is written.
Discretionary dependencies are defined by the project team. For example,
a project team might follow good practice and not start the detailed design
of a new information system until the users sign off on all of the analysis
work. Discretionary dependencies are sometimes referred to as soft logic
and should be used with care because they may limit later scheduling
options.
External dependencies involve relationships between project and non-proj-
ect activities. For example, the installation of a new operating system and
other software may depend on delivery of new hardware from an external
supplier. Even though delivery of the hardware may not be included in the
scope of the project, you should add an external dependency to it because
late delivery will affect the project schedule.
As with activity definition, it is important that project stakeholders work together
to define the activity dependencies in their project. If you do not define the sequence of
activities, you cannot use some of the most powerful scheduling tools available to project
managers: network diagrams and critical path analysis.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

229
6.4b Network Diagrams
Network diagrams are the preferred technique for showing activity sequencing. A network
diagram is a schematic display of the logical relationships among project activities and
their sequencing. Some people refer to network diagrams as project schedule network dia-
grams or PERT charts. PERT is described later in this chapter. Figure 6-2 shows a sample
network diagram for Project X.
Note: Assume all durations are in days; A=1 means Activity A has a
duration of 1 day.
86
7
52
3
4
A = 1
B = 2
C = 3
D = 4
E = 5
F = 4
G = 6
I = 2
H = 6
J = 3
A =
B
C =
1
FIGURE 6-2
Note the main elements on this network diagram. The letters A through J represent
activities with dependencies that are required to complete the project. These activities
come from the WBS and activity definition process described earlier. The arrows represent
the activity sequencing or relationships between tasks. For example, Activity A must be
done before Activity D, and Activity D must be done before Activity H.
The format of this network diagram uses the activity-on-arrow (AOA) approach or
the arrow diagramming method (ADM)—a network diagramming technique in which
activities are represented by arrows and connected at points called nodes to illustrate the
sequence of activities. A node is simply the starting and ending point of an activity. The
first node signifies the start of a project, and the last node represents the end.
Keep in mind that the network diagram represents activities that must be done to
complete the project. It is not a race to get from the first node to the last node. Every ac-
tivity on the network diagram must be completed in order to finish the project. Note also
that not every item on the WBS needs to be shown on the network diagram; only activities
with dependencies need to be shown. However, some people like to have start and end
milestones and to list every activity. It is a matter of preference. For large projects with
hundreds of activities, it might be simpler to include only activities with dependencies on
a network diagram. Sometimes it is enough to put summary tasks on a network diagram or
to break down the project into several smaller network diagrams.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Assuming that you have a list of the project activities and their start and finish nodes,
follow these steps to create an AOA network diagram:
1. Find all of the activities that start at Node 1. Draw their finish nodes, and draw ar-
rows between Node 1 and each of the finish nodes. Put the activity letter or name
on the associated arrow. If you have a duration estimate, write it next to the ac-
tivity letter or name, as shown in Figure 6-2. For example, A = 1 means that the
duration of Activity A is one day, week, or other standard unit of time. Be sure to
put arrowheads on all arrows to signify the direction of the relationships.
2. Continue drawing the network diagram, working from left to right. Look for
bursts and merges. Bursts occur when two or more activities follow a single
node. A merge occurs when two or more nodes precede a single node. For ex-
ample, in Figure 6-2, Node 1 is a burst because it goes into Nodes 2, 3, and 4.
Node 5 is a merge preceded by Nodes 2 and 3.
3. Continue drawing the AOA network diagram until all activities are included.
4. As a rule of thumb, all arrowheads should face toward the right, and no ar-
rows should cross on an AOA network diagram. You may need to redraw the
diagram to make it look presentable.
Even though AOA or ADM network diagrams are generally easy to understand and
create, a different method is more commonly used: the precedence diagramming method.
The precedence diagramming method (PDM) is a network diagramming technique in
which boxes represent activities. It is particularly useful for visualizing certain types of
time relationships.
Figure 6-3 illustrates the types of dependencies that can occur among project activities
based on a Microsoft Project help screen. After you determine the reason for a dependency
between activities (mandatory, discretionary, or external), you must determine the type of
FIGURE 6-3
The nature of the relationship between two linked tasks. You link tasks by defining a
dependency between their finish and start dates. For example, the “Contact caterers”
task must finish before the start of the “Determine menus” task. There are four kinds
of task dependencies in Microsoft Project.
Finish-to-start (FS) Task (B) cannot start until task (A)
finishes.
Task (B) cannot start until task (A)
starts.
Task (B) cannot finish until task (A)
finishes.
Task (B) cannot finish until task (A)
starts.
Task dependencies
Task dependency Example Description
Start-to-start (SS)
Finish-to-finish (FF)
Start-to-finish (SF)
A
B
A
B
A
B
A
B
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

dependency. Note that the terms activity and task are used interchangeably, as are relation-
ship and dependency. See Appendix A to learn how to create dependencies in Microsoft
Project 2013. The four types of dependencies or relationships between activities include:
Finish-to-start dependency: A relationship in which the “from” activity or
predecessor must finish before the “to” activity or successor can start. For
example, you cannot provide user training until after software or a new system
has been installed. Finish-to-start is the most common type of relationship or
dependency, and AOA network diagrams use only finish-to-start dependencies.
Start-to-start dependency: A relationship in which the “from” activity cannot
start until the “to” activity or successor is started. For example, on IT proj-
ects, a group of activities might start simultaneously, such as the many tasks
that occur when a new system goes live.
Finish-to-finish dependency: A relationship in which the “from” activity must
be finished before the “to” activity can be finished. One task cannot finish before
another finishes. For example, quality control efforts cannot finish before pro-
duction finishes, although the two activities can be performed at the same time.
Start-to-finish dependency: A relationship in which the “from” activity must
start before the “to” activity can be finished. This type of relationship is rarely
used, but it is appropriate in some cases. For example, an organization might
strive to stock raw materials just in time for the manufacturing process to be-
gin. A delay in starting the manufacturing process should delay completion of
stocking the raw materials. Another example would be a babysitter who wants
to finish watching a young child but is dependent on the parent’s arrival. The
parent must show up or “start” before the babysitter can finish the task.
Figure 6-4 illustrates Project X using the precedence diagramming method. Notice
that the activities are placed inside boxes, which represent the nodes on this diagram.
Arrows show the relationships between activities. This figure was created using Microsoft
Project, which automatically places additional information inside each node. Each task
box includes the start and finish dates, which are labeled Start and Finish; the task ID
number, labeled ID; the task’s duration, labeled Dur; and the names of resources, if any,
that are assigned to the task. These resources are labeled Res. The border of boxes for
FIGURE 6-4
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Taurus

232
tasks on the critical path appears automatically in red in the Microsoft Project network
diagram view. In Figure 6-4, the boxes for critical tasks have a thicker border.
The precedence diagramming method is used more often than AOA network diagrams
and offers a number of advantages over the AOA technique. First, most project management
software uses the precedence diagramming method. Second, using this method avoids the
need to use dummy activities. Dummy activities have no duration and no resources, but are
occasionally needed on AOA network diagrams to show logical relationships between activi-
ties. These activities are represented with dashed arrow lines and have zeros for their dura-
tion estimates. Third, the precedence diagramming method shows different dependencies
among tasks, whereas AOA network diagrams use only finish-to-start dependencies. You will
learn more about activity sequencing using Project 2013 in Appendix A.
6.5 ESTIMATING ACTIVITY RESOURCES
Before you can estimate the duration for each activity, you must have a good idea of the
quantity and type of resources (people, equipment, and materials) that will be assigned to
each activity. The nature of the project and the organization will affect resource estimates.
Expert judgment, an analysis of alternatives, estimating data, and project management
software are tools that can assist in resource estimating. The people who help determine
what resources are necessary must have experience and expertise in similar projects and
with the organization performing the project.
Important questions to answer when estimating activity resources include:
How difficult will specific activities be on this project?
Is anything unique in the project’s scope statement that will affect resources?
What is the organization’s history in doing similar activities? Has the organi-
zation done similar tasks before? What level of personnel did the work?
Does the organization have people, equipment, and materials that are capa-
ble and available for performing the work? Could any organizational policies
affect the availability of resources?
Does the organization need to acquire more resources to accomplish the work?
Would it make sense to outsource some of the work? Will outsourcing increase
or decrease the amount of resources needed and when they will be available?
Answering these questions requires important inputs such as a project’s schedule
management plan, activity list, activity attributes, resource calendars, risk register, activ-
ity cost estimates, enterprise environmental factors, and organizational process assets
such as policies regarding staffing and outsourcing. During the early phases of a project,
the project team may not know which specific people, equipment, and materials will be
available. For example, the team might know from past projects that a mix of experienced
and inexperienced programmers will work on a project. The team might also be able to ap-
proximate the number of people or hours needed to perform specific activities.
It is important to thoroughly brainstorm and evaluate alternatives related to re-
sources, especially on projects that involve people from multiple disciplines and compa-
nies. Because most projects involve many human resources and the majority of costs are
for salaries and benefits, it is often effective to solicit ideas from different people to help
develop alternatives and address resource-related issues early in a project. The resource
estimates should also be updated as more detailed information becomes available.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

233
The main outputs of the resource estimating process include a list of activity re-
source requirements, a resource breakdown structure, and project documents updates.
A resource breakdown structure is a hierarchical structure that identifies the project’s
resources by category and type. Resource categories might include analysts, programmers,
and testers. This information would be helpful in determining resource costs, acquiring
resources, and so on. For example, if junior employees will be assigned to many activi-
ties, the project manager might request that additional activities, time, and resources be
approved to help train and mentor those employees. In addition to providing the basis
for estimating activity durations, estimating activity resources provides vital information
for project cost estimates (Chapter 7), project human resource management (Chapter 9),
project communications management (Chapter 10), project risk management (Chapter
11), and project procurement management (Chapter 12).
6.6 ESTIMATING ACTIVITY DURATIONS
After working with key stakeholders to define activities, determine their dependencies,
and estimate their resources, the next process in project time management is to estimate
the duration of activities. It is important to note that duration includes the actual amount
of time worked on an activity plus elapsed time. For example, even though it might take
one workweek or five workdays to do the actual work, the duration estimate might be two
weeks to allow extra time needed to obtain outside information. The people or resources
assigned to a task will also affect the task duration estimate. As another example, if some-
one asked for an estimate of when you plan to finish reading a particular book, you might
give an answer of two months. Two months would be the duration estimate, even if you
only plan to spend 20 hours actually reading the book.
Do not confuse duration with effort, which is the number of workdays or work hours
required to complete a task. (Duration is normally entered in the Duration column in soft-
ware such as Microsoft Project 2013, while effort is entered in a Work column. See Appen-
dix A for more information.) A duration estimate of one day could be based on eight hours
of work or 80 hours of work, assuming that multiple people are working on a task that day.
Duration relates to the time estimate on a calendar, not the effort estimate. For example,
you might plan to spend 20 hours reading a book—the effort estimate—and spread that
time out over two months—the duration.
Of course, duration and effort are related, so project team members must docu-
ment their assumptions when creating duration estimates. The people who will actually
do the work, in particular, should have a lot of say in duration estimates because their
performances will be evaluated based on their ability to meet the estimates. It is also
helpful to review similar projects and seek the advice of experts in estimating activity
durations.
Project team members must also update the estimates as the project progresses. If
scope changes occur on the project, the duration estimates should be updated to reflect
those changes.
There are several inputs to activity duration estimates, including the schedule man-
agement plan, activity list, activity attributes, activity resource requirements, resource
calendars, project scope statement, risk register, resource breakdown structure, enterprise
environmental factors, and organizational process assets. In addition to reviewing past
project information, the team should review the accuracy of the duration estimates thus
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

234
far on the project. For example, if team members find that all of their estimates have been
much too long or short, they should update the estimates to reflect what they have learned.
One of the most important considerations in making activity duration estimates is the
availability of resources, especially human resources. What specific skills do people need
to do the work? What are the skill levels of the people assigned to the project? How many
people are expected to be available to work on the project at any one time?
The outputs of activity duration estimates include the estimates themselves and
project documents updates. Duration estimates are often provided as a discrete number,
such as four weeks; as a range, such as three to five weeks; or as a three-point estimate. A
three-point estimate includes an optimistic, most likely, and pessimistic estimate, such as
three weeks for the optimistic scenario, four weeks for the most likely scenario, and five
weeks for the pessimistic scenario. The optimistic estimate is based on a best-case sce-
nario, while the pessimistic estimate is based on a worst-case scenario. The most likely es-
timate, as you might expect, is based on a most likely or expected scenario. A three-point
estimate is required for performing PERT estimates, as described later in this chapter, and
for performing Monte Carlo simulations, as described in Chapter 11, Project Risk Manage-
ment. Other duration estimating techniques include analogous and parametric estimating
and reserve analysis, as described in Chapter 7, Project Cost Management. Expert judg-
ment is also an important tool for developing good activity duration estimates.
6.7 DEVELOPING THE SCHEDULE
Schedule development uses the results of all the preceding project time management pro-
cesses to determine the start and end dates of the project and its activities. Project time
management processes often go through several iterations before a project schedule is final-
ized. The ultimate goal of developing a realistic project schedule is to provide a basis for
monitoring project progress for the time dimension of the project. The main outputs of this
process are the project schedule, a schedule baseline, schedule data, project calendars, proj-
ect management plan updates, and project documents updates. Some project teams create a
computerized model to create a network diagram, enter resource requirements and availabil-
ity by time period, and adjust other information to quickly generate alternative schedules.
See Appendix A for information on using Project 2013 to assist in schedule development.
Several tools and techniques assist in schedule development:
A Gantt chart is a common tool for displaying project schedule information.
Critical path analysis is a very important tool for developing and controlling
project schedules.
Critical chain scheduling is a technique that focuses on limited resources
when creating a project schedule.
PERT analysis is a means for considering schedule risk on projects.
The following sections provide samples of each of these tools and techniques and dis-
cuss their advantages and disadvantages.
6.7a Gantt Charts
Gantt charts provide a standard format for displaying project schedule information by
listing project activities and their corresponding start and finish dates in calendar form.
Gantt charts are sometimes referred to as bar charts because the activities’ start and end
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Taurus

235
dates are shown as horizontal bars. Figure 6-5 shows a simple Gantt chart for Project X
created with Microsoft Project. Figure 6.6 shows a Gantt chart that is more sophisticated
and is based on a software launch project from a template provided by Microsoft. The
activities on the Gantt chart are driven by the deliverables on the WBS, and should co-
incide in turn with the activity list and milestone list. Notice that the Gantt chart for the
software launch project contains milestones, summary tasks, individual task durations,
and arrows showing task dependencies.
FIGURE 6-5
Notice the different symbols on the Gantt chart for the software launch project
(see Figure 6-6):
The black diamond represents a milestone. In Figure 6-6, Task 1, “Marketing
Plan distributed,” is a milestone that occurs on March 17. Tasks 3, 4, 8, 9, 14, 25,
27, 43, and 45 are also milestones. For very large projects, top managers might
want to see only milestones on a Gantt chart. Microsoft Project allows you to fil-
ter information displayed on a Gantt chart so you can easily show specific tasks,
such as milestones.
The thick black bars with arrows at the beginning and end represent sum-
mary tasks. For example, Activities 12 through 15—“Develop creative briefs,”
“Develop concepts,” “Creative concepts,” and “Ad development”—are all
subtasks of the summary task called “Advertising,” Task 11. WBS activities
are referred to as tasks and subtasks in most project management software.
The light gray horizontal bars for Tasks 5, 6, 7, 10, 12, 13, 15, 22, 24, 26,
and 44 represent the duration of each individual task. For example, the light
gray bar for Subtask 5, “Packaging,” starts in mid-February and extends until
early May.
Arrows connecting these symbols show relationships or dependencies be-
tween tasks. Gantt charts often do not show dependencies, which is their ma-
jor disadvantage. If dependencies have been established in Microsoft Project,
they are automatically displayed on the Gantt chart.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

WBS hierarchy shown
by indentations Summary
task
Milestone
Individual task bar Arrows show
dependencies
FIGURE 6-6
6.7b Adding Milestones to Gantt Charts
Milestones can be a particularly important part of schedules, especially for large projects.
Many people like to focus on meeting milestones, so you can create them to emphasize im-
portant events or accomplishments on projects. Normally, you create milestones by enter-
ing tasks with zero duration. In Microsoft Project, you can mark any task as a milestone by
checking the appropriate box in the Advanced tab of the Task Information dialog box. The
duration of the task will not change to zero, but the Gantt chart will show the milestone
symbol to represent that task based on its start date. See Appendix A for more information.
To make milestones meaningful, some people use the SMART criteria to help define
them. The SMART criteria are guidelines suggesting that milestones should be:
Specific
Measurable
Assignable
Realistic
Time-framed
For example, distributing a marketing plan is specific, measurable, and assignable if
everyone knows what should be in the marketing plan, how it should be distributed, how
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

237
many copies should be distributed and to whom, and who is responsible for the actual
delivery. Distributing the marketing plan is realistic and able to be time-framed if it is an
achievable event and scheduled at an appropriate time.
B E S T P R A C T I C E
In his book, The Happiness Advantage, Shawn Achor shares principles of positive psy-
chology that can fuel success at work. One problem many people have at work is feeling
overwhelmed. They complain that they are working all the time, but they cannot get
their work done. Achor suggests that the 20-second rule can help people improve their
focus by minimizing barriers to change.
The 20-second rule capitalizes on people’s preference for taking the path of least
resistance. For example, you can more easily resist having an extra scoop of ice cream if
you have to wait 20 seconds in line for it rather than have it served to you. Many people
have trouble focusing on work because they are easily distracted by checking their e-mail,
stocks, news, social media, etc. Achor recommends making it more difficult for yourself
to be distracted. For example, keep e-mail closed while you are working. Don’t leave your
favorite non-work-related websites open or have your passwords saved in them. You can
actually “save time by adding time”—but only to the distracting behaviors at work.7
6.7c Using Tracking Gantt Charts to Compare Planned and Actual Dates
You can use a special form of a Gantt chart to evaluate progress on a project by showing
actual schedule information. Figure 6-7 shows a Tracking Gantt chart—a Gantt chart that
compares planned and actual project schedule information. The planned schedule dates
FIGURE 6-7
Planned dates
Actual dates Slipped milestone
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

238
for activities are called the baseline dates, and the entire approved planned schedule is
called the schedule baseline. The Tracking Gantt chart includes columns labeled “Start”
and “Finish” to represent actual start and finish dates for each task, as well as columns
labeled “Baseline Start” and “Baseline Finish” to represent planned start and finish dates
for each task. (These columns are hidden in Figure 6-7.) In this example, the project is
completed, but several tasks missed their planned start and finish dates.
To serve as a progress evaluation tool, a Tracking Gantt chart uses a few additional
symbols:
Notice that the Gantt chart in Figure 6-7 often shows two horizontal bars for tasks.
The top horizontal bar represents the planned or baseline duration for each task.
The bar below it represents the actual duration. Subtasks 1.2 and 1.3 illustrate this
type of display. If these two bars are the same length, meaning they start and end
on the same dates, then the actual schedule was the same as the planned schedule
for that task. This scheduling occurred for Subtask 1.1, in which the task started
and ended as planned on March 4. If the bars do not start and end on the same
dates, then the actual schedule differed from the planned or baseline schedule. If
the top horizontal bar is shorter than the bottom one, the task took longer than
planned, as you can see for Subtask 1.2. If the top horizontal bar is longer than the
bottom one, the task took less time than planned. A striped horizontal bar, as illus-
trated by Main Tasks 1 and 2, represents the planned duration for summary tasks.
The black bar adjoining it shows progress for summary tasks. For example, Main
Task 2 clearly shows that the actual duration took longer than planned.
A white diamond on the Tracking Gantt chart represents a slipped milestone.
A slipped milestone means the milestone activity was completed later than
originally planned. The last task provides an example of a slipped milestone
because the final report and presentation were completed later than planned.
Percentages to the right of the horizontal bars display the percentage of work
completed for each task. For example, 100 percent means the task is finished,
and 50 percent means the task is still in progress but is 50 percent completed.
A Tracking Gantt chart is based on the percentage of work completed for project tasks or
the actual start and finish dates. It allows the project manager to monitor schedule progress
on individual tasks and the whole project. For example, Figure 6-7 shows that the project is
completed. It started on time, but it finished a little late, on May 13 (5/13) instead of May 8.
The main advantage of using Gantt charts is that they provide a standard format for
displaying planned and actual project schedule information. In addition, they are easy to
create and understand. The main disadvantage of Gantt charts is that they do not usually
show relationships or dependencies between tasks. If Gantt charts are created using proj-
ect management software and tasks are linked, then the dependencies will be displayed,
but differently than they would be displayed on a network diagram. Whether you view de-
pendencies on a Gantt chart or network diagram is a matter of personal preference.
6.7d Critical Path Method
Many projects fail to meet schedule expectations. Critical path method (CPM)—also called
critical path analysis—is a network diagramming technique used to predict total project du-
ration. This important tool helps you combat project schedule overruns. A critical path for
a project is the series of activities that determine the earliest time by which the project can
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

239
be completed. It is the longest path through the network diagram and has the least amount
of slack or float. Slack or float is the amount of time an activity may be delayed without
delaying a succeeding activity or the project finish date. Normally, several tasks are done in
parallel on projects, and most projects have multiple paths through a network diagram. The
longest path or the path that contains the critical tasks is what drives the completion date
for the project. You are not finished with the project until you have finished all the tasks.
6.7e Calculating the Critical Path
To find the critical path for a project, you must first develop a good network diagram,
which in turn requires a good activity list based on the WBS. Once you create a network
diagram, you must also estimate the duration of each activity to determine the critical
path. Calculating the critical path involves adding the durations for all activities on each
path through the network diagram. The longest path is the critical path.
Figure 6-8 shows the AOA network diagram for Project X again. Note that you can use
either the AOA or precedence diagramming method to determine the critical path on proj-
ects. Figure 6-8 shows all of the paths—a total of four—through the network diagram. Note
that each path starts at the first node (1) and ends at the last node (8) on the AOA network
diagram. This figure also shows the length or total duration of each path through the network
diagram. These lengths are computed by adding the durations of each activity on the path.
Because path B-E-H-J has the longest duration at 16 days, it is the critical path for the project.
What does the critical path really mean? Even though the critical path is the lon-
gest path, it represents the shortest time required to complete a project. If one or more
FIGURE 6-8
8
J = 3
Path 1:
Path 2:
Path 3:
Path 4:
A-D-H-J
B-E-H-J
B-F-J
C-G-I-J
Length = 1+4+6+3 = 14 days
Length = 2+5+6+3 = 16 days
Length = 2+4+3 = 9 days
Length = 3+6+2+3 = 14 days
Since the critical path is the longest path through the network diagram, Path 2,
B-E-H-J, is the critical path for Project X.
Note: Assume all durations are in days.
J =
6
I = 2
H = 6H = 6
s.
6
I = 2
7
5
D = 4
E = 5
F = 4
G = 6
D
E
all durations are in
2
3
4
A = 1
B = 2
C = 3
A =
B
C =
1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

activities on the critical path take longer than planned, the whole project schedule will
slip unless the project manager takes corrective action.
Project teams can be creative in managing the critical path. For example, Joan Knut-
son, a well-known author and speaker in the project management field, often describes
how a gorilla helped Apple Inc. complete a project on time. Team members worked in an
area with cubicles, and whoever was in charge of the current task on the critical path had
a stuffed gorilla on top of his or her cubicle. Everyone knew that person was under the
most time pressure and did not need distractions. When a critical task was completed, the
person in charge of the next critical task received the gorilla.
6.7f Growing Grass Can Be on the Critical Path
People are often confused about what a project’s critical path really means. Some people
think the critical path includes the most critical activities, but it is concerned only with
the time dimension of a project. The fact that its name includes the word critical does not
mean that it includes all critical activities. For example, Frank Addeman, Executive Proj-
ect Director at Walt Disney Imagineering, explained in a keynote address at a PMI-ISSIG
Professional Development Seminar that growing grass was on the critical path for building
Disney’s Animal Kingdom theme park! The 500-acre park required special grass for its ani-
mal inhabitants, and some of the grass took years to grow. Another misconception is that
the critical path is the shortest path through the network diagram. In some areas, such as
transportation modeling, identifying the shortest path in network diagrams is the goal. For
a project, however, each task or activity on the critical path must be done in order to com-
plete the project. It is not a matter of choosing the shortest path.
Other aspects of critical path analysis may cause confusion. Can there be more than
one critical path on a project? Does the critical path ever change? In the Project X ex-
ample, suppose that Activity A has a duration estimate of three days instead of one day.
This new duration estimate would make the length of Path 1 equal to 16 days. Now the
project has two longest paths of equal duration, so there are two critical paths. Therefore,
a project can have more than one critical path. Project managers should closely monitor
performance of activities on the critical path to avoid late project completion. If there is
more than one critical path, project managers must keep their eyes on all of them.
The critical path on a project can change as the project progresses. For example, sup-
pose everything is going as planned at the beginning of the project. Suppose that Activities
A, B, C, D, E, F, and G all start and finish as planned. Then suppose that Activity I runs into
problems. If Activity I takes more than four days, it will cause path C-G-I-J to be longer
than the other paths, assuming they progress as planned. This change would cause path C-
G-I-J to become the new critical path. Therefore, the critical path can change on a project.
6.7g Using Critical Path Analysis to Make Schedule Trade-Offs
It is important to know the critical path throughout the life of a project so the project
manager can make trade-offs. If a task on the critical path is behind schedule, the project
manager must be aware of the problem and decide what to do about it. Should the sched-
ule be renegotiated with stakeholders? Should more resources be allocated to other items
on the critical path to make up for that time? Is it acceptable for the project to finish
behind schedule? By keeping track of the critical path, the project manager and the team
take a proactive role in managing the project schedule.
A technique that can help project managers make schedule trade-offs is determining
the free slack and total slack for each project activity. Free slack or free float is the amount
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

of time an activity can be delayed without delaying the early start date of any immediately
following activities. The early start date is the earliest possible time an activity can start
based on the project network logic. Total slack or total float is the amount of time an activ-
ity can be delayed from its early start without delaying the planned project finish date.
Project managers calculate free slack and total slack by doing a forward and backward
pass through a network diagram. A forward pass determines the early start and early finish
dates for each activity. The early finish date is the earliest possible time an activity can finish
based on the project network logic. The project start date is equal to the early start date for
the first network diagram activity. The early start plus the duration of the first activity is equal
to the early finish date of the first activity. It is also equal to the early start date of each sub-
sequent activity unless an activity has multiple predecessors. When an activity has multiple
predecessors, its early start date is the latest of the early finish dates of those predecessors.
For example, Tasks D and E immediately precede Task H in Figure 6-8. The early start date
for Task H, therefore, is the early finish date of Task E, because it occurs later than the early
finish date of Task D. A backward pass through the network diagram determines the late start
and late finish dates for each activity in a similar fashion. The late start date is the latest possi-
ble time an activity might begin without delaying the project finish date. The late finish date is
the latest possible time an activity can be completed without delaying the project finish date.
Project managers can determine the early and late start and finish dates of each activ-
ity by hand. For example, Figure 6-9 shows a simple network diagram with three tasks, A,
B, and C. Tasks A and B both precede Task C. Assume that all duration estimates are in
days. Task A has an estimated duration of 5 days, Task B has an estimated duration of
FIGURE 6-9
ES = early start
EF = early finish
LS = late start
LF = late finish
ES EF
LS LF
Legend:
0 5
5 10
A=5
0 0
0 0
Start
0 10
0 10
B=10
10 17
10 17
C=7
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

242
10 days, and Task C has an estimated duration of 7 days. There are only two paths
through this small network diagram: Path A-C has a duration of 12 days (5+7), and path
B-C has a duration of 17 days (10+7). Because path B-C is longer, it is the critical path.
There is no float or slack on this path, so the early and late start and finish dates are the
same. However, Task A has 5 days of float or slack. Its early start date is day 0, and its late
start date is day 5. Its early finish date is day 5, and its late finish date is day 10. Both the
free and total float amounts for Task A are 5 days.
Using project management software is a much faster and easier way to determine early
and late start and finish dates and free and total slack amounts for activities. Table 6-1
shows the free and total slack for all activities on the network diagram for Project X using
the data from Figure 6-8 and assuming that Tasks A, B, and C started on August 3, 2015.
(The network diagram is shown in Figure 6-4, which was created with Microsoft Project.)
The data in this table was created by selecting the Schedule Table view in Microsoft Project.
Knowing the amount of float or slack allows project managers to know whether the
schedule is flexible and how flexible it might be. For example, at 7 days (7d), Task F has
the most free and total slack. The most slack on any other activity is only 2 days (2d).
Understanding how to create and use slack information provides a basis for negotiating
project schedules. See the Help information in Microsoft Project or research other re-
sources for more detailed information on calculating slack.
6.7h Using the Critical Path to Shorten a Project Schedule
It is common for stakeholders to want to shorten a project schedule estimate. A project
team may have done its best to develop a project schedule by defining activities, deter-
mining sequencing, and estimating resources and durations for each activity. The results
of this work may have shown that the project team needs 10 months to complete the proj-
ect, but the sponsor might ask if the project can be done in eight or nine months. (Rarely
do people ask the project team to take longer than suggested.) By knowing the critical
path, the project manager and the team can use several duration compression techniques
to shorten the project schedule. One technique is to reduce the duration of activities on
the critical path. The project manager can shorten the duration of critical-path activities
by allocating more resources to those activities or by changing their scope.
TABLE 6-1
Task Name Start Finish Late Start Late Finish Free Slack Total Slack
A 8/3/15 8/3/15 8/5/15 8/5/15 0d 2d
B 8/3/15 8/4/15 8/3/15 8/4/15 0d 0d
C 8/3/15 8/5/15 8/5/15 8/7/15 0d 2d
D 8/4/15 8/7/15 8/6/15 8/11/15 2d 2d
E 8/5/15 8/11/15 8/5/15 8/11/15 0d 0d
F 8/5/15 8/10/15 8/14/15 8/17/15 7d 7d
G 8/6/15 8/13/15 8/10/15 8/17/15 0d 2d
H 8/12/15 8/19/15 8/12/15 8/19/15 0d 0d
I 8/14/15 8/17/15 8/18/15 8/19/15 2d 2d
J 8/20/15 8/24/15 8/20/15 8/24/15 0d 0d
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

243
Recall that Sue Johnson in the opening case was having schedule problems with the
online registration project because several users missed important project review meetings
and one of the senior programmers quit. If Sue and her team created a realistic project
schedule, produced accurate duration estimates, and established dependencies between
tasks, they could analyze their status in terms of meeting the May 1 deadline. If some ac-
tivities on the critical path had already slipped and they did not build in extra time at the
end of the project, then they would have to take corrective actions to finish the project on
time. Sue could request that her company or the college provide more people to work on
the project in an effort to make up time. She could also request that the scope of activities
be reduced to complete the project on time. Sue could also use project time management
techniques, such as crashing or fast tracking, to shorten the project schedule.
Crashing is a technique for making cost and schedule trade-offs to obtain the greatest
amount of schedule compression for the least incremental cost. For example, suppose that
one of the items on the critical path for the online registration project was entering course
data for the new semester into the new system. If this task has not yet been done and was
originally estimated to take two weeks based on the college providing a part-time data
entry clerk, Sue could suggest that the college have the clerk work full time to finish the
task in one week instead of two. This change would not cost Sue’s company more money,
and it could shorten the project end date by one week. If the college could not meet this
request, Sue could consider hiring a temporary data entry person for one week to help
get the task done faster. By focusing on tasks on the critical path that could be done more
quickly for no extra cost or a small cost, the project schedule can be shortened.
The main advantage of crashing is shortening the time needed to finish a project. The
main disadvantage of crashing is that it often increases total project costs. You will learn
more about project costs in Chapter 7, Project Cost Management.
Another technique for shortening a project schedule is fast tracking. Fast tracking
involves doing activities in parallel that you would normally do in sequence. For example,
Sue Johnson’s project team may have planned not to start any of the coding for the on-
line registration system until all of the analysis was done. Instead, they could consider
starting some coding activity before the analysis is completed. The main advantage of fast
tracking, like crashing, is that it can shorten the time needed to finish a project. The main
disadvantage is that it can lengthen the project schedule because starting some tasks too
soon often increases project risk and results in rework.
6.7i Importance of Updating Critical Path Data
In addition to finding the critical path at the beginning of a project, it is important to update
the schedule with actual data. After the project team completes activities, the project man-
ager should document the actual durations of those activities. The project manager should
also document revised estimates for activities in progress or yet to be started. These revisions
often cause a project’s critical path to change, resulting in a new estimated completion date
for the project. Again, proactive project managers and their teams stay on top of changes so
they can make informed decisions and keep stakeholders involved in major project decisions.
6.7j Critical Chain Scheduling
Another technique that addresses the challenge of meeting or beating project finish dates
is an application of the Theory of Constraints called critical chain scheduling. The Theory
of Constraints (TOC) is a management philosophy developed by Eliyahu M. Goldratt and
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

244
discussed in his books The Goal and Critical Chain. The Theory of Constraints is based
on the metaphor of a chain and its weakest link: Any complex system at any point in time
often has only one aspect or constraint that limits the ability to achieve more of the sys-
tem’s goal. For the system to attain any significant improvements, that constraint must be
identified, and the whole system must be managed with it in mind. Critical chain sched-
uling is a method that considers limited resources when creating a project schedule and
includes buffers to protect the project completion date.
An important concept in critical chain scheduling is the availability of scarce re-
sources. Some projects cannot be done unless a particular resource is available to work
on one or several tasks. For example, if a television network wants to produce a show cen-
tered around a particular celebrity, it must first check the availability of that celebrity. As
another example, if a particular piece of equipment is needed full time to complete each
of two tasks that were originally planned to occur simultaneously, critical chain schedul-
ing acknowledges that you must either delay one of those tasks until the equipment is
available or find another piece of equipment in order to meet the schedule. Other impor-
tant concepts related to critical chain scheduling include multitasking and time buffers.
Although many people are proud to say they are good at multitasking, multitasking
is not a good thing to do if you want to finish a project in a timely manner. Multitasking
occurs when a resource works on more than one task at a time. This situation occurs
frequently on projects. People are assigned to multiple tasks within the same project or
different tasks on multiple projects. For example, suppose someone is working on three
different tasks—Task 1, Task 2, and Task 3—for three different projects, and each task
takes 10 days to complete. If the person did not multitask, and instead completed each
task sequentially starting with Task 1, then Task 1 would be completed after day 10, Task
2 would be completed after day 20, and Task 3 would be completed after day 30, as shown
in Figure 6-10a. However, because many people in this situation try to please all three par-
ties who need their tasks completed, they often work on the first task for some time, then
the second, then the third, then go back to the first task, and so on, as shown in Figure
6-10b. In this example, the tasks were all half-done one at a time, then completed one at a
time. Task 1 is now completed at the end of day 20 instead of day 10, Task 2 is completed
at the end of day 25 instead of day 20, and Task 3 is still completed on day 30. This exam-
ple illustrates how multitasking can delay task completion. Multitasking also often involves
wasted setup time, which increases total duration.
Task 1 completed
after 10 days
Task 1 Task 2 Task 3
10 days 10 days 10 days
Without
multitasking
Task 2 completed
after 20 days
Task 3 completed
after 30 days
FIGURE 6-10a
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

245
Task 1 completed
after 20 days
Task 1 Task 2 Task 3
5 days
With
multitasking
after 25 days
Task 1 Task 2 Task 3
5 days 5 days 5 days 5 days 5 days
Task 3 completed
after 30 days
Task 2 completed
FIGURE 6-10b
Critical chain scheduling assumes that resources do not multitask or at least mini-
mize multitasking. Someone should not be assigned to two tasks simultaneously on the
same project when critical chain scheduling is in effect. Likewise, critical chain theory
suggests that projects be prioritized so that people who are working on more than one
project at a time know which tasks take priority. Preventing multitasking avoids
resource conflicts and wasted setup time caused by shifting between multiple tasks
over time.
An essential concept to improving project finish dates with critical chain scheduling is
to change the way people make task estimates. Many people add a safety or buffer—
additional time to complete a task—to an estimate to account for various factors. These
factors include the negative effects of multitasking, distractions, and interruptions,
fear that estimates will be reduced, and Murphy’s Law. Murphy’s Law states that if some-
thing can go wrong, it will. Critical chain scheduling removes buffers from individual
tasks and instead creates a project buffer, which is time added before the project’s due
date. Critical chain scheduling also protects tasks on the critical chain from being
delayed by using feeding buffers, which consist of time added before tasks on the
critical chain if they are preceded by other tasks that are not on the
critical path.
Figure 6-11 provides an example of a network diagram constructed using critical
chain scheduling. Note that the critical chain accounts for a limited resource, X, and the
schedule includes use of feeding buffers and a project buffer in the network diagram.
The tasks marked with an X are part of the critical chain, which can be interpreted
as being the critical path using this technique. The task estimates in critical chain
scheduling should be shorter than traditional estimates because they do not include
their own buffers. Not having task buffers should mean fewer occurrences of
Parkinson’s Law, which states that work expands to fill the time allowed. The feeding
and project buffers protect the date that really needs to be met—the project
completion date.
Several organizations have reported successes with critical chain scheduling. For
example, the What Went Right feature shows how the healthcare industry is learning to
think differently by using the Theory of Constraints.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Critical Chain
FIGURE 6-11 8
FB X
X
FB X
Completion
date
Project
buffer
Critical chain
Critical chain
X = Tasks done by limited resource
FB = Feeding buffer
Critical chain
FB
W H A T W E N T R I G H T ?
Experts in healthcare quality management have thought carefully about how scheduling
works at a doctor’s office or healthcare clinic and have considered how it might be improved:
Consider a relatively simple system of a physician’s office or clinic. The steps in the
process could be patients checking in, filling out forms, having vital signs taken by a
nurse, seeing the physician, seeing the nurse for a prescribed procedure such as vac-
cination, and so forth. These steps could take place in a simple linear sequence or
chain. … Each link in this chain has the ability to perform its tasks at different aver-
age rates. In this example, the first resource can process 13 patients, charts, or blood
samples per hour; the second can process 17, and so forth. One may think that this
process can produce 13 per hour, the average of all resources. In fact, this process or
chain only can produce an average of eight per hour. The chain is only as strong as its
weakest link and the rate of the slowest resource in this example, the weakest link, is
eight. This is true regardless of how fast each of the other resources can process indi-
vidually, how much work is stuffed into the pipeline, or how complex the process or
set of interconnected processes is to complete. Moreover, improving the performance
of any link besides the constraint does nothing to improve the system as a whole.9
In fact, the Avraham Y. Goldratt Institute (www.goldratt.com) applied this think-
ing at a client’s site and showed just how well critical chain scheduling can work. The
National University Hospital in Singapore decreased patient admission times by more
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

247
than 50 percent. Improved scheduling lowered average wait times, which went from
6 to 8 hours to less than three hours. By applying critical chain techniques, the hospital
admitted 63 percent of patients in less than 1.5 hours. Although these times still seem
long, they show significant improvement.10
As you can see, critical chain scheduling is a fairly complicated yet powerful tool that
involves critical path analysis, resource constraints, and changes in how buffers are used
as part of task estimates. Some people consider critical chain scheduling one of the most
important new concepts in the field of project management.
6.7k Program Evaluation and Review Technique (PERT)
When there is a high degree of uncertainty about the individual activity duration esti-
mates, the network analysis Program Evaluation and Review Technique (PERT) can
be used to estimate project duration. PERT applies the critical path method (CPM) to a
weighted average duration estimate. This approach was developed at about the same time
as CPM, in the late 1950s, and it also uses network diagrams, which are still sometimes
referred to as PERT charts.
PERT uses probabilistic time estimates—duration estimates based on using optimis-
tic, most likely, and pessimistic estimates of activity durations—instead of one specific or
discrete duration estimate, as CPM does. To use PERT, you calculate a weighted average
for the duration estimate of each project activity using the following formula:
PERT weight average 5
optimistic time 1 4 * most likely time 1 pessimistic time
6
By using the PERT weighted average for each activity duration estimate, the total
project duration estimate takes into account the risk or uncertainty in the individual
activity estimates.
Suppose that Sue Johnson’s project team in the opening case used PERT to deter-
mine the schedule for the online registration system project. The team would have to col-
lect numbers for the optimistic, most likely, and pessimistic duration estimates for each
project activity. Suppose that one of the activities was to design an input screen for the
system. Someone might estimate that it would take about two weeks or 10 workdays to
do this activity. Without using PERT, the duration estimate for that activity would be 10
workdays. Using PERT, the project team would also need to estimate the pessimistic and
optimistic times for completing this activity. Suppose an optimistic estimate is that the in-
put screen can be designed in eight workdays, and a pessimistic time estimate is 24 work-
days. Applying the PERT formula, you get the following:
PERT weight average 5
8 workdays 1 4 * 10 workdays 1 24 workdays
6
5 12 workdays
Instead of using the most likely duration estimate of 10 workdays, the project team
would use 12 workdays when doing critical path analysis. These additional two days could
help the project team get the work completed on time.
The main advantage of PERT is that it attempts to address the risk associated with
duration estimates. Because many projects exceed schedule estimates, PERT may help
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

248
in developing schedules that are more realistic. PERT’s main disadvantages are that it in-
volves more work than CPM because it requires several duration estimates, and there are
better probabilistic methods for assessing schedule risk. (See the information on Monte
Carlo simulations in Chapter 11, Project Risk Management.)
6.7l Agile and Time Management
Recall from Chapter 2 that two of the core values of the Manifesto for Agile Software
Development are “customer collaboration over contract negotiation” and “responding to
change over following a plan.” These values seem to contradict some of the structured
project time management processes and tools described in this chapter. Agile methods like
Scrum were designed to address collaboration and flexibility, especially on projects with a
complex scope of work. For example, the product owner defines and prioritizes the work
to be done within a sprint, so customer collaboration is designed into the process. The
short period of each sprint (normally two to four weeks) and daily Scrum meetings provide
an environment where team members collaborate to focus on completing specific tasks.
An adaptive or agile approach can be used on large projects, even after they are
started using a more prescriptive approach. For example, the FBI says that switching to an
agile approach is what helped them complete the Sentinel project described in the What
Went Wrong? feature earlier in the chapter. The system went live “thanks to the fact that
it was rescued by following an agile software development methodology… The primary
lesson? Agile actually works. It’s not perfect, and many people in government and in the
contractor community still struggle with it, but it’s succeeding where it counts—enabling
the rollout of large-scale IT projects that are on time, on budget and actually do what
stakeholders want them to do. Imagine that.”11
How was project time management different after moving to an agile approach? After
changing to a Scrum method in 2010, the work for the Sentinel project was organized into
user stories based on the original systems requirements specifications. Each user story
was allocated a number of story points based on difficulty. At the beginning of each two-
week sprint, the development team identified which user stories to do during each sprint.
At the end of each sprint the team demonstrated the system, regardless of whether all of
the work was completed, but only the user stories that passed tests (approved by the cus-
tomers) were reported as complete. If user stories were not complete, they were moved to
the product backlog. This approach helped the team focus on delivering a working system
that met customer needs in a specified timeframe. In other words, the emphasis was on
completing some useful work for the customer in short time increments versus trying to
define all the work required first and then scheduling when it could be done.12
6.8 CONTROLLING THE SCHEDULE
The final process in project time management is controlling the schedule. Like scope
control, schedule control is a portion of the integrated change control process in project
integration management. The goal of schedule control is to know the status of the sched-
ule, influence the factors that cause schedule changes, determine that the schedule has
changed, and manage changes when they occur.
The main inputs to schedule control are the project management plan, project sched-
ule, work performance data, project calendars, schedule data, and organizational process
assets. Some of the tools and techniques include:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

249
Performance reviews, where progress reports are often provided
A schedule change control system, operated as part of the integrated change
control system described in Chapter 4, Project Integration Management
A scheduling tool and/or project management software, such as Project 2013
or similar software
Variance analysis, such as analyzing float or slack and using earned value, as
described in Chapter 7, Project Cost Management
What-if scenario analysis, which can be done manually or with the aid of
software
Adjusting leads and lags
Schedule compression, such as crashing and fast tracking, as described ear-
lier in this chapter
Resource optimization techniques, such as resource leveling, as described in
Chapter 9, Project Human Resource Management
The main outputs of schedule control include work performance measurements, orga-
nizational process assets updates such as lessons-learned reports related to schedule con-
trol, change requests, project management plan updates, and project documents updates.
Many issues are involved in controlling changes to project schedules. It is important
first to ensure that the project schedule is realistic. Many projects, especially in IT, have
very unrealistic schedule expectations. It is also important to use discipline and leadership
to emphasize the importance of following and meeting project schedules. Although the vari-
ous tools and techniques assist in developing and managing project schedules, project man-
agers must handle several personnel-related issues to keep projects on track. “Most projects
fail because of people issues, not from failure to draw a good PERT chart.”13 Project manag-
ers can perform a number of reality checks that will help them manage changes to project
schedules. Several soft skills can help project managers to control schedule changes.
6.8a Reality Checks on Scheduling and the Need for Discipline
It is important for projects to have realistic schedule goals and for project managers to use
discipline to help meet those goals. One of a project manager’s first reality checks is to re-
view the draft schedule that is usually included in the project charter. Although this draft
schedule might include only a project start and end date, the project charter sets some
initial schedule expectations for the project. Next, the project manager and project team
should prepare a more detailed schedule and get stakeholders’ approval. To establish the
schedule, it is critical to get involvement and commitment from all project team members,
top management, the customer, and other key stakeholders.
Another type of reality check comes from progress meetings with stakeholders. The
project manager is responsible for keeping the project on track, and key stakeholders like
to stay informed, often through high-level periodic reviews. Project managers often illus-
trate progress with a Tracking Gantt chart that shows key deliverables and activities. The
project manager needs to understand the schedule, including why activities are or are not
on track, and take a proactive approach to meeting stakeholder expectations. It is also
important to verify schedule progress, as Sue Johnson from the opening case discovered
(see the Case Wrap-Up later in this chapter). Just because a team member says a task was
completed on time does not always mean that it was. Project managers must review the
actual work and develop a good relationship with team members to ensure that work is
completed as planned or changes are reported as needed.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Top management hates surprises, so the project manager must be clear and honest in
communicating project status. By no means should project managers create the illusion
that the project is going fine when it is actually having serious problems. When serious
conflicts arise that could affect the project schedule, the project manager must alert top
management and work with them to resolve the conflicts.
Project managers must also use discipline to control project schedules. Several IT
project managers have discovered that setting firm dates for key project milestones helps
minimize schedule changes. It is very easy for scope creep to raise its ugly head on IT
projects. Insisting that important schedule dates be met and that proper planning and
analysis be completed up front helps everyone focus on doing what is most important for
the project. This discipline results in meeting project schedules.
6.9 USING SOFTWARE TO ASSIST IN PROJECT
TIME MANAGEMENT
Several types of software are available that assist with project time management. Software
for facilitating communications helps project managers exchange schedule-related infor-
mation with project stakeholders. Decision support models can help project managers
analyze various trade-offs that can be made to address schedule issues.
However, project management software was designed specifically for perform-
ing project management tasks. You can use project management software to draw
network diagrams, determine the critical path for a project, create Gantt charts, and
report, view, and filter specific project time management information. For example,
Figures 6-4, 6-5, 6-6, 6-7, and Table 6-1 were all created using Microsoft Project; Ap-
pendix A shows many more examples of using this software to assist in project time
management.
Many projects involve hundreds of tasks with complicated dependencies. After you
enter the necessary information, project management software automatically generates a
network diagram and calculates the critical path(s) for the project. It also highlights the
critical path in red on the network diagram.
Project management software also calculates the free and total float or slack for all ac-
tivities. Using project management software eliminates the need to perform cumbersome
calculations manually and allows for “what if” analysis as activity duration estimates or
dependencies change. Recall that knowing which activities have the most slack allows the
project manager to reallocate resources or make other changes to compress the schedule
or help keep it on track.
Project 2013 easily creates Gantt charts and Tracking Gantt charts, which make
it easier for project teams to track actual schedule performance versus the planned or
baseline schedule. However, for a project to benefit from using Tracking Gantt charts,
actual schedule information must be entered in a timely manner. Some organizations
use e-mail or other communications software to send updated task and schedule in-
formation to the person responsible for updating the schedule. He or she can then
quickly authorize these updates and enter them directly into the project management
software. This process provides an accurate and up-to-date project schedule in Gantt
chart form.
Project 2013 also includes many built-in reports, views, and filters to assist in proj-
ect time management. For example, a project manager can quickly run a report to list all
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

tasks that are scheduled to start soon, and then send a reminder to the people responsible
for these tasks. A project manager who was presenting project schedule information to top
management could create a Gantt chart showing only summary tasks or milestones. You
can also create custom reports, views, tables, and filters. See Appendix A to learn how to
use the project time management features of Project 2013.
G L O B A L I S S U E S
Most software companies use case studies or customer testimonials to showcase how
their software helps customers solve business problems. Microsoft tells the customer
story of Mexico’s Secretary of Economy, who wanted to ensure that IT initiatives
aligned with business goals and improved project management efficiency. Internal
IT project requests often took several weeks to fulfill because the organization lacked
a centralized method of capturing project information and used several
diagramming tools.
The Director General of Information Technology decided to establish an Office of
Project Management and search for a solution that combined professional diagramming
capabilities with project management and collaboration tools. Assistant Director General
of the Office of Information Technology, Carlos Benítez Gonzales, worked with other
agencies to find the best solution. After deploying several of Microsoft’s tools (Visio, Proj-
ect, and SharePoint), the organization was able to handle more internal IT projects with-
out adding staff, while fulfilling requests 60 percent faster.
“By documenting and incorporating governance procedures and project lifecycle
stages into a standardized workflow process, the Secretary’s IT team can finish projects
in less time. Benítez estimates that it previously took an average of five business days
to fulfill requests. The team can now complete the same work in two business days on
average … ‘We now have a single platform for managing process information that used to
be scattered throughout the organization and inaccessible because it was stored on local
computers,’ says Benítez. The IT team can now handle four times the number of concur-
rent projects without the need to hire additional staff.”14
Words of Caution on Using Project Management Software
Many people misuse project management software because they do not understand the
concepts behind creating a network diagram, determining the critical path, or setting a
schedule baseline. They might also rely too heavily on sample files or templates in devel-
oping their own project schedules. Understanding the underlying concepts (or even being
able to work with the tools manually) is critical to successful use of project management
software, as is understanding the specific needs of your project.
Many top managers, including software professionals, have made blatant errors using
various versions of Microsoft Project and similar tools. For example, one top manager did
not know how to establish dependencies among project activities and entered every single
start and end date for hundreds of activities. When asked what would happen if the project
started a week or two late, she responded that she would have to reenter all of the dates.
This manager did not understand the importance of establishing relationships among
the tasks, which allows the software to update formulas automatically when the inputs
change. If the project start date slips by one week, the project management software will
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

252
update all the other dates automatically, as long as they are not hard-coded into the soft-
ware. (Hard-coding involves entering all activity dates manually instead of letting the soft-
ware calculate them based on durations and relationships.) If one activity cannot start before
another ends, and the first activity’s actual start date is two days late, the start date for the
succeeding activity will automatically be moved back two days. To achieve this type of func-
tionality, tasks that have relationships must be linked in project management software.
Another top manager on a large IT project did not know how to set a baseline in Mi-
crosoft Project. He spent almost one day every week copying and pasting information from
Microsoft Project into a spreadsheet and using complicated “IF” statements to figure out
what activities were behind schedule. He had never received training on Microsoft Project
and did not know about many of its capabilities. To use any software effectively, users must
have adequate training in the software and an understanding of its underlying concepts.
Many project management software programs also come with templates or sample
files. It is very easy to use these files without considering unique project needs. For ex-
ample, a project manager for a software development project can use the Microsoft Project
Software Development template file, the files from similar projects done in the past, or
sample files purchased from other companies. All of these files include suggested tasks,
durations, and relationships. There are benefits to using templates or sample files, such as
less setup time and a reality check if the project manager has never led a certain type of
project before. However, there are drawbacks to this approach. Many assumptions made in
these template files might not apply to the project, such as a design phase that takes three
months to complete or the performance of certain types of testing. Project managers and
their teams should be careful not to rely too much on templates or sample files and ignore
the unique concerns of their particular projects.
C A S E W R A P – U P
It was now March 15, just a month and a half before the new online registration system
was supposed to go live. The project was in total chaos. Sue Johnson thought she could
handle all of the conflicts that kept occurring on the project, and she was too proud and
scared to admit to her top management or the college president that things were not going
well. She spent a lot of time preparing a detailed schedule for the project, and she thought
she was using the project management software well enough to keep up with project sta-
tus. However, the five main programmers on the project all figured out a way to generate
automatic updates for their tasks every week, saying that everything was completed as
planned. They paid very little attention to the actual plan and hated filling out status in-
formation. Sue did not check most of their work to verify that it was actually completed.
In addition, the head of the Registrar’s Office was uninterested in the project and del-
egated sign-off responsibility to one of his clerks, who did not completely understand the
registration process. When Sue and her team started testing the new system, she learned
they were using last year’s course data, which caused additional problems because the col-
lege was moving from quarters to semesters in the new term. How could they have missed
that requirement? Sue hung her head in shame and anguish as she walked into a meeting
with her manager to ask for help. She learned the hard way how difficult it was to keep a
project on track. She wished she had spent more time talking face to face with key project
stakeholders, especially her programmers and the Registrar’s Office representatives, to
verify that the project was on schedule and that the schedule was updated accurately.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

253
Chapter Summary





Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

254



Quick Quiz

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

255
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Quick Quiz Answers
Discussion Questions

pad-
ding estimates
Exercises


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

257

TABLE 6-2
Activity Initial Node Final Node Estimated Duration
A 1 2 2
B 2 3 2
C 2 4 3
D 2 5 4
E 3 6 2
F 4 6 3
G 5 7 6
H 6 8 2
I 6 7 5
J 7 8 1
K 8 9 2
© Cengage Learning 2016


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

258
TABLE 6-3
Activity Initial Node Final Node Estimated Duration
A 1 2 10
B 1 3 12
C 1 4 8
D 2 3 4
E 2 5 8
F 3 4 6
G 4 5 4
H 4 6 8
I 5 6 6
J 5 8 12
K 6 7 8
L 7 8 10
© Cengage Learning 2016



www.microsoft.com
/project www.matchware.com
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

259

Running Case


Tasks




Key Terms
activity
activity attributes
activity list
activity-on-arrow (AOA)
arrow diagramming method (ADM)
backward pass
baseline dates
buffer
burst
crashing
critical chain scheduling
critical path
critical path method (CPM) or critical path
analysis
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

dependency
discretionary dependencies
dummy activities
duration
early finish date
early start date
effort
external dependencies
fast tracking
feeding buffers
finish-to-finish dependency
finish-to-start dependency
float
forward pass
free slack (free float)
Gantt chart
late finish date
late start date
mandatory dependencies
merge
milestone
multitasking
Murphy’s Law
network diagram
node
Parkinson’s Law
PERT weighted average
precedence diagramming method (PDM)
probabilistic time estimates
Program Evaluation and Review Technique
(PERT)
project buffer
project time management
relationship
resource breakdown structure
resources
schedule baseline
slack
slipped milestone
SMART criteria
start-to-finish dependency
start-to-start dependency
task
Theory of Constraints (TOC)
three-point estimate
total slack (total float)
Tracking Gantt chart
End Notes
ABC Online
Minneapolis Star
Tribune

InfoWorld Tech Watch
FederalTimes.com
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Newsweek
The Happiness Advantage
Critical Chain

Quality Management in Health Care
www.goldratt.com
/resultsoverview
CIO.com
Computerworld
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R7
PROJECT COST
MANAGEMENT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

264
O P E N I N G C A S E
Juan Gonzales was a systems analyst and network specialist for the waterworks depart-
ment of a major Mexican city. He enjoyed helping the city develop its infrastructure.
His next career objective was to become a project manager so he could have even more
influence. One of his colleagues invited him to attend an important project review meet-
ing for large government projects, including the Surveyor Pro project, in which Juan was
most interested. The Surveyor Pro project was a concept for developing a sophisticated
information system that included expert systems, object-oriented databases, and wire-
less communications. The system would provide instant, graphical information to help
government surveyors do their jobs. For example, after a surveyor touched a map on the
screen of a handheld device, the system would prompt the surveyor to enter the type of
information needed for that area. This system would help in planning and implementing
many projects, from laying fiber-optic cable to installing water lines.
Juan was very surprised, however, that the majority of the meeting was spent dis-
cussing cost-related issues. The government officials were reviewing many existing pro-
jects to evaluate their performance and the potential impact on the government’s budget
before discussing funding for any new projects. Juan did not understand many of the
terms and charts being presented. What was this “earned value” they kept referring to?
How were they estimating what it would cost to complete projects or how long it would
take? Juan thought he would learn more about the new technologies the Surveyor Pro
project would use, but he discovered that the cost estimates and projected benefits were
of most interest to the government officials at the meeting. It also seemed that consider-
able effort would go toward detailed financial studies before any technical work could
even start. Juan wished he had taken some accounting and finance courses so he could
understand the acronyms and concepts people were discussing. Although Juan had a
degree in electrical engineering, he had no formal education in finance and little experi-
ence with it. However, if Juan could understand information systems and networks, he
was confident that he could understand financial issues on projects as well. He jotted
down questions to discuss with his colleagues after the meeting.
7.1 THE IMPORTANCE OF PROJECT COST MANAGEMENT
IT projects have a poor track record in meeting budget goals. A 2011 study published in the
Harvard Business Review examined IT change initiatives in almost 1,500 projects and re-
ported an average cost overrun of 27 percent. Cost overrun is the additional percentage or
dollar amount by which actual costs exceed estimates. The study was considered the largest
ever to analyze IT projects. The projects ranged from enterprise resource planning to man-
agement information and customer relationship management systems. Most projects incurred
high expenses, with an average cost of $167 million; the largest project cost $33 billion.1
The most important finding in the study, however, was the discovery of a large num-
ber of gigantic overages when analyzing the project overrun data. One in six of all projects
studied contained a “black swan”: a high-impact event that is rare and unpredictable, but
not improbable in retrospect. These IT black swan projects had an average cost overrun
of 200 percent and a schedule overrun of almost 70 percent. “This highlights the true pit-
fall of IT change initiatives: It’s not that they’re particularly prone to high cost overruns
on average, as management consultants and academic studies have previously suggested.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo
影响很大的事件是罕见并且不可预估的。同时也是不可能回顾的

265
It’s that an unusually large proportion of them incur massive overages—that is, there are
a disproportionate number of black swans. By focusing on averages instead of the more
damaging outliers, most managers and consultants have been missing the real problem.”2
Obviously, IT projects have room for improvement in meeting cost goals. This chapter de-
scribes important concepts in project cost management, particularly planning cost management,
creating good estimates, and using earned value management (EVM) to assist in cost control.
W H A T W E N T W R O N G ?
The United Kingdom’s National Health Service (NHS) IT modernization program was
called “the greatest IT disaster in history” by one London columnist. This 10-year pro-
gram, which started in 2002, was created to provide an electronic patient records system,
appointment booking, and a prescription drug system in England and Wales. Britain’s
Labor government estimates that the program will eventually cost more than $55 bil-
lion, a $26 billion overrun. The program has been plagued by technical problems due to
incompatible systems, resistance from physicians who say they were not adequately con-
sulted about system features, and arguments among contractors about who’s responsible
for what.3 A government audit in June 2006 found that the program, one of the largest
civilian IT projects undertaken worldwide, was progressing despite high-profile problems.
In an effort to reduce cost overruns, the NHS program would no longer pay for products
until delivery, shifting some financial responsibility to prime contractors, including BT
Group, Accenture, and Fujitsu Services.4 On September 22, 2011, government officials
in the United Kingdom announced that they were scrapping the National Programme for
Health IT. Health Secretary Andrew Lansley said that the program “let down the NHS and
wasted taxpayers’ money.”5
7.1a What Is Cost?
A popular cost accounting textbook states, “Accountants usually define cost as a resource
sacrificed or foregone to achieve a specific objective.”6 Webster’s dictionary defines cost as
“something given up in exchange.” Costs are often measured in monetary amounts, such
as dollars, that must be paid to acquire goods and services. (For convenience, the exam-
ples in this chapter use dollars for monetary amounts.) Because projects cost money and
consume resources that could be used elsewhere, it is very important for project managers
to understand project cost management.
Many IT professionals, however, often react to cost overrun information with a smirk.
They know that many of the original cost estimates for IT projects are low or based on
unclear project requirements, so naturally there will be cost overruns. Not emphasizing
the importance of realistic project cost estimates from the outset is only one part of the
problem. In addition, many IT professionals think that preparing cost estimates is a job for
accountants. On the contrary, preparing good cost estimates is a demanding, important
skill that many professionals need to acquire.
Another perceived reason for cost overruns is that many IT projects involve new tech-
nology or business processes. Any new technology or business process is untested and has
inherent risks. Thus, costs grow and failures are to be expected, right? Wrong. Using good
project cost management can change this false perception.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo
专栏作家

lenovo
主要承包商

lenovo
从一开始

lenovo

lenovo
固有风险

Taurus

Taurus

266
7.1b What Is Project Cost Management?
Recall from Chapter 1 that the triple constraint of project management involves balancing
scope, time, and cost goals. Chapters 5 and 6 discuss project scope and time management,
and this chapter describes project cost management. Project cost management includes
the processes required to ensure that a project team completes a project within an ap-
proved budget. Notice two crucial phrases in this definition: “a project” and “approved
budget.” Project managers must make sure their projects are well defined, have accurate
time and cost estimates, and have a realistic budget that they were involved in approving.
It is the project manager’s job to satisfy project stakeholders while continuously striv-
ing to reduce and control costs. There are four processes for project cost management:
1. Planning cost management involves determining the policies, procedures,
and documentation that will be used for planning, executing, and controlling
project cost. The main output of this process is a cost management plan.
2. Estimating costs involves developing an approximation or estimate of the
costs of the resources needed to complete a project. The main outputs of the
cost estimating process are activity cost estimates, basis of estimates, and
project documents updates.
3. Determining the budget involves allocating the overall cost estimate to in-
dividual work items to establish a baseline for measuring performance. The
main outputs of the cost budgeting process are a cost baseline, project fund-
ing requirements, and project documents updates.
4. Controlling costs involves controlling changes to the project budget. The
main outputs of the cost control process are work performance information,
cost forecasts, change requests, project management plan updates, project
documents updates, and organizational process assets updates.
Figure 7-1 summarizes these processes and outputs, showing when they occur in a
typical project.
To understand each of the project cost management processes, you must first under-
stand the basic principles of cost management. Many of these principles are not unique to
project management; however, project managers need to understand how these principles
relate to their specific projects.
7.2 BASIC PRINCIPLES OF COST MANAGEMENT
Many IT projects are never initiated because IT professionals do not understand the impor-
tance of basic accounting and finance principles. Important concepts such as net present
value analysis, return on investment, and payback analysis were discussed in Chapter 4,
Project Integration Management. Likewise, many projects that are started never finish
because of cost management problems. Most members of an executive board have a better
understanding of financial terms than IT terms, and are more interested in finance. There-
fore, IT project managers need to be able to present and discuss project information both
in financial terms and technical terms. In addition to net present value analysis, return on
investment, and payback analysis, project managers must understand several other cost
management principles, concepts, and terms. This section describes general topics such
as profits, life cycle costing, cash flow analysis, tangible and intangible costs and benefits,
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo
项目综合管理

lenovo

direct costs, sunk costs, learning curve theory, and reserves. Another important topic—
earned value management—is one of the key tools and techniques for controlling project
costs; it is described in detail in the section on cost control.
Profits are revenues minus expenditures. To increase profits, a company can increase
revenues, decrease expenses, or try to do both. Most executives are more concerned with
profits than with other issues. When justifying investments in new information systems
and technology, it is important to focus on the impact on profits, not just revenues or
expenses. Consider an e-commerce application that you estimate will increase revenues
for a $100 million company by 10 percent. You cannot measure the potential benefits of
the application without knowing the profit margin. Profit margin is the ratio of profits to
revenues. If revenues of $100 generate $2 in profits, there is a 2 percent profit margin. If
the company loses $2 for every $100 in revenue, there is a 22 percent profit margin.
Life cycle costing provides a big-picture view of the cost of a project throughout its
life cycle. This helps you develop an accurate projection of a project’s financial costs and
benefits. Life cycle costing considers the total cost of ownership, or development plus
support costs, for a project. For example, a company might complete a project to develop
and implement a new customer service system in 1 or 2 years, but the new system could
be in place for 10 years. Project managers, with assistance from financial experts in their
organizations, should create estimates of the costs and benefits of the project for its entire
life cycle (10 years in the preceding example). Recall from Chapter 4 that the net present
value analysis for the project would include the entire 10-year period of costs and ben-
efits. Top management and project managers need to consider the life cycle costs of proj-
ects when they make financial decisions.
FIGURE 7-1
Planning
Process: Plan cost management
Outputs: Cost management plan
Process: Estimate costs
Outputs: Activity cost estimates, basis of estimates, project documents
updates
Process: Determine budget
Outputs: Cost baseline, project funding requirements, project
documents updates

Project Start Project Finish
Monitoring and Controlling
Process: Control costs
Outputs: Work performance information, cost forecasts, change requests,
project management plan updates, project documents updates,
organizational process assets updates
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo
总拥有成本

lenovo

268
M E D I A S N A P S H O T
A primary goal of many projects is to achieve some type of financial benefits, measured
using life cycle costing. Project success criteria often include reaching a certain return on
investment (ROI) over the life cycle. You cannot measure ROI for projects if you do not
have a benefits measurement process in place. How do you know if you earned or saved
a certain amount each year after the project was completed if you do not have a way to
measure it? According to a 2015 report by PMI:
Many organizations do not have a benefits measurement process at all.
Only twenty percent of organizations report having a high level of benefits
realization maturity.
Thirty-nine percent of high-performing organizations report high benefits
realization maturity compared to nine percent of low performers.
“Organizations with mature benefits realization processes can benefit from:
Clearly identifying the strategic rewards prior to starting a project
Effectively assessing and monitoring risks to project success
Proactively planning for making necessary changes in the organization
Explicitly defining accountability for project success
Routinely extending responsibility for integration to the project team.”7
Organizations have a history of not spending enough money in the early phases of
IT projects, which affects total cost of ownership. For example, it is much more cost-
effective to spend money on defining user requirements and doing early testing on IT proj-
ects than to wait for problems to appear after implementation. Recall from Chapter 5 that
correcting a software defect late in a project costs much more than fixing the defect early.
Because organizations depend on reliable IT, huge costs are associated with downtime.
When Facebook was down for 20 minutes on September 3, 2014, they lost
a little more than $22,453 for every minute or more than $500,000.8
On August 19, 2013, Amazon.com went down for about 30 minutes, costing
them $66,240 per minute or nearly $2 million.9
For Fortune 1000 companies, the average cost of an infrastructure failure
is $100,000 per hour; the average cost of a critical application failure is
$500,000 to $1 million per hour, or $8,300 to $16,600 per minute.10
In 2014, the average annual cost of unplanned application downtime in
Fortune 1000 companies was $1.25 billion to $2.5 billion.11
W H A T W E N T R I G H T ?
An important cost-cutting strategy has been inspired by the global emphasis on improv-
ing the environment. Investing in green IT and other initiatives has helped both the envi-
ronment and companies’ bottom lines. Michael Dell, CEO of Dell, said he aimed to make
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

269
Cash flow analysis is a method for determining the estimated annual costs and benefits
for a project and the resulting annual cash flow. Project managers must conduct cash flow
analysis to determine net present value. Most consumers understand the basic concept of
cash flow: If they do not have enough money in their wallets or bank accounts, they can-
not purchase something. Top management must consider cash flow concerns when select-
ing projects in which to invest. If top management selects too many projects that have high
cash flow needs in the same year, the company will not be able to support all of its projects
and maintain its profitability. It is also important to clarify the year used to analyze dollar
amounts. For example, if a company bases all costs on 2012 estimates, it would need to
account for inflation and other factors when projecting costs and benefits in future-year dollars.
Tangible and intangible costs and benefits are categories for determining how well an
organization can define the estimated costs and benefits for a project. Tangible costs or
benefits are easy to measure in dollars. For example, suppose that the Surveyor Pro proj-
ect described in the chapter’s opening case included a preliminary feasibility study. If a
company completed this study for $100,000, its tangible cost is $100,000. If a government
agency estimated that it could have done the study for $150,000, the tangible benefits of
the study would be $50,000 to the government: It could pay for the study and then assign
the government workers who would have done the study to other projects.
In contrast, intangible costs or benefits are difficult to measure in dollars. Suppose
that Juan and a few other people spent their own personal time using government-owned
computers, books, and other resources to research areas related to the study. Although
their hours and the government-owned materials would not be billed to the project, they
could be considered intangible costs. Intangible benefits for projects often include items
like goodwill, prestige, and general statements of improved productivity that an organiza-
tion cannot easily translate into dollar amounts. Because intangible costs and benefits are
difficult to quantify, they are often harder to justify.
Direct costs can be directly related to creating the products and services of the proj-
ect. You can attribute direct costs to a particular project. For example, direct costs include
his company “carbon neutral” in 2008. “The computer giant is looking to zero-out
its carbon emissions through a number of initiatives, such as offering small busi-
nesses and consumers curbside recycling of their old computers, stuffing small re-
cycling bags with free postage into new printer-ink cartridge boxes, and operating a
‘Plant a Tree for Me’ program.”12 Dell did reach his goal; as of March 2012, Dell had
helped its customers save almost $7 billion in energy costs.
Dell continues to practice corporate responsibility by helping the environ-
ment. In 2014, they reported the following progress:
Recovered 230.9 million pounds of used electronics and are on track to
reach our goal of 2 billion pounds by 2020
Reduced the average energy intensity of our product line by 23.2 percent
compared to FY12
Decreased operational emissions by 10 percent
Used more than 10 million pounds of post-consumer recycled plastics
in our products13
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo
澄清阐明

lenovo
膨胀 通货膨胀 夸张

lenovo
突出

lenovo
初步可行性分析

lenovo
有形和无形

lenovo
名望声望

lenovo
商誉

lenovo

lenovo

Taurus

the salaries of people working full time on the project and the cost of hardware and soft-
ware purchased specifically for the project. Project managers should focus on direct costs
because they can be controlled.
Indirect costs are not directly related to the products or services of the project, but
are indirectly related to performing work on the project. For example, indirect costs would
include the cost of electricity, paper towels, and other necessities in a large building that
houses 1,000 employees who work on many projects. Indirect costs are allocated to
projects, and project managers have very little control over them.
Sunk cost is money that has been spent in the past. Consider it gone, like a sunken
ship that can never be raised. When deciding what projects to invest in or continue, you
should not include sunk costs. For example, in the chapter’s opening case, suppose that
Juan’s office had spent $1 million on a project over the past three years to create a geo-
graphic information system, but had never produced anything valuable. If his government
were evaluating what projects to fund next year and an official suggested continuing to
fund the geographic information system project because $1 million had been spent on it
already, the official would incorrectly be making sunk cost a key factor in the project se-
lection decision. Many people fall into the trap of continuing to spend money on a failing
project because so much money has been spent on it already. This trap is similar to gam-
blers who continue betting because they have already lost money. Sunk costs should be
forgotten, even though it is often difficult to think that way.
Learning curve theory states that when many items are produced repetitively, the
unit cost of those items decreases in a regular pattern as more units are produced. For
example, suppose that the Surveyor Pro project would potentially produce 1,000 handheld
devices that could run the new software and access information via satellite. The cost of
the first handheld unit would be much higher than the cost of the thousandth unit. Learn-
ing curve theory can help estimate costs on projects that involve the production of large
quantities of items.
Learning curve theory also applies to the amount of time required to complete some
tasks. For example, the first time a new employee performs a specific task, it will probably
take longer than the tenth time that employee performs a very similar task. Effort esti-
mates, therefore, should be lower for more experienced workers.
Reserves are dollar amounts included in a cost estimate to mitigate cost risk by allow-
ing for future situations that are difficult to predict. Contingency reserves allow for future
situations that may be partially planned for (sometimes called known unknowns) and are
included in the project cost baseline. For example, if an organization knows it has a 20
percent rate of turnover for IT personnel, it should include contingency reserves to pay
for recruiting and training costs of IT personnel. Management reserves allow for future
situations that are unpredictable (sometimes called unknown unknowns). For example,
if a project manager gets sick for two weeks or an important supplier goes out of business,
management reserve could be set aside to cover the resulting costs. Management reserves
are not included in a cost baseline, as you will learn later in this chapter.
7.3 PLANNING COST MANAGEMENT
The first step in project cost management is planning how the costs will be managed
throughout the life of the project. Project costs, like project schedules, grow out of the
basic documents that initiate a project, like the project charter. The project manager and
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo
陷阱 圈套

lenovo
赌徒

lenovo

lenovo

lenovo
储备金

lenovo

lenovo

lenovo
招聘和培训

lenovo

lenovo
停业

lenovo

lenovo

已经花掉的但是没有产生任何价值的钱,在进行后边决策时候不应该考虑在内,不应该因为已经有了沉没花费就继续进行投资,沉没投资不应该作为决策的因素

同样的产品进行大批量生产,第一次的花费要远远大于这批产品花费的平均值,与学习曲线表现的进程类似

同上,对于要做重复性工作的人来说,第一次做这个工作会因为不熟悉等因素造成花费的时间比第十次第一百次多很多,也可以利用学习曲线来说明

other stakeholders use expert judgment, analytical techniques, and meetings to produce
the cost management plan.
The cost management plan, like the scope and schedule management plans, can be
informal and broad or formal and detailed, based on the needs of the project. In general, a
cost management plan includes the following information:
Level of accuracy: Activity cost estimates normally have rounding guidelines,
such as rounding to the nearest $100. There may also be guidelines for the
amount of contingency funds to include, such as 10 or 20 percent.
Units of measure: Each unit used in cost measurements, such as labor hours
or days, should be defined.
Organizational procedures links: Many organizations refer to the work
breakdown structure (WBS) component used for project cost accounting as
the control account (CA). Each control account is often assigned a unique
code that is used in the organization’s accounting system. Project teams must
understand and use these codes properly.
Control thresholds: Similar to schedule variance, costs often have a specified
amount of variation allowed before action needs to be taken, such as ±10 per-
cent of the baseline cost.
Rules of performance measurement: If the project uses earned value man-
agement (EVM), as described later in this chapter, the cost management
plan would define measurement rules, such as how often actual costs will be
tracked and to what level of detail.
Reporting formats: This section would describe the format and frequency of
cost reports required for the project.
Process descriptions: The cost management plan would also describe how to
perform all of the cost management processes.
7.4 ESTIMATING COSTS
Project managers must take cost estimates seriously if they want to complete projects
within budget constraints. After developing a good resource requirements list, project
managers and their project teams must develop several estimates of the costs for these
resources. Recall from Chapter 6 that an important process in project time management is
estimating activity resources, which provides a list of activity resource requirements. For
example, if an activity for a project is to perform a particular type of test, the list of activ-
ity resource requirements would describe the skill level of the people needed to perform
the test, the number of people and hours suggested to perform the test, the need for spe-
cial software or equipment, and other requirements. All of this information is required to
develop a good cost estimate. This section describes various types of cost estimates, tools
and techniques for estimating costs, typical problems associated with IT cost estimates,
and a detailed example of a cost estimate for an IT project.
7.4a Types of Cost Estimates
One of the main outputs of project cost management is a cost estimate. Project managers
normally prepare several types of cost estimates for most projects. Three basic types of
estimates include the following:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

精确度

计算单位

组织性程序
的链接

控制界限,极限

绩效考核标准

A rough order of magnitude (ROM) estimate provides an estimate of what a
project will cost. A ROM estimate can also be referred to as a ballpark estimate,
a guesstimate, a swag, or a broad gauge. This type of estimate is done very early
in a project or even before a project is officially started. Project managers and
top management use this estimate to help make project selection decisions. The
time frame for this type of estimate is often three or more years prior to project
completion. A ROM estimate’s accuracy is typically -50 percent to +100 percent,
meaning the project’s actual costs could be 50 percent below the ROM estimate
or 100 percent above. For example, the actual cost for a project with a ROM
estimate of $100,000 could range from $50,000 to $200,000. For IT project esti-
mates, this accuracy range is often much wider. Many IT professionals automati-
cally double estimates for software development because of the history of cost
overruns on IT projects.
A budgetary estimate is used to allocate money into an organization’s bud-
get. Many organizations develop budgets at least two years into the future.
Budgetary estimates are made one to two years prior to project completion.
The accuracy of budgetary estimates is typically -10 percent to +25 percent,
meaning the actual costs could be 10 percent less or 25 percent more than
the budgetary estimate. For example, the actual cost for a project with a bud-
getary estimate of $100,000 could range from $90,000 to $125,000.
A definitive estimate provides an accurate estimate of project costs. Defini-
tive estimates are used for making many purchasing decisions for which
accurate estimates are required and for estimating final project costs. For
example, if a project involves purchasing 1,000 personal computers from an
outside supplier in the next three months, a definitive estimate would be re-
quired to aid in evaluating supplier proposals and allocating the funds to pay
the chosen supplier. Definitive estimates are made one year or less prior to
project completion. A definitive estimate should be the most accurate of the
three types of estimates. The accuracy of this type of estimate is normally -5
percent to +10 percent, meaning the actual costs could be 5 percent less or
10 percent more than the definitive estimate. For example, the actual cost
for a project with a definitive estimate of $100,000 could range from $95,000
to $110,000. Table 7-1 summarizes the three basic types of cost estimates.
TABLE 7-1
Type of Estimate When Done Why Done How Accurate
Rough order of
magnitude (ROM)
Very early in the project life
cycle, often 3–5 years before
project completion
Provides estimate of cost for
selection decisions
-50% to +100%
Budgetary Early, 1–2 years out Puts dollars in the budget
plans
-10% to +25%
Definitive Later in the project, less than
1 year out
Provides details for
purchases, estimates
actual costs
-5% to +10%
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

The number and type of cost estimates vary by application area. For example, the
Association for the Advancement of Cost Engineering (AACE) International identifies five
types of cost estimates for construction projects: order of magnitude, conceptual, prelimi-
nary, definitive, and control. The main point is that estimates are usually done at various
stages of a project and should become more accurate as time progresses.
In addition to creating cost estimates for the entire project and activity cost esti-
mates, it is also important to provide supporting details for the estimates and updates to
project documents. The supporting details include the ground rules and assumptions used
in creating the estimate, a description of the project (such as scope statement and WBS)
used as a basis for the estimate, and details on the cost estimation tools and techniques
used to create the estimate. These supporting details should make it easier to prepare an
updated estimate or similar estimate as needed.
Another important consideration in preparing cost estimates is labor costs, because a
large percentage of total project costs are often labor costs. Many organizations estimate
the number of people or hours they need by department or skill over the life cycle of a
project. For example, when Northwest Airlines developed initial cost estimates for its res-
ervation system project, ResNet, it determined the maximum number of full-time equiva-
lent (FTE) staff it could assign to the project each year by department. Table 7-2 shows
this information. Note the small number of contractors that Northwest Airlines planned
to use. Labor costs are often much higher for contractors, so it is important to distinguish
between internal and external resources. (See the companion website for this text to read
the detailed case study on ResNet, including cost estimates.)
TABLE 7-2
Department Year 1 Year 2 Year 3 Year 4 Year 5 Totals
Information systems 24 31 35 13 13 116
Marketing systems 3 3 3 3 3 15
Reservations 12 29 33 9 7 90
Contractors 2 3 1 0 0 6
Totals 41 66 72 25 23 227
© Cengage Learning 2016
7.4b Cost Estimation Tools and Techniques
As you can imagine, developing a good cost estimate is difficult. Fortunately, several tools
and techniques are available to assist in creating one. These tools and techniques include
expert judgment, analogous cost estimating, bottom-up estimating, three-point estimating,
parametric estimating, the cost of quality, project management estimating software, ven-
dor bid analysis, and reserve analysis.
Analogous estimates, also called top-down estimates, use the actual cost of a pre-
vious, similar project as the basis for estimating the cost of the current project. This
technique requires a good deal of expert judgment and is generally less costly than other
techniques, but it is also less accurate. Analogous estimates are most reliable when the
previous projects are similar in fact, not just in appearance. In addition, the groups
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

preparing cost estimates must have the needed expertise to determine whether certain
parts of the project will be more or less expensive than analogous projects. For example,
estimators often try to find a similar project and then customize or modify it for known
differences. However, if the project to be estimated involves a new programming language
or working with a new type of hardware or network, the analogous estimate technique
could easily result in too low an estimate.
Bottom-up estimates involve estimating the costs of individual work items or activi-
ties and summing them to get a project total. This approach is sometimes referred to as
activity-based costing. The size of the individual work items and the experience of the
estimators drive the accuracy of the estimates. If a detailed WBS is available for a project,
the project manager could require each person who is responsible for a work package to
develop a cost estimate for that work package, or at least an estimate of the amount of re-
sources required. Someone in the financial area of an organization often provides resource
cost rates, such as labor rates or costs per pound of materials, which can be entered into
project management software to calculate costs. The software automatically calculates
information to create cost estimates for each level of the WBS and finally for the entire
project. Using smaller work items increases the accuracy of the cost estimate because the
people assigned to do the work develop the cost estimate instead of someone unfamiliar
with the work. The drawback with bottom-up estimates is that they are usually time-
intensive and therefore expensive to develop.
Three-point estimates involve estimating the most likely, optimistic, and pessimistic
costs for items. You can use a formula like the PERT weighted average described in
Chapter 6, Project Time Management, to calculate cost estimates or use a Monte Carlo
simulation, described in Chapter 11, Project Risk Management.
Parametric estimating uses project characteristics (parameters) in a mathematical
model to estimate project costs. For example, a parametric model might provide an es-
timate of $50 per line of code for a software development project based on the program-
ming language the project is using, the level of expertise of the programmers, the size and
complexity of the data involved, and so on. Parametric models are most reliable when the
historical information used to create the model is accurate, the parameters are readily
quantifiable, and the model is flexible in terms of the project’s size. Many projects involv-
ing building construction use parametric estimates based on cost per square foot. The
costs vary based on the quality of construction, location, materials, and other factors. In
practice, many people find that using a combination or hybrid approach with analogous,
bottom-up, three-point, and parametric estimating provides the best cost estimates.
Other considerations when preparing cost estimates are how much to include in re-
serves, as described earlier; the cost of quality, as described in Chapter 8, Project Quality
Management; and other cost estimating methods such as vendor bid analysis, as described
in Chapter 12, Project Procurement Management. Using software to assist in cost
estimating is described later in this chapter.
7.4c Typical Problems with IT Cost Estimates
Although many tools and techniques can assist in creating project cost estimates, many
IT project cost estimates are still very inaccurate, especially those for new technologies or
software development. Tom DeMarco, a well-known author on software development, sug-
gests four reasons for these inaccuracies and some ways to overcome them.14
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Estimates are done too quickly. Developing an estimate for a large software
project is a complex task that requires significant effort. Many estimates must
be done quickly and before clear system requirements have been produced. For
example, the Surveyor Pro project described in the opening case involves a lot of
complex software development. Before fully understanding what information sur-
veyors need in the system, someone would have to create a ROM estimate and
budgetary estimates for this project. Rarely are the more precise, later cost esti-
mates less than the earlier estimates for IT projects. It is important to remember
that estimates are done at various stages of the project, and project managers
need to explain the rationale for each estimate.
People lack estimating experience. The people who develop software cost
estimates often do not have much experience with cost estimation, especially
for large projects. They also do not have enough accurate, reliable project
data on which to base estimates. If an organization uses good project man-
agement techniques and develops a history of keeping reliable project infor-
mation, including estimates, the organization’s estimates should improve.
Enabling IT people to receive training and mentoring on cost estimating will
also improve cost estimates.
Human beings are biased toward underestimation. For example, senior IT
professionals or project managers might make estimates based on their own
abilities and forget that many younger people will be working on a project.
Estimators might also forget to allow for extra costs needed for integration
and testing on large IT projects. It is important for project managers and top
management to review estimates and ask important questions to make sure
the estimates are not biased.
Management desires accuracy. Management might ask for an estimate but
really want a more accurate number to help them create a bid to win a ma-
jor contract or get internal funding. This problem is similar to the situation
discussed in Chapter 6, Project Time Management, in which top managers or
other stakeholders want project schedules to be shorter than the estimates.
It is important for project managers to help develop good cost and schedule
estimates and to use their leadership and negotiation skills to stand by those
estimates.
It is also important to be cautious with initial estimates. Top management never for-
gets the first estimate and rarely, if ever, remembers how approved changes affect the
estimate. It is a never-ending and crucial process to keep top management informed about
revised cost estimates. It should be a formal process, albeit a possibly painful one.
7.4d How to Develop a Cost Estimate
One of the best ways to learn how the cost estimating process works is by studying sample
cost estimates. Every cost estimate is unique, just as every project is unique. You can see
a short sample cost estimate in Chapter 3 for JWD Consulting’s project management in-
tranet site project. You can also view the ResNet cost estimate on the companion website
for this text.
This section includes a step-by-step approach for developing a cost estimate for the
Surveyor Pro project described in the opening case. Of course, it is much shorter and
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

simpler than a real cost estimate, but it illustrates a process to follow and uses several of
the tools and techniques described earlier.
Before beginning a cost estimate, you must gather as much information as possible
about the project and ask how the organization plans to use the cost estimate. If the cost
estimate will be the basis for contract awards and performance reporting, it should be a
definitive estimate and as accurate as possible, as described earlier.
It is also important to clarify the ground rules and assumptions for the estimate. The
Surveyor Pro project cost estimate includes the following ground rules and assumptions:
This project was preceded by a detailed study and proof of concept to show that
it was possible to develop the hardware and software needed by surveyors and
link the new devices to existing information systems. The proof of concept proj-
ect produced a prototype handheld device and much of the software to provide
basic functionality and link to the Global Positioning System (GPS) and other
government databases used by surveyors. Some data is available to help estimate
future labor costs, especially for the software development, and to help estimate
the cost of the handheld devices.
The main goal of this project is to produce 100 handheld devices, continue
developing the software (especially the user interface), test the new system in
the field, and train 100 surveyors in selected cities to use the new system. A
follow-up contract is expected for a much larger number of devices based on
the success of this project.
The project has the following WBS:
1. Project management
2. Hardware
2.1 Handheld devices
2.2 Servers
3. Software
3.1 Licensed software
3.2 Software development
4. Testing
5. Training and support
6. Reserves
Costs must be estimated by WBS and by month. The project manager will re-
port progress on the project using earned value analysis, which requires this
type of estimate.
Costs will be provided in U.S. dollars. Because the project length is one year,
inflation will not be included.
The project will be managed by the government’s project office. The project
will require a part-time project manager and four team members. The team
members will help manage various parts of the project and provide their
expertise in the areas of software development, training, and support. Their
total hours will be allocated as follows: 25 percent to project management,
25 percent to software development, 25 percent to training and support, and
25 percent to non-project work.
The project involves purchasing the handheld devices from the same com-
pany that developed the prototype device. Based on producing 100 devices,
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

the cost rate is estimated to be $600 per unit. The project will require four
additional servers to run the software required for the devices and for manag-
ing the project.
The project requires purchased software licenses for accessing the GPS and
three other external systems. Software development includes developing a
graphical user interface for the devices, an online help system, and a new
module for tracking surveyor performance using the device.
Testing costs should be low due to the success of the prototype project. An
estimate based on multiplying the total hardware and software estimates by
10 percent should be sufficient.
Training will include instructor-led classes in five different locations. The
project team believes it will be best to outsource most of the training, includ-
ing developing course materials, holding the sessions, and providing help desk
support for three months as the surveyors start using their devices in the field.
Because several risks are related to this project, include 20 percent of the
total estimate as reserves.
You must develop a computer model for the estimate so that you can easily
change several inputs, such as the number of labor hours for various activi-
ties or labor rates.
Fortunately, the project team can easily access cost estimates and actual information
from similar projects. A great deal of information is available from the proof of concept
project, and the team can also talk to contractors from the past project to help them de-
velop the estimate. Computer models are also available, such as a software-estimating tool
based on function points. Function points are a means of measuring software size based
on what the software does for end users. Function points are comprised of inputs, outputs,
inquiries, internal data, and external interface data. Allen Albrecht initially defined this
metric in the 1970s, and today it is the international standard used to measure software
size. It is the most commonly used software size metric, followed by lines of code.15
Because the estimate must be provided by WBS and by month, the team first reviews
a draft of the project schedule. The team decides to begin by estimating the cost of each
WBS item and then determine when the work will be performed, even though costs may
be incurred at different times than when the work is performed. The team’s budget expert
has approved this approach for the estimate. The team has further assumptions and infor-
mation for estimating the costs for each WBS category:
1. Project management: Estimate based on compensation for the part-time
project manager and 25 percent of the four team members’ time. The bud-
get expert for this project suggested using a labor rate of $100/hour for the
project manager and $75/hour for each team member, based on working an
average of 160 hours per month, full time. Therefore, the total hours for the
project manager under this category are 960 (160/2 * 12 5 960). Costs are
also included for the four project team members who are each working
25 percent of their time: a total of 160 hours per month for all project
personnel (160 * 12 5 1920). An additional amount for all contracted labor
is estimated by multiplying 10 percent of the total estimates for software
development and testing costs (10% * ($594,000 + $69,000)).
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

2. Hardware
2.1 Handheld devices: 100 devices estimated by contractor at $600 per
unit.
2.2 Servers: Four servers estimated at $4,000 each, based on recent server
purchases.
3. Software
3.1 Licensed software: License costs will be negotiated with each supplier.
Because there is a strong probability of large future contracts and great
publicity if the system works well, costs are expected to be lower than
usual. A cost of $200/handheld device will be used.
3.2 Software development: This estimate will include two approaches: a
labor estimate and a function point estimate. The higher estimate will
be used. If the estimates differ by more than 20 percent, the project
will require a third estimation approach. The supplier who developed
the proof of concept project will provide the labor estimate input, and
local technical experts will make the function point estimates.
4. Testing: Based on similar projects, testing will be estimated as 10 percent of
the total hardware and software cost.
5. Training and support: Based on similar projects, training will be estimated
on a per-trainee basis, plus travel costs. The cost per trainee (100 total) will
be $500, and travel will cost $700/day/person for the instructors and project
team members. The team estimates that the project will require a total of 12
travel days. Labor costs for the project team members will be added to this
estimate because they will assist in training and providing support after the
training. The labor hours estimate for team members is 1,920 hours total.
6. Reserves: As directed, reserves will be estimated at 20 percent of the total
estimate.
The project team then develops a cost model using the preceding information.
Figure 7-2 shows a spreadsheet that summarizes the costs by WBS item. Notice that the
WBS items are listed in the first column, and some are broken down into more detail
based on how the costs are estimated. For example, the project management category is
broken down into three subcategories because the project manager, team members, and
contractors will each perform project management activities that must be accounted for in
the costs. Also notice the columns for entering the number of units or hours and the cost
per unit or hour. Several items are estimated using this approach. The estimate includes
some short comments, such as reserves being 20 percent of the total estimate. Also notice
that you can easily change several input variables, such as number of hours or cost per
hour, to revise the estimate.
The asterisk by the software development item in Figure 7-2 provides reference for de-
tailed information on how this more complicated estimate was made. Recall the assumption
that software development must be estimated using two approaches, and that the higher esti-
mate would be used as long as both estimates differed by no more than 20 percent. The labor
estimate was used in this case because it was slightly higher than the function point estimate
($594,000 versus $567,000). Figure 7-3 shows how the function point estimate was made,
and the Best Practice feature provides more information on function point estimates. As you
can see, many assumptions were made in producing the function point estimate. By putting
the information into a cost model, you can easily change several inputs to adjust the estimate.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

# Units/Hrs. Cost/Unit/Hr. Subtotals WBS Level 2 Totals % of Total
WBS Items
1. Project Management $306,300 20%
Project manager $100 $96,000
Project team members $75 $144,000
Contractors (10% of software
development and testing) $66,300
2. Hardware $76,000 5%
2.1 Handheld devices $600 $60,000
2.2 Servers $4,000 $16,000
3. Software $614,000 40%
3.1 Licensed software $200 $20,000
3.2 Software development* $594,000
4. Testing (10% of total hardware
and software costs) $69,000 $69,000 5%
5. Training and Support $202,400 13%
Trainee cost $500 $50,000
Travel cost $700 $8,400
Project team members $75 $144,000
6. Reserves (20% of total estimate) $253,540 $253,540 17%
Total project cost estimate $1,521,240
*See software development estimate.
960
1920
100
4
100
100
12
1920
Subtotal $1,267,700
Surveyor Pro Project Cost Estimate Created October 5
FIGURE 7-2
FIGURE 7-3
Surveyor Pro Software Development Estimate Created October 5
1. Labor Estimate # Units/Hrs. Cost/Unit/Hr. Subtotals Calculations
Contractor labor estimate 3000 $150 $450,000 3000 ! 150
Project team member estimate 1920 $75 $144,000 1920 ! 75
Total labor estimate $594,000 Sum above two values
2. Function point estimate Quantity Conversion
Factor
Function
Points
Calculations
External inputs 10 4 40 10 ! 4
External interface files 3 7 21 3 ! 7
External outputs 4 5 20 4 ! 5
External queries 6 4 24 6 ! 4
Logical internal tables 7 10 70 7 !10
Total function points 175 Sum above function point
values
Java 2 language equivalency
value
46 Assumed value from
reference
Source lines of code (SLOC) estimate 8,050 175 ! 46
Productivity×KSLOC^Penalty
(in months)
29.28 3.13 ! 8.05^1.072
(see reference)
Total labor hours
(27 hours/function point)* 4,725 27*175
Cost/labor hour ($120/hour) $120 Assumed value from
budget expert
Total function point estimate $567,000 4,725 ! 120
* Based on historical data
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

B E S T P R A C T I C E
Software expert and author Alvin Alexander shared his knowledge on the challenging
topic of estimating software development costs in several presentations and a book called
Cost Estimating in an Agile Development Environment (2015). Alexander describes how
to use Function Point Analysis (FPA) techniques based on his personal experience work-
ing on a multimillion dollar software project over five years. (Recall that function points
are a means of measuring software size in terms that are meaningful to end users.) The
project initially used a more traditional, waterfall approach but later moved to a more
agile approach.
Alexander explained that at the beginning of the project, when requirements
documents were very long and detailed, the programming work took about three times
the amount of time that was required to create the requirements (a ratio of 3:1). Later
in the project, after their client trusted them more and actually knew the developers
by name, the requirements were much shorter (more like user stories), and the ratio of
programming work to requirements work was much higher—6:1 to 9.5:1. User stories
describe what users do or need to do as part of their job function, focusing on the “who,”
“what,” and “why” of a requirement in a simple, concise way. Developers can analyze
user stories to estimate the number of internal logical files (ILFs)—a group of logically re-
lated data that resides entirely within the application boundary and is maintained through
external inputs. You can then use the ILFs to approximate the number of function points,
and then multiply by a certain number of hours/function point to estimate the
person-hours needed to develop the software.16
World class organizations take about half as long as average organizations (19 versus
35 hours) to develop one function point. They use consistent documentation (for require-
ments, analysis, and use cases), they follow consistent processes for developing software,
and their technical staff focus on business instead of technology. “It is impossible to
separate world-class organizations from world-class metrics organizations.”17
It is very important to have several people review the project cost estimate. It is also
helpful to analyze the total dollar value as well as the percentage of the total amount for
each major WBS category. For example, a senior executive could quickly look at the
Surveyor Pro project cost estimate and decide if the numbers are reasonable and the
assumptions are well documented. In this case, the government had budgeted $1.5 million
for the project, so the estimate was in line with that amount. The WBS Level 2 items, such
as project management, hardware, software, and testing, also seemed to be at appropriate
percentages of the total cost based on similar past projects. In some cases, a project team
might also be asked to provide a range estimate for each item instead of one discrete
amount. For example, the team might estimate that the testing costs will be between
$60,000 and $80,000 and document their assumptions in determining those values.
It is also important to update cost estimates, especially if any major changes occur on
a project.
After the total cost estimate is approved, the team can then allocate costs for each
month based on the project schedule and when costs will be incurred. Many organizations
also require that the estimated costs be allocated into certain budget categories, as
described in the next section.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

7.5 DETERMINING THE BUDGET
Determining the budget involves allocating the project cost estimate to individual mate-
rial resources or work items over time. These material resources or work items are based
on the activities in the work breakdown structure for the project. The cost management
plan, scope baseline, activity cost estimates, basis of estimates, project schedule, resource
calendars, risk register, agreements, and organizational process assets are all inputs for
determining the budget. The main goal of the cost budgeting process is to produce a cost
baseline for measuring project performance and to determine project funding require-
ments. The process may also result in project documents updates, such as items being
added, removed, or modified in the scope statement or project schedule.
The Surveyor Pro project team would use the cost estimate from Figure 7-2 along with
the project schedule and other information to allocate costs for each month. Figure 7-4
provides an example of a cost baseline for this project. A cost baseline is a time-phased
budget that project managers use to measure and monitor cost performance. Again, it’s
important for team members to document assumptions they made when developing the
cost baseline and have several experts review it.
Most organizations have a well-established process for preparing budgets. For example,
many organizations require budget estimates to include the number of FTE for each month
of the project. One FTE normally means 40 hours of work. One person could be assigned
full-time to a project to provide one FTE, or two people could be assigned half-time to pro-
vide one FTE. This number provides the basis for estimating total compensation costs each
year. Many organizations also want to know the amount of money projected to be paid to
suppliers for their labor costs or other purchased goods and services. Other common
budget categories include travel, depreciation, rents and leases, and other supplies and ex-
penses. It is important to understand these budget categories before developing an estimate
to make sure data is collected accordingly. Organizations use this information to track costs
across projects and non-project work and to look for ways to reduce costs. They also use the
information for legal and tax purposes.
FIGURE 7-4
WBS Items
1. Project Management
1.1 Project manager 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 96,000
1.2 Project team members 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 144,000
1.3 Contractors 6,027 6,027 6,027 6,027 6,027 6,027 6,027 6,027 6,027 6,027 6,027 66,300
2. Hardware
2.1 Handheld devices 30,000 30,000 60,000
2.2 Servers 8,000 8,000 16,000
3. Software
3.1 Licensed software 10,000 10,000 20,000
3.2 Software development 60,000 60,000 80,000 127,000 127,000 90,000 50,000 594,000
4. Testing 6,000 8,000 12,000 15,000 15,000 13,000 69,000
5. Training and Support
5.1 Trainee cost 50,000 50,000
5.2 Travel cost 8,400 8,400
5.3 Project team members 24,000 24,000 24,000 24,000 24,000 24,000 144,000
6. Reserves 10,000 10,000 30,000 30,000 60,000 40,000 40,000 30,000 3,540 253,540
Totals 20,000 86,027 92,027 172,027 223,027 198,027 185,027 173,027 148,427 90,027 80,027 53,567 1,521,240
1 2 3 4 5 6 7 8 9 10 11 12 Totals
*See the lecture slides for this chapter on the companion website for a larger view of this and other
figures in this chapter. Numbers are rounded, so some totals appear to be off.
Surveyor Pro Project Cost Baseline Created October 10*
Months
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

282
In addition to providing a cost baseline, estimating costs for each major project ac-
tivity over time provides project managers and top management with a foundation for
project cost control, as described in the next section. Cost budgeting, as well as requested
changes or clarifications, may result in updates to the cost management plan, which is a
subsidiary part of the project management plan. See Appendix A for information on using
Project 2013 for cost control.
Cost budgeting also provides information for project funding requirements. Some
projects have all funds available when the project begins, but others must rely on peri-
odic funding to avoid cash flow problems. If the cost baseline shows that more funds are
required in certain months than are expected to be available, the organization must make
adjustments to avoid financial problems.
7.6 CONTROLLING COSTS
Controlling project costs includes monitoring cost performance, ensuring that only ap-
propriate project changes are included in a revised cost baseline, and informing project
stakeholders of authorized changes to the project that will affect costs. The project man-
agement plan, project funding requirements, work performance data, and organizational
process assets are inputs for controlling costs. Outputs of this process are work perfor-
mance information, cost forecasts, change requests, project management plan updates,
project documents updates, and organizational process asset updates.
Several tools and techniques assist in project cost control. As shown in Appendix A,
Project 2013 has many cost management features to help you enter budgeted costs, set a
baseline, enter actuals, calculate variances, and run various cost reports.
In addition to using software, however, you need a change control system to define
procedures for changing the cost baseline. This cost control change system is part of the
integrated change control system described in Chapter 4, Project Integration Management.
Because many projects do not progress exactly as planned, new or revised cost estimates
are often required, as are estimates to evaluate alternate courses of action.
Performance review meetings can be a powerful tool for helping to control project costs.
People often perform better when they know they must report on their progress. Another
very important tool for cost control is performance measurement. Although many general ac-
counting approaches are available for measuring cost performance, earned value management
(EVM) is a powerful cost control technique that is unique to the field of project management.
7.6a Earned Value Management
Earned value management (EVM) is a project performance measurement technique that
integrates scope, time, and cost data. Given a cost performance baseline, project manag-
ers and their teams can determine how well the project is meeting scope, time, and cost
goals by entering actual information and then comparing it to the baseline. A baseline is
the budget figure in the original project plan plus approved changes. Actual information
includes whether or not a WBS item was completed, approximately how much of the work
was completed, when the work actually started and ended, and how much the completed
work actually cost.
In the past, earned value management was used primarily on large government proj-
ects. Today, however, more and more companies are realizing the value of using this tool
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

to help control costs. Moreover, a discussion by several academic experts in earned value
management and a real practitioner revealed the need to clarify how to calculate earned
value. Brenda Taylor, a senior project manager for P2 Project Management Solutions in
Johannesburg, South Africa, questioned the accuracy of calculating earned value simply
by multiplying the planned value to date by a percentage complete value. She suggested
using the rate of performance instead, as described below.
Earned value management involves calculating three values for each activity or sum-
mary activity from a project’s WBS.
1. The planned value (PV), also called the budget, is the portion of the
approved total cost estimate planned to be spent on an activity during a
given period. Table 7-3 shows an example of earned value calculations.
Suppose that a project included a summary activity of purchasing and
installing a new web server. Suppose further that, according to the plan,
it would take one week and cost a total of $10,000 for the labor hours,
hardware, and software. Therefore, the planned value (PV) for the activity
that week is $10,000.
2. The actual cost (AC) is the total direct and indirect costs incurred in ac-
complishing work on an activity during a given period. For example, suppose
that it actually took two weeks and cost $20,000 to purchase and install the
new web server. Assume that $15,000 of these actual costs were incurred
during Week 1 and $5,000 was incurred during Week 2. These amounts are
the actual cost (AC) for the activity each week.
3. The earned value (EV) is an estimate of the value of the physical work actu-
ally completed. EV is based on the original planned costs for the project or
activity and the rate at which the team is completing work on the project
or activity to date. The rate of performance (RP) is the ratio of actual work
completed to the percentage of work planned to have been completed at any
given time during the life of the project or activity. For example, suppose
that the server installation was halfway completed by the end of Week 1.
The rate of performance would be 50 percent because by the end of Week 1,
the planned schedule reflects that the task should be complete but only
50 percent of the work has been completed. In Table 7-3, the earned value
estimate after one week is therefore $5,000.18
TABLE 7-3
Activity Week 1
Earned value (EV) 5,000
Planned value (PV) 10,000
Actual cost (AC) 15,000
Cost variance (CV) -10,000
Schedule variance (SV) -5,000
Cost performance index (CPI) 33%
Schedule performance index (SPI) 50%
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

284
The earned value calculations in Table 7-4 are carried out as follows:
EV 5 10,000 * 50% 5 5,000
CV 5 5,000 – 15,000 5 -10,000
SV 5 5,000 – 10,000 5 -5,000
CPI 5 5,000/15,000 5 33%
SPI 5 5,000/10,000 5 50%
Table 7-4 summarizes the formulas used in earned value management. Note that the
formulas for variances and indexes start with EV, the earned value. Variances are calcu-
lated by subtracting the actual cost or planned value from EV, and indexes are calculated
by dividing EV by the actual cost or planned value. After you total the EV, AC, and PV data
for all activities on a project, you can use the CPI and SPI to project how much it will cost
and how long it will take to finish the project based on performance to date. Given the
budget at completion and original time estimate, you can divide by the appropriate index
to calculate the estimate at completion (EAC) and estimated time to complete, assuming
that performance remains the same. There are no standard acronyms for the terms
estimated time to complete or original time estimate.
Cost variance (CV) is the earned value minus the actual cost. If cost variance is a neg-
ative number, it means that performing the work cost more than planned. If cost variance
is a positive number, performing the work cost less than planned.
Schedule variance (SV) is the earned value minus the planned value. A negative
schedule variance means that it took longer than planned to perform the work, and
a positive schedule variance means that the work took less time than planned.
The cost performance index (CPI) is the ratio of earned value to actual cost; it can be
used to estimate the projected cost of completing the project. If the CPI is equal to one, or
100 percent, then the planned and actual costs are equal—the costs are exactly as bud-
geted. If the CPI is less than one or less than 100 percent, the project is over budget. If the
CPI is greater than one or more than 100 percent, the project is under budget.
The schedule performance index (SPI) is the ratio of earned value to planned value;
it can be used to estimate the projected time to complete the project. Similar to the cost
performance index, an SPI of one, or 100 percent, means the project is on schedule. If the
SPI is greater than one or 100 percent, then the project is ahead of schedule. If the SPI is
less than one or 100 percent, the project is behind schedule.
TABLE 7-4
Term Formula
Earned value (EV) EV 5 PV to date * RP
Cost variance (CV) CV 5 EV – AC
Schedule variance (SV) SV 5 EV – PV
Cost performance index (CPI) CPI 5 EV/AC
Schedule performance index (SPI) SPI 5 EV/PV
Estimate at completion (EAC) EAC 5 BAC/CPI
Estimated time to complete Original time estimate/SPI
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

285
Note that in general, negative numbers for cost and schedule variance indicate prob-
lems in those areas. Negative numbers mean the project is costing more than planned or
taking longer than planned. Likewise, a CPI and SPI of less than one or less than 100 per-
cent also indicate problems.
The cost performance index can be used to calculate the estimate at completion (EAC)—
an estimated cost of completing a project based on performance to date. Similarly, the sched-
ule performance index can be used to calculate an estimated time to complete the project.
You can graph earned value information to track project performance. Figure 7-5
shows an earned value chart for a one-year project after five months. Note that the actual
cost and earned value lines end at five months because the data was collected or esti-
mated at that point. The chart includes three lines and two points, as follows:
Planned value (PV), the cumulative planned amounts for all activities by month.
Note that the planned value line extends for the estimated length of the project
and ends at the BAC point.
Actual cost (AC), the cumulative actual amounts for all activities by month.
Earned value (EV), the cumulative earned value amounts for all activities by
month.
Budget at completion (BAC), the original total budget for the project, or
$100,000 in this example. The BAC point is plotted on the chart at the origi-
nal time estimate of 12 months.
Estimate at completion (EAC), estimated to be $122,308 in this example.
This number is calculated by taking the BAC, or $100,000 in this case, and
dividing by the CPI, which was 81.761 percent. This EAC point is plotted on
the chart at the estimated time to complete of 12.74 months. This number
FIGURE 7-5
120,000
Month
80,000
60,000
40,000
20,000

$
Earned value (EV)
1 2 3 4 5 6 7 8
100,000
9 10 11
Actual cost (AC)
Planned value (PV)
Budget at completion (BAC)
Estimate at completion (EAC)
12 13
An EAC
point above
and to the
right of the
BAC point
means the
project is
projected to
cost more
and take
longer than
planned
Actual cost (AC) Planned value (PV) Earned value (EV)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

286
is calculated by taking the original time estimate, or 12 months in this case,
and dividing by the SPI, which in this example was 94.203 percent.
Viewing earned value information in chart form helps you visualize how the project is
performing. For example, you can see the planned performance by looking at the planned
value line. If the project goes as planned, it will finish in 12 months and cost $100,000.
Notice in the example in Figure 7-5 that the actual cost line is always on or above the
earned value line, which indicates that costs are equal to or more than planned. The
planned value line is close to the earned value line and is slightly higher in the last month.
This relationship means that the project has been on schedule until the last month, when
the project fell behind schedule.
Top managers who oversee multiple projects often like to see performance information
in a graphical form, such as the earned value chart in Figure 7-5. For example, in the open-
ing case, the government officials were reviewing earned value charts and EACs for several
different projects. Earned value charts allow you to see quickly how projects are perform-
ing. If there are serious cost and schedule performance problems, top management may de-
cide to terminate projects or take other corrective action. The EACs are important inputs
to budget decisions, especially if total funds are limited. Earned value management is an
important technique when used effectively, because it helps top management and project
managers evaluate progress and make sound management decisions. Consult the PMBOK®
Guide and other resources for more information and calculations about earned value.
If earned value management is such a powerful cost control tool, then why doesn’t ev-
ery organization use it? Why do many government projects require it, but many commer-
cial projects don’t? Two reasons are EVM’s focus on tracking actual performance versus
planned performance and the importance of percentage completion data in making cal-
culations. Many projects, particularly IT projects, do not have good planning information,
so tracking performance against a plan might produce misleading information. Several
cost estimates are usually made on IT projects, and keeping track of the most recent cost
estimate and the associated actual costs could be cumbersome. In addition, estimating
percentage completion of tasks might produce misleading information. What does it mean
to say that a task is actually 75 percent complete after three months? Such a statement
is often not synonymous with saying the task will be finished in one more month or after
spending an additional 25 percent of the planned budget.
To make earned value management simpler to use, organizations can modify the level
of detail and still reap the benefits of the technique. For example, you can use percentage
completion data such as 0 percent for items not yet started, 50 percent for items in prog-
ress, and 100 percent for completed tasks. As long as the project is defined in enough detail,
this simplified percentage completion data should provide enough summary information
to allow managers to see how well a project is doing overall. You can get very accurate total
project performance information using these simple percentage complete amounts. For ex-
ample, using simplified percentage complete amounts for a one-year project with weekly re-
porting and an average task size of one week, you can expect about a 1 percent error rate.19
You can enter and collect earned value data only at summary levels of the WBS.
Quentin Fleming, author of the book Earned Value Project Management,20 often gives
presentations about earned value management. Many people express their frustration in
trying to collect such detailed information. Fleming explains that you do not have to col-
lect information at the work package level to use earned value management. It is most im-
portant to have a deliverable-oriented WBS, and many WBS items can summarize several
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

subdeliverables. For example, you might have a WBS for a house that includes items for
each room in the house. Collecting earned value data for each room would provide mean-
ingful information instead of trying to collect detailed information for each component in
the room, such as flooring, furniture, and lighting.
It is important to remember that the heart and soul of EVM are estimates. The entire
EVM process begins with an estimate; when the estimate is off, all the calculations will be
off. Before an organization attempts to use EVM, it must learn to develop good estimates.
Earned value management is the primary method available for integrating perfor-
mance, cost, and schedule data. It can be a powerful tool for project managers and top
management to use in evaluating project performance. Project management software,
such as Project 2013, includes tables for collecting earned value data and reports that
calculate variance information. Project 2013 also allows you to easily produce an earned
value chart, similar to the one in Figure 7-5, without importing the data into Microsoft
Excel. See the project cost management section of Appendix A for an example of using
earned value management.
Another approach to evaluating the performance of multiple projects is project portfo-
lio management, as described in the following section.
G L O B A L I S S U E S
The Project Management Institute conducted a major study in 2011 to help understand
and gauge the current level of EVM practice. The researchers surveyed more than 600
project management practitioners in 61 countries, providing a cross-sectional view of the
most current EVM practices. Respondents were classified by industry sector, motivation
for EVM usage, organizational role, and geographic location. The study included the fol-
lowing key findings:
EVM is used worldwide, and it is particularly popular in the Middle East, South
Asia, Canada, and Europe.
Most countries require EVM for large defense or government projects, as shown in
Figure 7-6.
EVM is also used in such private-industry sectors as IT, construction, energy, and
manufacturing. However, most private companies have not yet applied EVM to their
projects because management does not require it, feeling it is too complex and not
cost effective.
The level of EVM use and maturity varies among organizations and projects, but
budget size appears to be the most important decision factor.
EVM’s contributions and cost effectiveness are widely recognized; most respondents
said they agree or strongly agree that EVM provides early warning signs, helping
them to control project scope, time, and cost. EVM’s contribution to cost
performance was ranked higher than schedule performance, and the difference was
statistically significant.
Top barriers to enhanced use of EVM were lack of motivation and lack of expertise.
Top management support, buy-in of project staff, training, organizational culture
and leadership, and maturity of the project management system were the most
important factors in successful use of EVM.21
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

288
7.6b Project Portfolio Management
As you saw in Chapter 1, many organizations now collect and control an entire suite
of projects or investments as one set of interrelated activities in one place—a portfolio.
Several software tools provide graphics to summarize performance on a portfolio of proj-
ects, as shown in Chapter 4. Key metrics, including cost performance, are often shown in
green, yellow, or red, indicating that things are going as planned, that problems exist, or
that major problems exist, respectively. Project managers need to understand how their
projects fit into the bigger picture. For example, there can be a portfolio for IT projects
and portfolios for other types of projects. Looking at broad categories of similar projects
enables project managers to help their organizations make wise investment decisions.
An organization can view project portfolio management as having five levels, from
simplest to most complex, as follows:
1. Put all your projects in one database.
2. Prioritize the projects in your database.
3. Divide your projects into two or three budgets based on type of investment,
such as utilities or required systems to keep things running, incremental
upgrades, and strategic investments.
4. Automate the repository.
5. Apply modern portfolio theory, including risk-return tools that map project
risk on a curve.
FIGURE 7-6
19.5
51.3
29.2
31.9 32.2
35.8
0
10
20
30
40
50
60
A few pilot
projects
Large and critical
projects
Organization-wide
standard for
all projects
Pe
rc
en
ta
ge
Defense/Government Private industry
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

289
Many project managers also want to move on to manage larger projects, become pro-
gram managers, then vice presidents, and eventually CEOs. Understanding project portfo-
lio management, therefore is important for both project and organizational success.
Jane Walton, the project portfolio manager for IT projects at Schlumberger, saved
the company $3 million in one year by organizing the organization’s 120 IT projects into
a portfolio. Manufacturing companies have used project portfolio management since the
1960s, and Walton anticipated the need to justify investments in IT projects just as man-
agers have to justify capital investment projects. She found that 80 percent of the organi-
zation’s projects overlapped, and that 14 separate projects were trying to accomplish the
same thing. Other managers, such as Douglas Hubbard, president of a consulting firm, see
the need to use project portfolio management, especially for IT projects. Hubbard sug-
gests, “IT investments are huge, risky investments. It’s time we do this.”22
Project portfolio managers can start by using spreadsheet software to develop and
manage project portfolios, or they can use sophisticated software designed to help manage
project portfolios. Several software tools available today help project portfolio managers
summarize earned value and project portfolio information, as described in the following
section.
7.7 USING PROJECT MANAGEMENT SOFTWARE TO ASSIST
IN PROJECT COST MANAGEMENT
Most organizations use software to assist with project cost management. Spreadsheets
are a common tool for cost estimating, cost budgeting, and cost control. Many companies
also use more sophisticated and centralized financial software to provide important cost-
related information to accounting and finance personnel. This section focuses on how you
can use project management software in cost management. Appendix A includes a section
on using the cost management features in Project 2013.
Project management software can increase a project manager’s effectiveness during
each process of project cost management. It can help you study overall project informa-
tion or identify and focus on tasks that are over a specified cost limit. You can use the soft-
ware to assign costs to resources and tasks, prepare cost estimates, develop cost budgets,
and monitor cost performance. Project 2013 has several standard cost reports: cash flow,
budget, over-budget tasks, over-budget resources, and earned value reports. For several of
these reports, you must enter percentage completion information and actual costs, just as
you do when manually calculating earned value or other analyses.
Many IT project managers use other tools to manage cost information because they do
not know that they can use project management software, or they do not track costs based
on a WBS, as most project management software does. Instead of using dedicated project
management software for cost management, some IT project managers use company ac-
counting systems; others use spreadsheet software to achieve more flexibility. Project
managers who use other software often do so because these other systems are more gener-
ally accepted in their organizations and more people know how to use them. To improve
project cost management, several companies have developed methods to link data be-
tween their project management software and their main accounting software. Regardless,
users need training to use dedicated project management software and understand the
available features.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Many organizations are using software to organize and analyze all types of project
data into project portfolios and across the entire enterprise. Enterprise or project port-
folio management (PPM) tools integrate information from multiple projects to show the
projects’ status and health. In 2012, over half of the respondents in two different studies
(PMI’s PMI Pulse of the Profession™ and a PricewaterhouseCoopers survey) reported
frequent use of PPM. The highest adoption rates were reported by organizations in retail,
insurance, auto, banking and capital markets, telecommunications, manufacturing,
energy, and defense. The main reasons organizations use project portfolio management
included customer satisfaction, cost reduction, and revenue growth.23
More recently, a 2014 report from Gartner says the market for PPM software contin-
ues to grow, with annual sales over $1.65 billion. “Demand for IT PPM applications has not
wavered in more than 13 years, but, rather, increased exponentially over the past
10 years. The pace of change… is driving continued demand for enterprise software prod-
ucts that can help with the effective planning, execution, and management of projects and
programs materializing from the need for today’s enterprises to change and adapt quickly
to shifts in the business climate.”24
A study by Forrester estimates that companies are achieving returns of 250 percent
from their investments in PPM tools. At a Planisware PPM Solutions Summit in 2014, cus-
tomers shared examples of their success stories in achieving even higher returns:
Pfizer uses PPM software to accelerate innovation and improve transparency and
accountability of resources to deliver scientific excellence. Pfizer can quickly ac-
cess trusted data analytics to make strategic resource allocations that maximize
portfolio value.
Ford uses Planisware to gain greater transparency over their portfolio of
projects. Greater transparency gives management a better understanding of
resources shared across projects, and enhances communication about statuses.
They can quickly alert affected program managers and product development
teams of potential risks so they can implement risk management strategies.25
As with using any software, however, managers must make sure that the data is accu-
rate and up to date, and ask pertinent questions before making any major decisions.
C A S E W R A P – U P
After talking to his colleagues about the meeting, Juan had a better idea about the
importance of project cost management. He understood the value of doing detailed
studies before making major expenditures on new projects, especially after learning
about the high cost of correcting defects late in a project. He also learned the importance
of developing good cost estimates and keeping costs on track. He enjoyed seeing how the
cost estimate was developed for the Surveyor Pro project, and was eager to learn more
about various estimating tools and techniques.
At the meeting, government officials cancelled several projects when the project
managers showed how poorly the projects were performing and admitted that they did
not do much planning and analysis early in the projects. Juan knew that he could not fo-
cus on just the technical aspects of projects if he wanted to move ahead in his career. He
began to wonder whether several projects the city was considering were really worth the
taxpayers’ money. Issues of cost management added a new dimension to Juan’s job.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter Summary
Quick Quiz
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

292
PMBOK® Guide?


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Quick Quiz Answers
Discussion Questions
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

294
Exercises
=
=
=
=
Cost Estimating in an Agile Development Environment
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

295
Running Case
Tasks
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

296
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Key Terms
actual cost (AC)
analogous estimates
baseline
bottom-up estimates
budget at completion (BAC)
budgetary estimate
cash flow analysis
contingency reserves
cost baseline
cost performance index (CPI)
cost variance (CV)
definitive estimate
direct costs
earned value (EV)
earned value management (EVM)
estimate at completion (EAC)
function points
indirect costs
intangible costs or benefits
known unknowns
learning curve theory
life cycle costing
management reserves
overrun
parametric estimating
planned value (PV)
profit margin
profits
project cost management
rate of performance (RP)
reserves
rough order of magnitude (ROM)
estimate
schedule performance index (SPI)
schedule variance (SV)
sunk cost
tangible costs or benefits
top-down estimates
unknown unknowns
End Notes
Harvard Business Review hbr.org/2011/09/why-your-it-project-may-be-riskier-than-
you-think/
2
InformationWeek
www.informationweek.com/uk-health-system-it-upgrade-called-a-disaster/d/d-id/1043912?
4 IDG News Service
www.infoworld.com/article/2655787/database/datacenter-failure-pinches-uk-health-service.
html
5
iHealthBeat www.ihealthbeat.org/articles/2011/9/23/uk-health-service-to-dismantle-
nationwide-health-it-program
6 Cost Accounting
®
www.pmi.org/~/media/PDF/learning/pulse-of-the-profession-2015.ashx
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

298
8 AgileOne
www.agilone.com/blog/facebook-downtime-costs-them-more
9 Forbes www.forbes.
com/sites/kellyclay/2013/08/19/amazon-com-goes-down-loses-66240-per-minute/
Blogs, Business of DevOps devops.
com/2015/02/11/real-cost-downtime/
DevOps and the Cost of Downtime: Fortune 1000 Best Practice Metrics Quantified
Tech Culture CNET www.cnet.com/
news/dells-green-goal-for-2008/
FY 2014 Corporate Responsibility Report: A Progress Report on Our 2020 Legacy
of Good Plan i.dell.com/sites/doccontent/corporate/corp-comm/en/Documents/fy14-cr-
report
Controlling Software Projects
www.ifpug.
org/publications-products/what-are-function-points-fact-sheet
Cost Estimating in an Agile Development Environment
alvinalexander.com/downloads/Book3-EstimatingInAnAgileEnvironment .
www.softwaremetrics.com/files/OneHour ,
Project
Management Journal
Earned Value Project Management, Third
Edition
Earned Value Management: A Global and Cross-Industry Perspective on
Current EVM Practice
22 CIO Magazine
Pulse of the Profession® In-Depth Report: Portfolio
Management
24 MarketScope for IT Project and Portfolio
Management Software Applications
25
www.planisware.com/news/
leaders-innovation-divulge-best-practices-planiswares-user-summit.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R 8
PROJECT QUALITY
MANAGEMENT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

300
8.1 THE IMPORTANCE OF PROJECT QUALITY MANAGEMENT
Most people have heard jokes about how cars would work if they followed a development
history similar to that of computers. A well-known Internet joke goes as follows:
At the COMDEX computer exposition, Bill Gates, the founder and CEO of Microsoft Cor-
poration, stated: “If General Motors had kept up with technology like the computer indus-
try has, we would all be driving $25 cars that got 1,000 miles to the gallon.” In response
to Gates’ comments, General Motors issued a press release stating: “If GM had developed
technology like Microsoft, we would all be driving cars with the following characteristics:
For no reason whatsoever your car would crash twice a day.
Every time they repainted the lines on the road, you would have to buy a
new car.
Macintosh would make a car that was powered by the sun, reliable, five times as
fast, and twice as easy to drive, but would run on only five percent of the roads.
New seats would force everyone to have the same size hips.
The airbag system would say “Are you sure?” before going off.
Occasionally, for no reason whatsoever, your car would lock you out and re-
fuse to let you in until you simultaneously lifted the door handle, turned the
key, and grabbed hold of the radio antenna.”1
O P E N I N G C A S E
A large medical instruments company just hired Scott Daniels, a senior consultant from
a large consulting firm, to lead a project to resolve the quality problems with the com-
pany’s new Executive Information System (EIS). A team of internal programmers and
analysts worked with several company executives to develop this new system. Many
executives were hooked on the new, user-friendly EIS. They loved the way the system
allowed them to track sales of various medical instruments quickly and easily by prod-
uct, country, hospital, and sales representative. After successfully testing the new EIS
with several executives, the company decided to make the system available to all levels
of management.
Unfortunately, several quality problems developed with the new EIS after a few
months of operation. People complained that they could not get into the web-based sys-
tem. The system started going down a couple of times a month, and the response time
was reportedly getting slower. Users complained when they could not access information
within a few seconds. Several people kept forgetting how to log in to the system, thus
increasing the number of calls to the company’s help desk. There were complaints that
some of the reports in the system gave inconsistent information. How could a summary
report show totals that were not consistent with a detailed report on the same informa-
tion? The executive sponsor of the EIS wanted the problems fixed quickly and accu-
rately, so he decided to hire an expert in quality from outside the company whom he
knew from past projects. Scott Daniels’ job was to lead a team of people from both the
medical instruments company and his own firm to identify and resolve quality-related
issues with the EIS and to develop a plan to help prevent quality problems on future
projects.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

301
Most people simply accept poor quality from many IT products. So what if your com-
puter crashes a couple of times a month? Just make sure you back up your data. So what
if you cannot log in to the corporate intranet or the Internet right now? Just try a little
later when it is less busy. So what if the latest update of your word-processing software has
several known bugs? You like the software’s new features, and all new software has bugs.
Is quality a real problem with IT projects?
Yes, it is! IT is not just a luxury available in some homes, schools, or offices. Companies
throughout the world provide employees with access to computers. The majority of people
in the United States use the Internet, and usage in other countries continues to grow rapidly.
Many aspects of our daily lives depend on high-quality IT products. Food is produced and dis-
tributed with the aid of computers; cars have computer chips to track performance; children
use computers to help them learn in school; corporations depend on technology for many
business functions; and millions of people rely on technology for entertainment and personal
communications. Computing everywhere and the Internet of things, as described in Chapter 1,
are expanding our reliance on IT to smart appliances and devices (TVs, refrigerators, thermo-
stats, etc.), pay-as-you-go services, and much more. Many IT projects develop mission-critical
systems that are used in life-and-death situations, such as navigation systems on aircraft and
computer components built into medical equipment. Financial institutions and their custom-
ers also rely on high-quality information systems. Customers get very upset when systems
provide inaccurate financial data or reveal information to unauthorized users that could lead
to identity theft. When one of these systems does not function correctly, it is much more than
a slight inconvenience, as described in the following “What Went Wrong?” examples.
W H A T W E N T W R O N G ?
In 1981, a small timing difference caused by a computer program change created a
1-in-67 chance that the space shuttle’s five onboard computers would not synchro-
nize. The error caused a launch abort.2
In 1986, two hospital patients died after receiving fatal doses of radiation from a
Therac 25 machine. A software problem caused the machine to ignore calibration
data.3
In one of the biggest software errors in banking history, Chemical Bank mistak-
enly deducted about $15 million from more than 100,000 customer accounts.
The problem resulted from a single line of code in an updated computer pro-
gram that caused the bank to process every withdrawal and transfer at its auto-
mated teller machines (ATMs) twice. For example, a person who withdrew $100
from an ATM had $200 deducted from his or her account, though the receipt in-
dicated only a withdrawal of $100. The mistake affected 150,000 transactions.4
In 2015, The United States Department of Justice unsealed indictments in what
it described as “the largest data breach of names and e-mail addresses in the
history of the internet.” Two people hacked into at least eight e-mail service
providers, stealing more than a billion e-mail addresses. They allegedly used
the data to send spam, making millions of dollars from an affiliate marketing
arrangement with another individual.5
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

302
Before you can improve the quality of IT projects or any type of project, it is impor-
tant to understand the basic concepts of project quality management.
8.2 WHAT IS PROJECT QUALITY MANAGEMENT?
Project quality management is a difficult knowledge area to define. The International
Organization for Standardization (ISO) defines quality as “the totality of characteristics of
an entity that bear on its ability to satisfy stated or implied needs” (ISO8042:1994) or “the
degree to which a set of inherent characteristics fulfils requirements” (ISO9000:2000).
Many people spent many hours developing these definitions, yet they are still vague.
Other experts define quality based on conformance to requirements and fitness for use.
Conformance to requirements means that the project’s processes and products meet writ-
ten specifications. For example, if the project scope statement requires delivery of 100
computers with specific processors and memory, you could easily check whether suitable
computers had been delivered. Fitness for use means that a product can be used as it was
intended. If these computers were delivered without monitors or keyboards and were left
in boxes on the customer’s shipping dock, the customer might not be satisfied because the
computers would not be fit for use. The customer may have assumed that the delivery in-
cluded monitors and keyboards, unpacking the computers, and installation so they would
be ready to use.
The purpose of project quality management is to ensure that the project will satisfy
the needs for which it was undertaken. Recall that project management involves meeting
or exceeding stakeholder needs and expectations. The project team must develop good
relationships with key stakeholders, especially the main customer for the project, to under-
stand what quality means to them. After all, the customer ultimately decides if quality is
acceptable. Many technical projects fail because the project team focuses only on meeting
the written requirements for the main products being created and ignores other stakeholder
needs and expectations for the project. For example, the project team should know what
successfully delivering 100 computers means to the customer.
Quality, therefore, must be on an equal level with project scope, time, and cost. If a
project’s stakeholders are not satisfied with the quality of the project management or the
resulting products of the project, the project team will need to adjust scope, time, and cost
to satisfy the stakeholder. Meeting only written requirements for scope, time, and cost is
not sufficient. To achieve stakeholder satisfaction, the project team must develop a good
working relationship with all stakeholders and understand their stated or implied needs.
Project quality management involves three main processes:
1. Planning quality management includes identifying which quality require-
ments and standards are relevant to the project and how to satisfy them.
Incorporating quality standards into project design is a key part of quality
planning. For an IT project, quality standards might include allowing for
system growth, planning a reasonable response time for a system, or ensur-
ing that the system produces consistent and accurate information. Quality
standards can also apply to IT services. For example, you can set standards
for how long it should take to get a reply from a help desk or how long it
should take to ship a replacement part for a hardware item under warranty.
The main outputs of planning quality management are a quality manage-
ment plan, a process improvement plan, quality metrics, quality checklists,
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

303
and project documents updates. A metric is a standard of measurement.
Examples of common metrics include failure rates of products, availability of
goods and services, and customer satisfaction ratings.
2. Performing quality assurance involves periodically evaluating overall proj-
ect performance to ensure that the project will satisfy the relevant quality
standards. The quality assurance process involves taking responsibility for
quality throughout the project’s life cycle. Top management must take the
lead in emphasizing the roles all employees play in quality assurance, espe-
cially senior managers’ roles. The main outputs of this process are change
requests, project management plan updates, project documents updates, and
organizational process asset updates.
3. Controlling quality involves monitoring specific project results to ensure
that they comply with the relevant quality standards while identifying ways
to improve overall quality. This process is often associated with the tech-
nical tools and techniques of quality management, such as Pareto charts,
quality control charts, and statistical sampling. You will learn more about
these tools and techniques later in this chapter. The main outputs of quality
control include quality control measurements, validated changes, validated
deliverables, work performance information, change requests, project man-
agement plan updates, project documents updates, and organizational pro-
cess asset updates.
Figure 8-1 summarizes these processes and outputs, showing when they occur in a
typical project.
Planning
Process: Plan quality management
Outputs: Quality management plan, process improvement plan, quality metrics,
quality checklists, and project documents updates
Executing
Process: Perform quality assurance
Outputs: Change requests, project management plan updates,
project documents updates, and organizational process
asset updates
Monitoring and Controlling
Process: Perform quality control
Outputs: Quality control measurements, validated changes,
validated deliverables, work performance information,
change requests, project management plan updates,
project documents updates, and organizational
process asset updates
Project Start Project Finish
FIGURE 8-1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

304
8.3 PLANNING QUALITY MANAGEMENT
Project managers today have a vast knowledge base of information related to quality, and
the first step to ensuring project quality management is planning. Planning quality man-
agement implies the ability to anticipate situations and prepare actions that bring about
the desired outcome. The current thrust in modern quality management is the prevention
of defects through a program of selecting the proper materials, training and indoctrinat-
ing people in quality, and planning a process that ensures the appropriate outcome. In
project quality management planning, it is important to identify relevant quality standards
for each unique project and to design quality into the products of the project and the
processes involved in managing the project.
Several tools and techniques are available for planning quality management. For exam-
ple, design of experiments is a technique that helps identify which variables have the most
influence on the overall outcome of a process. Understanding which variables affect outcome
is a very important part of quality planning. For example, computer chip designers might
want to determine which combination of materials and equipment will produce the most reli-
able chips at a reasonable cost. You can also apply design of experiments to project manage-
ment issues such as cost and schedule trade-offs. Junior programmers or consultants cost less
than senior programmers or consultants, but you cannot expect them to complete the same
level of work in the same amount of time. An appropriately designed experiment to compute
project costs and durations for various combinations of junior and senior programmers or
consultants can allow you to determine an optimal mix of personnel, given limited resources.
Refer to the section on the Taguchi method later in this chapter for more information.
Quality planning also involves communicating the correct actions for ensuring quality
in a format that is understandable and complete. In quality planning for projects, it is im-
portant to describe key factors that directly contribute to meeting the customer’s require-
ments. Organizational policies related to quality, the particular project’s scope statement
and product descriptions, and related standards and regulations are all important input to
the quality planning process.
As mentioned in the discussion of project scope management (see Chapter 5), it is
often difficult to completely understand the performance dimension of IT projects. Even if
the development of hardware, software, and networking technology would stand still for a
while, customers often have difficulty explaining exactly what they want in an IT project.
Important scope aspects of IT projects that affect quality include functionality and fea-
tures, system outputs, performance, and reliability and maintainability.
Functionality is the degree to which a system performs its intended function.
Features are the system’s special characteristics that appeal to users. It is impor-
tant to clarify what functions and features the system must perform, and what
functions and features are optional. In the EIS example in the chapter’s opening
case, the mandatory functionality of the system might allow users to track sales
of specific medical instruments by predetermined categories such as the product
group, country, hospital, and sales representative. Mandatory features might be a
graphical user interface with icons, menus, and online help.
System outputs are the screens and reports the system generates. It is impor-
tant to define clearly what the screens and reports look like for a system. Can
the users easily interpret these outputs? Can users get all of the reports they
need in a suitable format?
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

305
Performance addresses how well a product or service performs the customer’s
intended use. To design a system with high-quality performance, project stake-
holders must address many issues. What volumes of data and transactions
should the system be capable of handling? How many simultaneous users
should the system be designed to handle? What is the projected growth rate in
the number of users? What type of equipment must the system run on? How
fast must the response time be for different aspects of the system under dif-
ferent circumstances? For the EIS in the opening case, several of the quality
problems appear to relate to performance issues. The system is failing a couple
of times a month, and users are unsatisfied with the response time. The proj-
ect team may not have had specific performance requirements or tested the
system under the right conditions to deliver the expected performance. Buying
faster hardware might address these performance issues. Another performance
problem that might be more difficult to fix is that some reports are generating
inconsistent results. This could be a software quality problem that is difficult
and costly to correct because the system is already in operation.
Reliability is the ability of a product or service to perform as expected under
normal conditions. In discussing reliability for IT projects, many people use
the term IT service management.
Maintainability addresses the ease of performing maintenance on a product.
Most IT products cannot reach 100 percent reliability, but stakeholders must
define their expectations. For the EIS, what are the normal conditions for
operating the system? Should reliability tests be based on 100 people ac-
cessing the system at once and running simple queries? Maintenance for the
EIS might include uploading new data into the system or performing mainte-
nance procedures on the system hardware and software. Are the users willing
to have the system be unavailable several hours a week for system mainte-
nance? Providing help desk support could also be a maintenance function.
How fast a response do users expect for help desk support? How often can
users tolerate system failure? Are the stakeholders willing to pay more for
higher reliability and fewer failures?
These aspects of project scope are just a few of the requirement issues related to qual-
ity management planning. Project managers and their teams need to consider all of these
project scope issues in determining quality goals for the project. The main customers for
the project must also realize their role in defining the most critical quality needs for the
project and constantly communicate these needs and expectations to the project team.
Because most IT projects involve requirements that are not set in stone, it is important for
all project stakeholders to work together to balance the quality, scope, time, and cost di-
mensions of the project. Project managers, however, are ultimately responsible for qual-
ity management on their projects.
Project managers should be familiar with basic quality terms, standards, and re-
sources. For example, the ISO provides information based on inputs from 163 different
countries. The ISO has an extensive website (www.iso.org), which is the source of ISO
9000 and more than 19,500 international standards for business, government, and society
as of May 2015. If you’re curious where the acronym came from, the word “iso” comes
from the Greek language, meaning “equal.” IEEE also provides many standards related to
quality and has detailed information on its website (www.ieee.org).
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

8.4 PERFORMING QUALITY ASSURANCE
It is one thing to develop a plan for ensuring the quality of a project; it is another to
ensure delivery of high-quality products and services. Quality assurance includes all of
the activities related to satisfying the relevant quality standards for a project. Another
goal of quality assurance is continuous quality improvement. Important inputs for per-
forming quality assurance are the quality management plan, process improvement plan,
quality metrics, quality control measurements, and project documents.
Many companies understand the importance of quality assurance and have entire
departments dedicated to it. They have detailed processes in place to make sure their
products and services conform to various quality requirements. They also know they must
offer those products and services at competitive prices. To be successful in today’s com-
petitive business environment, good companies develop their own best practices and eval-
uate other organizations’ best practices to continuously improve the way they do business.
The Japanese word for improvement or change for the better is kaizen; a kaizen approach
has been used in many organizations since the end of World War II. Another popular term,
lean, involves evaluating processes to maximize customer value while minimizing waste.
Kanban, as described briefly in Chapter 2, is a technique often used in lean. See the fol-
lowing What Went Right? for more information, and consult other texts, articles, and web-
sites for more detailed information on kaizen, lean, kanban, and other aspects of quality
assurance.
Several tools used in quality planning can also be used in quality assurance. Design
of experiments, as described under quality planning, can also help ensure and improve
product quality. Benchmarking generates ideas for quality improvements by comparing
W H A T W E N T R I G H T ?
In 2005 David J. Anderson, a founder of the Agile movement and author of several books,
visited Tokyo’s Imperial Palace gardens during a trip to Japan. He noticed that kanban
was used at the gardens to manage the flow of visitors and realized that it could be ap-
plied to many processes, including software development.
Kanban uses five core properties:
1. Visual workflow
2. Limit work-in-progress
3. Measure and manage flow
4. Make process policies explicit
5. Use models to recognize improvement opportunities
In his book Kanban, Anderson explains that the application of kanban is different for
every team. Visitors to his company saw that no set of kanban boards were alike, and all
of their teams used a different process to develop software. Anderson explains that kan-
ban requires some type of process to already be in place, and it is used to incrementally
improve the process. It gives teams permission to be different. “Each team’s situation
is different. They evolve their process to fit their context … The simple act of limiting
work-in-progress with kanban encourages higher quality and greater performance.”6
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

307
specific project practices or product characteristics to those of other projects or products
within or outside the performing organization. For example, if a competitor has an EIS
with an average downtime of only one hour a week, that might be a benchmark for which
to strive.
An important tool for quality assurance is a quality audit. A quality audit is a struc-
tured review of specific quality management activities that help identify lessons learned
and that could improve performance on current or future projects. In-house auditors or
third parties with expertise in specific areas can perform quality audits; these quality
audits can be scheduled or random. Industrial engineers often perform quality audits by
helping to design specific quality metrics for a project and then applying and analyzing
the metrics throughout the project. For example, the Northwest Airlines Resnet project
(which is available on the companion website for this text) provides an excellent example
of using quality audits to emphasize the main goals of a project and then track progress in
reaching those goals. The main objective of the Resnet project was to develop a new res-
ervation system to increase direct airline ticket sales and reduce the time it took for sales
agents to handle customer calls. The measurement techniques for monitoring these goals
helped Resnet’s project manager and project team supervise various aspects of the project
by focusing on meeting those goals. Measuring progress toward increasing direct sales and
reducing call times also helped the project manager justify continued investments
in Resnet.
8.5 CONTROLLING QUALITY
Many people only think of quality control when they think of quality management,
perhaps because there are many popular tools and techniques in this area. Before you
learn about these tools and techniques, it is important to distinguish quality control from
quality planning and quality assurance.
Although one of the main goals of quality control is to improve quality, the main out-
comes of this process are acceptance decisions, rework, and process adjustments.
Acceptance decisions determine if the products or services produced as part of
the project will be accepted or rejected. If they are accepted, they are considered
to be validated deliverables. If project stakeholders reject some of the project’s
products or services, there must be rework. For example, the executive who
sponsored development of the EIS in the chapter’s opening case was obviously
not satisfied with the system and hired an outside consultant, Scott Daniels, to
lead a team to address and correct the quality problems.
Rework is action taken to bring rejected items into compliance with prod-
uct requirements, specifications, or other stakeholder expectations. Rework
often results in requested changes and validated defect repair, and it results
from recommended defect repair or corrective or preventive actions. Rework
can be very expensive, so the project manager must strive to do a good job
of quality planning and quality assurance to avoid this need. Because the EIS
did not meet all of the stakeholders’ expectations for quality in the opening
case, the medical instruments company was spending additional money
for rework.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Process adjustments correct or prevent further quality problems based on
quality control measurements. Process adjustments often result in updates to
organization process assets and the project management plan. For example,
Scott Daniels, the consultant in the opening case, might recommend that the
medical instruments company purchase a faster server for the EIS to correct
the response-time problems. This change would require changes to the proj-
ect management plan because it would require more project-related work.
The company also hired Scott to develop a plan to help prevent future IT
project quality problems.
8.6 TOOLS AND TECHNIQUES FOR QUALITY CONTROL
Quality control includes many general tools and techniques. This section describes the
Seven Basic Tools of Quality, statistical sampling, and Six Sigma and discusses how they
can be applied to IT projects. The section concludes with a discussion of testing, because
IT projects use testing extensively to ensure quality.
The designation of the Seven Basic Tools of Quality arose in postwar Japan, suppos-
edly inspired by the seven famous weapons of Benkei. The following seven tools are listed
in the PMBOK® Guide, Fifth Edition:
1. Cause-and-effect diagrams trace complaints about quality problems back to
the responsible production operations. In other words, they help you find
the root cause of a problem. They are also known as fishbone or Ishikawa
diagrams, named after their creator, Kaoru Ishikawa. You can also use the
technique known as the 5 whys, in which you repeatedly ask the question
“Why?” to help peel away the layers of symptoms that can lead to the root
cause of a problem. (Using five questions is a good rule of thumb, although
other numbers can be used.) These symptoms can be branches on the
cause-and-effect diagram.
Figure 8-2 provides an example of a cause-and-effect diagram that
Scott Daniels, the consultant in the opening case, might create to discover
why users cannot log in to the EIS. Notice that it resembles the skeleton
of a fish, hence the name fishbone diagram. This diagram lists the main
areas that could be the cause of the problem: the EIS system’s hardware,
the user’s hardware or software, or the user’s training. The figure de-
scribes two of these areas, the individual user’s hardware and training, in
more detail.
Using the 5 whys, you could first ask why users cannot get into the sys-
tem, then why they keep forgetting their passwords, why they did not reset
their passwords, and why they did not check a box to save a password. The
root cause of the problem would have a significant impact on actions taken
to solve the problem. If many users could not get into the system because
their computers did not have enough memory, the solution might be to
upgrade memory for those computers. If many users could not get into the
system because they forgot their passwords, there might be a much quicker,
less expensive solution.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

309
Problem: Users
cannot get into
system
Training
User did not
check box to
save password
Not
enough
memory
User did not
reset password
User keeps
forgetting
password
System Hardware
Processor
too slow
Software User’s Hardware
Not enough
hard disk
storage
FIGURE 8-2
2. A control chart is a graphic display of data that illustrates the results of a
process over time. Control charts allow you to determine whether a pro-
cess is in control or out of control. When a process is in control, any varia-
tions in the results of the process are created by random events. Processes
that are in control do not need to be adjusted. When a process is out of
control, variations in the results of the process are caused by nonrandom
events. When a process is out of control, you need to identify the causes of
those nonrandom events and adjust the process to correct or
eliminate them.
Figure 8-3 provides an example of a control chart for a process that
manufactures 12-inch wood rulers by machines on an assembly line. Each
point on the chart represents a length measurement for a ruler that comes
off the assembly line. The customer has specified that all rulers it purchases
must be between 11.90 and 12.10 inches long, or 12 inches plus or minus
0.10 inches. The scale on the vertical axis goes from 11.90, the lower speci-
fication limit, to 12.10, the upper specification limit. The lower and up-
per control limits on the quality control chart are 11.91 and 12.09 inches,
respectively. This means the manufacturing process is designed to produce
rulers between 11.91 and 12.09 inches long.
Looking for and analyzing patterns in process data is an important part
of quality control. You can use quality control charts and the seven run rule
to look for patterns in data. The seven run rule states that if seven data
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

310
points in a row are all below the mean or above the mean, or are all increas-
ing or decreasing, then the process needs to be examined for
nonrandom problems.
In Figure 8-3, data points that violate the seven run rule are marked
with stars. Note that you include the first point in a series of points that are
all increasing or decreasing. In the ruler manufacturing process, these data
points may indicate that a calibration device needs adjustment. For exam-
ple, the machine that cuts the wood for the rulers might need to be adjusted
or the blade on the machine might need to be replaced.
3. A checksheet is used to collect and analyze data. It is sometimes called
a tally sheet or checklist, depending on its format. Figure 8-4 provides a
sample checksheet that Scott Daniels could use to track the media source of
complaints about the EIS. Note that tally marks are used to enter each data
occurrence manually. In this example, most complaints arrive via text mes-
sage, and there are more complaints on Monday and Tuesday than on other
days of the week. This information might be useful in improving the process
for handling complaints.
4. A scatter diagram helps to show if there is a relationship between two vari-
ables. The closer data points are to a diagonal line, the more closely the
two variables are related. For example, Figure 8-5 provides a sample scatter
diagram that Scott Daniels might create to compare user satisfaction ratings
of the EIS system to the age of respondents to see if there is a relationship.
Scott might find that younger users are less satisfied with the system, for
example, and make decisions based on that finding.
FIGURE 8-3
12.10
Time dimension
12.06
12.02
11.98
11.94
11.90
In
ch
es
12.08
12.04
12.00
11.96
11.92
Mean
Upper Control Limit 12.09
0 5 10 15 20 25 30
Upper Spec Limit 12.10
Lower Control
Limit 11.91
Lower Spec
Limit 11.90
Denotes violation of 7 run rule
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

311
0
10
20
30
40
50
60
2 2.5 3 3.5 4 4.5 5
A
ge
o
f
Re
sp
on
de
nt
User Satisfaction Rating
FIGURE 8-5
5. A histogram is a bar graph of a distribution of variables. Each bar repre-
sents an attribute or characteristic of a problem or situation, and the height
of the bar represents its frequency. For example, Scott Daniels might ask
the Help Desk to create a histogram to show how many total complaints
they received each week about the EIS system. Figure 8-6 shows a sample
histogram.
6. A Pareto chart is a histogram that can help you identify and prioritize
problem areas. The variables described by the histogram are ordered by
frequency of occurrence. Pareto charts help you identify the vital few con-
tributors that account for most quality problems in a system. Pareto analysis
is sometimes referred to as the 80-20 rule, meaning that 80 percent of prob-
lems are often due to 20 percent of the causes.
E-mail
Text
Phone call
Total
System Complaints
11 10 8 6 7 3
12
29
8
494
Day
Source Monday Tuesday Wednesday Thursday Friday Saturday Sunday Total
FIGURE 8-4
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

312
For example, suppose there was a detailed history of user complaints
about the EIS. The project team could create a Pareto chart based on that
data, as shown in Figure 8-7.
Notice that login problems are the most frequent user complaint, fol-
lowed by the system locking up, the system being too slow, the system being
hard to use, and the reports being inaccurate. The first complaint accounts
for 55 percent of the total complaints. The first and second complaints to-
gether account for almost 80 percent of the total complaints. Therefore, the
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6
Week
N
um
be
r
of
C
om
pl
ai
nt
s
FIGURE 8-6
FIGURE 8-7
100
80
60
40
20
0
Log-in
problems
System
locks up
System is
too slow
System is
too hard
to use
Reports
are
inaccurate
N
um
be
r
of
c
om
pl
ai
nt
s
th
is
w
ee
k
90
70
50
30
10
100%
80%
60%
40%
20%
0%
90%
70%
50%
30%
10%
Cumulative%
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

313
company should focus on making it easier to log in to the system to improve
quality, because most complaints fall under that category. The company
should also address why the system locks up.
Because Figure 8-7 shows that inaccurate reports are rarely mentioned,
the project manager should investigate who made this complaint before spend-
ing a lot of effort on addressing the problem. The project manager should also
find out if complaints about the system being too slow were actually due to the
user not being able to log in or the system locking up. You can use the template
file for this chart and other charts on the companion website for this text, and
you can find videos and articles that explain how to create the charts.
7. Flowcharts are graphic displays of the logic and flow of processes that help you
analyze how problems occur and how processes can be improved. They show
activities, decision points, and the order of how information is processed.
Figure 8-8 provides a simple example of a flowchart that shows the process
a project team might use for accepting or rejecting deliverables. The American
Society for Quality (ASQ) calls this basic quality tool stratification, a tech-
nique that shows data from a variety of sources to see if a pattern emerges.
In addition to flowcharts, run charts are also used for stratification.
A run chart displays the history and pattern of variation of a process over
time. It is a line chart that shows data points plotted in the order of occur-
rence. You can use run charts to perform trend analysis and forecast future
outcomes based on historical results. For example, trend analysis can help
you analyze how many defects have been identified over time and see if
Deliverable
Acceptance
Request
Route to
appropriate
decision
makers
Accepted?
Sign
approval
section
Notify
requestor
and log in
system
Document
required
additional
work
YES
NO
FIGURE 8-8
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

314
there are trends. Figure 8-9 shows a sample run chart of the number of de-
fects each month for three different types of defects. You can easily see the
patterns of Defect 1 increasing over time, Defect 2 decreasing the first sev-
eral months and then holding steady, and Defect 3 fluctuating each month.
8.6a Statistical Sampling
Statistical sampling is a key concept in project quality management. Members of a proj-
ect team who focus on quality control must have a strong understanding of statistics, but
other project team members need to understand only the basic concepts. These concepts
include statistical sampling, certainty factor, standard deviation, and variability. Standard
deviation and variability are fundamental concepts for understanding quality control
charts. This section briefly describes these concepts and describes how a project manager
might apply them to IT projects. Refer to statistics texts for additional details.
Statistical sampling involves choosing part of a population of interest for inspection.
For example, suppose that a company wants to develop an electronic data interchange
(EDI) system for handling invoice data from all of its suppliers. Assume also that in the past
year, the company received 50,000 invoices from 200 different suppliers. It would be very
time consuming and expensive to review every invoice to determine data requirements for
the new system. Even if the system developers did review all 200 invoice forms from the
different suppliers, the data might be entered differently on every form. Statisticians have
developed techniques to determine an appropriate sample size when it is impractical or im-
possible to study every member of a population. Using statistical techniques, the system de-
velopers might find that 100 invoices would be enough to determine the data requirements.
The size of the sample depends on how representative you want it to be. A simple for-
mula for determining sample size is:
Sample size = 0.25 * (certainty factor/acceptable error)2
The certainty factor denotes how confident you want to be that the sampled data
includes only variations that naturally exist in the population. You calculate the certainty
0
2N
um
be
r
of
d
ef
ec
ts
4
6
8
10
12
14
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Defect 1 Defect 2 Defect 3
FIGURE 8-9
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

315
factor from tables that are available in statistics books. Table 8-1 shows some commonly
used certainty factors. The acceptable error is related to the desired certainty and is 1 –
percent certainty/100. So if you set your desired certainty to 95 percent, then the accept-
able error value is 1 – 95/100 = .05.
For example, suppose that the developers of the EDI system would accept a 95 per-
cent certainty that a sample of invoices would contain no variation unless it was present
in the population of total invoices. They would then calculate the sample size as:
Sample size = 0.25 * (1.960/.05)2 = 384
If the developers would accept 90 percent certainty, they would calculate the sample
size as:
Sample size = 0.25 * (1.645/.10)2 = 68
If the developers would accept 80 percent certainty, they would calculate the sample
size as:
Sample size = 0.25 * (1.281/.20)2 = 10
Assume that the developers decide on 90 percent for the certainty factor. Then they
would need to examine 68 invoices to determine the type of data the EDI system would
need to capture. As stated earlier, even if they reviewed all 200 invoices, some data could
be entered differently. Additional means of data collection should be used to ensure that
important user requirements are met.
8.6b Six Sigma
The work of many project quality experts contributed to the development of today’s Six
Sigma principles. There has been some confusion in the past few years about the term
Six Sigma. This section summarizes recent information about this important concept and
explains how organizations worldwide use Six Sigma principles to improve quality, de-
crease costs, and better meet customer needs.
In their book The Six Sigma Way, authors Peter Pande, Robert Neuman, and Roland
Cavanagh define Six Sigma as “a comprehensive and flexible system for achieving, sus-
taining and maximizing business success. Six Sigma is uniquely driven by close under-
standing of customer needs, disciplined use of facts, data, and statistical analysis, and
diligent attention to managing, improving, and reinventing business processes.”7
Six Sigma’s target for quality is no more than 3.4 defects, errors, or mistakes per
million opportunities. This target number is explained in more detail later in this section.
An organization can apply Six Sigma principles to the design and production of a product,
a help desk, or other customer-service process.
TABLE 8-1
Desired Certainty Certainty Factor
95% 1.960
90% 1.645
80% 1.281
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Projects that use Six Sigma principles for quality control normally follow a five-phase
improvement process called DMAIC (pronounced de-MAY-ick), which stands for Define,
Measure, Analyze, Improve, and Control. DMAIC is a systematic, closed-loop process for
continued improvement that is scientific and fact based. The following are brief descrip-
tions of each phase of the DMAIC improvement process:
1. Define: Define the problem/opportunity, process, and customer require-
ments. Important tools used in this phase include a project charter, a
description of customer requirements, process maps, and Voice of the
Customer (VOC) data. Examples of VOC data include complaints, surveys,
comments, and market research that represent the views and needs of the
organization’s customers.
2. Measure: Define measures and then collect, compile, and display data. Mea-
sures are defined in terms of defects per opportunity.
3. Analyze: Scrutinize process details to find improvement opportunities. A proj-
ect team working on a Six Sigma project, normally referred to as a Six Sigma
team, investigates and verifies data to prove the suspected root causes of qual-
ity problems and substantiates the problem statement. An important tool in
this phase is the fishbone or Ishikawa diagram, described earlier in this chapter.
4. Improve: Generate solutions and ideas for improving the problem. A final
solution is verified with the project sponsor, and the Six Sigma team devel-
ops a plan to pilot test the solution. The Six Sigma team reviews the results
of the pilot test to refine the solution, if needed, and then implements the
solution where appropriate.
5. Control: Track and verify the stability of the improvements and the predict-
ability of the solution. Control charts are one tool used in the control phase.
How Is Six Sigma Quality Control Unique?
How does using Six Sigma principles differ from using previous quality control initiatives?
Many people remember other quality initiatives from the past few decades, such as Total
Quality Management (TQM) and Business Process Reengineering (BPR). The origins of
many Six Sigma principles and tools are found in these previous initiatives; however, sev-
eral new ideas are included in Six Sigma principles that help organizations improve their
competitiveness and bottom-line results:
Using Six Sigma principles is an organization-wide commitment. CEOs, top
managers, and all levels of employees in an organization that embraces Six
Sigma principles have seen remarkable improvements due to its use. There
are often huge training investments, but they pay off as employees practice Six
Sigma principles and produce higher-quality goods and services at lower costs.
Six Sigma training normally follows the “belt” system, similar to a martial arts
class in which students receive different-color belts for each training level.
In Six Sigma training, those in the Yellow Belt category receive the minimum
level of training, which is normally two to three full days for project team
members who work on Six Sigma projects on a part-time basis. Those in the
Green Belt category usually participate in two to three full weeks of training.
Those in the Black Belt category normally work on Six Sigma projects full-time
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

317
and attend four to five full weeks of training. Project managers are often Black
Belts. The Master Black Belt category describes experienced Black Belts who
act as technical resources and mentors to people with lower-level belts.
Organizations that successfully implement Six Sigma principles have the
ability and willingness to adopt two seemingly contrary objectives at the
same time. For example, Six Sigma organizations believe that they can be
creative and rational, focus on the big picture and minute details, reduce er-
rors and get things done faster, and make customers happy and make a lot of
money. Authors James Collins and Jerry Porras describe this as the “We can
do it all” or “Genius of the And” approach in their book, Built to Last.8
Six Sigma is not just a program or a discipline to organizations that have ben-
efited from it. Six Sigma is an operating philosophy that is customer-focused
and strives to drive out waste, raise levels of quality, and improve financial
performance at breakthrough levels. A Six Sigma organization sets high goals
and uses the DMAIC improvement process to achieve extraordinary quality
improvements.
Many organizations do some of what now fits under the definition of Six Sigma, and
many Six Sigma principles are not brand-new. What is new is its ability to bring together
many different themes, concepts, and tools into a coherent management process that can
be used on an organization-wide basis.
Six Sigma and Project Selection and Management
Organizations implement Six Sigma by selecting and managing projects. An important
part of project management is good project selection.
Joseph M. Juran stated, “All improvement takes place project by project, and in no
other way.”9 This statement is especially true for Six Sigma projects. Pande, Neuman, and
Cavanagh conducted an informal poll to find out the most critical and most commonly
mishandled activity in launching Six Sigma, and the unanimous answer was project selec-
tion. “It’s a pretty simple equation, really: Well-selected and -defined improvement proj-
ects equal better, faster results. The converse equation is also simple: Poorly selected and
defined projects equal delayed results and frustration.”10
Organizations must be careful to apply higher quality where it makes sense. An article
in Fortune stated that companies that have implemented Six Sigma have not necessarily
boosted their stock values. Although GE boasted savings of more than $2 billion in 1999
due to its use of Six Sigma, other companies, such as Whirlpool, could not clearly demon-
strate the value of their investments. Why can’t all companies benefit from Six Sigma? Be-
cause minimizing defects does not matter if an organization makes a product that people
do not want. As one of Six Sigma’s biggest supporters, Mikel Harry, put it, “I could geneti-
cally engineer a Six Sigma goat, but if a rodeo is the marketplace, people are still going to
buy a Four Sigma horse.”11
What makes a project a potential Six Sigma project? First, there must be a quality
problem or gap between the current and desired performance. This first criterion does not
apply to many projects, such as building a house, merging two corporations, or providing
an IT infrastructure for a new organization. Second, the project should not have a clearly
understood problem. Third, the solution should not be predetermined, and an optimal so-
lution should not be apparent.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Once a project is selected as a good candidate for Six Sigma, many project manage-
ment concepts, tools, and techniques described in this text come into play. For example,
Six Sigma projects usually have a business case, a project charter, requirements docu-
ments, a schedule, and a budget. Six Sigma projects are done in teams and have sponsors
called champions. There are also project managers, although they are often called team
leaders in Six Sigma organizations. In other words, Six Sigma projects are simply types of
projects that focus on supporting the Six Sigma philosophy by being
customer-focused and striving to drive out waste, raise levels of quality, and improve
financial performance at breakthrough levels.
Six Sigma and Statistics
An important concept in Six Sigma is improving quality by reducing variation. The term
sigma means standard deviation. Standard deviation measures how much variation ex-
ists in a distribution of data. A small standard deviation means that data clusters closely
around the middle of a distribution and there is little variability among the data. A large
standard deviation means that data is spread around the middle of the distribution and
there is relatively greater variability. Statisticians use the Greek symbol σ (sigma) to
represent the standard deviation.
Figure 8-10 provides an example of a normal distribution—a bell-shaped curve that
is symmetrical around the mean or average value of the population (the data being ana-
lyzed). In any normal distribution, 68.3 percent of the population is within one standard
deviation (1σ) of the mean, 95.5 percent of the population is within two standard devia-
tions (2σ), and 99.7 percent of the population is within three standard deviations (3σ) of
the mean.
Standard deviation is a key factor in determining the acceptable number of defec-
tive units in a population. Table 8-2 illustrates the relationship between sigma, the
FIGURE 8-10 d
68.3%
95.5%
99.7%
mean
–3 –2 –1 +1 +2 +3
The normal curve
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

319
percentage of the population within that sigma range, and the number of defective
units per billion. Note that this table shows that being plus or minus six sigma in pure
statistical terms means only two defective units per billion. Why, then, is the target
for Six Sigma programs 3.4 defects per million opportunities, as stated earlier in
this chapter?
Based on Motorola’s original work on Six Sigma in the 1980s, the convention used
for Six Sigma is a scoring system that accounts for more variation in a process than you
would typically find in a few weeks or months of data gathering. In other words, time
is an important factor in determining process variations. Table 8-3 shows a Six Sigma
conversion table applied to Six Sigma projects. The yield represents the number of units
handled correctly through the process steps. A defect is any instance in which the product
or service fails to meet customer requirements. Because most products or services have
multiple customer requirements, there can be several opportunities to have a defect. For
example, suppose that a company is trying to reduce the number of errors on customer
billing statements. There could be several errors on a billing statement due to a misspelled
name, incorrect address, wrong date of service, or calculation error. There might be
100 opportunities for a defect to occur on one billing statement. Instead of measuring the
number of defects per unit or billing statement, Six Sigma measures the number of defects
based on the number of opportunities.
TABLE 8-2
Specification Range
(in ± Sigmas)
Percent of Population
within Range
Defective Units
per Billion
1 68.27 317,300,000
2 95.45 45,400,000
3 99.73 2,700,000
4 99.9937 63,000
5 99.999943 57
6 99.9999998 2
© Cengage Learning 2016
TABLE 8-3
Sigma Yield Defects per Million Opportunities (DPMO)
1 31.0% 690,000
2 69.2% 308,000
3 93.3% 66,800
4 99.4% 6,210
5 99.97% 230
6 99.99966% 3.4
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

320
As you can see, the Six Sigma conversion table shows that a process operating at six
sigma means there are no more than 3.4 defects per million opportunities. However, most
organizations today use the term six sigma project in a broad sense to describe projects
that will help them in achieving, sustaining, and maximizing business success through
better business processes.
A term you may hear in the telecommunications industry is six 9s of quality, which is
a measure of quality control equal to 1 fault in 1 million opportunities. In the telecommuni-
cations industry, it means 99.9999 percent service availability or 30 seconds of downtime
a year. This level of quality has also been stated as the target goal for the number of errors
in a communications circuit, system failures, or errors in lines of code. Achieving six 9s of
quality requires continual testing to find and eliminate errors or enough redundancy and
backup equipment in systems to reduce the overall system failure rate to the required level.
8.6c Testing
Many IT professionals think of testing as a stage that comes near the end of IT product
development. Instead of putting serious effort into proper planning, analysis, and design of
IT projects, some organizations rely on testing just before a product ships to ensure some
degree of quality. In fact, testing needs to be done during almost every phase of the
systems development life cycle, not just before the organization ships or hands over a
product to the customer.
Figure 8-11 shows one way of portraying the systems development life cycle. This
example includes 17 main tasks involved in a software development project and shows
their relationship to each other. Every project should start by initiating the project,
conducting a feasibility study, and then performing project planning. The figure then
shows that preparing detailed requirements and the detailed architecture for the
system can be performed simultaneously. The oval-shaped phases represent actual
tests or tasks, which will include test plans to help ensure quality on software
development projects.12
Several of the phases in Figure 8-11 include specific work related to testing.
A unit test is done to test each individual component (often a program) to ensure
that it is as defect-free as possible. Unit tests are performed before moving on to
the integration test.
Integration testing occurs between unit and system testing to test function-
ally grouped components. It ensures that a subset or subsets of the entire
system work together.
System testing tests the entire system as one entity. It focuses on the big pic-
ture to ensure that the entire system is working properly.
User acceptance testing is an independent test performed by end users prior
to accepting the delivered system. It focuses on the business fit of the system
to the organization, rather than technical issues.
Other types of testing include alpha and beta testing, performance testing, and scal-
ability testing. For example, several companies, including Amazon and Target, have suf-
fered serious consequences when their websites crashed because they could not handle
demand due to inadequate scalability testing. To help improve the quality of software de-
velopment projects, it is important for organizations to follow a thorough and disciplined
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

321
testing methodology. System developers and testers must also establish a partnership with
all project stakeholders to make sure the system meets their needs and expectations and
the tests are done properly. As described in the next section, tremendous costs are in-
volved in failure to perform proper testing.
Testing alone, however, cannot always solve software defect problems, according to
Watts S. Humphrey, a renowned expert on software quality and Fellow at Carnegie
Mellon’s Software Engineering Institute. He believes that the traditional code/test/fix cycle
for software development is not enough. As code gets more complex, the number of de-
fects missed by testing increases and becomes the problem not just of testers, but also of
paying customers. Humphrey says that, on average, programmers introduce a defect for
every nine or 10 lines of code, and the finished software, after all testing, contains about
five to six defects per thousand lines of code.
Although there are many different definitions, Humphrey defines a software defect
as anything that must be changed before delivery of the program. Testing does not
FIGURE 8-11
1. Initiate Project
2. Feasibility
3. Project
Planning
4. Detailed
Requirements
7. Detailed
Architecture
8. Build Operating
Environment5. Product
Selection
6. System
Design
10. Unit Design
Development
11. Code
12. Unit Test
13. Integration
Test
14. System Test
15. User
Acceptance Test
16.
Implementation
17. Post
Implementation
It
er
at
iv
e
Buy Build
Testing Tasks
9. Physical
Database Design
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

322
sufficiently prevent software defects because the number of ways to test a complex system
is huge. In addition, users will continue to invent new ways to use a system that its de-
velopers never considered, so certain functionalities may never have been tested or even
included in the system requirements.
Humphrey suggests that people rethink the software development process to provide
no potential defects when you enter system testing. This means that developers must be
responsible for providing error-free code at each stage of testing. Humphrey teaches a
development process in which programmers measure and track the kinds of errors they
commit so they can use the data to improve their performance. He also acknowledges that
top management must support developers by letting them self-direct their work. Program-
mers need to be motivated and excited to do high-quality work and have some control
over how they do it.13
For additional information on software testing, you can visit www.ISTQB.org, the
website for the International Software Testing Qualifications Board. The board offers a
testing certification scheme that is known around the world, with more than 354,000
certified testers in over 100 countries.
8.7 MODERN QUALITY MANAGEMENT
Modern quality management requires customer satisfaction, prefers prevention to inspec-
tion, and recognizes management responsibility for quality. Several noteworthy people
helped develop the following theories, tools, and techniques that define modern quality
management.14 The suggestions from these quality experts led to many projects to improve
quality and provided the foundation for today’s Six Sigma projects. This section summarizes
major contributions made by Deming, Juran, Crosby, Ishikawa, Taguchi, and Feigenbaum.
8.7a Deming and His 14 Points for Management
Dr. W. Edwards Deming is known primarily for his work on quality control in Japan. Dem-
ing went to Japan after World War II at the request of the Japanese government to assist
in improving productivity and quality. Deming, a statistician and former professor at
New York University, taught Japanese manufacturers that higher quality meant greater
productivity and lower cost. American industry did not recognize Deming’s theories until
Japanese manufacturers started creating products that seriously challenged American
products, particularly in the auto industry. Ford Motor Company then adopted Deming’s
quality methods and experienced dramatic improvement in quality and sales thereafter.
By the 1980s, after seeing the excellent work coming out of Japan, several U.S. corpora-
tions vied for Deming’s expertise to help them establish quality improvement programs in
their own factories.
Many people are familiar with the Deming Prize, an award given to recognize high-
quality organizations, and Deming’s Cycle for Improvement: plan, do, check, and act. Most
Six Sigma principles are based on the plan-do-check-act model created by Deming.
Many people are also familiar with Deming’s 14 Points for Management, summarized
below from his text book Out of the Crisis15:
1. Create constancy of purpose for improvement of product and service.
2. Adopt the new philosophy.
3. Cease dependence on inspection to achieve quality.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

323
4. End the practice of awarding business based on price tag alone. Instead,
minimize total cost by working with a single supplier.
5. Improve constantly and forever every process for planning, production, and
service.
6. Institute training on the job.
7. Adopt and institute leadership.
8. Drive out fear.
9. Break down barriers between staff areas.
10. Eliminate slogans, exhortations, and targets for the workforce.
11. Eliminate numerical quotas for the workforce and numerical goals for
management.
12. Remove barriers that rob people of workmanship. Eliminate the annual rat-
ing or merit system.
13. Institute a vigorous program of education and self-improvement for
everyone.
14. Put everyone in the company to work to accomplish the transformation.
8.7b Juran and the Importance of Top Management Commitment to Quality
Joseph M. Juran, like Deming, taught Japanese manufacturers how to improve their pro-
ductivity. U.S. companies later discovered him as well. He wrote the first edition of the
Quality Control Handbook in 1974, stressing the importance of top management com-
mitment to continuous product quality improvement. In 2000, at the age of 94, Juran
published the fifth edition of this famous handbook.16 He also developed the Juran Trilogy:
quality improvement, quality planning, and quality control. Juran stressed the difference
between the manufacturer’s view of quality and the customer’s view. Manufacturers often
focus on conformance to requirements, but customers focus on fitness for use. Most defi-
nitions of quality now use fitness for use to stress the importance of satisfying stated or
implied needs and not just meeting stated requirements or specifications. Juran developed
10 steps to quality improvement:
1. Build awareness of the need and opportunity for improvement.
2. Set goals for improvement.
3. Organize to reach the goals (establish a quality council, identify problems,
select projects, appoint teams, designate facilitators).
4. Provide training.
5. Carry out projects to solve problems.
6. Report progress.
7. Give recognition.
8. Communicate results.
9. Keep score.
10. Maintain momentum by making annual improvement part of the regular sys-
tems and processes of the company.
8.7c Crosby and Striving for Zero Defects
Philip B. Crosby wrote Quality Is Free in 1979 and is best known for suggesting that or-
ganizations strive for zero defects.17 He stressed that the costs of poor quality should in-
clude all the costs of not doing the job right the first time, such as scrap, rework, lost labor
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

324
hours and machine hours, customer ill will and lost sales, and warranty costs. Crosby sug-
gested that the cost of poor quality is so understated that companies can profitably spend
unlimited amounts of money on improving quality. Crosby developed the following 14
steps for quality improvement:
1. Make it clear that management is committed to quality.
2. Form quality improvement teams with representatives from each department.
3. Determine where current and potential quality problems lie.
4. Evaluate the cost of quality and explain its use as a management tool.
5. Raise the quality awareness and personal concern of all employees.
6. Take actions to correct problems identified through previous steps.
7. Establish a committee for the zero-defects program.
8. Train supervisors to actively carry out their part of the quality improvement
program.
9. Hold a “zero-defects day” to let all employees realize that there has been a
change.
10. Encourage individuals to establish improvement goals for themselves and
their groups.
11. Encourage employees to communicate to management the obstacles they
face in attaining their improvement goals.
12. Recognize and appreciate those who participate.
13. Establish quality councils to communicate on a regular basis.
14. Do it all over again to emphasize that the quality improvement program
never ends.
Crosby developed the Quality Management Process Maturity Grid in 1978. This grid
can be applied to an organization’s attitude toward product usability. For example, the
first stage in the grid is ignorance, where people might think they don’t have any problems
with usability. The final stage is wisdom, where people have changed their attitudes so
that usability defect prevention is a routine part of their operation.
8.7d Ishikawa’s Guide to Quality Control
Kaoru Ishikawa is best known for his 1972 book Guide to Quality Control.18 He devel-
oped the concept of quality circles and pioneered the use of cause-and-effect diagrams, as
described earlier in this chapter. Quality circles are groups of nonsupervisors and work
leaders in a single company department who volunteer to conduct group studies on how to
improve the effectiveness of work in their department. Ishikawa suggested that Japanese
managers and workers were totally committed to quality, but that most U.S. companies
delegated the responsibility for quality to a few staff members.
8.7e Taguchi and Robust Design Methods
Genichi Taguchi is best known for developing the Taguchi methods for optimizing the
process of engineering experimentation. Key concepts in the Taguchi methods are that
quality should be designed into the product and not inspected into it, and that quality is
best achieved by minimizing deviation from the target value. For example, if the target
response time for accessing the EIS described in the opening case is half a second, there
should be little deviation from this time. By the late 1990s, Taguchi had become, in the
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

325
words of Fortune magazine, “America’s new quality hero.”19 Many companies, including
Xerox, Ford, Hewlett-Packard, and Goodyear, have recently used Taguchi’s Robust Design
methods to design high-quality products. Robust Design methods focus on eliminating de-
fects by substituting scientific inquiry for trial-and-error methods.
8.7f Feigenbaum and Workers’ Responsibility for Quality
Armand V. Feigenbaum developed the concept of total quality control (TQC) in his 1983
book Total Quality Control: Engineering and Management.20 He proposed that the re-
sponsibility for quality should rest with the people who do the work. In TQC, product
quality is more important than production rates, and workers are allowed to stop produc-
tion whenever a quality problem occurs.
8.7g Malcolm Baldrige National Quality Award
The Malcolm Baldrige National Quality Award originated in 1987 in the United States to
recognize companies that have achieved a level of world-class competition through quality
management. The award was started in honor of Malcolm Baldrige, who was the U.S. Sec-
retary of Commerce from 1981 until his death in a rodeo accident in July 1987. Baldrige
was a proponent of quality management as a key element in improving the prosperity and
long-term strength of U.S. organizations. The Malcolm Baldrige National Quality Award is
given by the president of the United States to U.S. businesses and organizations. Organiza-
tions must apply for the award, and they must be judged outstanding in seven areas: lead-
ership, strategic planning, customer and market focus, information and analysis, human
resource focus, process management, and business results. Three awards may be given an-
nually in each of the categories of manufacturing, service, small business, and edu cation/
healthcare. The awards recognize achievements in quality and performance and raise
awareness about the importance of quality as a competitive edge; the award is not given
for specific products or services.
8.7h ISO Standards
The International Organization for Standardization (ISO) is a network of national stan-
dards institutes that work in partnership with international organizations, governments,
industries, businesses, and consumer representatives. ISO 9000, a quality system stan-
dard developed by the ISO, is a three-part, continuous cycle of planning, controlling, and
documenting quality in an organization. According to the ISO website (www.iso.org) in
March 2015, “The ISO 9000 family addresses various aspects of quality management and
contains some of ISO’s best known standards. The standards provide guidance and tools
for companies and organizations who want to ensure that their products and services con-
sistently meet customer’s requirements, and that quality is consistently improved.” The
ISO quality management standards and guidelines have earned a global reputation as the
basis for establishing quality management systems.
Standards continue to be updated, and new standards are developed as needed. For
example, in 2013, ISO collaborated with the International Electrotechnical Commission
(IEC) to publish a standard to help organizations integrate information security and ser-
vice management.21
ISO continues to offer standards to provide a framework for the assessment of soft-
ware processes. The overall goals of a standard are to encourage organizations that are
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

interested in improving quality of software products to employ proven, consistent, and
reliable methods for assessing the state of their software development processes. They can
also use their assessment results as part of coherent improvement programs. One of the
outcomes of assessment and consequent improvement programs is reliable, predictable,
and continuously improving software processes.
G L O B A L I S S U E S
In 2015, 15 electric cars were introduced throughout the world, including the Tesla
Model X, BMW X5 eDrive, VW Passat GTE Plug-in, Audi A3 e-Tron, Chevy Volt, and three
different Mercedes-Benz models. Fortunately, ISO provided standards to make them safe.
An even more impressive technology for automobiles—driverless cars—is sparking new
safety concerns. In a well-publicized event in March 2015, the Delphi car, a modified Audi
SQ5 equipped with radar, high-end microprocessors, and software, completed a trip across
the United States. A person did have to sit in the driver’s seat to comply with state laws.
Chris Urmson, the director of self-driving cars at Google, is committed to ensur-
ing that driverless vehicles are standard within five years. Google began testing them in
2009. About 33,000 people die on America’s roads every year, and drivers are the least
reliable part of the car. Urmson and his team at Google are using several quality tools and
techniques to improve the quality of driverless cars to reduce accident rates. “As we con-
tinue to work toward our vision of fully self-driving vehicles that can take anyone from
point A to point B at the push of a button, we’re thinking a lot about how to measure our
progress and our impact on road safety.”22
The contributions of quality experts, quality awards, and quality standards are impor-
tant parts of project quality management. The Project Management Institute was proud to
announce in 1999 that its certification department had become the first in the world to
earn ISO 9000 certification, and that the PMBOK® Guide had been recognized as an
international standard. Emphasizing quality in project management helps ensure that
projects create products or services that meet customer needs and expectations.
8.8 IMPROVING IT PROJECT QUALITY
In addition to some of the suggestions provided for using good quality planning, quality
assurance, and quality control, other important issues are involved in improving the qual-
ity of IT projects. Strong leadership, understanding the cost of quality, providing a good
workplace to enhance quality, and working toward improving the organization’s overall
maturity level in software development and project management can all help improve
quality.
8.8a Leadership
As Joseph M. Juran said in 1945, “It is most important that top management be quality-
minded. In the absence of sincere manifestation of interest at the top, little will happen
below.”23 Juran and many other quality experts argue that the main cause of quality prob-
lems is a lack of leadership.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

327
As globalization continues to increase and customers become more and more
demanding, creating high-quality products quickly at a reasonable price is essential for
staying in business. Having good quality programs in place helps organizations remain
competitive. To establish and implement effective quality programs, top management
must lead the way. A large percentage of quality problems are associated with manage-
ment, not technical issues. Therefore, top management must take responsibility for creat-
ing, supporting, and promoting quality programs.
Motorola provides an excellent example of a high-technology company that truly em-
phasizes quality. Leadership is one of the factors that helped Motorola achieve its great
success in quality management and Six Sigma. Top management emphasized the need to
improve quality and helped all employees take responsibility for customer satisfaction.
Strategic objectives in Motorola’s long-range plans included managing quality improve-
ment in the same way that new products or technologies were managed. Top management
stressed the need to develop and use quality standards and provided resources such as
staff, training, and customer inputs to help improve quality.
Leadership provides an environment conducive to producing quality. Management
must publicly declare the company’s philosophy and commitment to quality, imple-
ment company-wide training programs in quality concepts and principles, implement
measurement programs to establish and track quality levels, and actively demonstrate
the importance of quality. When every employee insists on producing high-quality
products, then top management has done a good job of promoting the importance
of quality.
8.8b The Cost of Quality
The cost of quality is the cost of conformance plus the cost of nonconformance. Confor-
mance means delivering products that meet requirements and fitness for use. Examples
include the costs associated with developing a quality plan, costs for analyzing and manag-
ing product requirements, and costs for testing. The cost of nonconformance means tak-
ing responsibility for failures or not meeting quality expectations.
The five major cost categories related to quality include:
1. Prevention cost: The cost of planning and executing a project so that it is
error-free or within an acceptable error range. Preventive actions such as
training, detailed studies related to quality, and quality surveys of suppli-
ers and subcontractors fall under this category. Recall from the discussion
of cost management (see Chapter 7) that detecting defects in information
systems during the early phases of the systems development life cycle is
much less expensive than during the later phases. One hundred dollars
spent refining user requirements could save millions by finding a defect
before implementing a large system. The Year 2000 (Y2K) issue provided
a good example of these costs. If organizations had decided during the
1960s, 1970s, and 1980s that all dates would need four computer charac-
ters to represent the year instead of two, they would have saved billions
of dollars.
2. Appraisal cost: The cost of evaluating processes and their outputs to ensure
that a project is error-free or within an acceptable error range. Activities
such as inspection and testing of products, maintenance of inspection and
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

test equipment, and processing and reporting inspection data all contribute
to appraisal costs of quality.
3. Internal failure cost: A cost incurred to correct an identified defect before
the customer receives the product. Items such as scrap and rework, charges
related to late payment of bills, inventory costs that are a direct result of
defects, costs of engineering changes related to correcting a design error,
premature failure of products, and correcting documentation all contribute
to internal failure cost.
4. External failure cost: A cost that relates to all errors not detected and cor-
rected before delivery to the customer. Items such as warranty cost, field
service personnel training cost, product liability suits, complaint handling,
and future business losses are examples of external failure costs.
5. Measurement and test equipment costs: The capital cost of equipment used
to perform prevention and appraisal activities.
Many industries tolerate a very low cost of nonconformance, but not the IT indus-
try. Tom DeMarco is famous for several studies he conducted on the cost of noncon-
formance in the IT industry. In the early 1980s, DeMarco found that the average large
company devoted more than 60 percent of its software development efforts to main-
tenance. Around 50 percent of development costs were typically spent on testing and
debugging software.24 Although these percentages may have improved some since the
1980s, they remain very high especially in light of the need to address computer secu-
rity issues.
Top management is primarily responsible for the high cost of nonconformance in IT.
Top managers often rush their organizations to develop new systems and do not give proj-
ect teams enough time or resources to do a project right the first time. To correct these
quality problems, top management must create a culture that embraces quality.
M E D I A S N A P S H O T
Computer viruses and malware software have been a quality concern for years. In a new
twist, consumers are now being warned that e-cigarettes, though better for health, can be
bad for computers.
According to the social media forum Reddit, an executive at a large corporation
found a malware infection on his computer. His IT staff investigated the problem, and
after looking at all traditional means of infection, they started looking at other possibili-
ties. The executive said he had recently quit smoking and started using an e-cigarette
made in China. IT found that the e-cigarette charger had malware hardcoded on it that
phoned home and infected the computer after it was plugged into the USB port.
Technical security experts confirmed that anything, including e-cigarette chargers,
can infect your computer if it can be inserted into a USB port. Dmitri Alperovitch, co-
founder and chief technology officer of Crowd Strike, a cyber threat research firm, said
the malware can then steal your files, capture your keystrokes, or turn on your web cam.
He also said that if possible, use an electrical outlet instead of a USB port to charge de-
vices, because you can’t infect an outlet.25
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

329
Although it is difficult to find reputable sources that confirm the problem-cigarette
charger story, there are many other quality concerns with new consumer products. For
example, several news agencies ran stories showing smart phone users that their where-
abouts were being tracked if they did not turn off a certain feature. Owners of smart TVs
are advised to turn off the voice recognition feature so manufacturers cannot eavesdrop
on them. As you can see, IT can be used to create many innovative products that people
want, but as the saying goes, “Let the buyer beware!”
8.8c The Impact of Organizational Influences, and Workplace Factors
on Quality
A study by Tom DeMarco and Timothy Lister produced interesting results related to or-
ganizations and relative productivity. Starting in 1984, DeMarco and Lister conducted
“Coding War Games” over several years; more than 600 software developers from
92 organizations participated. The games were designed to examine programming
quality and productivity over a wide range of organizations, technical environments,
and programming languages. The study demonstrated that organizational issues had a
much greater influence on productivity than the technical environment or program-
ming languages.
For example, DeMarco and Lister found that productivity varied by a factor of about
one to 10 across all participants. That is, one team may have finished a coding project in
one day while another team took 10 days to finish the same project. In contrast, produc-
tivity varied by an average of only 21 percent between pairs of software developers from
the same organization. If one team from an organization finished a coding project in one
day, the longest it took another team from the same organization to finish the project was
1.21 days.
DeMarco and Lister also found no correlation between productivity and programming
language, years of experience, or salary. Furthermore, the study showed that providing a
dedicated workspace and a quiet work environment were key factors in improving produc-
tivity. The results of the study suggested that top managers must focus on workplace fac-
tors to improve productivity and quality.26
In their book Peopleware DeMarco and Lister argue that major problems with work
performance and project failures are not technological but sociological in nature.27 They
suggest minimizing office politics and giving smart people physical space, intellectual re-
sponsibility, and strategic direction—and then just letting them work. The manager’s func-
tion is not to make people work but to make it possible for people to work by removing
political roadblocks. The Agile Manifesto described in Chapter 2 reiterates this concept of
focusing on individuals and interactions over processes and tools.
8.8d Expectations and Cultural Differences in Quality
Many experienced project managers know that a crucial aspect of project quality man-
agement is managing expectations. Although many aspects of quality can be clearly
defined and measured, many cannot. Different project sponsors, customers, users, and
other stakeholders have different expectations about various aspects of projects.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

330
It’s very important to understand these expectations and manage conflicts that might
occur due to differences in expectations. For example, in the opening case, several us-
ers were upset when they could not access information within a few seconds. In the
past, it may have been acceptable to wait two or three seconds for a system to load,
but many of today’s computer users expect systems to run much faster. Project manag-
ers and their teams must consider quality-related expectations as they define the proj-
ect scope.
Expectations can also vary based on an organization’s culture or geographic region.
Anyone who has traveled to different parts of an organization, a country, or the world
understands that expectations are not the same everywhere. For example, one depart-
ment in a company might expect workers to be in their work areas most of the workday
and to dress a certain way. Another department in the same company might focus
on whether workers produce expected results, no matter where they work or how
they dress.
People who work in other countries for the first time are often amazed at differ-
ent quality expectations. Visitors to other countries may complain about things they
once took for granted, such as easily making cell phone calls, using a train or subway
instead of relying on a car for transportation, or getting up-to-date maps. It’s important
to realize that different countries are at different stages of development in terms of
quality.
8.8e Maturity Models
Another approach to improving quality in software development projects and project man-
agement in general is the use of maturity models, which are frameworks for helping orga-
nizations improve their processes and systems. Maturity models describe an evolutionary
path of increasingly organized and systematically more mature processes. Many maturity
models have five levels, with the first level describing characteristics of the least organized
or mature organizations and the fifth level describing characteristics of the most organized
or mature organizations. Three popular maturity models include the Software Quality
Function Deployment (SQFD) model, the Capability Maturity Model Integration (CMMI),
and project management maturity models.
Software Quality Function Deployment Model
The Software Quality Function Deployment (SQFD) model is an adaptation of the qual-
ity function deployment model suggested in 1986 as an implementation vehicle for Total
Quality Management (TQM). SQFD focuses on defining user requirements and planning
software projects. The result of SQFD is a set of measurable technical product specifica-
tions and their priorities. Having clearer requirements can lead to fewer design changes,
increased productivity, and, ultimately, software products that are more likely to satisfy
stakeholder requirements. The idea of introducing quality early in the design stage was
based on Taguchi’s emphasis on Robust Design methods.28
Capability Maturity Model Integration
Another popular maturity model is in continuous development at the Software Engineer-
ing Institute (SEI) at Carnegie Mellon University. The SEI is a federally funded research
and development center established in 1984 by the U.S. Department of Defense with a
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

331
broad mandate to address the transition of software engineering technology. The Capabil-
ity Maturity Model Integration (CMMI) is “a process improvement approach that pro-
vides organizations with the essential elements of effective processes. It can be used to
guide process improvement across a project, a division, or an entire organization. CMMI
helps integrate traditionally separate organizational functions, set process improvement
goals and priorities, provide guidance for quality processes, and provide a point of refer-
ence for appraising current processes.”
The capability levels of the CMMI are:
0. Incomplete: At this level, a process is either not performed or partially per-
formed. No generic goals exist for this level, and one or more of the specific
goals of the process area are not satisfied.
1. Performed: A performed process satisfies the specific goals of the process
area and supports and enables the work needed to produce work products.
Although this capability level can result in improvements, those improve-
ments can be lost over time if they are not institutionalized.
2. Managed: At this level, a process has the basic infrastructure in place to
support it. The process is planned and executed based on policies and em-
ploys skilled people who have adequate resources to produce controlled
outputs. The process discipline reflected by this level ensures that existing
practices are retained during times of stress.
3. Defined: At this maturity level, a process is rigorously defined. Standards,
process descriptions, and procedures for each project are tailored from the
organization’s set of standard processes.
4. Quantitatively managed: At this level, a process is controlled using statisti-
cal and other quantitative techniques. The organization establishes quantita-
tive objectives for quality and process performance that are used as criteria
in managing the process.29
5. Optimizing: An optimizing process is improved based on an understanding
of the common causes of variation inherent in the process. The focus is on
continually improving the range of process performance through incremen-
tal and innovative improvements.30
Many companies that want to work in the government market have realized that they
will not get many opportunities even to bid on projects unless they have a CMMI Level 3.
According to one manager, “CMMI is really the future. People who aren’t on the bandwagon
now are going to find themselves falling behind.”31
Project Management Maturity Models
In the late 1990s, several organizations began developing project management maturity
models based on the CMMI. Just as organizations realized the need to improve their soft-
ware development processes and systems, they also realized the need to enhance their
project management processes and systems for all types of projects.
The PMI Standards Development Program published the first edition of the Organi-
zational Project Management Maturity Model (OPM3) in December 2003 and the third
edition was released in September 2013. More than 200 volunteers from around the world
were part of the initial OPM3 team. The model is based on market research surveys that
were sent to more than 30,000 project management professionals, and it incorporates
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

332
180 best practices and more than 2,400 capabilities, outcomes, and key performance indi-
cators.32 According to John Schlichter, the OPM3 program director, “The standard would
help organizations to assess and improve their project management capabilities as well as
the capabilities necessary to achieve organizational strategies through projects. The stan-
dard would be a project management maturity model, setting the standard for excellence
in project, program, and portfolio management best practices, and explaining the capabili-
ties necessary to achieve those best practices.”33
B E S T P R A C T I C E
OPM3 provides the following example to illustrate a best practice, capability, outcome,
and key performance indicator:
Best practice: Establish internal project management communities
Capability: Facilitate project management activities
Outcome: Establish local initiatives, meaning the organization develops
pockets of consensus around areas of special interest
Key performance indicator: The community addresses local issues
Best practices are organized into three levels: project, program, and portfolio. Within
each of those categories, best practices are categorized by four stages of process improve-
ment: standardize, measure, control, and improve. For example, the following list con-
tains several best practices listed in OPM3:
Project best practices:
Project Initiation Process Standardization
Project Plan Development Process Measurement
Project Scope Planning Process Control
Project Scope Definition Process Improvement
Program best practices:
Program Activity Definition Process Standardization
Program Activity Sequencing Process Measurement
Program Activity Duration Estimating Process Control
Program Schedule Development Process Improvement
Portfolio best practices:
Portfolio Resource Planning Process Standardization
Portfolio Cost Estimating Process Measurement
Portfolio Cost Budgeting Process Control
Portfolio Risk Management Planning Process Improvement34
Several other companies provide similar project management maturity models. The
International Institute for Learning, Inc., has five levels in its model called common
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

333
language, common processes, singular methodology, benchmarking, and continuous im-
provement. ESI International Inc.’s model has five levels called ad hoc, consistent, inte-
grated, comprehensive, and optimizing. Regardless of the names of each level, the goal is
clear: Organizations want to improve their ability to manage projects. Many organizations
are assessing where they stand in terms of project management maturity, just as they did
for software development maturity with the SQFD and CMMI maturity models. Organiza-
tions are recognizing that they must make a commitment to the discipline of project man-
agement to improve project quality.
8.9 USING SOFTWARE TO ASSIST IN PROJECT
QUALITY MANAGEMENT
This chapter provides examples of several tools and techniques used in project quality
management. Software can be used to assist with several of these tools and techniques.
For example, you can use spreadsheet and charting software to create charts and diagrams
from many of the Seven Basic Tools of Quality. You can use statistical software packages
to help you determine standard deviations and perform many types of statistical analy-
ses. You can create Gantt charts using project management software to help you plan and
track work related to project quality management. Specialized software products can as-
sist people with managing Six Sigma projects, creating quality control charts, and assess-
ing maturity levels. Project teams need to decide what types of software will help them
manage their particular projects.
As you can see, quality is a very broad topic, and it is only one of the 10 project man-
agement knowledge areas. Project managers must focus on defining how quality relates to
their specific projects and ensure that those projects satisfy the needs for which they were
undertaken.
C A S E W R A P – U P
Scott Daniels assembled a team to identify and resolve quality-related issues with the
EIS and to develop a plan to help the medical instruments company prevent future qual-
ity problems. The team’s first task was to research the problems with the EIS. The team
created a cause-and-effect diagram similar to the one in Figure 8-2. The team also cre-
ated a Pareto chart (see Figure 8-7) to help analyze the many complaints the Help Desk
received and documented about the EIS. After further investigation, Scott and his team
found that many managers using the system were very inexperienced in using comput-
ers beyond basic office automation systems. They also found that most users received no
training on how to properly access or use the new EIS. The team found no major prob-
lems with the EIS hardware or the users’ individual computers. The complaints about
reports not giving consistent information all came from one manager, who had actually
misread the reports, so there were no problems with the software design. Scott was very
impressed with the quality of the entire project, except for the training. Scott reported
his team’s findings to the project sponsor of the EIS, who was relieved to find out that
the quality problems were not as serious as many people feared.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter 8
334
Chapter Summary
Quality is a serious issue. Mistakes in several mission-critical IT systems have caused deaths,
and quality problems in many business systems have resulted in major financial losses.
Customers are ultimately responsible for defining quality. Important quality concepts include
satisfying stated or implied stakeholder needs, conforming to requirements, and delivering items
that are fit for use.
Project quality management includes planning quality management, performing quality
assurance, and controlling quality. Planning quality management identifies which quality stand-
ards are relevant to the project and how to satisfy them. Performing quality assurance involves
evaluating overall project performance to ensure that the project will satisfy the relevant quality
standards. Controlling quality includes monitoring specific project results to ensure that they
comply with quality standards and identifying ways to improve overall quality.
Many tools and techniques are related to project quality management. The Seven Basic
Tools of Quality include cause-and-effect diagrams, control charts, checksheets, scatter dia-
grams, histograms, Pareto charts, and flowcharts. Statistical sampling helps define a realistic
number of items to include when analyzing a population. Six Sigma helps companies improve
quality by reducing defects. Standard deviation measures the variation in data. Testing is very
important in developing and delivering high-quality IT products.
Many people made significant contributions to the development of modern quality management,
including Deming, Juran, Crosby, Ishikawa, Taguchi, and Feigenbaum. Many organizations today
use their ideas, which also influenced Six Sigma principles. The Malcolm Baldrige National Quality
Award and ISO 9000 have also helped organizations emphasize the importance of improving quality.
There is much room for improvement in IT project quality. Strong leadership helps empha-
size the importance of quality. Understanding the cost of quality provides an incentive for its
improvement. Providing a good workplace can improve quality and productivity. Understanding
stakeholders’ expectations and cultural differences are also related to project quality manage-
ment. Developing and following maturity models can help organizations systematically improve
their project management processes to increase the quality and success rate of projects.
Several types of software are available to assist in project quality management. It is impor-
tant for project teams to decide which software will be most helpful for their particular projects.
Quick Quiz
1. ______ is the degree to which a set of inherent characteristics fulfills requirements.
a. Quality
b. Conformance to requirements
c. Fitness for use
d. Reliability
2. What is the purpose of project quality management?
a. to produce the highest-quality products and services possible
b. to ensure that appropriate quality standards are met
c. to ensure that the project will satisfy the needs for which it was undertaken
d. all of the above
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.


kaizen
335
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter 8
Out of the Crisis

Quick Quiz Answers
Discussion Questions


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

337
Exercises


Customer Complaints Frequency/Week
Customer is on hold too long 90
Customer gets transferred to wrong area or cut off 20
Service rep cannot answer customer’s questions 120
Service rep does not follow through as promised 40

337
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter 8
Running Case
Part 5: Project Quality Management

Tasks


Requested Guidelines # of Times Requested
How to find good participants 24
How participants should present their ideas 20
How to find local sharks 15
How to select participants 12
How to manage and engage the audience 7
How to set up the facilities 3
Key Terms
5 whys
acceptance decisions
appraisal cost
benchmarking
Capability Maturity Model Integration
(CMMI)
cause-and-effect diagram
checksheet
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

339
conformance
conformance to requirements
control chart
cost of nonconformance
cost of quality
defect
design of experiments
DMAIC (Define, Measure, Analyze, Improve,
Control)
external failure cost
features
fishbone diagram
fitness for use
flowchart
functionality
histogram
integration testing
internal failure cost
Ishikawa diagram
ISO 9000
kaizen
lean
maintainability
Malcolm Baldrige National Quality Award
maturity model
mean
measurement and test equipment costs
metric
normal distribution
Pareto analysis
Pareto chart
performance
prevention cost
process adjustments
project quality management
quality
quality assurance
quality audit
quality circles
quality control
reliability
rework
Robust Design methods
run chart
scatter diagram
seven run rule
six 9s of quality
Six Sigma
software defect
Software Quality Function Deployment
(SQFD) model
standard deviation
statistical sampling
system outputs
system testing
unit test
user acceptance testing
yield
End Notes
Consultants in Minnesota
Newsletter
Design News
Datamation
New York Times
339
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter 8
340
Naked Security
Kanban
7 The Six Sigma Way
Built to Last: Successful Habits of Visionary Compa-
nies
Productivity Digest
The Six Sigma Way
Fortune
Software Development Project Life Cycle Testing Methodology
User’s Manual
Pacific Connection
Project Management
Out of the Crisis
Juran’s Quality Handbook
Quality Is Free: The Art of Making Quality Certain
Guide to Quality Control
Fortune
Total Quality Control: Engineering and Management
www.iso.org/iso/news.htm?refid=Ref1696
Back
Channel
ASQ.com www.asq
.org/about-asq/who-we-are/bio_juran.html
Quality Controlling Software Projects: Management, Measurement and
Estimation
The Washington Post
Peopleware: Productive Projects and Teams
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

341
Peopleware: Productive Projects and Teams
Business Horizons
www.sei.cmu.edu/cmmi
/general/index.html
®
FCW.com
® PMForum.com
® Project Management World Today
Organizational Project Management Maturity Model
(OPM3®)
341
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R 9
PROJECT HUMAN RESOURCE
MANAGEMENT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

344
9.1 THE IMPORTANCE OF HUMAN RESOURCE MANAGEMENT
Many corporate executives have said, “People are our most important asset.” People
determine the success and failure of organizations and projects. Most project managers
agree that managing human resources effectively is one of the toughest challenges they
face. Project human resource management is a vital component of project management,
especially in the IT field—in which qualified people are often hard to find and keep. It is
important to understand global IT workforce issues and their implications for the future.
9.1a The Global IT Workforce
Although the IT labor market has had its ups and down, there will always be a need for
people to develop and maintain IT hardware, software, networks, and applications. The
global job market for IT workers is expanding, and the demand for project managers con-
tinues to increase:
By the end of 2014, there were almost 3 billion Internet users and 2.3 billion
mobile-broadband subscriptions. Two-thirds of Internet users were from
O P E N I N G C A S E
This was the third time someone from the Information Technology (IT) department tried
to work with Ben, the head of the F-44 radar upgrade project. The F-44 was one of five
aircraft programs in the company. The company had program managers in charge of
each aircraft program, with several project managers reporting to them. Workers sup-
porting each project were part of a matrix organization, with people from engineering, IT,
manufacturing, sales, and other departments allocated as needed to each project.
Ben had been with the company for almost 30 years, and was known for being
“rough around the edges” and very demanding. The company was losing money on the
F-44 radar upgrade project because the upgrade kits were not being delivered on time.
The Canadian government had written severe late-penalty fees into its contract, and
other customers were threatening to take their business elsewhere. Ben blamed it all on
the IT department for not letting his staff access the upgrade project’s information sys-
tem directly so they could work with their customers and suppliers more effectively. The
information system was based on very old technology that only a couple of people in the
company knew how to use. It often took days or even weeks for Ben’s group to get the
information they needed.
Ed Davidson, a senior programmer, attended a meeting with Sarah Ellis, an internal
IT business consultant. Sarah was in her early thirties and had advanced quickly in her
company, primarily due to her keen ability to work well with all types of people. Sarah’s
job was to uncover the real problems with IT support for the F-44 radar upgrade project,
and then develop a solution with Ben and his team. If she found it necessary to invest in
more IT hardware, software, or staff, Sarah would write a business case to justify these
investments and then work with Ed, Ben, and his group to implement the suggested solu-
tion as quickly as possible.
Ben and three of his project team members entered the conference room. Ben threw
his books on the table and started yelling at Ed and Sarah. Ed could not believe his eyes
or ears when Sarah stood nose to nose with Ben and started yelling right back at him.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

345
developing countries, as were 55 percent of mobile-broadband subscriptions.
Mobile-cellular subscriptions reached almost 7 billion, and over half were from
the Asia-Pacific region.1 By 2025, 100 billion connections will be generated glob-
ally, and 90 percent will come from intelligent sensors.2
By 2020, global information and communications technology (ICT) spending
is projected to grow to nearly $5 trillion.3 A survey of IT executives showed
that IT budgets were expected to increase by 4.3%. “IT is expected to again
kick up spending on security tools, customer-facing technologies and in-
formation exchange/collaboration technologies that comprise the so-called
SMAC stack — social and mobile tools, analytic systems and cloud comput-
ing. Meanwhile, it’s likely that hardware spending will continue to drop and
services budgets will continue to rise.”4
Project management was number two on Computerworld’s hottest skill list
for 2015, moving up from number five in 2014 and just behind programming/
application development.5
PMI estimates demand for 15.7 million project management jobs from 2010
to 2020, with 6.2 million of those jobs in the United States.6
These studies highlight the need for skilled IT workers and project managers. As the
economy changes and technology progresses, however, people need to continually upgrade
their skills to remain marketable and flexible. Negotiation and presentation skills are also
crucial to finding and keeping a good job. Workers need to know how they personally con-
tribute to an organization’s bottom line and how they can continue to do so.
9.1b Implications for the Future of IT Human Resource Management
It is crucial for organizations to practice what they preach about human resources. If
people truly are their greatest asset, organizations must work to fulfill their human re-
source needs and the needs of individual people in their organizations, regardless of the
job market. If organizations want to implement IT projects successfully, they need to un-
derstand the importance of project human resource management and make effective use
of people.
Proactive organizations address current and future human resource needs by im-
proving benefits, redefining work hours and incentives, and finding future workers. Many
organizations have changed their benefits policies to meet worker needs. Most workers
assume that companies provide some perks, such as casual dress codes, flexible work
hours, on-the-job training, continuing education, and tuition assistance. Other compa-
nies might provide on-site day care, fitness club discounts, or matching contributions to
retirement savings. Google, the winner of Fortune’s 100 Best Companies award six times
in recent years, provides employees with free gourmet meals, on-site doctors, a swimming
spa and corporate gym, beach volleyball, Foosball, video games, pool tables, ping-pong,
roller hockey, and weekly Thank Goodness It’s Friday (TGIF) parties! Google built a large,
outdoor sports complex in 2011 to help keep its employees in shape. The company also
provides indoor recreation with bowling alleys and a dance studio, and offers a generous
amount of leave for new parents (regardless of gender, including dads, domestic partners,
adoptive parents, and surrogate parents)—twelve weeks of fully paid “baby bonding” plus
$500.7 With an average of 130 applicants per hire, it’s almost ten times harder to get a job
at Google than it is to get into Harvard.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

346
Other trends affecting the future of human resource management relate to the hours
that organizations expect many IT professionals to work and how they reward performance.
Today people are happier when they can work less than 40 hours a week or work from
home. If companies plan their projects well, they can avoid the need for overtime, or they
can make it clear that overtime is optional. Many companies also outsource more of their
project work to manage the fluctuating demand for workers, as described in Chapter 12,
Project Procurement Management.
Companies can also provide incentives that use performance, not hours worked, as
the basis of rewards. If performance can be measured objectively, as it can in many as-
pects of IT jobs, then it should not matter where employees do their work or how long it
takes. For example, if a technical writer can produce a high-quality publication at home
in one week, the company should accept the arrangement instead of insisting that the
writer come to the office and take two weeks to produce the publication. Objective mea-
sures of work performance and incentives based on meeting those criteria are important
considerations.
G L O B A L I S S U E S
In early 2013, Marissa Meyer, Yahoo’s CEO, issued a memo stating that Yahoo employees
could no longer work from home. She believed that people needed to work side-by-side
to have the best communication and collaboration. This new policy caused quite a stir
throughout the world as workers and managers discussed the pros and cons of working
from home.
Another CEO, Andy Mattes at Diebold, which makes ATMs, took the exact opposite
approach as Meyer and started recruiting employees who wanted to work from home. He
told The Huffington Post that he wanted to lure the best and brightest workers away from
Yahoo, HP, Oracle, and other companies cutting back on telecommuting.
Which CEO has the right approach? The Huffington Post would vote for Andy
Mattes. “Now, two years later, it’s clear: Telecommuting has won. Even Yahoo seems to
have softened its stance. Workers inside the company told HuffPost that some employees
still do occasionally work from home, depending on their job, and some do not have a
desk in the office. Yahoo declined to comment for this article.”8
The need to develop future talent in IT has important implications for everyone. Who
will maintain the systems we have today when the last of the “baby boomer” generation
retires? Who will continue to develop new technologies and innovative products based on
them? Some schools require all students to take computer literacy courses, although most
teenagers today already know how to use computers, iPods, iPads, cell phones, and other
technologies. But are today’s children learning the skills they’ll need to develop new tech-
nologies and work on global teams? As the workforce becomes more diverse, will more
women and minorities be ready and willing to enter IT fields? Several colleges, govern-
ment agencies, and private groups have programs to help recruit more women and minori-
ties into technical fields. Some companies provide options to assist employees who desire
work-life integration. Today’s efforts to come up with innovative ways to address these is-
sues will help to develop the human resources needed for future IT projects.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

347
W H A T W E N T W R O N G ?
A 2014 report by CompTIA found a gap between skills that employers wanted and what
they actually found in the IT workforce.
Even with 5.73 million people working in the U.S. IT industry, 68 percent of
IT firms report having a “very challenging” time finding new staff.
Fifty-two percent of organizations report having job openings, and 33 per-
cent say they are understaffed, while 42 percent say they are fully staffed
but want to hire more people in order to expand.
Fifty-eight percent of businesses are concerned about the quality and
quantity of IT talent available for hire.
Top technology priorities in this survey included security, data storage,
and network infrastructure.
The number one strategy to handle understaffing is requiring workers to
put in more hours.
Ninety-four percent of IT professionals plan to pursue more training.9
9.2 WHAT IS PROJECT HUMAN RESOURCE MANAGEMENT?
Project human resource management includes the processes required to make the most
effective use of the people involved with a project. Human resource management includes
all project stakeholders: sponsors, customers, project team members, support staff, suppli-
ers supporting the project, and so on. Human resource management includes the following
four processes:
1. Planning human resource management involves identifying and document-
ing project roles, responsibilities, and reporting relationships. The main out-
put of this process is a human resource plan.
2. Acquiring the project team involves assigning the needed personnel to work
on the project. Key outputs of this process are project staff assignments, re-
source calendars, and project management plan updates.
3. Developing the project team involves building individual and group skills to
enhance project performance. Team-building skills are often a challenge for
many project managers. The main outputs of this process are team perfor-
mance assessments and enterprise environmental factors updates.
4. Managing the project team involves tracking team member performance,
motivating team members, providing timely feedback, resolving issues and
conflicts, and coordinating changes to help enhance project performance.
Outputs of this process include change requests, project management plan
updates, project documents updates, enterprise environmental factors up-
dates, and organizational process assets updates.
Figure 9-1 summarizes these processes and outputs, showing when they occur in a
typical project.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter 9
348
You were introduced to several topics related to human resource management, includ-
ing understanding organizations, stakeholders, and different organizational structures, in
Chapter 2, The Project Management and Information Technology Context. You will learn
about other related issues in Chapter 13, Project Stakeholder Management. This chap-
ter expands on some of those topics and introduces other important concepts in project
human resource management, including theories about managing and leading people,
resource loading, and resource leveling. You also learn how to use software to assist in
project human resource management.
9.3 KEYS TO MANAGING AND LEADING PEOPLE
Industrial-organizational psychologists and management theorists have devoted extensive
research and thought to the field of managing and leading people at work. Psychosocial
issues that affect how people work and how well they work include motivation, influence
and power, effectiveness, emotional intelligence, and leadership. This section reviews the
contributions of Abraham Maslow, Frederick Herzberg, David McClelland, and Douglas
McGregor to an understanding of motivation; the work of H. J. Thamhain and D. L.
Wilemon on influencing workers and reducing conflict; the effect of power on project
teams; Stephen Covey’s work on how people and teams can become more effective;
Howard Gardner and Daniel Goleman’s focus on emotional intelligence; and recent
research on leadership. The final part of this section looks at some implications and
recommendations for project managers.
© Cengage Learning 2016
FIGURE 9-1 Project human resource management summary
Planning
Process: Plan human resource management
Output: Human resource plan
Executing
Process: Acquire project team
Outputs: Project staff assignments, resource calendars, project
management plan updates
Process: Develop project team
Outputs: Team performance assessments, enterprise environmental
factors updates
Project Start Project Finish
Process: Manage project team
Outputs: Change requests, project management plan updates,
project documents updates, enterprise environmental
factors updates, and organizational process assets updates
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

9.3a Motivation Theories
Psychologists, managers, coworkers, teachers, parents, and most people in general struggle
to understand what motivates people to do what they do. Intrinsic motivation causes peo-
ple to participate in an activity for their own enjoyment. For example, some people love to
read, write, or play an instrument because it makes them feel good. Extrinsic motivation
causes people to do something for a reward or to avoid a penalty. For example, some
young children would prefer not to play an instrument, but they do because they receive a
reward or avoid a punishment for doing so. Why do some people require no external moti-
vation to produce high-quality work while others require significant external motivation to
perform routine tasks? Why can’t you get someone who is extremely productive at work
to do simple tasks at home? Humankind is fascinated with asking and trying to answer
these types of questions. A basic understanding of motivational theory will help anyone
who works or lives with other people to understand themselves and others. Keep in mind
that the following are brief summaries, and you are encouraged to research these topics
further, especially as they relate to working with people on projects.
Maslow’s Hierarchy of Needs
Abraham Maslow, a highly respected psychologist who rejected the dehumanizing negativ-
ism of psychology in the 1950s, is best known for developing a hierarchy of needs. In the
1950s, proponents of Sigmund Freud’s psychoanalytic theory promoted the idea that hu-
man beings were not the masters of their destiny and that all their actions were governed
by unconscious processes dominated by primitive sexual urges. During the same period, be-
havioral psychologists saw human beings as controlled by the environment. Maslow argued
that both schools of thought failed to recognize unique qualities of human behavior: love,
self-esteem, belonging, self-expression, and creativity. He argued that these unique qualities
enable people to make independent choices, which gives them full control of their destiny.
Figure 9-2 shows the basic pyramid structure of Maslow’s hierarchy of needs, which
states that people’s behaviors are guided or motivated by a sequence of needs. At the bot-
tom of the hierarchy are physiological needs. Once physiological needs are satisfied, safety
needs guide behavior. Once safety needs are satisfied, social needs come to the forefront,
and so on up the hierarchy. The order of these needs and their relative sizes in the pyramid
are significant. Maslow suggests that each level of the hierarchy is a prerequisite for the lev-
els above. A person cannot consider self-actualization without first addressing basic needs
of security and safety. For example, people in an emergency, such as a flood or hurricane,
do not worry about personal growth. Personal survival will be their main motivation. Once
a particular need is satisfied, however, it no longer serves as a potent motivator of behavior.
The bottom four needs in Maslow’s hierarchy—physiological, safety, social, and
esteem—are referred to as deficiency needs, and the highest level, self-actualization,
is considered a growth need. Only after meeting deficiency needs can people act upon
growth needs. Self-actualized people are problem-focused, have an appreciation for life,
are concerned about personal growth, and are able to have peak experiences.
Most people working on an IT project probably have their basic physiological and
safety needs met. If someone has a sudden medical emergency or is laid off from work,
however, physiological and safety needs will move to the forefront. The project manager
needs to understand each team member’s motivation, especially with regard to social, es-
teem, and self-actualization or growth needs. Team members who are new to a company
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

and city might be motivated by social needs. To address social needs, some companies
organize gatherings and social events for new workers. Other project members may find
these events to be an invasion of personal time that they would rather spend with their
friends and family, or working on an advanced degree.
Maslow’s hierarchy conveys a message of hope and growth. People can work to control
their own destinies and naturally strive to satisfy higher needs. Successful project manag-
ers know they must focus on meeting project goals, but they also must understand team
members’ personal goals and needs to provide appropriate motivation and maximize team
performance.
Herzberg’s Motivation-Hygiene Theory
Frederick Herzberg is best known for distinguishing between motivational factors and
hygiene factors when considering motivation in work settings. He referred to factors that
cause job satisfaction as motivators and factors that could cause dissatisfaction as hygiene
factors.
Herzberg was the head of Case Western University’s psychology department, and he
wrote the book Work and the Nature of Man in 1966 and a famous Harvard Business Re-
view article, “One More Time: How Do You Motivate Employees?” in 1968.10 Herzberg an-
alyzed the factors that affected productivity among a sample of 1,685 employees. Popular
beliefs at the time were that work output was most improved through larger salaries, more
supervision, or a more attractive work environment. According to Herzberg, these hygiene
factors would cause dissatisfaction if not present, but would not motivate workers to do
more if present. Today, professionals might also expect employers to provide health bene-
fits, training, and a computer or other equipment required to perform their jobs. Herzberg
found that people were motivated to work mostly by feelings of personal achievement and
recognition. Motivators, Herzberg concluded, included achievement, recognition, the work
itself, responsibility, advancement, and growth, as shown in Table 9-1.
FIGURE 9-2
A satisfied need is no longer a motivator
high
5. Self-
Actualization
4. Esteem
3. Social
2. Safety
1. Physiological
low
Challenging projects,
opportunities for
innovation and creativity
Recognition,
prestige, statusAcceptance, love,
affection, association
with a team/group Physical safety,
economic
securityFood,
water,
etc.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

In his books and articles, Herzberg explained why companies could not instill mo-
tivation by attempting to use positive factors such as reducing time spent at work, in-
creasing wages, offering fringe benefits, and providing human relations and sensitivity
training. He argued that people want to actualize themselves by being able to use their
creativity and work on challenging projects. They need stimuli to grow and advance, in
accordance with Maslow’s hierarchy of needs. Factors such as achievement, recogni-
tion, responsibility, advancement, and growth produce job satisfaction and are work
motivators.
M E D I A S N A P S H O T
Books and articles are written every year on the topic of human motivation. Videos are
also popular on this subject, especially one by Daniel Pink. RSA Animate used its popular
whiteboard drawing technique to summarize key points from Pink’s book in a YouTube
video called “Drive: The surprising truth about what motivates us.” Pink narrates the
video, summarizing several studies that suggest money often causes people to perform
worse on tasks that involve cognitive skills. He suggests that organizations should pay
people enough to eliminate resentments over money and stop using the carrot-and-stick
approach to motivation. Pink also suggests that managers focus on the following three
motivators:
Autonomy: People like to be self-directed and have freedom in their work.
Maslow, Herzberg, and other researchers also found that people are motivated
by autonomy. Pink gives an example of how an Australian software company
called Atlassian lets people decide what they want to work on, and with whom,
for one day every quarter. Workers show the results of their work that day in a
fun meeting. This one day of total autonomy has produced a large number of
new products and fixes to problems.
Mastery: People like to improve their skills, such as playing an instrument,
participating in a sport, writing software, and mastering work-related activi-
ties. Pink states that several products like UNIX, Apache, and Wikipedia
were created because people enjoyed the challenge and mastery involved.
TABLE 9-1
Hygiene Factors Motivators
Larger salaries Achievement
More supervision Recognition
More attractive work environment Work itself
Computer or other required equipment Responsibility
Health benefits Advancement
Training Growth
© Cengage Learning 2016
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Purpose: People want to work for a good purpose. When the profit motive is
separated from the purpose motive, people notice and do not perform as
well. Many great products were created for a purpose. For example, the
founder of Skype wanted to make the world a better place, and Steve Jobs,
the co-founder of Apple, wanted to put a “ding in the universe.”11
McClelland’s Acquired-Needs Theory
David McClelland proposed that a person’s specific needs are acquired or learned over
time and shaped by life experiences. The main categories of acquired needs include
achievement, affiliation, and power.12 Normally, one or two of these needs are dominant
in people.
Achievement: People who have a high need for achievement (nAch) seek to
excel, and tend to avoid both low-risk and high-risk situations to improve their
chances for achieving something worthwhile. Achievers need regular feedback
and often prefer to work alone or with other high achievers. Managers should
give high achievers challenging projects with achievable goals. Achievers should
receive frequent performance feedback, and although money is not an important
motivator to them, it is an effective form of feedback.
Affiliation: People with a high need for affiliation (nAff) desire harmonious
relationships with other people and need to feel accepted by others. They
tend to conform to the norms of their work group and prefer work that in-
volves significant personal interaction. Managers should try to create a coop-
erative work environment to meet the needs of people with a high need for
affiliation.
Power: People with a need for power (nPow) desire either personal power
or institutional power. People who need personal power want to direct oth-
ers and can be seen as bossy. People who need institutional power or social
power want to organize others to further the goals of the organization. Man-
agement should provide such employees with the opportunity to manage oth-
ers, emphasizing the importance of meeting organizational goals.
The Thematic Apperception Test (TAT) is a tool to measure the individual needs of
different people using McClelland’s categories. The TAT presents subjects with a series of
ambiguous pictures and asks them to develop a spontaneous story for each picture, as-
suming they will project their own needs into the story.
McGregor’s Theory X and Theory Y
Douglas McGregor was one of the great popularizers of a human relations approach to
management, and he is best known for developing Theory X and Theory Y. In his research,
documented in his 1960 book The Human Side of Enterprise, McGregor found that al-
though many managers spouted the right ideas, they actually followed a set of assump-
tions about worker motivation that he called Theory X (sometimes referred to as classical
systems theory).13 People who believe in Theory X assume that workers dislike and avoid
work if possible, so managers must use coercion, threats, and various control schemes
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

353
to have workers make adequate efforts to meet objectives. They assume that the average
worker wants to be directed and prefers to avoid responsibility, has little ambition, and
wants security above all else. Research clearly demonstrated that these assumptions were
not valid. McGregor suggested a different series of assumptions about human behavior
that he called Theory Y (sometimes referred to as human relations theory). Managers who
believe in Theory Y assume that employees do not inherently dislike work, but consider it
as natural as play or rest. The most significant rewards are the satisfaction of esteem and
self-actualization needs, as described by Maslow. McGregor urged managers to motivate
people based on Theory Y notions.
In 1981, William Ouchi introduced another approach to management in his book
Theory Z: How American Business Can Meet the Japanese Challenge.14 Theory Z is based
on the Japanese approach to motivating workers, which emphasizes trust, quality, col-
lective decision making, and cultural values. Whereas Theory X and Theory Y emphasize
how management views employees, Theory Z also describes how workers perceive man-
agement. Theory Z workers, it is assumed, can be trusted to do their jobs to their utmost
ability, as long as management can be trusted to support them and look out for their well-
being. Theory Z emphasizes job rotation, broadening of skills, generalization versus spe-
cialization, and the need for continuous training of workers.
9.3b Influence and Power
Many people working on a project do not report directly to project managers, and project
managers often do not have control over project staff who report to them. For example, if
they are given work assignments they do not like, many workers will simply quit or trans-
fer to other departments or projects. People are free to change jobs when they like.
H. J. Thamhain and D. L. Wilemon investigated the approaches that project managers
use to deal with workers and how those approaches relate to project success. They identi-
fied nine influence bases that are available to project managers:
1. Authority: the legitimate hierarchical right to issue orders
2. Assignment: the project manager’s perceived ability to influence a worker’s
later work assignments
3. Budget: the project manager’s perceived ability to authorize others’ use of
discretionary funds
4. Promotion: the ability to improve a worker’s position
5. Money: the ability to increase a worker’s pay and benefits
6. Penalty: the project manager’s perceived ability to dispense or cause
punishment
7. Work challenge: the ability to assign work that capitalizes on a worker’s en-
joyment of doing a particular task, which taps an intrinsic motivational factor
8. Expertise: the project manager’s perceived special knowledge that others
deem important
9. Friendship: the ability to establish friendly personal relationships between
the project manager and others15
Top management grants authority to the project manager. However, assignment,
budget, promotion, money, and penalty influence bases are not automatically avail-
able to project managers as part of their position. Others’ perceptions are important in
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

354
establishing the usefulness of these influence bases. For example, any manager can influ-
ence workers by providing challenging work; the ability to provide challenging work (or
take it away) is not a special ability of project managers. In addition, project managers
must earn the ability to influence by using expertise and friendship.
Thamhain and Wilemon found that projects were more likely to fail when project
managers relied too heavily on using authority, money, or penalty to influence people.
When project managers used work challenge and expertise to influence people, projects
were more likely to succeed. The effectiveness of work challenge in influencing people is
consistent with Maslow’s and Herzberg’s research on motivation. The importance of exper-
tise as a means of influencing people makes sense on projects that involve special knowl-
edge, as in most IT projects.
In 2013, Thamhain published a study of 72 global project teams, and the results again
showed that people issues have the strongest impact on project performance. Managers
cannot succeed by simply issuing work orders, preparing plans, or providing guidelines.
They must emphasize common values and goals to focus and unify global teams. “In par-
ticular, the field study shows that certain conditions related to the people side, such as
personal interest, pride and satisfaction with the work, professional work challenge, ac-
complishments and recognition, appear most favorable toward unifying culturally diverse
project teams and their work processes. These conditions serve as a bridging mechanism
between organizational goals and personal interests, between central control and local
management norms, and between following a project plan and adaptive problem solving.
These are some of the conditions crucial to project success in complex multi-cultural
organizations.”16
Influence is related to power, which is the ability to influence behavior to get people
to do things they would not otherwise do. Power is much stronger than influence, because
it is often used to force people to change their behavior. There are five main types of
power, according to French and Raven’s classic study, “The Bases of Social Power.”17
Coercive power involves using punishment, threats, or other negative ap-
proaches to get people to do things they do not want to do. This type of power
is similar to Thamhain and Wilemon’s influence category called penalty.
For example, a project manager can threaten to fire workers or subcontrac-
tors to try to get them to change their behavior. If the project manager really
has the power to fire people, he or she could follow through on the threat.
Recall, however, that influencing by using penalties is correlated with unsuc-
cessful projects. Still, coercive power can be very effective in stopping nega-
tive behavior. For example, if students tend to hand in assignments late, an
instructor can have a policy in the syllabus for late penalties, such as a 20
percent grade reduction for each day an assignment is late. Workers’ pay can
be docked if they arrive late for work, or they might be fired if they arrive late
more than once.
Legitimate power is getting people to do things based on a position of author-
ity. This type of power is similar to the authority basis of influence. If top
management gives project managers organizational authority, they can use
legitimate power in several situations. They can make key decisions without
involving the project team, for example. Overemphasis on legitimate power
or authority also correlates with project failure.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

355
Expert power involves using personal knowledge and expertise to get people
to change their behavior. People who perceive that project managers are
experts in certain situations will follow their suggestions. For example, if a
project manager has expertise in working with a particular IT supplier and its
products, the project team will be more likely to follow the project manager’s
suggestions on how to work with that vendor and its products.
Reward power involves using incentives to induce people to do things. Re-
wards can include money, status, recognition, promotions, and special work
assignments. Many motivation theorists suggest that only certain types of
rewards, such as work challenge, achievement, and recognition, truly induce
people to change their behavior or work hard.
Referent power is based on a person’s own charisma. People who have refer-
ent power are held in very high regard; others will do what they say based
on that regard. People such as Martin Luther King, Jr., John F. Kennedy, and
Bill Clinton had referent power. Very few people possess the natural charisma
that underlies referent power.
It is important for project managers to understand what types of influence and power
they can use in different situations. New project managers often overemphasize their
position—their legitimate power or authority influence—especially when dealing with
project team members or support staff. They also neglect the importance of reward power
or work challenge influence. People often respond much better to a project manager who
motivates them with challenging work and provides positive reinforcement for doing a
good job. Project managers should understand the basic concepts of influence and power,
and should practice using them to their own advantage and to help their teams.
9.3c Covey and Improving Effectiveness
Stephen Covey, author of The 7 Habits of Highly Effective People: Powerful Lessons in
Personal Change,18 expanded on the work done by Maslow, Herzberg, and others to de-
velop an approach for helping people and teams become more effective. Covey’s first three
habits of effective people—be proactive, begin with the end in mind, and put first things
first—help people achieve a private victory by becoming independent. After achieving
independence, people can then strive for interdependence by developing the next three
habits—think win/win, seek first to understand then to be understood, and synergize.
(Synergy is the concept that the whole is equal to more than the sum of its parts.) Finally,
everyone can work on Covey’s seventh habit—sharpen the saw—to develop and renew
their physical, spiritual, mental, social, and emotional selves.
Project managers can apply Covey’s seven habits to improve effectiveness on projects,
as follows:
1. Be proactive. Covey, like Maslow, believes that people have the ability to be
proactive and choose their responses to different situations. Project managers
must be proactive in anticipating and planning for problems and inevitable
changes on projects. They can also encourage their team members to be pro-
active in working on their project activities.
2. Begin with the end in mind. Covey suggests that people focus on their val-
ues, what they want to accomplish, and how they want to be remembered in
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

356
their lives. He suggests writing a mission statement to help achieve this habit.
Many organizations and projects have mission statements that help them fo-
cus on their main purpose.
3. Put first things first. Covey developed a time management system and ma-
trix to help people prioritize their time. He suggests that most people need
to spend more time doing things that are important, but not urgent. Such
activities include planning, reading, and exercising. Project managers need
to spend a lot of time working on important but not urgent activities, such as
developing various project plans, building relationships with major project
stakeholders, and mentoring project team members. They also need to avoid
focusing only on important and urgent activities—putting out fires.
4. Think win/win. Covey presents several paradigms of interdependence; think
win/win is the best choice in most situations. When you use a win/win para-
digm, parties in potential conflict work together to develop new solutions that
benefit all parties. Project managers should strive to use a win/win approach
in making decisions, but in competitive situations they sometimes must use a
win/lose paradigm.
5. Seek first to understand, then to be understood. Empathic listening is listen-
ing with the intent to understand. It is more powerful than active listening
because you set aside your personal interests and focus on truly understand-
ing the other person. When you practice empathic listening, you can begin
two-way communication. This habit is critical for project managers so they
can understand their stakeholders’ needs and expectations.
6. Synergize. A project team can synergize by creating collaborative products
that are much better than a collection of individual efforts. Covey also em-
phasizes the importance of valuing differences in others to achieve synergy.
Synergy is essential to many highly technical projects; in fact, several major
breakthroughs in IT occurred because of synergy. For example, in his Pulitzer
Prize-winning book, The Soul of a New Machine, Tracy Kidder documented
the synergistic efforts of a team of Data General researchers to create a new
32-bit superminicomputer during the 1970s.19
7. Sharpen the saw. When you practice sharpening the saw, you take time to
renew yourself physically, spiritually, mentally, and socially. The practice of
self-renewal helps people avoid burnout. Project managers must make sure
that they and their project teams have time to retrain, reenergize, and oc-
casionally even relax to avoid burnout. A simple technique like encouraging
people to stand up and walk around for a brief time every hour can improve
physical health and mental performance.
Douglas Ross, author of Applying Covey’s Seven Habits to a Project Management
Career, related Covey’s habits to project management. Ross suggests that Habit 5—Seek
first to understand, then to be understood—differentiates good project managers from
average or poor ones. People have a tendency to focus on their own agendas instead of
first trying to understand other people’s points of view. Empathic listening can help proj-
ect managers and team members find out what motivates different people. Understand-
ing what motivates key stakeholders and customers can mean the difference between a
project’s success or failure. Once project managers and team members begin to practice
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

357
empathic listening, they can communicate and work together to tackle problems more
effectively.20
Before you can practice empathic listening, you first have to get people to talk to you.
In many cases, you must work on developing a rapport with the other person. Rapport is a
relation of harmony, conformity, accord, or affinity. Without rapport, people cannot begin
to communicate. For example, in the chapter’s opening case, Ben was not ready to talk to
anyone from the IT department, even if Ed and Sarah were ready to listen. Ben was angry
about the lack of support he received from the IT department and bullied anyone who re-
minded him of that group. Before Sarah could begin to communicate with Ben, she had to
establish rapport.
One technique for establishing rapport is mirroring. Mirroring is matching certain
behaviors of the other person. People tend to like others who are like themselves, and
mirroring helps you take on some of the other person’s characteristics. It also helps them
realize if they are behaving unreasonably, as in the chapter’s opening case. You can mir-
ror someone’s tone and tempo of voice, breathing, movements, or body postures. After
Ben started yelling at her, Sarah quickly decided to mirror his voice tone, tempo, and
body posture. She stood nose to nose with Ben and started yelling back at him. This ac-
tion made Ben realize what he was doing, and it also made him notice and respect his
colleague from the IT department. Once Ben overcame his anger, he could start commu-
nicating his needs. In most cases, however, such extreme measures are not needed, and
mirroring must be used with caution. When done improperly or with the wrong person, it
could result in very negative consequences.
Recall the importance of getting users involved in IT projects. For organizations to be
truly effective in IT project management, they must find ways to help users and develop-
ers of information systems work together. It is widely accepted that organizations make
better project decisions when business professionals and IT staff collaborate. It is also
widely accepted that this task is easier said than done. Many companies have been very
successful in integrating technology and business departments, but many other companies
continue to struggle with this issue.
9.3d Emotional Intelligence
As the title suggests, Howard Gardner’s book Frames of Mind: The Theory of Multiple In-
telligences, introduced the concept of using more than one way to think of and measure
human intelligence. Gardner suggested the need to develop both interpersonal intelligence
(the capacity to understand the motivations, intentions, and desires of others) and intrap-
ersonal intelligence (the capacity to understand oneself, one’s feelings, and motivations).
Empathic listening is an example of interpersonal intelligence, while knowing that you
have a high need for achievement is an example of intrapersonal intelligence. The concept
emotional intelligence—knowing and managing one’s own emotions and understanding
the emotions of others for improved performance—became popular in 1995 when Daniel
Goleman’s book, Emotional Intelligence, became a best-seller.
Several articles and books have been written on the need for project managers to de-
velop their emotional intelligence (EI). For example, Anthony C. Mersino, PMP, author of
Emotional Intelligence for Project Managers: The People Skills You Need to Achieve Out-
standing Results, says that EI comes into play as project managers work on team build-
ing, collaboration, negotiation, and relationship development. EI is also becoming a more
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

358
sought after characteristic. According to a CareerBuilder.com survey of over 2,600 U.S.
hiring managers and human resource professionals:
71 percent said they value EI in an employee more than IQ.
59 percent said they would not hire someone who has a high IQ but low EI.
75 percent said they are more likely to promote an employee with high EI
than an employee with a high IQ.21
9.3e Leadership
As defined in Chapter 1, a leader focuses on long-term goals and big-picture objectives
while inspiring people to reach those goals. Leadership is a soft skill, and there is no
one best way to be a leader. Peter Northouse, author of a popular textbook called Lead-
ership: Theory and Practice, says, “In the past 60 years, as many as 65 different clas-
sification systems have been developed to define the dimensions of leadership.”22 Some
classification systems focus on group processes, while others focus on personality traits
or behaviors. People discuss transformational leaders, transactional leaders, and servant
leaders, to name a few. There are many different leadership styles, and the one thing
most experts agree on is that the best leaders are able to adapt their style to needs of the
situation.
Daniel Goleman, author of Emotional Intelligence, also wrote a book called Primal
Leadership, which describes six different styles of leadership and situations where they
are most appropriate:
1. Visionary: Needed when an organization needs a new direction, and the goal
is to move people towards a new set of shared dreams. The leader articulates
where the group is going, but lets them decide how to get there by being free
to innovate, experiment, and take calculated risks.
2. Coaching: One-on-one style that focuses on developing individuals, show-
ing them how to improve their performance. This approach works best with
workers who show initiative and request assistance.
3. Affiliative: Emphasizes the importance of team work and creating harmony
by connecting people to each other. This approach is effective when trying to
increase morale, improve communication, or repair broken trust.
4. Democratic: Focuses on people’s knowledge and skills and creates a com-
mitment to reaching shared goals. This leadership style works best when the
leader needs the collective wisdom of the group to decide on the best direc-
tion to take for the organization.
5. Pacesetting: Used to set high standards for performance. The leader wants
work to be done better and faster and expects everyone to put forth their best
effort.
6. Commanding: Most often used, also called autocratic or military style
leadership. This style is most effective in a crisis or when a turnaround is
needed.
Goleman points out that “The goal for leaders should be to develop a solid under-
standing of the different styles of leadership and their implications, and reach the point
where choosing the right one for the situation becomes second nature to them.”23
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

W H A T W E N T R I G H T ?
It’s important for professional societies to stay abreast of skills needed in their profession.
In 2015, PMI acknowledged that project management professionals need to be continually
updating their skills by developing a new Continuing Certification Requirements (CCR) pro-
gram. Applicants who want to renew a PMI certification must now demonstrate ongoing pro-
fessional development that meets the new PMI Talent Triangle. The Talent Triangle includes:
Technical project management: Knowledge, skills, and behaviors related to specific
domains of project, program, and portfolio management
Strategic and business management: Knowledge of and expertise in the
industry or organization that enhances performance and better delivers
business outcomes
Leadership: Knowledge, skills, and behaviors specific to leadership-oriented,
cross-cutting skills that help an organization achieve its business goals.
PMI has always emphasized the need to stay abreast of technical project manage-
ment, but now it is placing more emphasis on strategic and business management as well
as leadership skills. PMI often surveys individuals and organizations, and in a recent re-
port, 75 percent of organizations ranked leadership skills as most important for success-
ful navigation of complexity in projects. “Managing complex projects requires project
managers who are able to establish the vision, mission and expected outcomes in a way
that is broad enough to be complete yet simple enough to understand. It also requires
the skill to align the team to that vision. These are project managers who have become
project executives with the leadership skill and business acumen to drive success.24
It is important to understand and pay attention to concepts of motivation, influence,
power, effectiveness, emotional intelligence, and leadership in all project processes. It is
also important to remember that projects operate within an organizational environment.
The challenge comes from applying the preceding theories to the many unique people in-
volved in particular projects.
Many important topics related to motivation, influence, power, effectiveness, emo-
tional intelligence, and leadership are relevant to project management. Projects are done
by and for people, so it is important for project managers and team members to under-
stand and practice key concepts related to these topics. Remember that everyone prefers
to work with people they like and respect, and it is important to treat others with respect,
regardless of their title or position. This is especially true for people in support roles, such
as administrative assistants, security guards, or members of the cleaning crew. You never
know when you may need their help at a critical point in a project.
9.4 DEVELOPING THE HUMAN RESOURCE PLAN
To develop a human resource plan for a project, you must identify and document project
roles, responsibilities, skills, and reporting relationships. The human resource plan often
includes an organizational chart for the project, detailed information on roles and respon-
sibilities, and a staffing management plan.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Before creating an organizational chart or any part of the human resource plan for a
project, top management and the project manager must identify what types of people the
project needs to ensure success. If the key to success lies in having the best Java program-
mers you can find, planning should reflect that need. If the real key to success is having
a top-notch project manager and respected team leaders, that need should drive human
resource planning.
9.4a Project Organizational Charts
Recall from Chapter 2 that the nature of IT projects often means that project team mem-
bers come from different backgrounds and possess a wide variety of skills. It can be very
difficult to manage such a diverse group of people, so it is important to provide a clear
organizational structure for a project. After identifying important skills and the types of
people needed to staff a project, the project manager should work with top management
and project team members to create an organizational chart for the project. Figure 9-3
provides part of an organizational chart for a large project that involves hardware and
software development. For example, in the chapter’s opening case, a program manager
might be in charge of every project related to the F-44 aircraft, and each major compo-
nent of the aircraft, like the radar system, might have its own dedicated project manager.
Note that the project personnel include a deputy project manager, subproject managers,
and teams. Other boxes on the chart represent each functional department supporting
the project, such as systems engineering, quality assurance, and configuration manage-
ment, as well as an external independent test group. Deputy project managers fill in for
project managers in their absence and assist them as needed. Subproject managers are
responsible for managing the subprojects into which a large project might be divided.
FIGURE 9-3
Project Manager
Deputy Project
Manager
Project Technical
Lead
Independent
Test Group
Quality
Assurance
Configuration
Management
Systems
Engineering
S/W Subproject
Manager 2
S/W Subproject
Manager 1
Team 1 Team 1Team 2 Team 2 Team 1 Team 2Team 3
H/W Subproject
Manager
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

For example, an aircraft radar upgrade project could involve several major software
(S/W) upgrades as well as hardware (H/W) upgrades, so a subproject manager could be
in charge of each upgrade. This structure is typical for large projects that use a matrix
organizational structure. When many people work on a project, clearly defining and al-
locating project work is essential. (For example, visit the companion website for this text
to see the project organizational chart that Northwest Airlines used for its large Resnet
project.) Smaller projects usually do not have deputy project managers or subproject
managers. On smaller projects, the project managers might have team leaders reporting
directly to them.
In addition to defining an organizational structure for a project, it is also important to
follow a work definition and assignment process. Figure 9-4 provides a framework for de-
fining and assigning work that consists of four steps:
1. Finalizing the project requirements
2. Defining how the work will be accomplished
3. Breaking down the work into manageable elements
4. Assigning work responsibilities
The work definition and assignment process is carried out during the proposal and
startup phases of a project. Note that the process is iterative, often taking more than
one pass. A Request for Proposal (RFP) or draft contract often provides the basis for de-
fining and finalizing work requirements, which are then documented in a final contract
and technical baseline. If the project does not require an RFP, then the internal project
charter and scope statement would provide the basis for defining and finalizing work
requirements, as described in Chapter 5, Project Scope Management. The project team
leaders then decide on a technical approach for how to do the work. Should work be
broken down using a product-oriented approach or a phased approach? Will the project
FIGURE 9-4
RFP, Contract, Charter,
Scope Statement
Steps Key Outputs
Requirements Finalization Finalized Project Scope BaselineFinalized Technical Baseline
How Work Will Be Done Program/Team ApproachTechnical Approaches
Break Down the Work Work Breakdown Structure (WBS)Activity Definitions
Assign the Work Organizational BreakdownStructure (OBS)
OBS Responsibilities
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

team outsource some of the work or subcontract to other companies? Once the proj-
ect team has decided on a technical approach, it develops a work breakdown structure
(WBS) to establish manageable elements of work, as described in Chapter 5. The team
then develops activity definitions for the work involved in each activity on the WBS, as
you learned in Chapter 6, Project Time Management. The last step is assigning
the work.
Once the project manager and project team have broken down the work into man-
ageable elements, the project manager assigns work to organizational units. The project
manager often bases these work assignments on where the work fits in the organization
and uses an organizational breakdown structure to conceptualize the process. An
organizational breakdown structure (OBS) is a specific type of organizational chart that
shows which organizational units are responsible for which work items. The OBS can be
based on a general organizational chart and then broken down into more detail, based on
specific units within departments in the company or units in any subcontracted compa-
nies. For example, OBS categories might include software development, hardware devel-
opment, and training.
9.4b Responsibility Assignment Matrices
After developing an OBS, the project manager can develop a responsibility assignment
matrix. A responsibility assignment matrix (RAM) maps the work of the project, as de-
scribed in the WBS, to the people responsible for performing the work, as described in the
OBS. Figure 9-5 shows an example of a RAM. The RAM allocates work to responsible and
performing organizations, teams, or individuals, depending on the desired level of detail.
For smaller projects, it is best to assign individual people to WBS activities. For very large
projects, it is more effective to assign the work to organizational units or teams, as shown
in Figure 9-5.
In addition to using a RAM to assign detailed work activities, you can use it to de-
fine general roles and responsibilities on projects. This type of RAM can include the
FIGURE 9-5
WBS activities
Systems Engineering
Software Development
Hardware Development
Test Engineering
Quality Assurance
Configuration Management
Integrated Logistics Support
Training
1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6 1.1.7 1.1.8
R R P
R P
R P
P
R P
R P
P
R P
R
OBS
units
R = Responsible organizational unit
P = Performing organizational unit
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

363
stakeholders in the project. Some organizations use RACI charts to show four key roles
for project stakeholders:
Responsibility: Who does the task?
Accountability: Who signs off on the task or has authority for it?
Consultation: Who has information necessary to complete the task?
Informed: Who needs to be notified of task status and results?
As shown in Table 9-2, a RACI chart lists tasks vertically and lists individuals or
groups horizontally. Each intersecting cell contains an R, A, C, or I. A task may have
multiple R, C, or I entries, but there can be only one A entry per row to clarify who is ac-
countable for each task. For example, a mechanic is responsible for repairing a car, but
the shop owner is accountable for the repairs being made properly. The car owner and
parts supplier would be other stakeholders with various roles for different work activities,
as shown in Table 9-2. Project managers can use the RACI codes or any other codes to
help clarify the roles that different organizational units or specific stakeholders have in
getting the work done.
TABLE 9-2
Car Owner Shop Owner Mechanic Parts Supplier
Pay for parts and services A, R C
Determine parts and services
needed
C A, R C
Supply parts C C A, R
Install parts I A R
© Cengage Learning 2016
9.4c Staffing Management Plans and Resource Histograms
A staffing management plan describes when and how people will be added to the project
team and taken off it. The level of detail may vary based on the type of project. For ex-
ample, if an IT project is expected to need 100 people on average over a year, the staff-
ing management plan would describe the types of people needed to work on the project,
such as Java programmers, business analysts, and technical writers, and the number
of each type of person needed each month. The plan would also describe how these re-
sources would be acquired, trained, rewarded, and reassigned after the project. All of
these issues are important to meeting the needs of the project, the employees, and the
organization.
The staffing management plan often includes a resource histogram, which is a column
chart that shows the number of resources assigned to a project over time. Figure 9-6 pro-
vides an example of a histogram that might be used for a six-month IT project. Notice that
the columns represent the number of people needed in each area—managers, business
analysts, programmers, and technical writers. By stacking the columns, you can see the
total number of people needed each month. After determining the project staffing needs,
the next steps in project human resource management are to acquire the necessary staff
and then develop the project team.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

364
9.5 ACQUIRING THE PROJECT TEAM
During the late 1990s, the IT job market became extremely competitive. It was a seller’s
market with corporations competing fiercely for a shrinking pool of qualified, experienced
IT professionals. In the early 2000s, the market declined tremendously, so employers
could be very selective in recruiting. Today, many organizations again face a shortage of IT
staff. Regardless of the current job market, however, acquiring qualified IT professionals
is critical. There is a saying that the project manager who is the smartest person on the
team has done a poor job of recruiting. In addition to recruiting team members, it is also
important to assign the appropriate type and number of people to work on projects at the
appropriate times. This section addresses important topics related to acquiring the project
team: resource assignment, resource loading, and resource leveling.
9.5a Resource Assignment
After developing a staffing management plan, project managers must work with other
people in their organizations to assign personnel to their projects or to acquire additional
human resources needed to staff the project. Project managers with strong influencing
and negotiating skills are often good at getting internal people to work on their projects.
However, the organization must ensure that people are assigned to the projects that
best fit their skills and the needs of the organization. The main outputs of this process
are project staff assignments, resource availability information, and updates to the staff-
ing management plan. Many project teams also find it useful to create a project team
directory.
FIGURE 9-6
Jan
0
N
um
be
r
of
P
eo
pl
e
1
2
3
4
5
6
7
8
Feb March April May June
Managers Business analysts Programmers Technical writers
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

365
Organizations that do a good job of staff acquisition have good staffing plans. These
plans describe the number and type of people who are currently in the organization and
the number and type of people anticipated to be needed for the project based on current
and upcoming activities. An important component of staffing plans is maintaining a com-
plete and accurate inventory of employees’ skills. If there is a mismatch between the cur-
rent mix of people’s skills and needs of the organization, it is the project manager’s job to
work with top management, human resource managers, and other people in the organiza-
tion to address staffing and training needs.
It is also important to have good procedures in place for hiring subcontractors and
recruiting new employees. Because the Human Resource department is normally respon-
sible for hiring people, project managers must work with their human resource managers
to address any problems in recruiting appropriate people. It is also a priority to address
retention issues, especially for IT professionals.
One innovative approach to hiring and retaining IT staff is to offer existing employees
incentives for helping recruit and retain personnel. For example, several consulting com-
panies give their employees one dollar for every hour worked by a new person they helped
recruit. This provides an incentive for current employees to help attract new people and
to keep all of them working at the company. Another approach to attract and retain IT
professionals is to provide benefits based on personal need. For example, some people
might want to work only four days a week or have the option of working a couple of days a
week from home. As it becomes more difficult to find good IT professionals, organizations
must become more innovative and proactive in addressing this issue.
It is very important to consider the needs of individuals and the organization when
making recruiting and retention decisions and to study the best practices of leading com-
panies in these areas. It is also important to address a growing trend in project teams—
many team members work in a virtual environment. See the section on managing the
project team for suggestions on working with virtual team members.
B E S T P R A C T I C E
Best practices can also include the best places for people to work. Fortune magazine
publishes a list of the “100 Best Companies to Work For” in the United States every
year, with Google taking top honors for the sixth time in 2015. Companies want to make
the list and be known for being a great place to work, and people are drawn to work for
companies on the list. Working Mothers magazine lists the best companies in the United
States for women based on benefits for working families. The Times online (www.time-
sonline.co.uk) provides the London Sunday Times list of the “100 Best Companies to
Work For,” a key benchmark against which U.K. companies can judge their performance
as employers. The Great Place to Work Institute, which produces Fortune magazine’s
“100 Best Companies to Work For,” uses the same selection methodology for more than
20 international lists, including all 15 countries of the European Union, Brazil, Korea,
and a number of other countries throughout Latin America and Asia. Companies make
these lists based on feedback from their best critics: their own employees. Quotes from
employees often show why their companies made the lists:
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

366
“Working here can make you feel that you’ve made it into the technical equivalent
of Major League Baseball or the NFL—you’re at the top of your field.” #1: Google
“Although people come from across the world, from different cultures, and from
different life experiences,” one employee says, “everyone shares a passion for
problem-solving and a positive attitude about teamwork.” #2: Boston Cons-
ulting Group
“Our health insurance benefits are awesome, our schedules are flexible and
we can keep our bodies healthy at our gym,” says one team member. “ACUITY
takes not only good care of me, but also my family.” #3: ACCUITY
“SAS has provisions to support you at whatever stage of life you are in – child
care for your newborn to preschooler, resources for dealing with your teenager
and college planning, help with your elderly parent,” says one employee. “More
importantly, a real sense of community is built when people work together for
so long.” #4 SAS25
9.5b Resource Loading
Chapter 6, Project Time Management, described using network diagrams to help manage
a project’s schedule. One of the problems or dangers inherent in scheduling processes is
that they often do not address the issues of resource utilization and availability. This is
why the development of critical chain scheduling is so important. Schedules tend to focus
primarily on time rather than both time and resources, which includes people. An impor-
tant measure of a project manager’s success is how well he or she balances the trade-offs
among performance, time, and cost. During a period of crisis, it is occasionally possible to
add resources—such as additional staff—to a project at little or no cost. Most of the time,
however, resolving performance, time, and cost trade-offs entails additional costs to the
organization. The project manager’s goal must be to achieve project success without in-
creasing the costs or time required to complete the project. The key to accomplishing this
goal is effectively managing human resources on the project.
Once people are assigned to projects, two techniques are available to project man-
agers that help them use project staff most effectively: resource loading and resource
leveling. Resource loading refers to the amount of individual resources that an existing
schedule requires during specific time periods. Resource loading helps project managers
understand the demands of a project on the organization’s resources and on individual
people’s schedules. Project managers often use resource histograms, like the one shown in
Figure 9-6, to depict period-by-period variations in resource loading. A resource histogram
can be very helpful in determining staffing needs or in identifying staffing problems.
A resource histogram can also show when work is being overallocated to a certain
person or group. Overallocation means that not enough resources are available to perform
the assigned work during a given time period. Figure 9-7 shows a sample resource histo-
gram created in Microsoft Project. This histogram illustrates how much one person, Joe
Franklin, is assigned to work on the project each week. The numbers on the vertical axis
represent the percentage of Joe’s available time that is allocated for him to work on the
project. The top horizontal axis represents time in weeks. Note that Joe Franklin is overal-
located most of the time. For example, for most of March and April and part of May, Joe’s
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

367
work allocation is 300 percent of his available time. If Joe is normally available eight hours
per day, this means he would have to work 24 hours a day to meet this staffing projection!
Overallocation can happen for many reasons. Many people don’t use the resource as-
signment features of project management software properly. (See Appendix A for detailed
information on using Microsoft Project 2013.) You also need to provide good estimates of
how many hours are required to accomplish work. As mentioned in Chapter 6, Project Time
Management, a typical worker does productive work between 70 and 80 percent of the time.
If people are assigned to work for 40 hours in a week, you should estimate that they will ac-
complish 28 to 32 hours of productive work. Of course, there are exceptions to this rule of
thumb, but it is unrealistic to assume that all workers are productive 100 percent of the time.
9.5c Resource Leveling
Resource leveling is a technique for resolving resource conflicts by delaying tasks. It is
a form of network analysis in which resource management concerns drive scheduling
decisions (start and finish dates). The main purpose of resource leveling is to create a
smoother distribution of resource usage. Project managers examine the network diagram
for areas of slack or float, and to identify resource conflicts. For example, you can some-
times remove overallocations by delaying noncritical tasks, which does not result in an
overall schedule delay. At other times, you will need to delay the project completion date
FIGURE 9-7
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

368
to reduce or remove overallocations. Appendix A explains how to use Microsoft Project
2013 to level resources using both of these approaches. You can also view resource lev-
eling as addressing the resource constraints described in critical chain scheduling (see
Chapter 6, Project Time Management).
Overallocation is one type of resource conflict. If a certain resource is overallocated,
the project manager can change the schedule to remove resource overallocation. If a cer-
tain resource is underallocated, the project manager can change the schedule to try to
improve the use of the resource. Resource leveling, therefore, aims to minimize period-by-
period variations in resource loading by shifting tasks within their slack allowances.
Figure 9-8 illustrates a simple example of resource leveling. The network diagram at
the top of this figure shows that Activities A, B, and C can all start at the same time. Ac-
tivity A has a duration of two days and will take two people to complete; Activity B has a
duration of five days and will take four people to complete; and Activity C has a duration
of three days and will take two people to complete. The histogram in the lower-left corner
of this figure shows the resource usage if all activities start on day one. The histogram in
Project network with Activities A,
B, and C and durations as shown.
Activity A has 3 days of slack, and
Activity C has 2 days of slack.
Assume Activity A has 2 workers,
B has 4 workers, and C has 2 workers.
2
4
6
8
2
4
6
8
0 1 2 3 4 5 0 1 2 3 4 5
W
or
ke
rs
W
or
ke
rs CA
B
A
B
B B
C C
Resource usage if all
activities start on day one
Resource usage if Activity C
is delayed 2 days, its total slack
4
2
3
A=2 days
B=5 days
C=3 days
Days Days
1
FIGURE 9-8
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

the lower-right corner shows the resource usage if Activity C is delayed two days, its total
slack allowance. Notice that the lower-right histogram is flat or leveled; that is, its activi-
ties are arranged to take up the least space, saving days and numbers of workers. You may
recognize this strategy from the computer game Tetris, in which you earn points for keep-
ing the falling shapes as level as possible. In the same way, resources are used best when
they are leveled.
Resource leveling has several benefits. First, when resources are used on a more
constant basis, they require less management. For example, it is much easier to man-
age someone who is scheduled to work 20 hours per week on a project for the next three
months than it is to manage the same person for 10 hours one week, 40 the next, 5 the
next, and so on.
Second, resource leveling may enable project managers to use a just-in-time inven-
tory type of policy for subcontractors or other expensive resources. For example, a project
manager might want to level resources for work that must be done by particular subcon-
tractors such as testing consultants. This leveling might allow the project to use four out-
side consultants full-time to perform testing for four months instead of spreading out the
work over more time or using more than four people. The latter approach is usually more
expensive. Recall from Chapter 6 that crashing and fast tracking can also be used along
with resource allocation to improve a project schedule.
Third, resource leveling results in fewer problems for project personnel and acco-
unting departments. Increasing and decreasing labor levels and human resources often
produce additional work and confusion. For example, if people with expertise in the
same area are only assigned to a project two days a week and they need to work together,
then the schedule needs to reflect this need. The Accounting department might com-
plain when subcontractors charge a higher rate for billing less than 20 hours a week on
a project. The accountants will remind project managers to strive to get the lowest rates
possible.
Finally, resource leveling often improves morale. People like to have stability in their
jobs. It is very stressful for people not to know what projects they will be working on from
week to week or even from day to day.
Project management software can automatically level resources. However, the
project manager must be careful in using the results without making adjustments.
Automatic leveling often pushes out the project’s completion date. Resources may also
be reallocated to work at times that are inappropriate with other constraints. To ensure
that the leveling is done appropriately, a wise project manager would have his or her
work checked by a team member who is proficient in using the project management
software.
9.6 DEVELOPING THE PROJECT TEAM
Even if a project manager has successfully recruited enough skilled people to work on
a project, the project manager must ensure that people can work together as a team
to achieve project goals. Many IT projects have talented people working on them,
but it takes teamwork to complete most projects successfully. The main goal of team
development is to help people work together more effectively to improve project
performance.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

First published in 1965 and modified in the 1970s, Dr. Bruce Tuckman’s model of
team development remains relevant today. The Tuckman model describes five stages of
team development:
1. Forming involves the introduction of team members, either at the initiation
of the team or as new members are introduced. This stage is necessary, but
little work is actually achieved.
2. Storming occurs when team members have different opinions for how the
team should operate. People test each other, and there is often conflict within
the team.
3. Norming is achieved when team members have developed a common work-
ing method, and cooperation and collaboration replace the conflict and mis-
trust of the previous phase.
4. Performing occurs when the emphasis is on reaching the team’s goals rather
than working on team process. Relationships are settled, and team members
are likely to build loyalty toward each other. At this stage, the team is able to
manage tasks that are more complex and cope with greater change.
5. Adjourning involves the break-up of the team after it successfully reaches its
goals and completes the work.26
There is an extensive body of literature on team development. This section highlights
a few important tools and techniques for team development, including training, team-
building activities, and reward and recognition systems.
9.6a Training
Project managers often recommend that people take specific training courses to improve
individual and team development. For example, Sarah from the opening case had gone
through training in emotional intelligence and dealing with difficult people. She was famil-
iar with the mirroring technique and felt comfortable using that approach with Ben. Many
other people would not have reacted so quickly and effectively in the same situation. If
Ben and Sarah did reach agreement on what actions they could take to resolve the F-44
aircraft program’s IT problems, it might result in a new project to develop and deliver a
new system for Ben’s group. If Sarah became the project manager for this new project, she
would understand the need for special training in interpersonal skills for specific people in
her department and Ben’s. Individual team members could take special training classes to
improve their interpersonal skills. If Sarah thought the whole project team could benefit
from taking training together to learn to work as a team, she could arrange for a special
team-building session for the entire project team and key stakeholders.
It is very important to provide training in a just-in-time fashion. For example, if Sarah
were preparing for a technical assignment that required her to learn a new programming
language, training to deal with difficult people would not help her much. However, the
training was very timely for her new consulting position. Many organizations provide e-
learning opportunities for their employees so they can learn specific skills at any time
and any place. They have also found that e-learning is sometimes more cost-effective than
traditional instructor-led training courses. It is important to make sure that the timing
and delivery method for the training is appropriate for specific situations and individuals.
Organizations have also found that it is often more economical to train current employees
in particular areas than it is to hire new people who already possess those skills.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Several organizations that have successfully implemented Six Sigma principles have
taken a unique and effective approach to training. They only let high-potential employees at-
tend Six Sigma Black Belt training, which is a substantial investment of time and money. In
addition, they do not let employees into a particular Black Belt course until the employees
have had a potential Six Sigma project approved that relates to their current job. Attendees
can then apply the new concepts and techniques they learn in the classes to their jobs. High-
potential employees feel rewarded by being picked to take this training, and the organization
benefits by having these employees implement high-payoff projects because of the training.
9.6b Team-Building Activities
Many organizations provide in-house team-building training activities, and many also use
services provided by external companies that specialize in this area. It is important to
understand individual needs, including learning styles, past training, and physical limita-
tions, when determining team-building training options. Two common approaches to team-
building activities are physical challenges and psychological preference indicator tools.
Several organizations have teams go through physically challenging activities to help
them develop as a team. Military basic training or boot camps provide one example. Men
and women who want to join the military must first finish basic training, which often in-
volves strenuous physical activities such as rappelling off towers, running and marching
in full military gear, going through obstacle courses, passing marksmanship training, and
mastering survival training. Many organizations use a similar approach by sending teams
to special locations where they work together to navigate white water rapids, climb moun-
tains or rocks, and participate in rope courses. Research shows that physical challenges
often help teams of strangers to work together more effectively, but it can cause already
dysfunctional teams to have even more problems.
Even more organizations have teams participate in mental team-building activities
in which they learn about themselves, each other, and how to work as a group most ef-
fectively. It is important for people to understand and value each other’s differences
to work effectively as a team. Three common exercises used in mental team building
include the Myers-Briggs Type Indicator, Wilson Learning Social Styles Profile, and the
DISC Profile.
The Myers-Briggs Type Indicator
The Myers-Briggs Type Indicator (MBTI) is a popular tool for determining personality
preferences. During World War II, Isabel B. Myers and Katherine C. Briggs developed the
first version of the MBTI based on psychologist Carl Jung’s theory of psychological type.
The four dimensions of psychological type in the MBTI include:
Extrovert/Introvert (E/I): This first dimension determines if you are generally
extroverted or introverted, which signifies whether you draw energy from other
people (extrovert) or from yourself (introvert).
Sensation/Intuition (S/N): This second dimension relates to the manner in
which you gather information. Sensation (or Sensing) type people take in
facts, details, and reality and describe themselves as practical. Intuitive type
people are imaginative, ingenious, and attentive to hunches or intuition.
They describe themselves as innovative and conceptual.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Thinking/Feeling (T/F): Thinking judgment is objective and logical, and feel-
ing judgment is subjective and personal.
Judgment/Perception (J/P): This fourth dimension concerns people’s at-
titudes toward structure. Judgment type people like closure and task
completion. They tend to establish deadlines and take them seriously, ex-
pecting others to do the same. Perceiving types prefer to keep things open
and flexible. They regard deadlines more as a signal to start rather than
complete a project and do not feel that work must be done before play or
rest begins.27
Much more than this simple sketch is involved in determining personality types, and
many books are available on this topic. In 1998, David Keirsey published Please Under-
stand Me II: Temperament, Character, Intelligence.28 This book includes a test called the
Keirsey Temperament Sorter, which is a personality type preference test based on the
work of Jung, Myers, and Briggs. The test is easy to take and interpret.
An interesting study of the MBTI types within the general population of the United
States and information systems (IS) developers revealed some significant contrasts.29
The two groups of people were most similar in the judgment/perception dimension,
with slightly more than half of each group preferring the judgment type (J). There were
significant differences, however, in the other three dimensions. Most people would not
be surprised to learn that most IS developers are introverts. This study found that
75 percent of IS developers were introverts, and only 25 percent of the general popula-
tion were introverts. This personality type difference might help explain some of the
problems users have communicating with developers. Another sharp contrast found in
the study was that almost 80 percent of IS developers were thinking types compared
to 50 percent of the general population. IS developers were also much more likely
to be intuitive (about 55 percent) than the general population (about 25 percent).
These results fit with Keirsey’s classification of NT (Intuitive/Thinking types) people as
rationals. Educationally, they tend to study the sciences, enjoy technology as a hobby,
and pursue systems work. Keirsey also suggests that no more than 7 percent of the
general population are NTs. Would you be surprised to know that Bill Gates is classified
as a rational?30
Project managers can often benefit from knowing their team members’ MBTI profiles
by adjusting their management styles for each person. For example, if the project man-
ager is a strong N and one of the team members is a strong S, the project manager should
provide more concrete, detailed explanations for that person’s task assignments. Project
managers may also want to make sure they have a variety of personality types on their
teams. For example, if all team members are strong introverts, it may be difficult for them
to work well with users and other important stakeholders who are extroverts.
Like any test, you should use the MBTI with caution. Several studies argue that the
lack of progress in improving software development teams and other teams is due in part
to the inappropriate use of psychological tests and basic misunderstandings of personality
theory. “Software engineers often complain about those who, in the course of their work,
do some programming in support of their professional activities: the claim being that such
individuals are not professionals and do not understand the discipline. The same can be
said of those who adopt psychological approaches without the relevant qualifications and
background.”31
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Taurus

373
The Social Styles Profile
Many organizations also use the Social Styles Profile in team-building activities. Psycholo-
gist David Merril, who helped develop the Wilson Learning Social Styles Profile, describes
people as falling into four approximate behavioral profiles, or zones, based on their asser-
tiveness and responsiveness:
Drivers are proactive and task-oriented. They are firmly rooted in the present,
and they strive for action. Adjectives to describe drivers include pushy, severe,
tough, dominating, harsh, strong-willed, independent, practical, decisive, and
efficient.
Expressives are proactive and people-oriented. They are future-oriented and
use their intuition to look for fresh perspectives on the world around them.
Adjectives to describe expressives include manipulating, excitable, undisci-
plined, reacting, egotistical, ambitious, stimulating, wacky, enthusiastic, dra-
matic, and friendly.
Analyticals are reactive and task-oriented. They are past-oriented and strong
thinkers. Adjectives to describe analyticals include critical, indecisive, stuffy,
picky, moralistic, industrious, persistent, serious, expecting, and orderly.
Amiables are reactive and people-oriented. They think in terms of the present,
past, or future depending on the situation, and they strongly value relationships.
Adjectives to describe amiables include conforming, unsure, ingratiating, depen-
dent, awkward, supportive, respectful, willing, dependable, and agreeable.32
Figure 9-9 shows these four social styles and their two main determinants: assertive-
ness and responsiveness. To determine your level of assertiveness, ask if you are more
FIGURE 9-9
A
sk
-D
ir
ec
te
d
A
ss
er
ti
ve
ne
ss
People-Directed Responsiveness
Task-Directed Responsiveness
Tell-D
irected A
ssertiveness
Analytical Driver
Amiable Expressive
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

374
likely to tell people what to do or ask them what should be done. To determine your re-
sponsiveness to tasks, ask whether you focus on the task itself or on the people involved
in performing the task.
Knowing the social styles of project stakeholders can help project managers under-
stand why certain people may have problems working together. For example, drivers are
often very impatient working with amiables, and analyticals often have difficulties under-
standing expressives.
DISC Profile
Similar to the Social Styles Profile, the DISC Profile uses a four-dimensional model of
normal behavior. The four dimensions—Dominance, Influence, Steadiness, and
Compliance—provide the basis for the name DISC. Note that other, similar, terms are
sometimes used for some of these letters, such as stability for steadiness or conscientious-
ness for compliance. The DISC Profile is based on the 1928 work of psychologist William
Moulton Marston. The DISC Profile reveals people’s behavioral tendencies under certain
situations. For example, it reveals how you tend to behave under stress, in conflict, when
communicating, and when avoiding certain activities. According to www.onlinediscpro-
file.com, “over 5 million people have taken various forms of the DISC Profile throughout
the world. Marston’s original work continues to be enhanced by ongoing behavioral
research and profiles can be found in more than 50 languages by various publishers of the
disc assessment.”33
Figure 9-10 shows the four dimensions of the DISC Profile model and describes key
characteristics of each dimension. Notice that each dimension is also associated with a
color and emphasis, such as I, We, You, or It:
FIGURE 9-10
Dominance (Red)
Direct, decisive, assertive,
outcome oriented, competitive,
self assured, takes control, has
to win
I
Influence (Yellow)
Persuasive, optimistic,
outgoing, verbal, enthusiastic,
strives to win others over,
leadership through acclimation
We
Compliance (Blue)
Data driven, risk averse,
concerned, works well alone,
prefers processes and procedures,
not very communicative or social
It
Steadiness (Green)
Calm, sincere, sympathetic,
cooperative, cautious, conflict
averse, good listener, wants to
maintain stability
You
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

375
Dominance: Represented by red and emphasizing “I,” dominance traits include
being direct, decisive, assertive, outcome-oriented, competitive, self-assured,
controlling, and wanting to win.
Influence: Represented by yellow and emphasizing “We,” influence traits in-
clude being persuasive, optimistic, outgoing, verbal, enthusiastic, striving to
win others over, and practicing leadership through acclimation.
Steadiness: Represented by green and emphasizing “You,” steadiness traits
include being calm, sincere, cautious, conflict averse, a good listener, and
wanting to maintain stability.
Compliance: Represented by blue and emphasizing “It,” compliance traits
include being data driven, risk averse, concerned, working well alone, pre-
ferring processes and procedures, and not being very communicative
or social.
Like the Social Styles Profile, people in opposite quadrants, such as Dominance and
Steadiness or Influence and Compliance, can have problems understanding each other.
Many other team-building activities and tests are available. For example, some
people take Dr. Meredith Belbin’s test to help determine which of nine team roles they
might prefer. Again, professionals should use any team-building or personality tool with
caution. In reality, most professionals must be flexible and do whatever is needed for
their teams to succeed. Project managers can use their leadership and coaching skills to
help all types of people communicate better with each other and focus on meeting
project goals.
9.6c Reward and Recognition Systems
Another important tool for promoting team development is the use of team-based reward
and recognition systems. If management rewards teamwork, they will promote or rein-
force the philosophy that people work more effectively in teams. Some organizations offer
bonuses, trips, or other rewards to workers that meet or exceed company or project goals.
In a project setting, project managers can recognize and reward people who willingly work
overtime to meet an aggressive schedule objective or go out of their way to help a team-
mate. Project managers should not reward people who work overtime just to get extra pay
or because of their own poor work or planning.
Project managers must continually assess their team’s performance. When they find
areas in which individuals or the entire team can improve, it’s their job to find the best
way to develop their people and improve performance.
9.7 MANAGING THE PROJECT TEAM
In addition to developing the project team, the project manager must lead it in perform-
ing various project activities. (Note that PMI uses the word managing the project team as
the third process for human resource management versus leading, so that wording is used
here as well.) After assessing team performance and related information, the project man-
ager must decide if changes should be requested to the project, or if updates are needed
to enterprise environmental factors, organizational process assets, or the project manage-
ment plan. Project managers must use their soft skills to find the best way to motivate and
manage each team member.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

376
9.7a Tools and Techniques for Managing Project Teams
Several tools and techniques are available to assist in managing project teams:
Observation and conversation: Project managers need to observe team mem-
bers at work to assess how they are performing and ask team members how
they feel about their work. Many project managers like to practice “management
by walking around” (MBWA) to physically see and hear their team members at
work. Informal or formal conversations about how a project is going can provide
crucial information. For virtual workers, project managers can observe and dis-
cuss work and personal issues via e-mail, telephone, web conference, or other
media.
Project performance appraisals: Just as managers provide performance ap-
praisals for their workers, so can project managers. The need for project
performance appraisals and the types required vary depending on the length
of the project, its complexity, organizational policies, contract requirements,
and related communications. Even if a project manager does not provide offi-
cial project performance appraisals for team members, it is still important to
provide timely performance feedback. If a team member hands in sloppy or
late work, the project manager should determine the reason and take appro-
priate action. Perhaps the team member had a death in the family and could
not concentrate. Perhaps the team member was planning to leave the project.
The reasons for the behavior should have a strong impact on the action the
project manager takes.
Interpersonal skills: As you learned in Chapter 1, project managers must
possess several interpersonal skills. To be effective, it is especially important
to focus on leadership, influencing, and decision-making skills.
Conflict management: Few projects are completed without conflicts. Some
types of conflict are actually desirable on projects, but many are not. It’s im-
portant for project managers to understand strategies for handling conflicts
and to proactively manage conflict.
Blake and Mouton (1964) delineated five basic modes or strategies for handling con-
flicts in their popular managerial grid. Each strategy has high, medium, or low importance
on two levels: importance of the task or goal (or concern for production), and importance
of the relationship between the conflicting parties (concern for people). These modes are
shown in Figure 9-11.
1. Confrontation: When using the confrontation mode, project managers face
a conflict directly using a problem-solving approach that allows affected par-
ties to work through their disagreements. This approach is also called the
problem-solving mode or win/win using Covey’s terminology. When the task
and relationship are both of high importance, this mode is usually the most
effective.
2. Compromise: With the compromise mode, project managers use a give-
and-take approach to resolving conflicts. They bargain and search for solu-
tions that bring some degree of satisfaction to all the parties in a dispute.
This mode works best when both the task and relationship are of medium
importance.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

377
3. Smoothing: When using the smoothing mode, the project manager deempha-
sizes or avoids areas of differences and emphasizes areas of agreement. This
approach is also called accommodating, and it is best used when the relation-
ship is of high importance and the task is of low importance.
4. Forcing: The forcing mode can be viewed as the win/lose approach to conflict
resolution. Project managers exert their viewpoint at the potential expense of
another viewpoint. If the task is of high importance and the relationship is of
low importance, this mode can be very effective.
5. Withdrawal: When using the withdrawal mode, project managers retreat
or withdraw from an actual or potential disagreement. This approach is also
called avoiding, and is normally the least desirable conflict-handling mode,
unless the task and relationship are both of low importance.
More recent studies recognize a sixth conflict-handling mode:
6. Collaborating: Using the collaborating mode, decision makers incorporate
different viewpoints and insights to develop consensus and commitment.
Even though managers might not agree on a decision, they commit to follow-
ing it in the best interests of the organization.
Project managers must also realize that not all conflict is bad. Conflict often produces
important results, such as new ideas, better alternatives, and motivation to work harder and
more collaboratively. Project team members may become stagnant or develop groupthink—
conformance to the values or ethical standards of a group—if there are no conflicting
An Introduction to Project Management, Fourth Edition
FIGURE 9-11
Forcing
Compromise
Smoothing/
Accommodating
Confrontation/
Problem-solving
Collaborating
Withdrawal/
Avoidance
HighMediumLow
Low
Medium
High
Task Importance
Re
la
ti
on
sh
ip
Im
po
rt
an
ce
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

378
viewpoints on various aspects of a project. Research by Karen Jehn, Professor of
Management at the University of Melbourne, suggests that task-related conflict, which is
derived from differences over team objectives and how to achieve them, often improves
team performance. Emotional conflict, however, stems from personality clashes and misun-
derstandings, and often depresses team performance. Project managers should create an en-
vironment that encourages and maintains the positive and productive aspects of conflict.34
9.7b General Advice on Managing Teams
According to Patrick Lencioni, a well-known author and consultant on teams, “Teamwork
remains the one sustainable competitive advantage that has been largely untapped …
teamwork is almost always lacking within organizations that fail, and often present within
those that succeed.”35 However, teamwork is challenging to create, and because teams are
subject to dysfunction, maintaining teamwork is equally challenging. The five dysfunc-
tions of teams are:
1. Absence of trust
2. Fear of conflict
3. Lack of commitment
4. Avoidance of accountability
5. Inattention to results
Lencioni’s books provide suggestions for overcoming each of these dysfunctions.
For example, he suggests that team members take the Myers-Briggs Type Indicator, as
described earlier in this chapter, to help people open up to each other and build trust.
To master conflict, he suggests that teams practice having unfiltered, passionate debates
about important issues. To achieve commitment, he stresses the importance of expressing
all possible ideas and getting people to agree to disagree, but then having them commit
to decisions. To embrace accountability, Lencioni emphasizes the importance of clarify-
ing and focusing on everyone’s top priorities. He also suggests that peer pressure and the
distaste for letting down a colleague are often better motivators than authoritative inter-
vention. Finally, using some type of scoreboard to focus on team results helps eliminate
ambiguity so everyone knows what it means to achieve positive results.
Additional suggestions for ensuring that teams are productive include the following:
Be patient and kind with your team. Assume the best about people; do not as-
sume that your team members are lazy and careless.
Fix the problem instead of blaming people. Help people work out problems by
focusing on behaviors.
Establish regular, effective meetings. Focus on meeting project objectives and
producing positive results.
Allow time for teams to go through Tuckman’s basic team-building stages of
forming, storming, norming, performing, and adjourning. Don’t expect teams
to work at the highest performance level right away.
Limit the size of work teams to three to seven members.
Plan some social activities to help project team members and other stake-
holders get to know each other better. Make the social events fun and not
mandatory.
Stress team identity. Create traditions that team members enjoy.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Nurture team members and encourage them to help each other. Identify and
provide training that will help individuals and the team as a whole become
more effective.
Acknowledge individual and group accomplishments.
Take additional actions to work with virtual team members. If possible, have
a face-to-face or phone meeting at the start of a virtual project or when intro-
ducing a virtual team member. Screen people carefully to make sure they can
work effectively in a virtual environment. Clarify how virtual team members
will communicate.
As you can imagine, team development, leadership, and management are critical con-
cerns on many IT projects. To paraphrase Keirsey, many IT project managers must break
out of their rational/NT preference and focus on empathically listening to other people to
address their concerns and create an environment in which individuals and teams can
grow and prosper.
9.8 USING SOFTWARE TO ASSIST IN HUMAN
RESOURCE MANAGEMENT
Earlier in this chapter, you read that a simple responsibility assignment matrix or re-
source histograms are useful tools that can help you effectively manage human resources
on projects. You can use several different software packages, including spreadsheets or
project management software such as Microsoft Project 2013, to create matrixes and his-
tograms. Many people do not realize that Project 2013 provides a variety of human
resource management tools, some of which include assigning and tracking resources,
resource leveling, resource usage reports, overallocated resource reports, and to-do lists.
You can learn how to use many of these functions and features in Appendix A.
You can use Project 2013 to assign resources such as equipment, materials, facilities,
and people to tasks. It enables you to allocate individual resources to individual projects
or to pool resources and share them across multiple projects. By defining and assigning
resources in Project 2013, you can:
Keep track of resources through stored information and reports on resource
assignments.
Identify potential resource shortages that could cause a project to miss
scheduled deadlines and possibly extend the duration of a project.
Identify underutilized resources and reassign them, which may enable you to
shorten a project’s schedule and reduce costs.
Use automated leveling to make level resources easier to manage.
Just as many project management professionals are unaware of the powerful cost-
management features of Project 2013, many are unaware of its powerful human resource
management features. The Microsoft Enterprise Project Management Solution provides
additional human resource management capabilities. You can also purchase add-in soft-
ware for Microsoft products or purchase software from other companies to manage your
project’s human resources. With the aid of this software, project managers can have more
information available in useful formats to help them decide how to manage human re-
sources most effectively.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Project resource management involves much more than using software to assess and
track resource loading and to level resources. People are the most important asset on most
projects, and human resources are very different from other resources. You cannot simply
replace people in the same way that you replace a piece of equipment. It is essential to
treat people with consideration and respect, to understand what motivates them, and to
communicate carefully with them. What makes good project managers great is not their
use of tools, but their ability to enable project team members to deliver their best work on
a project.
C A S E W R A P – U P
After Sarah yelled back at Ben, he said, “You’re the first person who’s had the guts to
stand up to me.” After that brief introduction, Sarah, Ben, and the other meeting par-
ticipants had a good discussion about what was happening on the F-44 upgrade project.
Sarah was able to write a justification to get Ben’s group special software and support to
download key information from the old system so they could manage their project better.
When Sarah stood nose to nose with Ben and yelled at him, she used a technique for es-
tablishing rapport called mirroring. Although Sarah was not a loud and obnoxious person,
she saw that Ben was and decided to mirror his behavior and attitude. She put herself
in his shoes for a while, which helped break the ice so Sarah, Ben, and the other people
at the meeting could start communicating and working together as a team to solve their
problems.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter Summary
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Quick Quiz
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

383
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

384
Quick Quiz Answers
Discussion Questions
Exercises
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

385
www.humanmetrics.com www.personalitytype.com
www.keirsey.com
Running Case
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

386
www.humanmetrics.com
Key Terms
coercive power
collaborating mode
compromise mode
confrontation mode
deputy project managers
emotional intelligence
empathic listening
expert power
extrinsic motivation
forcing mode
groupthink
hierarchy of needs
intrinsic motivation
legitimate power
mirroring
Myers-Briggs Type Indicator (MBTI)
organizational breakdown structure
(OBS)
overallocation
power
RACI charts
rapport
referent power
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

387
resource histogram
resource leveling
resource loading
responsibility assignment matrix
(RAM)
reward power
smoothing mode
staffing management plan
subproject managers
synergy
team development
Tuckman model
withdrawal mode
Endnotes
telecompaper.com
Computerworld
Computerworld
Fortune
fortune.com/best-companies/
The
Huffington Post
CompTIA www.comptia.org/resources/
state-of-the-it-skills-gap-2014.
Harvard Business
Review
www.youtube.com/watch?v=u6XAPnuFjJc
The Achieving Society
The Human Side of Enterprise
Theory Z: How American Business Can Meet the Japanese Challenge
Technology Management
American Journal of Industrial and Business Management
dx.doi.org/10.4236/ajibm.2013.32020
Studies in Social
Power
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

388
The 7 Habits of Highly Effective People: Powerful Lessons in Personal
Change
The Soul of a New Machine
PM
Network
Leadership: Theory and Practice
®
us. greatrated.com/rankings/2015-fortune-100-best-companies-to-work-for-list.
Group Organization Management
Gifts Differing: Understanding Personality Type
Please Understand Me II: Temperament, Character, Intelligence
Datamation
Keirsey.com
Communications of the ACM
The New Why Teams Don’t Work: What Goes Wrong
and How to Make It Right
OnlineDiscProfile.
com
Wharton Leadership Digest
Overcoming the Five Dysfunctions of a Team: A Field Guide for Leaders,
Managers, and Facilitators
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R 10
PROJECT COMMUNICATIONS
MANAGEMENT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:




Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

10.1 THE IMPORTANCE OF PROJECT COMMUNICATIONS
MANAGEMENT
Many experts agree that the greatest threat to the success of any project, especially IT
projects, is a failure to communicate. Many problems in other knowledge areas, such as
an unclear scope or unrealistic schedules, indicate problems with communication. It is
crucial for project managers and their teams to make good communication a priority,
especially with top management and other key stakeholders.
The IT field is constantly changing, and these changes come with a great deal of
technical jargon. When computer professionals communicate with people who aren’t as
proficient with or knowledgeable about computers—a group that includes many business
professionals and senior managers—technical jargon can often complicate matters and
create confusion. Even though most people use computers today, the gap between users
and developers increases as technology advances. This gap in knowledge and experience
causes some of the communication problems between technical professionals and their
business colleagues. Of course, not every computer professional is a poor communicator,
but most people in any field can improve their communication skills.
In addition, many educational systems for IT graduates promote strong technical skills
over strong communication and social skills. Most IT-related degree programs have many
O P E N I N G C A S E
Peter Gumpert worked his way up the corporate ladder in a large telecommunications
company. He was intelligent, competent, and a strong leader, but the company’s new
fiber-optic undersea telecommunications program was much larger and more compli-
cated than anything he had previously worked on, let alone managed. This program
consisted of several distinct projects, and Peter was in charge of overseeing them all. The
changing marketplace for undersea telecommunications systems and the large number
of projects involved made communications and flexibility critical concerns for Peter. For
missing milestone and completion dates, his company would suffer financial penalties
ranging from thousands of dollars per day for smaller projects to more than $250,000 per
day for larger projects. Many projects depended on the success of other projects, so Peter
had to understand and actively manage those critical interfaces.
Peter held several informal and formal discussions with the project managers who
reported to him on the program. He worked with them and his project executive assis-
tant, Christine Braun, to develop a communications plan for the program. He was still
unsure, however, about the best way to distribute information and manage all of the in-
evitable changes that would occur. He also wanted to develop consistent ways for project
managers to develop their plans and track performance without stifling their creativity
and autonomy. Christine suggested that they consider using some new communica-
tions technologies to keep important project information up to date and synchronized.
Although Peter knew a lot about telecommunications and laying fiber-optic lines, he was
not an expert in using information technology (IT) to improve the communication pro-
cess. In fact, that was part of the reason he had asked Christine to be his assistant. Could
they really develop a process for communicating that would be flexible and easy to use?
Time was of the essence, as more projects were being added to the fiber-optic undersea
telecommunications program every week.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

technical requirements, but few require courses in communications (speaking, writing, lis-
tening), psychology, sociology, and the humanities. People often assume that learning these
soft skills is easy, but they are important skills, so people must learn and develop them.
Many studies have shown that IT professionals need these soft skills just as much or even
more than other skills. You cannot totally separate technical skills and soft skills when working
on IT projects. For projects to succeed, every project team member needs both types of skills,
and needs to develop them continuously through formal education and on-the-job training.
Studies continue to show a high demand for IT professionals and the importance of
good communication and business skills. According to a 2014 article in the International
Journal of Business and Social Science:
Organizations are looking for workers with the correct mix of technical, soft, and
business skills.
The most important non-technical skills are problem solving, team work,
listening, the ability to adapt to new technologies and languages, time man-
agement, the ability to transfer knowledge to application, multitasking, verbal
communication, the ability to visualize and conceptualize, “be the customer”
mentality, interpersonal skills, understanding business culture, inter-team
communication, and give and receive constructive criticism.
“The need for these non-technical skills is so great that some IT companies
indicate that they will hire individuals with minimum technical skills so long
as they demonstrate solid soft and business skills.”1
This chapter highlights keys to good communications, describes the processes of proj-
ect communications management, provides suggestions for improving communications,
and describes how software can assist in project communications management.
The goal of project communications management is to ensure timely and appropri-
ate generation, collection, dissemination, storage, and disposition of project information.
There are three main processes in project communications management:
1. Planning communications management involves determining the informa-
tion and communications needs of the stakeholders. Who needs what infor-
mation? When will they need it? How will the information be given to them?
The outputs of this process include a communications management plan and
project documents updates.
2. Managing communications involves creating, distributing, storing, retriev-
ing, and disposing of project communications based on the communications
management plan. The main outputs of this process are project communica-
tions, project documents updates, project management plan updates, and or-
ganizational process assets updates. Recall from Chapter 4 that organizational
process assets include formal and informal plans, policies, procedures, guide-
lines, information systems, financial systems, management systems, lessons
learned, and historical information. These assets help people understand, fol-
low, and improve business processes in an organization.
3. Controlling communications involves monitoring and controlling project
communications to ensure that stakeholder communication needs are met.
Figure 10-1 summarizes these processes and outputs, showing when they occur in a
typical project.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

392
10.2 KEYS TO GOOD COMMUNICATIONS
Project managers say they spend as much as 90 percent of their time communicating.
Just as it is difficult to understand people and their motivations, it is also difficult to
communicate with people effectively. Several important concepts can help, such as
focusing on individual and group communication needs, using formal and informal
methods for communicating, providing important information in an effective and timely
manner, setting the stage for communicating bad news, and understanding communica-
tion channels.
10.2a Focusing on Group and Individual Communication Needs
Many top managers think they can just add more people to a project that is falling be-
hind schedule. Unfortunately, this approach often causes more setbacks because of the
increased complexity of communications. In his popular book The Mythical Man-Month,
Frederick Brooks illustrates this concept very clearly.2 People are not interchangeable
parts. You cannot assume that a task scheduled to take two months of one person’s time
can be done in one month by two people. A popular analogy is that you cannot take nine
women and produce a baby in one month!
It is important to understand individual and group preferences for communica-
tions. As you learned in Chapter 9, people have different personality traits that often
affect their communication preferences. For example, if you want to praise a project
team member for doing a good job, most introverts would be more comfortable receiv-
ing that praise in private, while most extroverts would like everyone to hear about
Planning
Process: Plan communications management
Outputs: Communications management plan, project documents updates
Executing
Process: Manage communications
Outputs: Project communications, project documents updates, project
management plan updates, and organizational process assets
updates
Monitoring and Controlling
Process: Control communications
Outputs: Work performance information, change requests, project
documents updates, and organizational process assets updates
Project Start Project Finish
FIGURE 10-1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

393
their good work. An intuitive person would want to understand how something fits
into the big picture, while a sensing person would prefer to have more focused, step-
by-step details. Strong thinkers would want to know the logic behind information,
while feeling people would want to know how the information affects them personally
as well as other people. A judging person would be very driven to meet deadlines with
few reminders, while a perceiving person would need more assistance in developing
and following plans.
However, every person is unique, so you cannot simply generalize based on a person-
ality profile or other traits. You need to seek first to understand, as author Stephen Covey
suggests in The 7 Habits of Highly Effective People, and put yourself in someone else’s
shoes before you can truly communicate.
It is important for project managers and their team members to be aware of their own
communication styles. As you learned in the previous chapter, many IT professionals have
different personality traits than the general population, such as being more introverted,
intuitive, and oriented to thinking (as opposed to feeling). These personality differences
can lead to miscommunication with people who are extroverted, sensation-oriented, and
feeling-oriented. For example, a user guide written by an IT professional might not provide
the detailed steps most users need. Many users also prefer face-to-face meetings or short
videos to learn how to use a new system instead of trying to follow a written guide. They
might prefer to have a two-way conversation in which they can get hands-on experience
and ask questions on the spot.
Also, the receiver of information rarely interprets it exactly as the sender in-
tended. Therefore, it is important to provide several methods of communication, such
as written words, visuals, videos, and meetings, and an environment that promotes
open dialogue. Instead of assuming that the receiver understands, you can build in
a feedback loop to make sure. For example, several teachers use clickers or similar
tools to quickly gauge how well their students understand a concept. Many are sur-
prised at the difference in what they think people understand and what they really do.
It is also difficult for many people to admit that they do not understand something.
Project managers and their teams must be patient and flexible when communicat-
ing information and focus on making sure their messages are understood. You cannot
overcommunicate!
W H A T W E N T W R O N G ?
Amusing examples of miscommunications are common, especially when they involve
the use of new technologies. For example, I was teaching an introductory course in in-
formation systems several years ago. Other instructors would often sit in on the course
to learn how to use the latest software applications. One day, students were learning
how to adjust settings and use short cuts on their computers. I would tell the students
to “right-click” and then select Properties, or “right-click” and then select Copy. At the
end of the class, an instructor quietly approached, waited until the other students were
gone, and then said, “I don’t know what I’m doing wrong.” She held up a piece of paper
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

394
on which she had written the word “click” about a dozen times. In other words, she
literally did write “click” when told to do so instead of right-clicking. I asked, “Are you
a Mac user?” Macintosh computers do not normally have a mouse with two buttons, so
users never have to right-click. I showed the instructor how to right-click with a mouse,
and in future classes made sure to point out operations that were different on PCs
than Macs.
Geographic location and cultural background also affect the complexity of project
communications. If project stakeholders are in different countries, it is often difficult or
impossible to schedule times for two-way communication during normal working hours.
Language barriers can also cause communication problems; the same word may have
very different meanings in different languages. Times, dates, and other units of mea-
sure are also interpreted differently. People from some cultures also communicate in
ways that might make others uncomfortable. For example, managers in some countries
still do not allow women or workers of lower ranks to give formal presentations. Some
cultures also reserve written documents for binding commitments. Taking the time to
research and understand these nuances of communications early in a project can help
tremendously.
10.2b Formal and Informal Methods for Communicating
It is not enough for project team members to submit reports to their project managers
and other stakeholders and then assume that everyone who needs to know the informa-
tion will read the reports. Occasionally, that approach might work, but many people prefer
informal communications. About half the general population are extroverts, so they enjoy
talking to other people. Often, many nontechnical professionals—from colleagues to
managers—prefer to have a two-way conversation about a project rather than reading
detailed reports, e-mails, or web pages to try to find pertinent information.
Many colleagues and managers want to know the people working on their projects and
develop a trusting relationship with them. They use informal discussions about the proj-
ect to develop these relationships. Therefore, project managers must be good at nurtur-
ing relationships through good communication. Many experts believe that the difference
between good project managers and excellent project managers is their ability to nurture
relationships and use empathic listening skills, as described in Chapter 9, Project Human
Resource Management.
Oral communication also helps build stronger relationships among project personnel
and project stakeholders. People like to interact with each other to get a true feeling for
how a project is going. Research conducted by Albert Mehrabian and discussed in his book
Silent Messages indicated that in face-to-face interactions information is communicated
through body language, tone of voice, and the spoken content.3 The lesson for project
communications today is that it is important to pay attention to more than someone’s ac-
tual words. A person’s tone of voice and body language say a lot about how they feel.
Effective creation and distribution of information depends on project managers and
project team members having good communication skills. Communicating includes
many different dimensions such as writing, speaking, and listening, and project personnel
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

395
need to use all of these dimensions in their daily routines. In addition, different people
respond positively to different levels or types of communication. For example, a project
sponsor may prefer to stay informed through informal discussions held once a week over
coffee. The project manager needs to be aware of this preference and take advantage of
it. The project sponsor will give better feedback about the project during these informal
talks than through some other form of communication. Informal conversations allow the
project sponsor to exercise a leadership role and provide insights and information that
are critical to the success of the project and the organization as a whole. Short face-to-
face meetings are often more effective than electronic communications, particularly for
sensitive information.
10.2c Distributing Important Information in an Effective
and Timely Manner
It is important to include detailed technical information that affects critical performance
features of products or services developed in a project. It is even more important to
document any changes in technical specifications that might affect product performance.
For example, if the fiber-optic undersea telecommunications program described in the
chapter’s opening case included a project to purchase and provide special diving gear,
and the supplier of the oxygen tanks enhanced the tanks so divers could stay under
water longer, other people would need to know about this important new capability.
The information should not be buried in an attachment with the supplier’s new product
brochure.
People have a tendency to avoid reporting bad news. If the oxygen tank vendor was
behind on production, the person in charge of the project to purchase the tanks might
wait until the last minute to report this critical information. This news could be deliv-
ered quickly via text through a website, e-mail, text message, or similar means. However,
people tend to become overwhelmed by too much information, and they might not under-
stand what it means to them on their particular project.
Oral communication via meetings and informal talks helps bring important
information—positive or negative—into the open. Because IT projects often require a lot
of coordination, it is a good idea to have short, frequent meetings. For example, some IT
project managers require all project personnel to attend a “stand-up” meeting every week
or even every morning, depending on project needs. Stand-up meetings have no chairs,
which forces people to focus on what they need to communicate. Recall that projects us-
ing an agile approach have daily meetings to make sure everyone is on the same page. If
people can’t meet face to face, they can have virtual meetings instead.
10.2d Setting the Stage for Communicating Bad News
It is important to put information in context, especially if it’s bad news. If there is a
problem, know how it will affect the whole project and the organization. Bad news might
seem like a major setback, but you can recommend steps to take to mitigate a problem.
Project sponsors and other senior managers want to know that you have evaluated the
impact of the situation, considered alternatives, and made a recommendation based on
your expertise. Project managers should know how a major problem might affect the
bottom line of the organization and be able to use their leadership skills to handle the
challenge.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter 10
396
An amusing example of how to mitigate bad news is provided in the following let-
ter from a college student to her parents. Variations of this letter can be found on many
websites.
Dear Mom and Dad, or should I say Grandma & Grandpa,
Yes, I am pregnant. No, I’m not married yet since Larry, my boyfriend, is out of a job.
Larry’s employers just don’t seem to appreciate the skills he has learned since he
quit high school. Larry looks much younger than you, Dad, even though he is three
years older. I’m quitting college and getting a job so we can get an apartment before
the baby is born. I found a beautiful apartment above a 24-hour auto repair garage
with good insulation so the exhaust fumes and noise won’t bother us.
I’m very happy. I thought you would be too.
Love, Ashley
P.S. There is no Larry. I’m not pregnant. I’m not getting married. I’m not quit-
ting school, but I am getting a “D” in Chemistry. I just wanted you to have some
perspective.
10.2e Determining the Number of Communication Channels
Another important aspect of communications is the number of people involved in a proj-
ect. As the number increases, the complexity of communication increases because there
are more channels or pathways through which people can communicate. You can use the
following simple formula to determine the number of communication channels as the
number of people involved in a project increases:
number of communication channels =
n 1n 2 1 2
2
where n is the number of people involved.
For example, two people have one communication channel: (2(2 − 1))/2 = 1. Three
people have three channels: (3(3 − 1))/2 = 3. Four people have six channels, five people
have 10, and so on. Figure 10-2 illustrates this concept. You can see that as the number
of people increases above three, the number of communication channels increases rap-
idly. Project managers should try to limit the size of teams or subteams to avoid mak-
ing communications too complex. For example, if three people are working together on
a particular project task, they have three communication channels. If you added two
more people to their team, you would have 10 communication channels, an increase
of seven. If you added three more people instead of two, you’d have 12 communica-
tion channels. You can see how quickly communication becomes more complex as you
increase team size.
Good communicators consider many factors before deciding how to distribute in-
formation, including the size of the group, the type of information, and the appropriate
communication medium. People often send e-mail messages that are quickly written and
therefore not as carefully planned as they should be. While this can be a problem even
with a small group of five recipients, the negative effects multiply many times when send-
ing such a message to a group of 500 people or more. When asked why you cannot always
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

397
send an e-mail to a very large team of people just as you could to a small one, one CIO
answered, “As a group increases in size, you have a whole slew of management challenges.
Communicating badly exponentially increases the possibility of making fatal mistakes.
A large-scale project has a lot of moving parts, which makes it that much easier to break
down. Communication is the oil that keeps everything working properly. It’s much easier
to address an atmosphere of distrust among a group of five team members than it is with a
team of 500 members.”4
However, in some situations you cannot have face-to-face meetings and must e-mail a
large group of people. Many IT professionals work on virtual projects in which they never
meet their project sponsors, other team members, or other project stakeholders. In a vir-
tual project environment, it is crucial for project managers to develop clear communica-
tion procedures. They must use e-mail, web conferencing, instant messaging, discussion
threads, project websites, and other technologies to communicate most information. They
might be able to use phone calls or other media occasionally, but in general, they must
rely on good written communications.
As you can see, project communication involves more than creating and sending sta-
tus reports or holding periodic meetings. Many good project managers know their personal
strengths and weaknesses in this area and surround themselves with people who comple-
ment their skills, just as Peter Gumpert did in the opening case by asking Christine to be
his assistant. It is good practice to share the responsibility for project communications
management with the entire project team.
3 people, 3 communication channels
2 people, 1 communication channel
4 people, 6 communication channels, etc.
number of communication channels = n(n – 1)2
FIGURE 10-2
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

398
10.3 PLANNING COMMUNICATIONS MANAGEMENT
Because communication is so important on projects, every project should include a
communications management plan—a document that guides project communications.
This plan should be part of the overall project management plan, as you learned in
Chapter 4, Project Integration Management. The communications management plan var-
ies with the needs of the project, but some type of written plan should always be prepared.
For small projects, such as the project management intranet site project described in
Chapter 3, the communications management plan can be part of the team contract. For
large projects, it should be a separate document. The communications management plan
should address the following items:
1. Stakeholder communications requirements
2. Information to be communicated, including format, content, and level of
detail
3. Who will receive the information and who will produce it
4. Suggested methods or technologies for conveying the information
5. Frequency of communication
6. Escalation procedures for resolving issues
7. Revision procedures for updating the communications management plan
8. A glossary of common terminology
It is important to know what kinds of information will be distributed to particular
stakeholders. By analyzing stakeholder communication needs, you can avoid wasting time
or money on creating or disseminating unnecessary information.
Table 10-1 provides part of a sample stakeholder communications analysis that shows
which stakeholders should get particular written communications. Note that the stake-
holder communications analysis includes columns that list the contact person for the
information, when the information is due, and the preferred format for the information.
Notice that the first stakeholder, customer management, wants a hard copy of the monthly
status reports plus a meeting to talk about them. You can create a similar table to show
which stakeholders should attend particular formal project meetings. It is always a good
idea to include comment sections with these types of tables to record special consider-
ations or details related to each stakeholder, document, meeting, or other component.
Have stakeholders review and approve the stakeholder communications analysis to ensure
that the information is correct and useful.
Many projects do not include enough initial information on communications. Project
managers, top management, and project team members often assume that using exist-
ing communication channels to relay project information is sufficient. The problem with
using existing channels is that each group (as well as other stakeholders) has different
communication needs. Creating some sort of communications management plan and
reviewing it with project stakeholders early in a project helps prevent or reduce later
communication problems. If an organization works on many projects, developing some
consistency in handling project communications helps the organization run smoothly.
Consistent communication helps organizations improve project communications,
especially for programs composed of multiple projects. For example, Peter Gumpert, the
program manager in the opening case, would benefit greatly from having a communica-
tions management plan that all of his project managers help develop and follow. Because
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

399
several of the projects have some of the same stakeholders, it is even more important to
develop a coordinated communications management plan. For example, if customers re-
ceive status reports from Peter’s company that have totally different formats and do not
coordinate information from related projects within the same company, they will question
the ability of Peter’s company to manage large programs.
Information about the content of essential project communications comes from the
work breakdown structure (WBS). In fact, many WBSs include a section for project com-
munications to ensure that reporting key information is a project deliverable. If reporting
essential information is an activity defined in the WBS, it becomes even more important
to know what project information to report, when to report it, how to report it, and who is
responsible for generating the report.
10.4 MANAGING COMMUNICATIONS
Managing communications is a large part of a project manager’s job. Getting project infor-
mation to the right people at the right time and in a useful format is just as important as
developing the information in the first place. The stakeholder communications analysis
serves as a good starting point for managing communications. Project managers and their
teams must decide who receives particular information, but they must also determine the
best way to create and distribute the information. Is it sufficient to send written reports
for project information? Is text appropriate, or would visuals or even videos communicate
the information better? Are meetings alone effective in distributing some project informa-
tion? Are meetings and written communications both required for project information?
What is the best way to provide information to virtual team members?
TABLE 10-1
Stakeholders
Document
Name
Document
Format Contact Person Due
Customer
management
Monthly status
report
Hard copy
and meeting
Tina Erndt,
Tom Silva
First of month
Customer business
staff
Monthly status
report
Hard copy Julie Grant,
Sergey Cristobal
First of month
Customer
technical staff
Monthly status
report
E-mail Li Chau,
Nancy Michaels
First of month
Internal
management
Monthly status
report
Hard copy and
meeting
Bob Thomson First of month
Internal business
and technical staff
Monthly status
report
Intranet Angie Liu First of month
Training
subcontractor
Training plan Hard copy Jonathan Kraus November 1
Software
subcontractor
Software
implementation
plan
E-mail Najwa Gates June 1
Comments: Put the titles and dates of documents in e-mail headings and have recipients acknowledge
receipt.
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

During project execution, project teams must address important considerations for
managing information, and they often end up updating business processes through im-
proved communications. For example, they might modify policies and procedures, modify
information systems, or incorporate new technologies to improve information distribu-
tion. For example, Peter Gumpert, the program manager in the opening case, might decide
that providing key project members with special apps on smartphones would enhance
communications. He would need to request additional funds to provide these devices and
apps, and training on how to use them.
After answering key questions related to project communications, project managers
and their teams must decide on the best way to create and distribute the information. Im-
portant considerations include the use of technology, the appropriate methods and media
to use, and performance reporting.
10.4a Using Technology to Enhance Information Creation
and Distribution
Technology can facilitate the process of creating and distributing information, when used
effectively. Most people and businesses rely on e-mail, instant messaging, websites, tele-
phones, cell phones, texting, and other technologies to communicate. Using a project
management information system, you can create and organize project documents, sched-
ules, meeting minutes, and customer requests, and make them available in an electronic
format. You can store this information locally or in the cloud. Storing templates and sam-
ples of project documents electronically can make accessing standard forms easier, thus
making information distribution easier. It is also important to have backup procedures
in place in case something goes wrong with normal communications technologies, as de-
scribed in the following “Global Issues” feature. Two important considerations in deciding
which technologies to use include the communication method and media, as described in
the next sections. You will learn more about using software to assist in project communi-
cations management later in this chapter.
G L O B A L I S S U E S
Natural disasters often disrupt communications around the world. For example, the scale
of the damage to Japan’s communications infrastructure after a 9.0 magnitude earth-
quake in March 2011 was unprecedented. Fortunately, thousands of employees from NTT
East worked around the clock to restore communications. As a result of their efforts, 4.75
million public phone calls were made on the day after the disaster. The following list
summarizes some facts and figures about the damage and the recovery efforts:
Approximately 90 trunk lines were severed as a result of damage to bridges and
railways.
990 exchange buildings were left without power.
1.5 million lines were damaged.
16 exchange buildings were destroyed.
2,700 km of aerial cables were damaged.
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

3,930 emergency-use public phone lines were set up.
NTT East donated 30,000 telephones to local authorities.
450 emergency Internet access points were created.5
It’s great that communications can be restored a day after a disaster, but often that’s
too late. The April 2015 Nepal earthquake killed over 8,800 people and injured more than
23,000. After cell phone and internet connections disappeared, several people turned to
older technology, like ham radios, to communicate information about missing victims
quickly.
To improve communications when the next disaster hits, researchers have been
working on a better solution. Danish designers Pernille Skjødt and Ida Stougaard created
a device called Reachi, which was a finalist in the 2015 Global Social Venture Competi-
tion. It uses a technology called mesh-networking that sends a signal from person to
person—the same technology used in the smartphone app called FireChat. The Reachi
is a single-function device that is sturdier than a phone, can survive immersion in water,
and runs on solar power. “The designers are currently finishing their final proof of con-
cept and coordinating with the Philippines Red Cross to plan a rollout across the country.
Eventually, they hope to bring it to other countries as well. It’s something that could be
useful anywhere; even the most-connected places on Earth can’t easily communicate
when standard infrastructure breaks.”6
10.4b Selecting the Appropriate Communication Methods and Media
There are three broad classifications for communication methods:
1. Interactive communication: As the name implies, two or more people in-
teract to exchange information via meetings, phone calls, or video confer-
encing. This method is usually the most effective way to ensure common
understanding.
2. Push communication: Information is sent or pushed to recipients without
their request via reports, e-mails, faxes, voice mails, and other means. This
method ensures that the information is distributed, but does not ensure that
it was received or understood.
3. Pull communication: Information is sent to recipients at their request via
websites, bulletin boards, e-learning, knowledge repositories like blogs and
wikis, and other means.
In addition to determining the appropriate method or methods for communicating
specific project information, it is important to consider which media to use. For example,
if you know that you must use interactive communication to review an important topic
with the project sponsor, you still need to determine which media to use. Table 10-2 pro-
vides guidelines from Practical Communications, Inc., a communications consulting firm,
about how well different types of media are suited to different communication needs.
These media include hard copy, phone calls, voice mail, e-mail, meetings, and websites.
For example, if you were trying to assess commitment of project stakeholders, a meeting
would be the most appropriate medium to use. (A face-to-face meeting would be prefera-
ble, but a web conference, in which participants could see and hear each other, would also
qualify as a meeting.) A phone call would be adequate, but the other media would not be

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

appropriate. Project managers must assess the needs of the organization, the project, and
individuals in determining which communication medium to use and when. They must
also be aware of new technologies that can enhance communications and collaboration,
as described in the following What Went Right? feature.
TABLE 10-2
Key: 1 = Excellent, 2 = Adequate, 3 = Inappropriate
How Well Medium Is Suited to:
Hard
Copy
Phone
Call
Voice
Mail E-mail Meeting Website
Assessing commitment 3 2 3 3 1 3
Building consensus 3 2 3 3 1 3
Mediating a conflict 3 2 3 3 1 3
Resolving a misunderstanding 3 1 3 3 2 3
Addressing negative behavior 3 2 3 2 1 3
Expressing support or appreciation 1 2 2 1 2 3
Encouraging creative thinking 2 3 3 1 3 3
Making an ironic statement 3 2 2 3 1 3
Conveying a reference document 1 3 3 3 3 2
Reinforcing one’s authority 1 2 3 3 1 1
Providing a permanent record 1 3 3 1 3 3
Maintaining confidentiality 2 1 2 3 1 3
Conveying simple information 3 1 1 1 2 3
Asking an informational question 3 1 1 1 3 3
Making a simple request 3 1 1 1 3 3
Giving complex instructions 3 3 2 2 1 2
Addressing many people 2 3 or 1* 2 2 3 1
*Depends on system functionality
Source: Tess Galati, Email Composition and Communication (EmC2), Practical Communications, Inc.,
www.praccom.com (2001)
W H A T W E N T W R O N G ?
A Frost & Sullivan study sponsored by Verizon Business and Microsoft Corp., called
“Meetings Around the World: The Impact of Collaboration on Business Performance,”
found that collaboration is a key driver of overall performance of companies around the
world. The impact of collaboration is twice as significant as a company’s aggressiveness
in pursuing new market opportunities and five times as significant as the external market
environment. The study defines collaboration as an interaction between culture and tech-
nology, such as audio and web conferencing, e-mail, and instant messaging. The research-
ers also created a method to measure how collaboration affects business performance.
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Of all the collaboration technologies that were studied, three were more commonly
present in high-performing companies than in low-performing ones: web conferencing,
audio conferencing, and meeting-scheduler technologies. “This study reveals a powerful
new metric business leaders can use to more successfully manage their companies and
achieve competitive advantage,” said Brian Cotton, a vice president at Frost & Sullivan.
“Measuring the quality and capability of collaboration in a given organization presents an
opportunity for management to prioritize technology investments, encourage adoption of
new tools and open up communications lines for improved collaboration.”7
The study also revealed regional differences in how people in various countries prefer
to communicate with one another. These differences highlight an opportunity for greater
cultural understanding to improve collaborative efforts around the world. For example:
American professionals are more likely to enjoy working alone, and they
prefer to send e-mail rather than call a person or leave a voice mail message.
They are also more comfortable with audio, video, and web conferencing
technologies than people from other regions. In addition, they tend to
multitask the most when on conference calls.
Europeans thrive on teamwork more than their counterparts elsewhere
and prefer to interact in real time with other people. They are more likely
to feel that it is irresponsible not to answer the phone, and they want
people to call them back rather than leave a voice mail message.
Professionals in the Asia-Pacific region, more than anywhere else, want to
be in touch constantly during the workday. As a result, they find the phone
to be an indispensable tool and prefer instant messaging to e-mail.
In a follow-up study sponsored by Verizon and Cisco, Frost & Sullivan examined the
role that collaboration solutions play in enabling high levels of organizational performance
and developed a model for measuring return on collaboration (ROC). Surveys from 3,662
managers across the globe were analyzed to estimate the return generated from deploy-
ing collaboration technology in critical business activities from six functional areas: in-
novations and new product development (Research & Development), employee retention
and churn/attrition (Human Resources), sales performance (Sales), customer acquisition
(Marketing), shareholder value (Investor Relations), and corporate reputation (Public Rela-
tions). The study results show the highest returns in the areas of sales performance and
innovations and new product development. “Our main finding was striking: As organiza-
tions deploy and use IP-enabled, advanced collaboration tools in their operations, they are
able to perform better on business critical activities, and realize a higher return on their
collaboration.8
10.4c Reporting Performance
Another important tool for managing project communications is performance
reporting. Performance reporting keeps stakeholders informed about how resources
are being used to achieve project objectives. It also motivates workers to have some
progress to report. Recall from Chapter 1 that progress reports are considered to be a
super tool—a tool that is extensively used and has been found to improve project perfor-
mance. Performance reports are normally provided as progress reports or status reports.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Many people use the two terms interchangeably, but some people distinguish between
them as follows:
Progress reports describe what the project team has accomplished during a
certain period. Many projects have each team member prepare a monthly report
or sometimes a weekly progress report. Team leaders often create consolidated
progress reports based on the information received from team members. A sam-
ple template for a monthly progress report is provided later in this chapter.
Status reports describe where the project stands at a specific point in time. Sta-
tus reports address where the project stands in terms of the triple constraint,
meeting scope, time, and cost goals. How much money has been spent to
date? How long did it take to do certain tasks? Is work being accomplished as
planned? Status reports can take various formats depending on the stakehold-
ers’ needs. As described in Chapter 2, when using agile project management,
progress is communicated via daily Scrum meetings and burndown charts.
Forecasts predict future project status and progress based on past information and
trends. How long will it take to finish the project based on how things are going? How
much more money will be needed to complete the project? Project managers can use
earned value management (see Chapter 7, Project Cost Management) to answer these
questions by estimating the budget at completion and projected completion date based on
how the project is progressing.
An important technique for performance reporting is the status review meeting. Sta-
tus review meetings, as described in Chapter 4, Project Integration Management, are a
good way to highlight information provided in important project documents, empower
people to be accountable for their work, and have face-to-face discussions about important
project issues. Many program and project managers hold periodic status review meetings
to exchange important project information and motivate people to make progress on their
parts of the project. Likewise, many top managers hold monthly or quarterly status review
meetings in which program and project managers must report overall status information.
Status review meetings sometimes become battlegrounds where conflicts between dif-
ferent parties come to a head. Project managers or higher-level top managers should set
ground rules for status review meetings to control the amount of conflict and should work
to resolve any potential problems. It is important to remember that project stakeholders
should work together to address performance problems.
10.5 CONTROLLING COMMUNICATIONS
The main goal of controlling communications is to ensure the optimal flow of informa-
tion throughout the entire project life cycle. The main inputs are the project management
plan, project communications, issue logs, work performance data, and organizational
process assets. (Issue logs are described in Chapter 13, Project Stakeholder Management.)
The project manager and project team should use their various reporting systems, expert
judgment, and meetings to assess how well communications are working. If communica-
tion problems exist, the project manager and team need to take action, which often re-
quires changes to the earlier processes of planning and managing project communications.
The main outputs of controlling communications are work performance information,
change requests, project documents updates, and organizational process assets updates.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

It is often beneficial to have a facilitator from outside the project team assess how well
communications are working. A facilitator can also help the team solve any communica-
tion problems. Many project teams need help in improving communications, and many
internal and external experts are available to help. The following section also provides sug-
gestions for improving project communications.
10.6 SUGGESTIONS FOR IMPROVING PROJECT
COMMUNICATIONS
Good communication is vital to the management and success of IT projects. So far in
this chapter, you have learned that project communications management can ensure
that essential information reaches the right people at the right time, that feedback and
reports are appropriate and useful, and that there are formalized processes for plan-
ning, managing, and controlling communications. This section highlights a few areas
that all project managers and project team members should consider in their quests to
improve project communications. This section provides guidelines for developing better
communication skills, running effective meetings, using e-mail, instant messaging, tex-
ting, kanban boards, and collaborative tools effectively, and using templates for project
communications.
10.6a Developing Better Communication Skills
Some people seem to be born with great communication skills. Others seem to have a
knack for picking up technical skills. It is rare to find someone with a natural ability for
both. Both types of skills, however, can be developed. Most IT professionals enter the field
because of their technical skills. Most find, however, that communication skills are the key
to advancing in their careers, especially if they want to become good project managers.
Most companies spend a lot of money on technical training for their employees, even
when employees might benefit more from communications training. Individuals are also
more likely to enroll voluntarily in classes to learn the latest technology than in classes
that develop soft skills.
Communication skills training usually includes role-playing activities in which par-
ticipants learn concepts such as building rapport, as described in Chapter 9, Project Hu-
man Resource Management. Training sessions also give participants a chance to develop
specific skills in small groups. Sessions that focus on presentation skills typically use video
to record the participants’ presentations. Most people are surprised to see some of their
mannerisms and enjoy the challenge of improving their skills. A minimal investment in
communication and presentation training can have a tremendous payback to individuals,
their projects, and their organizations.
As organizations become more global, they realize that they must also invest in ways
to improve communication with people from different countries and cultures. For exam-
ple, Apple released their new 2015 operating system, which included hundreds of diverse
emojis to appeal to users all over the world.
Many Americans are raised to speak their minds, while in some other cultures people
are offended by outspokenness. Decision makers from several countries, such as China,
focus on building personal relationships and trust rather than on facts and quick re-
sponses, like Americans. Not understanding how to communicate effectively with people
of other cultures and diverse backgrounds hurts projects and businesses. Many training
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

courses are available to educate people in cultural awareness, international business, and
international team building. Workers also need to learn how to participate in virtual meet-
ings and conference calls. Some people take these skills for granted, but many people need
assistance in becoming comfortable and productive in new work environments.
It takes leadership to help improve communication. If top management lets employ-
ees give poor presentations, write sloppy reports, offend people from different cultures, or
behave poorly at meetings, the employees will not want to improve their communication
skills. Top management must set high expectations and lead by example. Some organiza-
tions send all IT professionals to training that includes development of technical and com-
munication skills. Successful organizations allocate time in project schedules for preparing
drafts of important reports and presentations and incorporating feedback on the drafts. It
is good practice to include time for informal meetings with customers to help develop re-
lationships and provide staff to assist in relationship management. As with any other goal,
communication can be improved with proper planning, support, and leadership from top
management.
M E D I A S N A P S H O T
Many readers of this book grew up using social media sites like Facebook and Twitter. You
may be surprised to learn that 93 percent of recruiters check out social media profiles of
prospective hires. A 2014 article in Money magazine provides a list of “10 Social Media
Blunders That Cost a Millennial a Job—or Worse,” as follows:
1. Posting something embarrassing on the corporate Twitter feed.
2. Sexual oversharing.
3. Revealing company secrets.
4. Blowing your own cover.
5. Talking smack about a job before you’ve even accepted it.
6. Making fun of clients or donors.
7. Making fun of your boss/team.
8. Posting while you’re supposed to be working.
9. Complaining about your job.
10. Drinking in a photo—even if you’re over 21.9
10.6b Running Effective Meetings
A well-run meeting can be a vehicle for fostering team building and reinforcing expecta-
tions, roles, relationships, and commitment to the project. However, a poorly run meeting
can have a detrimental effect on a project. For example, a terrible kick-off meeting may
cause important stakeholders to decide not to support the project further.
Many people complain about the time they waste in unnecessary or poorly planned
and poorly executed meetings. The following guidelines can help improve time spent at
meetings:
Determine if a meeting can be avoided. Do not have a meeting if there is a bet-
ter way to achieve the objective at hand. For example, a project manager might
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

need approval from a top manager to hire another person for the project team.
It could take a week or longer to schedule even a 10-minute meeting on the top
manager’s calendar. Instead, an e-mail or phone call describing the situation and
justifying the request is a faster, more effective approach than having a meeting.
However, you often do need a face-to-face meeting in certain situations because
using e-mail or a phone call would be inappropriate. Consider which medium
would be most effective.
Define the purpose and intended outcome of the meeting. Be specific about
what should happen as a result of the meeting. Is the purpose to brainstorm
ideas, provide status information, or solve a problem? Make the purpose of a
meeting very clear to all meeting planners and participants. For example, if a
project manager calls a meeting of all project team members without know-
ing the true purpose of the meeting, everyone will focus on their own agendas
and very little will be accomplished. All meetings should have a purpose and
intended outcome.
Determine who should attend the meeting. Do certain stakeholders have to
be at a meeting to make it effective? Should only the project team leaders
attend a meeting, or should the entire project team be involved? Many meet-
ings are most effective with the minimum number of participants possible,
especially if decisions must be made. Other meetings require many attend-
ees. It is important to determine who should attend a meeting based on its
purpose and intended outcome.
Provide an agenda to participants before the meeting. Meetings are most
effective when the participants come prepared. Did they read reports before
the meeting? Did they collect necessary information? Some professionals re-
fuse to attend meetings if they do not have an agenda ahead of time. Insisting
on an agenda forces meeting organizers to plan the meeting and gives poten-
tial participants the chance to decide whether they need to attend.
Prepare handouts and visual aids, and make logistical arrangements
ahead of time. By creating handouts and visual aids, you must organize
thoughts and ideas. This usually helps the entire meeting run more effec-
tively. It is also important to make logistical arrangements by booking an
appropriate room, having necessary equipment available, and providing re-
freshments or entire meals, if appropriate. It takes time to plan for effective
meetings. Project managers and their team members must take time to pre-
pare for meetings, especially important ones with key stakeholders.
Run the meeting professionally. Introduce people, restate the purpose of
the meeting, and state any ground rules that attendees should follow. Have
someone facilitate the meeting to make sure that important items are dis-
cussed, watch the time, encourage participation, summarize key issues, and
clarify decisions and action items. Designate someone to take minutes and
then send them to all participants soon after the meeting. Minutes should
be short and focus on the crucial decisions and action items from the
meeting.
Set the ground rules for the meeting. State up front how the meeting will be
run. For example, can people speak at will, or will the facilitator lead discus-
sions? Can attendees use their laptops or other electronic devices during the
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter 10
408
meeting? Don’t assume that all meetings are run in the same way. Do what
works best in each specific case.
Build relationships. Depending on the culture of the organization and proj-
ect, it may help to build relationships by making meetings fun experiences.
For example, it may be appropriate to use humor, refreshments, or prizes for
good ideas to keep meeting participants actively involved. If used effectively,
meetings are a good way to build relationships.
10.6c Using E-Mail, Instant Messaging, Texting, Kanban Boards,
and Collaborative Tools Effectively
Because most people use e-mail and other electronic communication tools now, communi-
cations should improve, right? Not necessarily. In fact, few people have received any train-
ing or guidelines on when or how to use e-mail, instant messaging, texting, kanban boards,
or other collaborative tools, such as Microsoft SharePoint portals, Google Docs, or wikis.
A SharePoint portal allows users to create custom websites to access documents and ap-
plications stored on shared devices. Google Docs allows users to create, share, and edit
To DoTo Do
Task 4
Task 7
Task 8
o
4
7
8
Task 2
Task 5
Task 6
2
5
6
Task 1
Task 3
In Progress Done
FIGURE 10-3 Sample kanban board
Source: Kathy Schwalbe, An Introduction to Project Management, Fifth Edition (2015)
B E S T P R A C T I C E
One of the main features of kanban is visualizing workflow, which is often done by using
kanban boards. Figure 10-3 provides a very simple example of a kanban board. Notice
that the main categories where tasks are placed include To Do, In Progress, and Done.
Team members work together to complete all of the tasks, clearly showing which ones
need to be done (in the To Do section), which ones are being worked on (in the In Prog-
ress section), and which ones are completed (in the Done section). People using kanban
boards can tailor the concept to meet their needs. For example, they could create a phys-
ical board or use a wall in their office environment, write the names of tasks on sticky
notes, and physically move the sticky notes along the board or wall. Or, a team could use
an online tool to enter and track their workflow. They could add people’s names to each
task, color code tasks, include a calendar, or use whatever approach helps the team im-
prove their performance.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

documents, spreadsheets, and presentations online. A wiki is a website that enables any-
one who accesses it to contribute to or modify its content. Kanban boards visually show
tasks that need to be done, are in progress, or are completed. They have become a popular
tool to improve communications, as described in the Best Practice feature.
Even if people do know when to use e-mail or other tools for project communications,
they also need to know how to use the tools. New features are added to software programs
with every release, but often users are unaware of these features and do not receive train-
ing on how to use them. Do you know how to organize and file your e-mail messages, or
do you have hundreds of them in your inbox? Do you know how to use your address book
or how to create distribution lists? Have you ever used sorting features to find e-mail mes-
sages or documents by date, author, or key words? Do you use filtering software to prevent
spam? Do you know how to share your desktop with instant messaging to teach some-
one how to use software on your computer? Do you know how to track and incorporate
changes in Google Docs to create reports and spreadsheets as a collaborative effort? Does
everyone on your project team know how to use important features of your SharePoint
portal or wiki? Are you using a software tool for creating kanban boards that is tailored to
meet your needs? Project teams and organizations that emphasize using a shared reposi-
tory for good communications are often more productive. Many project management soft-
ware tools include the ability to share project documents and other communications, but
processes must be established first and followed.
Something as simple as a standard college course illustrates these issues. Many college
courses now use online course management software like Moodle or Blackboard. Instruc-
tors have learned to post the course syllabus, handouts, lecture notes, and other docu-
ments for the entire class to share. Students are often required to take quizzes, participate
in discussions, and post their own files on a central site. Posting all information in one
location enhances communications. If the instructor states in the syllabus that students
must check their e-mail frequently for course information, they will do so, even though
they might prefer to use text messaging. If they fail to check their e-mail, participate in
discussions, or generally use the online course tools, the consequences will affect their
grades.
Even if you know how to use all the features of these communication systems, you
will likely still need to learn how to put ideas into words clearly and effectively. For exam-
ple, the subject line for any e-mail message you write should clearly state the intention of
the e-mail. Folder and file names for collaborative projects should be clear and follow file
naming conventions, if provided. A business professional who does not write well might
prefer to talk to people than to send an e-mail or instant message. Poor writing often leads
to misunderstandings and confusion.
Project managers should do whatever they can to help their project stakeholders use
e-mail, instant messaging, texting, and other tools effectively and not waste time with poor
or unclear communications. Information sent via e-mail, instant messaging, texting, or
a collaborative tool should be appropriate for that medium. If you can communicate the
information better with a phone call or meeting, for example, then do so. If you introduce
a new technique, such as kanban boards, be sure to tailor it to meet your needs. Do not
use new tools because they are the latest fad. Use them because they improve commu-
nications and productivity. Learn how to use important features of your e-mail, texting,
instant messaging, and collaborative software, and make sure that everyone on your team
also learns.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

The following guidelines can help you use e-mail as a more effective communication
tool:
Be sure to send e-mail to the right people. Do not automatically “reply to all” on
an e-mail, for example, if it is not necessary.
Use meaningful subject lines in e-mails so readers can quickly see what infor-
mation the message contains. If the entire message can fit in the subject line,
put it there. For example, if a meeting is cancelled, just enter that message
in the subject line. Also, do not continue replying to an e-mail thread when
the subject has changed without changing the subject line. The subject line
should always relate to the latest topic.
Limit the content of the e-mail to one main subject. Send a second or third
e-mail if it relates to a different subject.
The body of the e-mail should be as clear and concise as possible. Use as few
words as possible while maintaining a clear and friendly tone. If three ques-
tions need to be answered, number them as questions 1, 2, and 3 and put
each on a separate line.
Always reread your e-mail before you send it. Also, be sure to check your
spelling using the spell-check function.
Limit the number and size of e-mail attachments. If you can include a link to
an online version of a document instead of attaching a file, do so.
Delete e-mail that you do not need to save or that does not require a re-
sponse. Do not even open e-mail that you know is not important, such as
spam. Use the e-mail blocking feature of the software, if available, to block
unwanted junk mail.
Make sure that your virus protection software is up to date. Never open e-
mail attachments if you do not trust the source.
Respond to e-mail quickly, if possible. It will take you longer to open and read
the e-mail again later. In addition, if you send an e-mail that does not require
a response, make that clear as well.
If you need to keep e-mail, file each message appropriately. Create folders
with meaningful names to file the e-mail messages you want to keep. File
them as soon as possible.
Most people are comfortable with using e-mail, but some may not be familiar with
other technologies. Develop a strategy for getting users up to date, and discuss when it’s
best to use other technologies versus e-mail. The following additional guidelines can help
you use other communication tools more effectively:
Collaborative tools continue to advance. Make sure that your team is using a
good tool. Many, like Google Docs and several wikis, are available for free.
Be sure to authorize the right people to share your collaborative documents.
Also ensure that other security is in place. Confidential project documents
should probably not be stored on Google Docs. Use more secure tools when
needed.
Make sure that the right person can authorize changes to shared documents
and that you back up files.
Develop a logical structure for organizing and filing shared documents. Use
good file-naming conventions for folder and document names.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

10.6d Using Templates for Project Communications
Many intelligent people have a hard time writing a performance report or preparing a
10-minute technical presentation for a customer review. Some people in these situations
are too embarrassed to ask for help. To make it easier to prepare project communica-
tions, project managers need to provide examples and templates for common project
communications such as project descriptions, project charters, monthly performance
reports, and issue logs. Good documentation from past projects can be an ample source
of examples. Samples and templates of both written and oral reports are particularly
helpful for people who have never had to write project documents or give project presen-
tations. Finding, developing, and sharing relevant templates and sample documents are
important tasks for many project managers. Several examples of project documentation
are provided throughout this text, including a business case, project charter, scope state-
ment, stakeholder analysis, WBS, Gantt chart, and cost estimate. The companion web-
site for this text includes the actual files used to create the templates for these sample
documents. A few of these templates and guidelines for preparing them are provided in
this section.
Figure 10-4 shows a sample template for a brief project description. This form could
be used to show a snapshot of an entire project on one page. For example, top managers
FIGURE 10-4
Start Project
Main Task 1
Project X Description
Scope: Briefly describe the scope of the project. What business functions are involved,
and what are the main products the project will produce?
Summarize the most critical assumptions for the project.Assumptions:
Cost: Provide the total estimated cost of the project. If desired, list the total cost
each year.
Schedule: Provide summary information from the project’s Gantt chart, as shown.
Focus on summary tasks and milestones.
Deliverable 1
Main Task 2
Deliverable 2
Main Task 3
Deliverable 3
End Project
Task Name August
Objective: Describe the objective of the project in one or two sentences. Focus on
the business benefits of doing the project.
September October November December January February March April
6/1
7/26
10/18
12/27
12/27
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

TABLE 10-3
I. Accomplishments for January (or appropriate month):
Describe most important accomplishments. Relate them to project’s Gantt chart.
Describe other important accomplishments, one bullet for each. If any issues were resolved
from the previous month, list them as accomplishments.
II. Plans for February (or following month):
Describe most important items to accomplish in the next month. Again, relate them to proj-
ect’s Gantt chart.
Describe other important items to accomplish, one bullet for each.
III. Issues: Briefly list important issues that surfaced or are still important. Managers hate surprises
and want to help the project succeed, so be sure to list issues.
IV. Project Changes (Dates and Description): List any approved or requested changes to the project.
Include the date of the change and a brief description.
© Cengage Learning 2016
might require that all project managers provide a brief project description as part of a
quarterly management review meeting. Peter Gumpert, the program manager in the open-
ing case, might request this type of document from all of his project managers to get an
overall picture of what each project involves. A project description should include the
project objective, scope, assumptions, cost information, and schedule information. This
template suggests including information from the project’s Gantt chart to highlight key de-
liverables and other milestones.
Table 10-3 shows a template for a monthly progress report. Sections of the progress
report include accomplishments from the current period, plans for the next period, issues,
and project changes. Recall that progress reports focus on accomplishments during a spe-
cific time period, while status reports focus on where the project stands at a certain point
in time. Because progress and status reports are effective ways to communicate project
information, it is important for project teams to tailor the reports to meet their specific
needs. Some organizations, such as JWD Consulting from Chapter 3, combine both prog-
ress and status information on the same template.
Table 10-4 provides a list of all of the documentation that should be organized and
filed at the end of a major project. From this list, you can see that a large project can gen-
erate a lot of documentation. In fact, some project professionals have observed that docu-
mentation for designing an airplane seems to weigh more than the airplane itself. (Smaller
projects usually generate much less documentation!)
The project manager and project team members should prepare a lessons-learned
report—a reflective statement that documents important information they have learned
from working on the project. The project manager often combines information from
all of the lessons-learned reports into a project summary report. See Chapter 3 for an
example of this type of lessons-learned report. Some items discussed in lessons-learned
reports include reflections on whether project goals were met, whether the project was
successful or not, the causes of variances on the project, the reasoning behind corrective
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

actions chosen, the use of different project management tools and techniques, and
personal words of wisdom based on team members’ experiences. On some projects, all
project members are required to write a brief lessons-learned report; on other projects,
just the team leads or project manager writes the report. These reports provide valuable
reflections by people who know what worked or did not work on the project. Everyone
learns in different ways and has different insights into a project, so it is helpful to have
more than one person provide inputs on the lessons-learned reports. These reports can
be an excellent resource and can help future projects run more smoothly. To reinforce
the benefits of lessons-learned reports, some companies require new project managers to
read past lessons-learned reports and discuss how they will incorporate some of the ideas
into their own projects. It is also important to organize and prepare project archives.
Project archives are a complete set of organized project records that provide an accurate
history of the project. These archives can provide valuable information for future
projects as well.
In the past few years, more and more project teams have started putting all or part
of their project information on project websites, including various templates and lessons-
learned reports. Project websites provide a centralized way of delivering project docu-
ments and other communications. Project teams can develop project websites using wikis,
web authoring tools, or by using free or paid sites available from Google, Basecamp, and
many other companies. The project team should be sure to address important issues in
creating and using a project website, such as security, access, and the type of content that
should be included.
Project teams can use one of the many software products available to assist in proj-
ect communications through the web. These products vary considerably in price and
TABLE 10-4
I. Project description
II. Project proposal and backup data (request for proposal, statement of work, proposal
correspondence, and so on)
III. Original and revised contract information and client acceptance documents
IV. Original and revised project plans and schedules (WBS, Gantt charts and network diagrams, cost
estimates, communications management plan, etc.)
V. Design documents
VI. Final project report
VII. Deliverables, as appropriate
VIII. Audit reports
IX. Lessons-learned reports
X. Copies of all status reports, meeting minutes, change notices, and other written and electronic
communications
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

functionality, as you learned in Chapter 1. For example, Figure 10-5 shows examples of
using Basecamp on various devices. Many project teams want to access project informa-
tion on mobile devices, so many tools now include this capability.
When the project team develops its project communications management plan,
it should determine what templates to use for key documentation. To make it more
convenient to use templates, the organization should make project templates readily
available online. The project team should also understand what types of documents
are expected by top management and customers for each project. For example,
if a project sponsor or customer wants a one-page monthly progress report for a
specific project, but the project team delivers a 20-page report, there are communica-
tion problems. In addition, if particular customers or top managers want specific items
to be included in all final project reports, they should make sure that the project team
is aware of those expectations and modifies templates for those reports to account for
the requirements.
10.7 USING SOFTWARE TO ASSIST IN PROJECT
COMMUNICATIONS
Many organizations are discovering how valuable project management software can be in
communicating project information across the organization. Project management software
can provide different views of information to help meet various communication needs.
For example, senior managers might only need to see summary screens with colors indi-
cating the overall health of all projects. Middle managers often want to see the status of
milestones for all of the projects in their area. Project team members often need to see all
project documentation. Often, one of the biggest communication problems on projects is
providing the most recent project plans, Gantt charts, specifications, meeting information,
FIGURE 10-5
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

and change requests to stakeholders in a timely fashion. Most project management soft-
ware allows users to insert hyperlinks to other project-related files. In Project 2013, you
can insert a hyperlink from a task or milestone listed in a Gantt chart to another file that
contains relevant information. For example, there might be a milestone that the project
charter was signed. You can insert a hyperlink from the Gantt chart to the Word file that
contains the project charter. You could also link appropriate tasks or milestones to Excel
files that contain a staffing management plan or cost estimate or to Microsoft PowerPoint
files with important presentations or other information. The Project 2013 file and all as-
sociated hyperlinked files could then be placed on a local area network server or web
server, allowing all project stakeholders easy access to important project information. (See
Appendix A for more information on using Microsoft Project 2013 to assist in project com-
munications management.)
Even though organizations routinely use many types of hardware and software to
enhance communications, they need to take advantage of new technologies and adjust
existing systems to serve the special communications needs of customers and project
teams. In addition to diverse customer and project needs, they have to address the chang-
ing expectations of consumers and the workforce. For example, several television shows
have harnessed communications technology to engage their audiences by letting them
vote online or via cell phone for their favorite singers, e-mail or tweet celebrities, or access
information on their websites or Facebook pages. Many people, especially younger people,
use instant messaging or text messages every day to communicate with friends. Some
business and technical professionals also find instant messaging and text messaging to be
useful tools for quickly communicating with colleagues, customers, suppliers, and others.
Blogs are journals on the web that allow users to write entries, respond to another poster’s
comments, create links, upload pictures, and post comments to journal entries. Blogs have
also become popular as a communication technology. If television shows and nontechnical
people can use advanced communications technologies, why can’t project stakeholders?
Employers have made changes to meet changing expectations and needs in commu-
nications. On several IT projects, project managers have found that their team members
can be more productive when they are allowed to work from home. Other project manag-
ers have no choice in the matter when some or all of their project team members work
remotely. As you learned in Chapter 9, Project Human Resource Management, studies
show that providing a quiet work environment and a dedicated workspace increases pro-
grammer productivity. Most people who work from home have well-equipped, comfort-
able offices with fewer distractions and more space than corporate offices. Workers also
appreciate the added bonus of avoiding traffic and having more flexible work schedules.
However, it is important to make sure that work is well defined and that communications
are in place to allow remote workers to work effectively.
Several products are available to assist individual consumers and organizations with
communications. Many products were developed or enhanced in recent years to address
the issue of providing fast, convenient, consistent, and up-to-date project information.
Webcasts are now a common tool for presenting video, graphics, sound, voice, and partici-
pant feedback live over the web. Podcasts and YouTube videos have also become popular
tools for providing various types of audio and video information, from exercise instructions
to class lectures. Most working adults and students have cell phones that they use to take
and send pictures or send and receive text messages or e-mail. Many high school or college
students text or tweet their friends to plan social activities or discuss academic topics.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

These same technologies can enhance project communications. For even more pow-
erful and integrated communications, enterprise project management software provides
many workgroup functions that allow a team of people at different locations to work to-
gether on projects and share project information. Workgroup functions allow the exchange
of messages through e-mail, an intranet, wireless devices, or the web. For example, you
can use Project 2013 to alert members about new or changed task assignments, and mem-
bers can return status information and notify other workgroup members about changes in
the schedule or other project parameters.
Microsoft Office Enterprise Project Management (EPM) Solution and similar products
also provide the following tools to enhance communications:
Portfolio management: By providing a centralized and consolidated view of
programs and projects, the user can evaluate and prioritize activities across the
organization. This feature makes it possible to maximize productivity, minimize
costs, and keep activities aligned with strategic objectives.
Resource management: Maximizing human resources is often the key to
minimizing project costs. This feature enables the user to maximize re-
source use across the organization to help plan and manage the workforce
effectively.
Project collaboration: Sharing project information is often a haphazard en-
deavor. Project collaboration enables an organization to share knowledge im-
mediately and consistently to improve communications and decision making,
C A S E W R A P – U P
Christine Braun worked closely with Peter Gumpert and his project managers to de-
velop a communications management plan for all of the fiber-optic undersea telecom-
munications projects. Peter was very skilled at running effective meetings, so everyone
focused on meeting specific objectives. Peter emphasized the importance of keeping
himself, the project managers, and other major stakeholders informed about the sta-
tus of all projects. He emphasized that the project managers were in charge of their
projects, and that he did not intend to tell them how to do their jobs. He just wanted
to have accurate and consistent information to help coordinate all of the projects and
make everyone’s jobs easier. When some of the project managers balked at the addi-
tional work of providing more project information in different formats, Peter openly dis-
cussed the issues with them in more detail. He then authorized each project manager to
use additional staff to help develop and follow standards for all project communications.
Christine used her strong technical and communications skills to create a website
that included samples of important project documents, presentations, and templates for
other people to download and use on their own projects. After determining the need for
more remote communications and collaboration between projects, Christine and other
staff members researched the latest hardware and software products. Peter authorized
funds for a new project led by Christine to evaluate and then purchase smartphones,
apps, and enterprise project management (EPM) software with wiki capability that could
be accessed via the web. All managers and technical staff, including Peter, received their
own devices, and any project stakeholder could request one and get one-on-one training
for how to use it with the new apps and EPM software.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

eliminate redundancies, and take advantage of best practices for project
management.
Communication is among the more important factors for success in project manage-
ment. While technology can aid in the communications process and be the easiest aspect
of the process to address, it is not the most important. Far more important is improving
an organization’s ability to communicate. Improving this ability often requires a cultural
change in an organization that takes a lot of time, hard work, and patience. IT personnel,
in particular, often need special coaching to improve their communications skills. The
project manager’s chief role in the communications process is that of facilitator. Project
managers must educate all stakeholders—management, team members, and customers—
on the importance of good project communications and ensure that the project has a good
communications management plan.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter Summary





Quick Quiz
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Quick Quiz Answers
Discussion Questions

® –



Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Exercises





Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

422
Running Case
Part 7: Project Communications Management


Key Terms
blogs
communications management plan
forecasts
Google Docs
lessons-learned report
progress reports
project archives
SharePoint portal
status reports
wiki
End Notes
International Journal
of Business and Social Science
The Mythical Man-Month
Silent messages: Implicit communication of emotions and attitudes
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

423
CIO Magazine
Co.Exist, Fast Company
Microsoft
Press Pass

Money,
http://time.com/money/3019899/10-facebook-twitter-mistakes-lost-job-millennials-viral/
(September 5, 2014).
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R11
PROJECT RISK MANAGEMENT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

426
11.1 THE IMPORTANCE OF PROJECT RISK MANAGEMENT
Project risk management is the art and science of identifying, analyzing, and responding
to risk throughout the life of a project and in the best interests of meeting project objec-
tives. A frequently overlooked aspect of project management, risk management can often
result in significant improvements in the ultimate success of projects. Risk management
can have a positive impact on selecting projects, determining their scope, and developing
realistic schedules and cost estimates. It helps project stakeholders understand the nature
of the project, involves team members in defining strengths and weaknesses, and helps to
integrate the other project management knowledge areas.
Good project risk management often goes unnoticed, unlike crisis management,
which indicates an obvious danger to the success of a project. The crisis, in turn, receives
the intense interest of the entire project team. Resolving a crisis has much greater visibil-
ity, often accompanied by rewards from management, than successful risk management.
In contrast, when risk management is effective, it results in fewer problems, and for the
few problems that exist, it results in more expeditious resolutions. It may be difficult for
outside observers to tell whether risk management or luck was responsible for the smooth
development of a new system, but project teams always know that their projects worked
out better because of good risk management. Managing project risks takes dedicated,
talented professionals. In response to this need, PMI introduced the PMI Risk Manage-
ment Professional (PMI-RMP)SM credential in 2008. (Consult PMI’s website for further
information.)
All industries, especially the software development industry, tend to underesti-
mate the importance of project risk management. William Ibbs and Young H. Kwak
O P E N I N G C A S E
Cliff Branch was the president of a small IT consulting firm that specialized in developing
Internet and mobile applications and providing full-service support. The staff consisted
of programmers, business analysts, database specialists, web designers, project manag-
ers, and others. The firm had 50 full-time people and planned to hire at least 10 more
in the next year. The firm also planned to increase the number of part-time consultants
it used. The company had done very well during the past few years, but it was recently
having difficulty winning contracts. Spending time and resources to respond to various
requests for proposals from prospective clients was becoming expensive. Many clients
were starting to require presentations and even some prototype development before
awarding a contract.
Cliff knew he had an aggressive approach to risk and liked to bid on the projects
with the highest payoff. He did not use a systematic approach to evaluate the risks in-
volved in various projects before bidding on them. He focused on the profit potentials
and on how challenging the projects were. His strategy was now causing problems for
the company because it was investing heavily in the preparation of proposals, yet win-
ning few contracts. Several employees who were not currently working on projects were
still on the payroll, and some of their part-time consultants were actively pursuing other
opportunities because they were being underutilized. What could Cliff and his company
do to better understand project risks? Should Cliff adjust his strategy for deciding what
projects to pursue? How?
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

帮助利益相关者理解项目特性,包括项目组成员定义优势劣势以及使得
其他的项目管理的知识领域变得更加完整

风险管理与危机管理的区别
:危机管理可视化程度高,
团队感兴趣程度高,并且通常伴随着来自管理的奖励

lenovo
专注的

427
studied project management maturity in 38 organizations in different industries. The
organizations were divided into four industry groups: engineering and construction,
telecommunications, information systems/software development, and high-tech man-
ufacturing. Survey participants answered 148 multiple-choice questions to assess how
mature their organization was in the project management knowledge areas of scope,
time, cost, quality, human resources, communications, risk, and procurement. The
rating scale ranged from 1 to 5, with 5 being the highest maturity rating. Table 11-1
shows the results of the survey. Notice that risk management was the only knowledge
area for which all ratings were less than 3. This study showed that all organizations
should put more effort into project risk management, especially companies in the in-
formation systems and software development industry, which had the lowest rating
of 2.75.1
TABLE 11-1
KEY: 1 = Lowest Maturity Rating, 5 = Highest Maturity Rating
Knowledge Area
Engineering/
Construction Telecommunications
Information
Systems
High-Tech
Manufacturing
Scope 3.52 3.45 3.25 3.37
Time 3.55 3.41 3.03 3.50
Cost 3.74 3.22 3.20 3.97
Quality 2.91 3.22 2.88 3.26
Human resources 3.18 3.20 2.93 3.18
Communications 3.53 3.53 3.21 3.48
Risk 2.93 2.87 2.75 2.76
Procurement 3.33 3.01 2.91 3.33
Source: Ibbs and Kwak
A similar survey was completed with software development companies in Mauritius,
South Africa. The average maturity rating was only 2.29 for all knowledge areas on a scale
of 1 to 5, with 5 being the highest maturity rating. The lowest average maturity rating,
1.84, was also in the area of project risk management, like the study by Ibbs and Kwak.
Cost management had the highest maturity rating of 2.5, and the survey authors noted
that organizations in the study were often concerned with cost overruns and had metrics
in place to help control costs. The authors also found that maturity rating was closely
linked to the success rate of projects, and that the poor rating for risk management was a
likely cause of project problems and failures.2
KLCI Research Group surveyed 260 software organizations worldwide to study soft-
ware risk management practices. The following points summarize some of their findings:
Ninety-seven percent of the participants said they had procedures in place to
identify and assess risk.
Eighty percent identified anticipating and avoiding problems as the primary
benefit of risk management.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

428
Seventy percent of the organizations had defined software development
processes.
Sixty-four percent had a Project Management Office.
Figure 11-1 shows the main benefits from software risk management practices cited
by survey respondents. In addition to anticipating and avoiding problems, risk manage-
ment practices helped software project managers prevent surprises, improve negotiations,
meet customer commitments, and reduce schedule slips and cost overruns.3
Although many organizations know that they do not do a good job of managing proj-
ect risk, little progress seems to have been made over the past decade in improving risk
management on a project level or an enterprise level. Several books and articles have been
written on the topic. For example shortly after the fall 2008 stock market crash, Dr. David
Hillson, PMP, wrote about the importance of project risk management. Hillson said:
There is no doubt that all sectors of industry and society are facing real challenges in
coping with the current fallout from the credit crunch. But risk management should not
be regarded as a nonessential cost to be cut in these difficult times. Instead, organisa-
tions should use the insights offered by the risk process to ensure that they can handle
the inevitable uncertainties and emerge in the best possible position in [the] future.
With high levels of volatility surrounding us on all sides, risk management is more
An
tic
ipa
te
/av
oid
pr
ob
lem
s
0%
20%
40%
60%
80%
100%
Pr
ev
en
t s
ur
pr
ise
s
Im
pr
ov
e a
bil
ity
to
ne
go
tia
te
M
ee
t c
us
to
me
r c
om
mi
tm
en
ts
Re
du
ce
sc
he
du
le
sli
ps
Re
du
ce
co
st
ov
er
ru
ns
No
ne
80%
60%
47% 47%
43%
6%%
o
f
Su
rv
ey
R
es
po
nd
en
ts
35%
FIGURE 11-1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo
波动性

429
needed now than ever, and cutting it would be a false economy. Rather than treating risk
management as part of the problem, we should see it as a major part of the solution.4
Hillson continues to write articles and books, give presentations, and provide videos
on his website at www.risk-doctor.com.
G L O B A L I S S U E S
Many people around the world suffered losses as various financial markets dropped in
the fall of 2008, even after the $700 billion economic stabilization act was passed by
the U.S. Congress. According to a survey of 316 global financial services executives con-
ducted in July 2008, over 70 percent of respondents believed that the losses during the
financial crisis were largely due to failures to address risk management issues. The ex-
ecutives identified several challenges in implementing risk management, including data
and company culture issues. For example, access to relevant, timely, and consistent data
continues to be a major obstacle in many organizations. Many respondents also said that
fostering a culture of risk management was a major challenge.
Executives and lawmakers finally started paying attention to risk management. Fifty-
nine percent of survey respondents said the financial crisis prompted them to scrutinize
their risk management practices in greater detail, and many institutions are revisiting
their risk management practices. The Financial Stability Forum (FSF) and the Institute
for International Finance (IIF) called for closer scrutiny of the risk management process.5
Risk continues to be an important issue in the financial industry, and organizations
are taking a more proactive approach by investing in IT such as cloud computing, big
data, and analytics to help them identify and mitigate risk. “Worldwide, the capital mar-
kets, banking and insurance sectors will spend roughly $78.6 billion on risk information
technologies and services (RITS) in 2015, according to a new study. What’s more, that
figure is expected to grow to $96.3 billion by 2018.”6
Before you can improve project risk management, you must understand what risk
is. A basic dictionary definition states that risk is “the possibility of loss or injury.” This
definition highlights the negativity often associated with risk and points out that uncer-
tainty is involved. Project risk management involves understanding potential problems
that might occur on the project and how they might impede project success. The PMBOK®
Guide, Fifth Edition refers to this type of risk as a negative risk or threat. However, there
are also positive risks or opportunities, which can result in good outcomes for a project.
A general definition of a project risk, therefore, is an uncertainty that can have a negative
or positive effect on meeting project objectives.
Managing negative risks involves a number of possible actions that project managers
can take to avoid, lessen, change, or accept the potential effects of risks on their projects.
Positive risk management is like investing in opportunities. It is important to note that
risk management is an investment—costs are associated with it. The investment that an
organization is willing to make in risk management activities depends on the nature of the
project, the experience of the project team, and the constraints imposed on both. In any
case, the cost for risk management should not exceed the potential benefits.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

对风险的一般定义为对实现项目目标可以带来负面及正面影响的不确定性

430
If there is so much risk in IT projects, why do organizations pursue them? Many com-
panies are in business today because they took risks that created great opportunities. Or-
ganizations survive over the long term when they pursue opportunities. IT is often a key
part of a business’s strategy; without it, many businesses might not survive. Given that all
projects involve uncertainties that can have negative or positive outcomes, the question
is how to decide which projects to pursue and how to identify and manage project risk
throughout a project’s life cycle.
B E S T P R A C T I C E
Some organizations make the mistake of addressing only tactical and negative risks when
performing project risk management. David Hillson (www.risk-doctor.com) suggests
overcoming this problem by widening the scope of risk management to encompass both
strategic risks and upside opportunities, which he refers to as integrated risk manage-
ment. Benefits of this approach include:
Bridging the strategy and tactics gap to ensure that project delivery is tied to
organizational needs and vision
Focusing projects on the benefits they exist to support, rather than producing
a set of deliverables
Managing opportunities proactively as an integral part of business processes at
both strategic and tactical levels
Providing useful information to decision makers at all levels when the
environment is uncertain
Allowing an appropriate level of risk to be taken intelligently with full awareness
of the degree of uncertainty and its potential effects on objectives7
In a 2014 paper, Hilson also described the importance of good working relationships as
a best practice in managing project risk. “… management of overall project risk becomes a
shared duty of both project sponsor and project manager, acting in partnership to ensure
that the project has the optimal chance of achieving its objectives within the allowable risk
threshold. Successful management of risk at this whole-project level therefore depends
largely on the effectiveness of the working relationship between these two key players.”8
Several risk experts suggest that organizations and individuals should strive to find a
balance between risks and opportunities in all aspects of projects and their personal lives.
The idea of striving for balance suggests that different organizations and people have
different attitudes toward risk. The PMBOK® Guide, Fifth Edition, states that these at-
titudes are based on two themes: “One is risk appetite, which is the degree of uncertainty
an entity is willing to take on, in anticipation of a reward. The other is risk tolerance,
which is the maximum acceptable deviation an entity is willing to accept on the project
or business objectives as the potential impact…. The project may be accepted if the risks
are within tolerances and are in balance with the rewards that may be gained by taking
the risks.”9 Some organizations or people have a neutral tolerance for risk, some have an
aversion to risk, and others are risk-seeking. These three preferences are part of the util-
ity theory of risk.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo
继承风险管理

lenovo
不可分割的部分

lenovo
前瞻性的

lenovo
战略层面及战术层面 战略指的是企业的整体战略,战术指的是具体的实施办法

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

有一些人对风险的忍耐程度是中立的,一些是不愿意承担风险的,还有一部分人是喜欢承担风险的风险

Risk utility is the amount of satisfaction or pleasure received from a potential payoff.
Figure 11-2 shows the basic difference between risk-averse, risk-neutral, and risk-seeking
preferences. The y-axis represents utility, or the amount of pleasure received from taking a
risk. The x-axis shows the amount of potential payoff or dollar value of the opportunity at
stake. Utility rises at a decreasing rate for a risk-averse person. In other words, when more
payoff or money is at stake, a person or organization that is risk-averse gains less satisfac-
tion from the risk, or has lower tolerance for the risk. Those who are risk-seeking have a
higher tolerance for risk, and their satisfaction increases when more payoff is at stake. A
risk-seeking person prefers outcomes that are more uncertain and is often willing to pay a
penalty to take risks. A risk-neutral person achieves a balance between risk and payoff. For
example, a risk-averse organization might not purchase hardware from a vendor who has not
been in business for a specified period of time. A risk-seeking organization might deliberately
choose start-up vendors for hardware purchases to gain new products with unusual features
that provide an advantage. A risk-neutral organization might perform a series of analyses to
evaluate possible purchase decisions. This type of organization evaluates decisions using a
number of factors—risk is just one of them.
The goal of project risk management can be viewed as minimizing potential negative
risks while maximizing potential positive risks. The term known risks is sometimes used
to describe risks that the project team has identified and analyzed. Known risks can be
managed proactively. However, unknown risks, or risks that have not been identified and
analyzed, cannot be managed.
As you can imagine, good project managers know it is good practice to take the
time to identify and manage project risks. Six major processes are involved in risk
management:
1. Planning risk management involves deciding how to approach and plan risk
management activities for the project. By reviewing the project management
plan, project charter, stakeholder register, enterprise environmental factors,
and organizational process assets, project teams can discuss and analyze risk
management activities for their particular projects. The main output of this
process is a risk management plan.
utility
potential payoff
utility
potential payoff
utility
potential payoff
Risk-Averse Risk-Neutral Risk-Seeking
FIGURE 11-2 r
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

432
2. Identifying risks involves determining which risks are likely to affect a project
and documenting the characteristics of each. The main output of this process
is the start of a risk register, which you will learn about later in this chapter.
3. Performing qualitative risk analysis involves prioritizing risks based on their
probability of occurrence and impact. After identifying risks, project teams
can use various tools and techniques to rank risks and update information in
the risk register. The main outputs are project documents updates.
4. Performing quantitative risk analysis involves numerically estimating the
effects of risks on project objectives. The main outputs of this process are
project documents updates.
5. Planning risk responses involves taking steps to enhance opportunities and
reduce threats to meeting project objectives. Using outputs from the preced-
ing risk management processes, project teams can develop risk response
strategies that often result in updates to the project management plan and
other project documents.
6. Controlling risk involves monitoring identified and residual risks, identifying new
risks, carrying out risk response plans, and evaluating the effectiveness of risk
strategies throughout the life of the project. The main outputs of this process in-
clude work performance information, change requests, and updates to the project
management plan, other project documents, and organizational process assets.
Figure 11-3 summarizes these processes and outputs, showing when they occur in a
typical project.
Planning
Process: Plan risk management
Outputs: Risk management plan
Process: Identify risks
Outputs: Risk register
Process: Perform qualitative risk analysis
Outputs: Project documents updates
Process: Perform quantitative risk analysis
Outputs: Project documents updates
Process: Plan risk responses
Outputs: Project management plan updates, project documents updates
Project Start Project Finish
Monitoring and Controlling
Process: Control risks
Outputs: Work performance information, change requests, project
management plan updates, project documents updates,
organizational process assets updates
FIGURE 11-3
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo
风险登记簿

433
The first step in project risk management is determining how to address this knowl-
edge area for a particular project by performing risk management planning.
11.2 PLANNING RISK MANAGEMENT
Planning risk management is the process of deciding how to approach risk management
activities and plan for them in a project; the main output of this process is a risk manage-
ment plan. A risk management plan documents the procedures for managing risk through-
out the project. Project teams should hold several planning meetings early in the project’s
life cycle to help develop the risk management plan. The project team should review
project documents as well as corporate risk management policies, risk categories, lessons-
learned reports from past projects, and templates for creating a risk management plan. It
is also important to review the risk tolerances of various stakeholders. For example, if the
project sponsor is risk-averse, the project might require a different approach to risk man-
agement than if the project sponsor were a risk seeker.
A risk management plan summarizes how risk management will be performed on a
particular project. Like plans for other knowledge areas, it becomes a subset of the proj-
ect management plan. Table 11-2 lists the general topics that a risk management plan
should address. It is important to clarify roles and responsibilities, prepare budget and
schedule estimates for risk-related work, and identify risk categories for consideration.
It is also important to describe how risk management will be done, including assessment
TABLE 11-2 a r
Topic Questions to Answer
Methodology How will risk management be performed on this project? What tools
and data sources are available and applicable?
Roles and responsibilities Which people are responsible for implementing specific tasks and
providing deliverables related to risk management?
Budget and schedule What are the estimated costs and schedules for performing risk-
related activities?
Risk categories What are the main categories of risks that should be addressed on
this project? Is there a risk breakdown structure for the project?
(See the information on risk breakdown structures later in this
chapter.)
Risk probability and impact How will the probabilities and impacts of risk items be assessed?
What scoring and interpretation methods will be used for the
qualitative and quantitative analysis of risks? How will the
probability and impact matrix be developed?
Revised stakeholders’ tolerances Have stakeholders’ tolerances for risk changed? How will those
changes affect the project?
Tracking How will the team track risk management activities? How will
lessons learned be documented and shared? How will risk
management processes be audited?
Risk documentation What reporting formats and processes will be used for risk
management activities?
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo
模板

lenovo

lenovo

434
of risk probabilities and impacts as well as the creation of risk-related documentation.
The level of detail included in the risk management plan can vary with the needs of the
project.
In addition to a risk management plan, many projects also include contingency plans,
fallback plans, contingency reserves, and management reserves.
Contingency plans are predefined actions that the project team will take if an
identified risk event occurs. For example, if the project team knows that a new
release of a software package may not be available in time to use for the proj-
ect, the team might have a contingency plan to use the existing, older version
of the software.
Fallback plans are developed for risks that have a high impact on meet-
ing project objectives and are put into effect if attempts to reduce the risk
do not work. For example, a new college graduate might have a main plan
and several contingency plans for where to live after graduation, but if
these plans do not work out, a fallback plan might be to live at home for a
while. Sometimes the terms contingency plan and fallback plan are used
interchangeably.
Contingency reserves or contingency allowances are funds included in
the cost baseline that can be used to mitigate cost or schedule overruns if
known risks occur. For example, if a project appears to be off course be-
cause the staff is not experienced with a new technology and the team had
identified that as a risk, the contingency reserves could be used to hire an
outside consultant to train and advise the project staff in using the new
technology.
Management reserves are funds held for unknown risks that are used for
management control purposes. They are not part of the cost baseline, but
they are part of the project budget and funding requirements. If the manage-
ment reserves are used for unforeseen work, they are added to the cost base-
line after the change is approved.
Contingency plans, fallback plans, and reserves show the importance of taking a pro-
active approach to managing project risks.
Before you can really understand and use project risk management processes on IT
projects, it is necessary to recognize and understand the common sources of risk.
11.3 COMMON SOURCES OF RISK ON IT PROJECTS
Several studies have shown that IT projects share some common sources of risk. For
example, the Standish Group did a follow-up study to its CHAOS research called Unfin-
ished Voyages. This study brought together 60 IT professionals to elaborate on how to
evaluate a project’s overall likelihood of being successful. Table 11-3 shows the Standish
Group’s success potential scoring sheet and the relative importance of the project success
criteria. User involvement was cited as being the most important criterion for successful
projects. If a potential project does not receive a minimum score, the organization might
decide not to work on it or to reduce the risks before the project invests too much time
or money.10
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo
详细说明

除了风险管理计划,许多的项目还包括应急计划,退路计划,应急储备以及管理储备

为可能出现的风险做计划

退路计划是为了预防出现对项目结果有很大影响的风险,并且应急计划并没有起到应有效果情况下启动的选项

contingency reserves 包含在费用底线中,就是说在制定计划时这部分花销已经包含在计划的最低花费中了。而management reserves 并不包含在最低花费中,但是包含在项目的整个budget中

用户参与被认为是定义项目成功的最重要的标准

435
TABLE 11-3 s s s t
Success Criterion Relative Importance
User involvement 19
Executive management support 16
Clear statement of requirements 15
Proper planning 11
Realistic expectations 10
Smaller project milestones 9
Competent staff 8
Ownership 6
Clear vision and objectives 3
Hard-working, focused staff 3
Total 100
Source: The Standish Group
The Standish Group provides specific questions for each success criterion to help de-
cide how many points to assign to a project. For example, the following five questions are
related to user involvement:
Do I have the right users?
Did I involve the users early and often?
Do I have a quality relationship with the users?
Do I make involvement easy?
Did I find out what the users need?
The number of questions corresponding to each success criterion determines the
number of points each positive response is assigned. For example, the topic of user in-
volvement includes five questions. For each positive reply, you would get 3.8 (19/5)
points; 19 represents the weight of the criterion, and 5 represents the number of ques-
tions. Therefore, you would assign a value to the user involvement criterion by adding
3.8 points to the score for each question you can answer positively.
Many organizations develop their own risk questionnaires. Broad categories of risks
described on these questionnaires might include:
Market risk: If the IT project will create a new product or service, will it be use-
ful to the organization or marketable to others? Will users accept and use the
product or service? Will someone else create a better product or service faster,
making the project a waste of time and money?
Financial risk: Can the organization afford to undertake the project? How
confident are stakeholders in the financial projections? Will the project meet
NPV, ROI, and payback estimates? If not, can the organization afford to con-
tinue the project? Is this project the best way to use the organization’s finan-
cial resources?
Technology risk: Is the project technically feasible? Will it use mature,
leading-edge, or bleeding-edge technologies? When will decisions be made
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

436
on which technology to use? Will hardware, software, and networks function
properly? Will the technology be available in time to meet project objectives?
Could the technology be obsolete before a useful product can be created? You
can also break down the technology risk category into hardware, software,
and network technology, if desired.
People risk: Does the organization have people with appropriate skills to
complete the project successfully? If not, can the organization find such
people? Do people have the proper managerial and technical skills? Do they
have enough experience? Does senior management support the project? Is
there a project champion? Is the organization familiar with the sponsor or
customer for the project? How good is the relationship with the sponsor or
customer?
Structure/process risk: What degree of change will the new project introduce
into user areas and business procedures? How many distinct user groups
does the project need to satisfy? With how many other systems does the new
project or system need to interact? Does the organization have processes in
place to complete the project successfully?
W H A T W E N T W R O N G ?
Performing risk management is important to improving the likelihood of project suc-
cess. But in1995, more than half of projects with significant cost or schedule overruns
had no risk management in place, according to a study conducted by KPMG, a large
consulting firm.11 Nearly 20 years later, the situation was much the same. In a 2013
KPMG survey of over 1,000 executives, although risk management was a high priority,
only 66 percent of companies said they often or constantly build it into their strategic
planning decisions. A key observation in the survey report is that “Risk management
is at the top of the global executive agenda…those companies that fail to manage them
well imperil their future.”12 Only 44 percent of executives believed their organiza-
tions were effective at developing stakeholders’ understanding of risk. The executives
also said challenges are growing faster than they can handle them. The top three risks
reported were growing regulatory pressure from governments, reputational risk, and
market risk.
Airline incidents cause concerns, especially when lives are lost. The Germanwings
crash in 2015 resulted in 150 deaths, allegedly due to the co-pilot’s poor mental state.
Senior managers are reviewing policies related to risk management to help prevent fu-
ture tragedies. Some changes can take place immediately, while others will take more
time. For example, the German air traffic control authority suggested investing in new
technologies like remote command of passenger planes, an approach that will take a
fair amount of time and money to implement. Other policy changes have already been
made. “Since the Germanwings crash, European airlines have implemented a rule that
two people must be in the cockpit at all times and Germany has set up a task force with
the aviation industry to consider changes to medical and psychological tests
for pilots.”13
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo
据说是因为副驾驶的不良精神状态

lenovo
悲剧

lenovo
远程指挥客机

lenovo
飞机行业

437
Reviewing a proposed project in terms of the Standish Group’s success criteria, a
risk questionnaire, or another similar tool is a good method for understanding common
sources of risk on IT projects. It is also useful to review the work breakdown structure
(WBS) for a project to see if there might be specific risks by WBS categories. For example,
if an item on the WBS involves preparing a press release and no one on the project team
has ever written one, it could be a negative risk if the release is not handled professionally.
A risk breakdown structure is a useful tool to help project managers consider potential
risks in different categories. Similar in form to a work breakdown structure, a risk breakdown
structure is a hierarchy of potential risk categories for a project. Figure 11-4 shows a sample
risk breakdown structure that might apply to many IT projects. The highest-level categories
are business, technical, organizational, and project management. Competitors, suppliers, and
cash flow are categories that fall under business risks. Under technical risks are the categories
of hardware, software, and network. Hardware could be broken down further to include mal-
functions, availability, and cost. Notice how the risk breakdown structure provides a simple,
one-page chart to help ensure that a project team considers important risk categories related
to all IT projects. For example, Cliff and his managers in the chapter’s opening case could
have benefited from considering several of the categories listed under project management—
estimates, communication, and resources. They could have discussed these risks and other
types of risks related to the projects their company bid on, and then developed appropriate
strategies for optimizing positive risks and minimizing negative ones.
In addition to identifying risk based on the nature of the project or products created,
it is also important to identify potential risks according to project management knowl-
edge areas, such as scope, time, cost, and quality. Notice that a major category in the
risk breakdown structure in Figure 11-4 is project management. Table 11-4 lists potential
negative risk conditions that can exist within each knowledge area.14
IT Project
Technical Organizational ProjectManagementBusiness
Cash flow
Suppliers
Competitors
Network Team support Resources
User support
Executive
support
Software
Hardware
Communication
Estimates
FIGURE 11-4
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo
层级

lenovo

438
Understanding common sources of risk is very helpful in risk identification, which is
the next step in project risk management.
11.4 IDENTIFYING RISKS
Identifying risks is the process of understanding what potential events might hurt or en-
hance a particular project. It is important to identify potential risks early, but you must
also continue to identify risks based on the changing project environment. Also remember
that you cannot manage risks if you do not identify them first. By understanding common
sources of risks and reviewing a project’s planning documents (for risk, cost, schedule,
quality, and human resource management), activity cost and duration estimates, the
scope baseline, stakeholder register, project documents, procurement documents, enter-
prise environmental factors, and organizational process assets, project managers and their
teams can identify many potential risks.
Another consideration for identifying risks is the likelihood of advanced discovery,
which is often viewed at a program level rather than a project level. The Risk Manage-
ment Guide for DOD Acquisition, Sixth Edition, addresses this concept and emphasizes
the need to establish high-level indicators for an entire program. For example, several
experts track asteroids to enable a response in case one threatens our planet. Although
the likelihood of a deadly asteroid is very low, the impact is extremely high. For IT pro-
grams, advanced discovery could involve monitoring an important supplier who might re-
move support for software used on several projects. Some suppliers provide early warning
for this possibility, while others do not. It is important for organizations to identify these
advanced discovery risks early and track their status in case time is needed to develop
responses.
TABLE 11-4 n r a e area
Knowledge Area Risk Conditions
Integration Inadequate planning; poor resource allocation; poor integration management;
lack of post-project review
Scope Poor definition of scope or work packages; incomplete definition
Time Errors in estimating time or resource availability; errors in determining
the critical path; poor allocation and management of float; early release of
competitive products
Cost Estimating errors; inadequate productivity, cost, change, or contingency
Quality Poor attitude toward quality; substandard design, materials, and workmanship;
inadequate quality assurance program
Human resource Poor conflict management; poor project organization and definition of
responsibilities; absence of leadership
Communications Carelessness in planning or communicating
Risk Ignoring risk; unclear analysis of risk; poor insurance management
Procurement Unenforceable conditions or contract clauses; adversarial relations
Stakeholders Lack of consultation with key stakeholder, poor sponsor engagement
Source: R.M. Wideman
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo

lenovo
合同条款

lenovo

lenovo

lenovo
诺言

全局来看主要包括四个方面:planning,resource allocation,integration management and post-project review. Of course, the qualifier are all negatives or poor.

主要是与definition 定义
相关

439
11.4a Suggestions for Identifying Risks
There are several tools and techniques for identifying risks. Project teams often begin this
process by reviewing project documentation, recent and historical information related to
the organization, and assumptions that might affect the project. Project team members
and outside experts often hold meetings to discuss this information and ask important
questions about it as they relate to risk. After identifying potential risks at the initial meet-
ing, the project team might then use different information-gathering techniques to further
identify risks. Four common techniques include brainstorming, the Delphi technique, in-
terviewing, and root cause analysis.
Brainstorming is a technique by which a group attempts to generate ideas or find a so-
lution for a specific problem by amassing ideas spontaneously and without judgment. This
approach can help the group create a comprehensive list of risks to address later during
qualitative and quantitative risk analysis. An experienced facilitator should run the brain-
storming session and introduce new categories of potential risks to keep the ideas flowing.
After the ideas are collected, the facilitator can group and categorize the ideas to make them
more manageable. Care must be taken, however, not to overuse or misuse brainstorming.
Although businesses use brainstorming widely to generate new ideas, the psychology lit-
erature shows that individual people working alone produce a greater number of ideas than
they produce through brainstorming in small, face-to-face groups. Group effects, such as
fear of social disapproval, the effects of authority hierarchy, and domination of the session
by one or two vocal people, often inhibit idea generation for many participants.15
The Delphi technique is an approach to gathering information that helps prevent
some of the negative group effects found in brainstorming. The basic concept of the
Delphi technique is to derive a consensus among a panel of experts who make predictions
about future developments. Developed by the Rand Corporation for the U.S. Air Force in
the late 1960s, the Delphi technique is a systematic, interactive forecasting procedure
based on independent and anonymous input regarding future events. The Delphi tech-
nique uses repeated rounds of questioning and written responses, including feedback to
responses in earlier rounds, to take advantage of group input while avoiding the possible
biasing effects of oral panel deliberations. To use the Delphi technique, you must select
a panel of experts for the particular area in question. For example, Cliff Branch from the
opening case could use the Delphi technique to help him understand why his company
is no longer winning many contracts. Cliff could assemble a panel of people with knowl-
edge in his business area. Each expert would answer questions related to Cliff’s situation,
and then Cliff or a facilitator would evaluate their responses, together with opinions and
justifications, and provide that feedback to each expert in the next iteration. Cliff would
continue this process until the group responses converge to a specific solution. If the re-
sponses diverge, the facilitator of the Delphi technique needs to determine if there is a
problem with the process.
Interviewing is a fact-finding technique for collecting information in face-to-face,
phone, e-mail, or virtual discussions. Interviewing people with similar project experience
is an important tool for identifying potential risks. For example, if a new project involves
using a particular type of hardware or software, people who had recent experience with
that hardware or software could describe their problems on a past project. If people have
worked with a particular customer, they might provide insight into the potential risks of
working for that customer again. It is important to be well prepared for leading interviews;
it often helps to create a list of questions to use as a guide during the interview.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

440
It is not uncommon for people to identify problems or opportunities without really
understanding them. Before suggesting courses of action, it is important to identify the
root cause of a problem or opportunity. Root cause analysis (as you learned in Chapter 8,
Project Quality Management) often results in identifying even more potential risks for a
project.
Another technique is a SWOT analysis of strengths, weaknesses, opportunities, and
threats, which is often used in strategic planning. SWOT analysis can also be used during
risk identification by having project teams focus on the broad perspectives of potential
risks for particular projects. (You first learned about SWOT analysis in Chapter 4, Project
Integration Management.) For example, before writing a particular proposal, Cliff Branch
could have a group of his employees discuss in detail their company’s strengths, their
weaknesses for the project, and what opportunities and threats exist. Do they know that
several competing firms are much more likely to win a certain contract? Do they know
that winning a particular contract will likely lead to future contracts and help expand their
business? Applying SWOT to specific potential projects can help identify the broad risks
and opportunities that apply in that scenario.
Three other techniques for risk identification include the use of checklists, analysis of
assumptions, and creation of diagrams:
Checklists that are based on risks encountered in previous projects provide a
meaningful template for understanding risks in a current project. You can use
checklists similar to those developed by the Standish Group and other IT re-
search consultants to help identify risks on IT projects.
It is important to analyze project assumptions to make sure they are valid.
Incomplete, inaccurate, or inconsistent assumptions might lead to identifying
more risks.
Diagramming techniques include using cause-and-effect diagrams or fish-
bone diagrams, flowcharts, and influence diagrams. Recall from Chapter 8,
Project Quality Management, that fishbone diagrams help you trace prob-
lems back to their root cause. System or process flowcharts are diagrams
that show how different parts of a system interrelate. For example, many
programmers create flowcharts to show programming logic. (A sample
flowchart is provided in Chapter 8.) Another type of diagram, an influence
diagram, represents decision problems by displaying essential elements,
including decisions, uncertainties, causality, and objectives, and how they
influence each other. (See other references, such as www.lumina.com/
software/influencediagrams.html, for detailed information on influence
diagrams.)
11.4b The Risk Register
The main output of risk identification is a list of identified risks and other information
needed to begin creating a risk register. A risk register is a document that contains results
of various risk management processes; it is often displayed in a table or spreadsheet format.
A risk register is a tool for documenting potential risk events and related information. Risk
events refer to specific, uncertain events that may occur to the detriment or enhancement
of the project. For example, negative risk events might include the performance failure of
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

a product created as part of a project, delays in completing work as scheduled, increases in
estimated costs, supply shortages, litigation against the company, and strikes. Examples of
positive risk events include completing work sooner or cheaper than planned, collaborating
with suppliers to produce better products, and good publicity resulting from the project.
Table 11-5 provides a sample of the format for a risk register that Cliff and his manag-
ers from the opening case might use on a new project. Actual data that might be entered
for one of the risks is included below the table. Notice the main headings often included
in the register. Many of these items are described in more detail later in this chapter. Ele-
ments of a risk register include:
An identification number for each risk event: The project team may want to sort
by risk events or quickly search for specific risk events, so they need to identify
each risk with a unique descriptor, such as an identification number.
A rank for each risk event: The rank is usually a number, with 1 representing
the highest risk.
The name of the risk event: Example names include defective server, late
completion of testing, reduced consulting costs, and good publicity.
A description of the risk event: Because the name of a risk event is often
abbreviated, it helps to provide a more detailed description. Consider using
a risk statement format similar to the following: “Because of , might occur, which would lead to .” For example, reduced consulting costs might be expanded to:
“Because this particular consultant enjoys working for our company and is
open to negotiating her rates, reduced consulting costs might occur, which
could lead to saving money on the project.”
The category under which the risk event falls: For example, defective server
might fall under the broader category of technology or hardware technology.
The root cause of the risk: The root cause of the defective server might be a
defective power supply.
Triggers for each risk: Triggers are indicators or symptoms of actual risk
events. For example, cost overruns on early activities may be symptoms of
poor cost estimates. Defective products may be symptoms of a low-quality
supplier. Documenting potential risk symptoms for projects also helps the
project team identify more potential risk events.
Potential responses to each risk: A potential response to the defective server
might be to include a clause in the supplier’s contract to replace the server
within a certain time period at a negotiated cost.
TABLE 11-5
No. Rank Risk Description Category
Root
Cause Triggers
Potential
Responses
Risk
Owner Probability Impact Status
R44 1
R21 2
R7 3
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

442
The risk owner or person who will take responsibility for the risk: For ex-
ample, a certain person might be in charge of any server-related risk events
and managing response strategies.
The probability of the risk occurring: There might be a high, medium, or low
probability of a certain risk event. For example, the risk might be low that
the server would actually be defective.
The impact to the project if the risk occurs: There might be a high, medium,
or low impact to project success if the risk event actually occurs. A defective
server might have a high impact on successfully completing a project
on time.
The status of the risk: Did the risk event occur? Was the response strategy
completed? Is the risk no longer relevant to the project? For example, a con-
tract clause may have been completed to address the risk of a defective server.
For example, the following data might be entered for the first risk in the register.
Notice that Cliff’s team is taking a proactive approach in managing this risk.
No.: R44
Rank: 1
Risk: New customer
Description: We have never done a project for this organization before and
don’t know too much about them. One of our company’s strengths is building
good customer relationships, which often leads to further projects with that
customer. We might have trouble working with this customer because they are
new to us.
Category: People risk
Root cause: We won a contract to work on a project without really getting to
know the customer.
Triggers: The new customer asked a lot of questions in person and via e-mail
that our existing customers would not, so we could easily misunderstand
their needs and expectations.
Potential responses: Make sure the project manager is sensitive to the fact
that this is a new customer and takes the time to understand them. Have the
PM set up a meeting to get to know the customer and clarify their expecta-
tions. Have Cliff attend the meeting, too.
Risk owner: Project manager
Probability: Medium
Impact: High
Status: PM will set up the meeting within the week.
After identifying risks, the next step is to understand which risks are most important
by performing qualitative risk analysis.
11.5 PERFORMING QUALITATIVE RISK ANALYSIS
Qualitative risk analysis involves assessing the likelihood and impact of identified risks to
determine their magnitude and priority. This section describes how to use a probability/
impact matrix to produce a prioritized list of risks. It also provides examples of using the
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

443
Top Ten Risk Item Tracking technique to produce an overall ranking for project risks and
to track trends in qualitative risk analysis. Finally, this section discusses the importance
of expert judgment in performing risk analysis.
11.5a Using Probability/Impact Matrixes to Calculate Risk Factors
People often describe a risk probability or consequence as being high, medium or moder-
ate, or low. For example, a meteorologist might predict a high probability or likelihood of
severe rain showers on a certain day. If that day happens to be your wedding day and you
are planning a large outdoor ceremony, the consequences or impact of severe showers
might also be high.
A project manager can chart the probability and impact of risks on a probability/
impact matrix or chart, which lists the relative probability of a risk occurring and the rela-
tive impact of the risk occurring. Many project teams would benefit from using this simple
technique to help them identify risks that need attention. To use this approach, project
stakeholders list the risks they think might occur on their projects. They then label a risk
as having a high, medium, or low probability of occurrence and a high, medium, or low
impact if it does occur.
The project manager then summarizes the results in a probability/impact matrix or
chart, as shown in Figure 11-5. For example, Cliff Branch and some of his project manag-
ers in the opening case could each identify three negative and positive potential risks for a
particular project. They could then label the probability of occurrence and impact of each
risk as being high, medium, or low. For example, one project manager might list a severe
market downturn as a negative risk that is low in probability but high in impact. Cliff may
have listed the same risk as being medium in both probability and impact. The team could
Pr
ob
ab
ili
ty
Medium
Impact
High
Medium
Low
Low High
risk 6
risk 3
risk 7
risk 9
risk 2
risk 5
risk 11
risk 8
risk 10
risk 1
risk 4
risk 12
FIGURE 11-5
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

444
then plot all of the risks on a matrix or chart, combine common risks, and decide where
those risks should be on the matrix or chart. The team should then focus on risks that fall
in the high sections of the probability/impact matrix or chart. For example, Risks 1 and 4
are listed as high in both probability and impact. Risk 6 is high in probability but low in
impact. Risk 9 is high in probability and medium in impact, and so on. The team should
then discuss how it plans to respond to the risks if they occur, as you will learn later in
this chapter in the section on risk response planning.
It may be useful to create a separate probability/impact matrix or chart for negative
risks and positive risks to make sure that both types are adequately addressed. Some proj-
ect teams also collect data on the probability of risks and the negative or positive impact
they could have on scope, time, and cost goals. Qualitative risk analysis is normally done
quickly, so the project team has to decide what type of approach makes the most sense for
its project.
Some project teams develop a single number for a risk score simply by multiply-
ing a numeric score for probability by a numeric score for impact. A more sophisticated
approach to using probability/impact information is to calculate risk factors. To quan-
tify risk probability and consequence, the U.S. Defense Systems Management College
(DSMC) developed a technique for calculating risk factors—numbers that represent the
overall risk of specific events, based on their probability of occurring and the conse-
quences to the project if they do occur. The technique makes use of a probability/impact
matrix that shows the probability of risks occurring and the impact or consequences of
the risks.
Probabilities of a risk occurring can be estimated based on several factors deter-
mined by the unique nature of each project. For example, factors to evaluate for potential
hardware or software technology risks could include the technology not being mature,
the technology being too complex, and an inadequate support base for developing the
technology. The impact of a risk occurring could include factors such as the availability
of fallback solutions or the consequences of not meeting performance, cost, and schedule
estimates.
Figure 11-6 provides an example of how risk factors were used to graph the probabil-
ity of failure and consequence of failure in a research study on proposed technologies for
designing more reliable aircraft. The figure classifies potential technologies (dots on the
chart) as high, medium, or low risk, based on the probability of failure and consequences
of failure. The researchers strongly recommended that the U.S. Air Force invest in the
low- to medium-risk technologies and suggested that it not pursue the high-risk technolo-
gies.16 The rigor involved in using the probability/impact matrix and risk factors can pro-
vide a much stronger argument than simply stating that risk probabilities or consequences
are high, medium, or low.
11.5b Top Ten Risk Item Tracking
Top Ten Risk Item Tracking is a qualitative risk analysis tool. In addition to identify-
ing risks, it maintains an awareness of risks throughout the life of a project by helping
to monitor risks. Using this tool involves establishing a periodic review of the project’s
most significant risk items with management; similar reviews can also occur with the cus-
tomer. The review begins with a summary of the status of the top ten sources of risk on
the project. The summary includes each item’s current ranking, previous ranking, num-
ber of times it appears on the list over a period of time, and a summary of progress made
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

445
in resolving the risk item since the previous review. The Microsoft Solution Framework
(MSF), the methodology Microsoft uses for managing projects, is an example of how one
company tracks risk items. It uses a risk management model that includes developing and
monitoring a top ten master list of risks. The methodology combines aspects of software
design and development, and building and deploying infrastructure, into a single-project
life cycle for guiding technology solutions of all kinds. (Consult Microsoft’s website for
more information on MSF.)
Table 11-6 provides an example of a Top Ten Risk Item Tracking chart that could
be used at a management review meeting for a project. This example includes only the
top five negative risk events. Notice that each risk event is ranked based on the current
month, previous month, and how many months it has been in the top ten. The last col-
umn briefly describes the progress for resolving each risk item. You can have separate
charts for negative and positive risks or combine them into one chart.
A risk management review accomplishes several objectives. First, it keeps manage-
ment and the customer (if included) aware of major influences that could prevent or en-
hance the project’s success. Second, by involving the customer, the project team may be
able to consider alternative strategies for addressing the risks. Third, the review promotes
confidence in the project team by demonstrating to management and the customer that
the team is aware of significant risks, has a strategy in place, and is effectively carrying
out that strategy.
The main output of qualitative risk analysis is updating the risk register. The ranking
column of the risk register should be filled in, along with a numeric value or rating of high,
medium, or low for the probability and impact of the risk event. Additional information
1.0
Consequence of Failure (Cf)
Low
Risk
Medium
Risk
High Risk
0.8
0.6
0.4
0.2
0 0.2 0.4 0.6 0.8 1.0
Probability
of Failure
(Pf)
FIGURE 11-6
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

446
is often added for risk events, such as identification of risks that need more attention in
the near term or those that can be placed on a watch list. A watch list is a list of risks that
have low priority but are still identified as potential risks. Qualitative analysis can also
identify risks that should be evaluated quantitatively, as you learn in the next section.
M E D I A S N A P S H O T
Even more than 100 years after the Titanic sank on April 15, 1912, people mark the an-
niversary on which more than 1,500 of the ship’s passengers and crew died. A recent
article in PMI’s Virtual Library explains how to avoid “the Titanic factor” in your projects
by analyzing the interdependence of risks. For example, the probability of one risk event
occurring might change if another one materializes, and the response to one risk event
might affect another. The article’s author addresses the issue of how project risks interact
and how project teams can address those risks. Some of the interdependent risk events
on the Titanic included the following:
The design of the bulkheads, rudder, and engines were integrated. As six of the
16 watertight compartments were breached and began flooding, the weight of
the water in the bow pulled the ship under until the bulkheads overtopped.
The rudder design was considered adequate for use on the open seas, but it
was undersized for the tight maneuvers required that fateful night. The central
propeller had a steam turbine as its power source, but this engine could not be
reversed and was stopped during the run up to the iceberg. This stopped the
water flow past the rudder and became a critical problem for the ship.
Several procedures were not followed, which had the cumulative effect of
creating other major problems. Iceberg reports from two other ships were not
passed on to the bridge. The wireless radio did not work most of the day, so
TABLE 11-6
MONTHLY RANKING
Risk Event
Rank This
Month
Rank Last
Month
Number of
Months in
Top Ten Risk Resolution Progress
Inadequate
planning
1 2 4 Working on revising the entire project
management plan
Poor
definition
2 3 3 Holding meetings with project customer
and sponsor to clarify scope
Absence of
leadership
3 1 2 Assigned a new project manager to lead
the project after the previous one quit
Poor cost
estimates
4 4 3 Revising cost estimates
Poor time
estimates
5 5 3 Revising schedule estimates
© Cengage Learning 2016
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

447
another critical iceberg warning failed to reach the Titanic’s captain. The ship
was traveling too fast for the amount of ice in the area, and visibility was
terrible that night.
Unknown risk events also contributed to the sinking of the Titanic. For exam-
ple, the steel in the hull could not withstand the cold temperatures, causing
it to break without bending. Iron rivet heads also burst due to the cold.17
11.6 PERFORMING QUANTITATIVE RISK ANALYSIS
Quantitative risk analysis often follows qualitative risk analysis, yet both processes can be
done together or separately. On some projects, the team may only perform qualitative risk
analysis. The nature of the project and availability of time and money affect which risk
analysis techniques are used. Large, complex projects involving leading-edge technolo-
gies often require extensive quantitative risk analysis. The main techniques for quantita-
tive risk analysis include data gathering, analysis and modeling techniques, and expert
judgment. Data gathering often involves interviewing experts and collecting probability
distribution information. This section focuses on using the quantitative risk analysis and
modeling techniques of decision tree analysis, simulation, and sensitivity analysis.
11.6a Decision Trees and Expected Monetary Value
A decision tree is a diagramming analysis technique used to help select the best course of
action when future outcomes are uncertain. A common application of decision tree analysis
involves calculating expected monetary value. Expected monetary value (EMV) is the prod-
uct of a risk event probability and the risk event’s monetary value. To illustrate this concept,
Figure 11-7 uses the issue of which project(s) an organization might pursue. Suppose Cliff
Branch’s firm was trying to decide if it should submit a proposal for Project 1, Project 2, both
projects, or neither project. The team could draw a decision tree with two branches, one for
Project 1 and one for Project 2. The firm could then calculate the expected monetary value
to help make this decision.
To create a decision tree, and to calculate expected monetary value specifically, you
must estimate the probabilities or chances of certain events occurring. For example,
Figure 11-7 shows a 20 percent probability (P = .20) that Cliff’s firm will win the contract for
Project 1, which is estimated to be worth $300,000 in profits—the outcome of the top branch
in the figure. There is an 80 percent probability (P = .80) that the firm will not win the con-
tract for Project 1, and the outcome is estimated to be −$40,000, meaning that the firm will
have invested $40,000 into Project 1 with no reimbursement if it does not win the contract.
The sum of the probabilities for outcomes for each project must equal one (for Project 1,
.20 plus .80). Probabilities are normally determined based on expert judgment. Cliff or other
people in his firm should have a sense of the likelihood of winning certain projects.
Figure 11-7 also shows probabilities and outcomes for Project 2. Suppose there is a
20 percent probability that Cliff’s firm will lose $50,000 on Project 2, a 10 percent prob-
ability that it will lose $20,000, and a 70 percent probability that it will earn $60,000.
Again, experts would need to estimate these dollar amounts and probabilities.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

448
To calculate the EMV for each project, multiply the probability by the outcome value
for each potential outcome for each project and sum the results. To calculate EVM for
Project 1, going from left to right, multiply the probability by the outcome for each branch
and sum the results. In this example, the EMV for Project 1 is $28,000.
.2($300,000) + .8(– $40,000) = $60,000 – $32,000 = $28,000
The EMV for Project 2 is $30,000.
.2(– $50,000) + .1(– $20,000) + .7($60,000) = – $10,000 – $2,000 + $42,000 = $30,000
Because the EMV provides an estimate for the total dollar value of a decision, you
want to have a positive number; the higher the EMV, the better. Because the EMV is
positive for both Projects 1 and 2, Cliff’s firm would expect a positive outcome from
each and could bid on both projects. If it had to choose between the two projects, per-
haps because of limited resources, Cliff’s firm should bid on Project 2 because it has a
higher EMV.
Notice in Figure 11-7 that if you just look at the potential outcome of the two proj-
ects, Project 1 looks more appealing. You could earn $300,000 in profits from Project 1,
but you could only earn $60,000 for Project 2. If Cliff were a risk seeker, he would natu-
rally want to bid on Project 1. However, there is only a 20 percent chance of earning the
$300,000 on Project 1, as opposed to a 70 percent chance of earning $60,000 on Project 2.
Using EMV helps account for all possible outcomes and their probabilities of occurrence,
thereby reducing the tendency to pursue overly aggressive or conservative risk strategies.
Decision
Probability (P)
Project 1
Project 2
P=.20
P=.80
times EMV of Outcome
p $300,000 = +$60,000
p –$40,000 = –$32,000
P=.20
P=.10
P=.70
p
p
p
–$50,000 = –$10,000
–$20,000 = –$2,000
$60,000 = $42,000
Project 1’s EMV = $60,000 – $32,000 = $28,000
Project 2’s EMV = –$10,000 – $2,000 + $42,000 = $30,000
FIGURE 11-7
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

449
11.6b Simulation
A more sophisticated technique for quantitative risk analysis is simulation, which uses
a representation or model of a system to analyze its expected behavior or performance.
Most simulations are based on some form of Monte Carlo analysis. Monte Carlo analysis
simulates a model’s outcome many times to provide a statistical distribution of the
calculated results. For example, Monte Carlo analysis can determine that a project will
finish by a certain date only 10 percent of the time, and determine another date for
which the project will finish 50 percent of the time. In other words, Monte Carlo analy-
sis can predict the probability of finishing by a certain date or the probability that the
cost will be equal to or less than a certain value.
You can use several different types of distribution functions when performing a Monte
Carlo analysis. The following example is a simplified approach. The basic steps of a Monte
Carlo analysis are:
1. Collect the most likely, optimistic, and pessimistic estimates for the variables
in the model. For example, if you are trying to determine the likelihood of
meeting project schedule goals, the project network diagram would be your
model. You would collect the most likely, optimistic, and pessimistic time
estimates for each task. Notice that this step is similar to collecting data for
performing PERT estimates. However, instead of applying the same PERT
weighted average formula, you perform the following steps in a Monte Carlo
simulation.
2. Determine the probability distribution of each variable. What is the likeli-
hood of a variable falling between the optimistic and most likely estimates?
For example, if an expert assigned to a particular task provides a most likely
estimate of 10 weeks, an optimistic estimate of eight weeks, and a pessimistic
estimate of 15 weeks, you then ask about the probability of completing that
task between 8 and 10 weeks. The expert might respond that there is a
20 percent probability.
3. For each variable, such as the time estimate for a task, select a random value
based on the probability distribution for the occurrence of the variable. For
example, using the preceding scenario, you would randomly pick a value be-
tween 8 weeks and 10 weeks 20 percent of the time and a value between
10 weeks and 15 weeks 80 percent of the time.
4. Run a deterministic analysis or one pass through the model using the
combination of values selected for each of the variables. For example,
one task described in the preceding scenario might have a value of 12 on
the first run. All of the other tasks would also have one random value as-
signed to them on the first run, based on their estimates and probability
distributions.
5. Repeat Steps 3 and 4 many times to obtain the probability distribution of
the model’s results. The number of iterations depends on the number of vari-
ables and the degree of confidence required in the results, but it typically lies
between 100 and 1,000. Using the project schedule as an example, the final
simulation results will show you the probability of completing the entire proj-
ect within a certain time period.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

450
Figure 11-8 illustrates the results from a Monte Carlo-based simulation of a proj-
ect schedule. The simulation was done using Microsoft Project and Risk+ software.
On the left side of Figure 11-8 is a chart displaying columns and an S-shaped curve.
The height of each column indicates how many times the project was completed in a
given time interval during the simulation run, which is the sample count. In this ex-
ample, the time interval was two working days, and the simulation was run 250 times.
The first column shows that the project was completed by January 29 only two times
during the simulation. The S-shaped curve shows the cumulative probability of com-
pleting the project on or before a given date. The right side of Figure 11-8 shows
the information in tabular form. For example, there is a 10 percent probability that
the project will be completed by 2/8 (February 8), a 50 percent chance of
completion by 2/17 (February 17), and a 90 percent chance of completion by
2/25 (February 25).
Several PC-based software packages that perform Monte Carlo simulations are
available. Many products display the major risk drivers for a project based on the
simulation results. This enables you to identify the chief source of uncertainty in a
project schedule. For example, a wide range for a certain task estimate might cause
most of the uncertainty in the project schedule. You will learn more about using simu-
lation software and other software related to project risk management later in this
chapter.
Sa
m
pl
e
Co
un
t
2/17 3/10
4.5
9.0
13.5
18.0
22.5
27.0
31.5
36.0
40.5
45.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
1/29
Date: 1/14 11:13:56 AM
Number of Samples: 250
Unique ID: 1
Name: Widget
Completion Std Deviation: 5.2 days
95% Confidence Interval: 0.6 days
Each bar represents 2 days
Cu
m
ul
at
iv
e
Pr
ob
ab
ili
ty
Completion Date
Prob
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40
0.45
0.50
Completion Probability Table
Date
2/4
2/8
2/9
2/10
2/11
2/12
2/15
2/15
2/16
2/17
Date
2/17
2/18
2/19
2/22
2/22
2/23
2/24
2/25
2/26
3/10
Prob
0.55
0.60
0.65
0.70
0.75
0.80
0.85
0.90
0.95
1.00
FIGURE 11-8 Sa
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

W H A T W E N T R I G H T ?
Microsoft Excel is a common tool for performing quantitative risk analysis. Microsoft provides
examples of how to use Excel to perform Monte Carlo simulation on its website, and explains
how several companies use Monte Carlo simulation as an important tool for decision making:
General Motors uses simulation for forecasting its net income, predicting structural
costs and purchasing costs of vehicles, and determining the company’s susceptibility
to different kinds of risk, such as interest rate changes and exchange rate fluctuations.
Eli Lilly uses simulation to determine the optimal plant capacity that should be
built for developing each drug.
Procter & Gamble uses simulation to model and optimally hedge foreign exchange
risk.18
Monte Carlo simulation can also help reduce schedule risk on agile projects. For
example, instead of using linear techniques, which assume a fixed future velocity and
a discrete completion date, you can use Monte Carlo simulation to estimate a range
of completion dates. “Consider a simple scenario where two teams both have an aver-
age velocity of 7.5. Using this average, either team could deliver the next 45 points in 6
iterations. However, suppose Team A’s historical velocity values were 10, 4, 5, and 11,
and Team B’s historical velocity values were 7, 8, 8, and 7. The average is the same, but
because the velocity values for Team A have a higher variance, there is greater risk when
predicting future results.”19
11.6c Sensitivity Analysis
Many people are familiar with using sensitivity analysis to see the effects of changing one
or more variables on an outcome. For example, many people perform a sensitivity analy-
sis to determine their monthly payments for a loan given different interest rates or peri-
ods of the loan. What will your monthly mortgage payment be if you borrow $100,000 for
30 years at a 6 percent rate? What will the payment be if the interest rate is 7 percent?
What will the payment be if you decide to pay off the loan in 15 years at 5 percent?
Many professionals use sensitivity analysis to help make several common business
decisions, such as determining break-even points based on different assumptions. People
often use spreadsheet software like Microsoft Excel to perform sensitivity analysis.
Figure 11-9 shows an example Excel file created to quickly show the break-even point for
a product based on various inputs: the sales price per unit, the manufacturing cost per
unit, and fixed monthly expenses. The current inputs result in a break-even point of 6,250
units sold. Users of this spreadsheet can change inputs and see the effects on the break-
even point in chart format. Project teams often create similar models to determine the
sensitivity of various project variables. For example, Cliff’s team could develop sensitivity
analysis models to estimate their profits on jobs by varying the number of hours required
to do the jobs or by varying costs per hour.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

452
The main outputs of quantitative risk analysis are updates to the risk register, such
as revised risk rankings or detailed information behind those rankings. The quantita-
tive analysis also provides high-level information about the probabilities of achieving
certain project objectives. This information might cause the project manager to suggest
changes in contingency reserves. In some cases, projects may be redirected or canceled
based on the quantitative analysis, or the quantitative analysis might be used to help
initiate new projects to help the current one succeed.
11.7 PLANNING RISK RESPONSES
After an organization identifies and quantifies risks, it must develop an appropriate re-
sponse to them. Developing a response to risks involves developing options and defining
strategies for reducing negative risks and enhancing positive risks.
The four basic response strategies for negative risks are:
Risk avoidance or eliminating a specific threat, usually by eliminating its causes.
Of course, not all risks can be eliminated, but specific risk events can be. For
example, a project team may decide to continue using a specific piece of hard-
ware or software on a project because the team knows it works. Other products
that could be used on the project may be available, but if the project team is
FIGURE 11-9 Sa se
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

453
unfamiliar with them, they could cause significant risk. Using familiar hardware
or software eliminates this risk.
Risk acceptance or accepting the consequences if a risk occurs. For example,
a project team planning a big project review meeting could take an active
approach to risk by having a contingency or backup plan and contingency
reserves if the team cannot get approval for a specific meeting site. On the
other hand, the team could take a passive approach and accept whatever fa-
cility the organization provides.
Risk transference or shifting the consequence of a risk and responsibility
for its management to a third party. For example, risk transference is often
used in dealing with financial risk exposure. A project team may purchase
special insurance or warranty protection for specific hardware needed for a
project. If the hardware fails, the insurer must replace it within a specified
period of time.
Risk mitigation or reducing the impact of a risk event by reducing the prob-
ability of its occurrence. Suggestions for reducing common sources of risk on
IT projects were provided at the beginning of this chapter. Other examples
of risk mitigation include using proven technology, having competent proj-
ect personnel, using various analysis and validation techniques, and buying
maintenance or service agreements from subcontractors.
Table 11-7 provides general mitigation strategies for technical, cost, and schedule risks
on projects.20 Note that increasing the frequency of project monitoring and using a work
breakdown structure (WBS) and Critical Path Method (CPM) are strategies for all three ar-
eas. Increasing the project manager’s authority is a strategy for mitigating technical and cost
risks, and selecting the most experienced project manager is recommended for reducing
schedule risks. Improving communication is also an effective strategy for mitigating risks.
The four basic response strategies for positive risks are:
Risk exploitation or doing whatever you can to make sure the positive risk hap-
pens. For example, suppose that Cliff’s company funded a project to provide
TABLE 11-7
Technical Risks Cost Risks Schedule Risks
Emphasize team support and avoid
stand-alone project structure
Increase the frequency of project
monitoring
Increase the frequency of
project monitoring
Increase project manager authority Use WBS and CPM Use WBS and CPM
Improve problem handling and
communication
Improve communication,
understanding of project goals, and
team support
Select the most
experienced project
manager
Increase the frequency of project
monitoring
Increase project manager
authority
Use WBS and CPM
source: J. Couillard
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

454
new computer classrooms for a nearby school in need. They might select one
of their top project managers to organize news coverage of the project, write a
press release, or hold some other public event to ensure that the project pro-
duces good public relations for the company, which could lead to more business.
Risk sharing or allocating ownership of the risk to another party. Using the
same example of implementing new computer classrooms, the project man-
ager could form a partnership with the school’s principal, school board, or
parent-teacher organization to share responsibility for achieving good public
relations for the project. On the other hand, the company might partner with
a local training firm that agrees to provide free training for all of the teachers
on how to use the new computer classrooms.
Risk enhancement or changing the size of the opportunity by identifying and
maximizing key drivers of the positive risk. For example, an important driver
of getting good public relations for the computer classrooms project might be
to generate awareness and excitement about it among students, parents, and
teachers. These groups might then do their own formal or informal advertis-
ing of the project and Cliff’s company, which in turn might interest other
groups and generate more business.
Risk acceptance also applies to positive risks when the project team does not
take any actions toward a risk. For example, the computer classrooms proj-
ect manager might assume that the project will result in good public relations
for the company and not feel compelled to do anything extra.
The main outputs of risk response planning include risk-related contractual agree-
ments, updates to the project management plan and other project documents, and updates
to the risk register. For example, if Cliff’s company decided to partner with a local training
firm on the computer classrooms project to share the opportunity of achieving good public
relations, it could write a contract with that firm. The project management plan and its
related plans might need to be updated if the risk response strategies require additional
tasks, resources, or time to accomplish. Risk response strategies often result in changes to
the WBS and project schedule, so plans that contain this information must be updated as
well. The risk response strategies also provide updated information for the risk register by
describing the risk responses, risk owners, and status information.
Risk response strategies often include identification of residual and secondary risks
as well as contingency plans and reserves, as described earlier. Residual risks are risks
that remain after all of the response strategies have been implemented. For example, even
though a stable hardware product may have been used on a project, there may still be a
risk that it fails to function properly. Secondary risks are a direct result of implementing
a risk response. For example, using the more stable hardware may have caused a risk of
peripheral devices failing to function properly.
11.8 CONTROLLING RISKS
Controlling risks involves executing the risk management processes to respond to risk
events and ensuring that risk awareness is an ongoing activity performed by the entire proj-
ect team throughout the entire project. Project risk management does not stop with the ini-
tial risk analysis. Identified risks may not materialize, or their probabilities of occurrence
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

455
or loss may diminish. Previously identified risks may be determined to have a greater prob-
ability of occurrence or a higher estimated loss value. Similarly, new risks will be identified
as the project progresses. Newly identified risks need to go through the same process as
those identified during the initial risk assessment. A redistribution of resources devoted to
risk management may be necessary because of relative changes in risk exposure.
Carrying out individual risk management plans involves monitoring risks based on
defined milestones and making decisions regarding risks and their response strategies.
It may be necessary to alter a strategy that becomes ineffective, implement a planned
contingency activity, or eliminate a risk from the list of potential risks when it no longer
exists. Project teams sometimes use workarounds—unplanned responses to risk events—
when they do not have contingency plans in place.
Tools and techniques for performing risk control include risk reassessment, risk audits,
variance and trend analysis, technical performance measurements, reserve analysis, and
status meetings or periodic risk reviews such as the Top Ten Risk Item Tracking method.
Outputs of this process are work performance information, change requests, and updates to
the project management plan, other project documents, and organizational process assets.
11.9 USING SOFTWARE TO ASSIST IN PROJECT
RISK MANAGEMENT
As you saw in several parts of this chapter, you can use a variety of software tools to en-
hance various risk management processes. Most organizations use software to create, up-
date, and distribute information in their risk registers. The risk register is often a simple
Microsoft Word or Excel file, but it can also be part of a more sophisticated database.
Spreadsheets can aid in tracking and quantifying risks, preparing charts and graphs, and
performing sensitivity analysis. Software can be used to create decision trees and estimate
expected monetary value.
More sophisticated risk management software, such as Monte Carlo simulation soft-
ware, can help you develop models and use simulations to analyze and respond to various
risks. Several high-end project management tools include simulation capabilities. You can
also purchase add-on software to perform Monte Carlo simulations using Excel (such as
Oracle’s Crystal Ball or Palisade’s @Risk for Excel) or Project 2013 (such as Deltek’s Risk+
or Palisade’s @Risk for Project). Several software packages have also been created specifi-
cally for project risk management. Although it has become easier to do sophisticated risk
analysis with new software tools, project teams must be careful not to rely too heavily on
software when performing project risk management. If a risk is not identified, it cannot be
managed, and intelligent, experienced people are needed to do a good job of identifying
risks. It also takes hard work to develop and implement good risk response strategies. Soft-
ware should be used as a tool to help make good decisions in project risk management,
not as a scapegoat when things go wrong.
Well-run projects, like a master violinist’s performance, an Olympic athlete’s gold
medal win, or a Pulitzer Prize-winning book, appear to be almost effortless. Those on the
outside—whether audiences, customers, or managers—cannot observe the effort that goes
into a superb performance. They cannot see the hours of practice, the edited drafts, or
the planning, management, and foresight that create the appearance of ease. To improve
IT project management, project managers should strive to make their jobs look easy—it
reflects the results of a well-run project.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

456
C A S E W R A P – U P
Cliff Branch and two of his senior people attended a seminar on project risk management
where the speaker discussed several techniques, such as estimating the expected mon-
etary value of projects and Monte Carlo simulations. Cliff asked the speaker how these
techniques could help his company decide which projects to bid on, because bidding
on projects often required up-front investments with the possibility of no payback. The
speaker walked through an example of EMV and then ran a quick Monte Carlo simula-
tion. Cliff did not have a strong math background and had a hard time understanding the
EMV calculations. He thought the simulation was much too confusing to have any practi-
cal use for him. He believed in his gut instincts much more than any math calculation or
computer output.
The speaker finally sensed that Cliff was not impressed, so she explained the impor-
tance of looking at the odds of winning project awards and not just at the potential prof-
its. She suggested using a risk-neutral strategy by bidding on projects that the company
had a good chance of winning (50 percent or so) and that had a good profit potential,
instead of focusing on projects that they had a small chance of winning and that had a
larger profit potential. Cliff disagreed with this advice, and he continued to bid on high-
risk projects. The two other managers who attended the seminar now understood why
the firm was having problems—their leader loved taking risks, even if it hurt the com-
pany. They soon found jobs with competing companies, as did several other employees.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

457
Chapter Summary








Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

458




Quick Quiz

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

459
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

460
Quick Quiz Answers
Discussion Questions


Exercises


Security Risk Man-
agement Guide.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.



Project Chance of Outcome Estimated Profits
Project 1 50 percent
50 percent
$120,000
−$50,000
Project 2 30 percent
40 percent
30 percent
$100,000
$ 50,000
−$60,000
Project 3 70 percent
30 percent
$ 20,000
−$ 5,000
Project 4 30 percent
30 percent
20 percent
20 percent
$ 40,000
$ 30,000
$ 20,000
−$50,000


Running Case

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

462
Key Terms
brainstorming
contingency allowances
contingency plans
contingency reserves
decision tree
Delphi technique
expected monetary value (EMV)
fallback plans
flowcharts
influence diagram
interviewing
known risks
management reserves
Monte Carlo analysis
probability/impact matrix or chart
residual risks
risk
risk acceptance
risk appetite
risk-averse
risk avoidance
risk breakdown structure
risk enhancement
risk events
risk exploitation
risk factors
risk management plan
risk mitigation
risk-neutral
risk owner
risk register
risk-seeking
risk sharing
risk tolerance
risk transference
risk utility
secondary risks
sensitivity analysis
Top Ten Risk Item Tracking
triggers
unknown risks
watch list
workarounds
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

463
Endnotes
Project
Management Journal

Issues in Informing Science
and Information Technology
Project Manager Today
PMI Global Congress Proceedings (2006).
PMI Global Congress Proceedings
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide),
StandishGroup.com
Software World
The Guardian
Creative Problem Solving and Opportunity Finding
support.office.com/en-ca/
article/Introduction-to-Monte-Carlo-simulation-64c0ba99-752a-4fa8-bbd3-4450d8db16f1
Project Management Journal
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R 12
PROJECT PROCUREMENT
MANAGEMENT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:




Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

466
12.1 THE IMPORTANCE OF PROJECT PROCUREMENT MANAGEMENT
Procurement means acquiring goods and services from an outside source. The term pro-
curement is widely used in government; many private companies use the terms purchas-
ing and outsourcing. Organizations or individuals who provide procurement services are
referred to as suppliers, vendors, contractors, subcontractors, or sellers; of these terms,
suppliers is the most widely used. Many IT projects involve the use of goods and ser-
vices from outside the organization. The Project Management Institute defines an outside
source as a source outside the project team, so the same organization can be a supplier to
the project team, or the project team can be a supplier to another group in the organiza-
tion. In fact, many IT departments in organizations are in direct competition with outside
vendors, and they are subject to the same kind of requirements definition, statements of
work, and bids. The rules and methods of sound project procurement practices are good
to follow regardless of who provides the services to whom.
As you learned in Chapter 2, outsourcing is a hot topic for research and debate, espe-
cially the implications of outsourcing to other countries, which is called offshoring. Gartner
estimated the value of the global IT industry in 2014 at $3.8 trillion, an increase of about
3.2 percent from 2013. The largest spending category is telecommunication services at
45 percent of the total or about $1.7 trillion.1 According to a study by the Center for Inter-
national Business Education (CIBER) and the International Offshoring Research Network’s
(ORN) Project at Duke University, the outsourcing market continues to grow:
U.S. companies are transferring more work abroad, especially in the areas of
IT infrastructure, application development and maintenance, and innovation
processes.
O P E N I N G C A S E
Marie McBride could not believe how much money her company was paying for out-
side consultants to help finish an important system conversion project. The consulting
company’s proposal said it would provide experienced professionals who had completed
similar conversions, and that the job would be finished in six months or less with four
consultants working full time. Nine months later her company was still paying high con-
sulting fees, and half of the original consultants on the project had been replaced with
new people. One new consultant had graduated from college only two months before
and had extremely poor communications skills. Marie’s internal staff complained that
they were wasting time training some of these “experienced professionals.” Marie talked
to her company’s purchasing manager about the contract, fees, and special clauses that
might be relevant to the problems they were having.
Marie was dismayed at how difficult it was to interpret the contract. It was very long
and obviously written by someone with a legal background. When she asked what her com-
pany could do because the consulting firm was not following its proposal, the purchasing
manager stated that the proposal was not part of the official contract. Marie’s company was
paying for time and materials, not specific deliverables. There was no clause stating the min-
imum experience level required for the consultants, nor were there penalty clauses for not
completing the work on time. There was a termination clause, however, meaning that the
company could terminate the contract. Marie wondered why her company had signed such
a poor contract. Was there a better way to procure services from outside the company?
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

467
India, China, and the Philippines are the preferred locations for outsourcing,
and Latin America is growing in popularity.
A shortage of qualified personnel, not cost savings, is the top reason for global
outsourcing of IT services.
According to Arie Lewin, director of CIBER, “For companies that are engaged
in offshoring, we’ve seen a significant jump in the number of respondents
who say offshoring activities have led to improved organizational flexibility.”2
G L O B A L I S S U E S
A recent approach to bringing IT jobs back to the U.S. is called urban onshoring. Soft-
ware testing in particular has sparked several organizations to work together to meet
the need for jobs in low income, high unemployment urban areas, improve quality and
efficiency, and reduce overseas costs. For example, Doran Jones Inc., a startup consult-
ing firm that does testing work for banks and media companies in Manhattan, partnered
with Per Scholas to create the first Urban Development Center (UDC) for software testing
projects. The UDC model develops the infrastructure, resources, and jobs in low-income
urban neighborhoods as part of a company’s Corporate Social Responsibility strategy. Per
Scholas is the oldest and largest professional IT workforce development program in New
York City. They provide technology education, training, and job placement services for
over 4,500 unemployed and low-income adults.
Several start-up companies are applying similar models in an effort to improve bleak
neighborhoods, like Hunts Point in the South Bronx. Startup Box, founded by husband
and wife team Majora Carter and James Chase, is initially focusing on quality assurance
testing for games and apps like Game Chaser. To recruit testers, they hold gaming tour-
naments in and around Hunts Point and provide feedback on the games to developers,
similar to a focus group.
Doran Jones Inc. and Startup Box do not want their work to be viewed as charity
projects. “As offshoring becomes more and more problematic in the ever-changing tech
world… on-shoring is a major market opportunity. They can make outsourcing more effi-
cient and diversify the talent pipeline in tech, in addition to bringing some much needed
jobs back to the US. Both Startup Box and Doran Jones have plans to replicate this urban
on shoring thing in other cities.”3
Politicians debate whether offshoring helps their own country or not. Andy Bork,
chief operating officer of a computer network service provider, described outsourcing
as an essential part of a healthy business diet. He described the idea of good versus bad
outsourcing as something like good versus bad cholesterol. He said that most people
view offshoring as being bad because it takes jobs away from domestic workers. How-
ever, many companies are realizing that they can use offshoring and create more jobs
at home. For example, Atlanta-based Delta Air Lines created 1,000 call-center jobs in
India in 2003, saving $25 million, which enabled it to add 1,200 jobs for reservations
and sales agents in the United States.4 Other companies, like Walmart, successfully man-
age the majority of their IT projects in-house with very little commercial software and
no outsourcing at all. Other organizations are moving IT services back in-house, such
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

468
as General Motors (GM). Randy Mott, the CIO of GM and former CIO of Walmart, Dell,
and Hewlett-Packard, overhauled GM’s IT operations and switched from outsourcing 90
percent of its IT services to only 10 percent from 2012–2015. See the What Went Right?
feature for a description of how Zulily uses in-house software development to provide a
competitive advantage.
W H A T W E N T R I G H T ?
Retailer Zulily is one of a growing number of organizations developing software in-house
to meet their need for speed and innovation. CIO Luke Friang said it would be nearly
impossible for off-the-shelf software to keep up with their pace. Zulily offers flash sales
where items are available for limited times only, and its website technology to track and
customize the shopping experience are an essential part of their business strategy. Other
companies gaining competitive advantages by developing innovative, in-house software
include General Motors and Tesla Motors Inc.
Zulily developed proprietary algorithms that track customers throughout the site and
quickly make adjustments to meet changing consumer preferences. The retailer, based
in Seattle, sends customers emails containing deals targeted to what they’ve bought from
the site and to their page viewing patterns. Zulily is also working on software to more
efficiently route merchandise within its fulfillment centers, and they are upgrading an
internal website it uses to exchange order information with vendors.
“ ‘You almost have to build the technology… from scratch because there won’t be
something out there on the market that fits perfectly,’ said Mr. Friang. Zulily’s sales
soared 97 percent to $285 million in one quarter, enabling the company to slightly raise
its forecast for 2014 sales to at least $1.2 billion, which would represent 74 percent
growth from last year. Zulily’s net income rose 94 percent to $7.8 million.”5
Deciding whether to outsource, what to outsource, and how to outsource are impor-
tant topics for many organizations throughout the world. Organizations are turning to
outsourcing to accomplish the following:
Access skills and technologies. Organizations can gain access to specific
skills and technologies when they are required by using outside resources. As
mentioned earlier, a shortage of qualified personnel is the main reason that
companies outsource IT services. A project may require experts in a particu-
lar field for several months, or it might require specific technologies from an
outside source. Planning for this procurement ensures that the needed skills
and technologies will be available for the project.
Reduce both fixed and recurrent costs. Outsourcing suppliers often can use
economies of scale that may not be available to the client alone, especially
for hardware and software. It can also be less expensive to outsource some la-
bor costs to other organizations in the same country or offshore. Companies
can use outsourcing to reduce labor costs on projects by avoiding the costs of
hiring, firing, and reassigning people to projects or paying their salaries when
they are between projects.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

469
Allow the client organization to focus on its core business. Most organiza-
tions are not in business to provide IT services, yet many have spent valuable
time and resources on IT functions when they should have focused on core
competencies such as marketing, customer service, and new product design.
By outsourcing many IT functions, employees can focus on jobs that are
critical to the success of the organization.
Provide flexibility. Outsourcing to provide extra staff during periods of peak
workloads can be much more economical than trying to staff entire projects
with internal resources. Many companies cite better flexibility in staffing as a
key reason for outsourcing. As you learned in Chapter 2, Apple says it could
not produce several of its products fast enough without outsourcing.
Increase accountability. A well-written contract—a mutually binding agree-
ment that obligates the seller to provide specified products or services and obli-
gates the buyer to pay for them—can clarify responsibilities and sharpen focus
on key deliverables of a project. Because contracts are legally binding, there is
more accountability for delivering the work as stated in the contract.
Organizations must also consider reasons they might not want to outsource. When an
organization outsources work, it often does not have as much control over the aspects of
projects that suppliers carry out. In addition, an organization could become too dependent
on particular suppliers. If those suppliers went out of business or lost key personnel, it could
cause great damage to a project. Organizations must also be careful to protect strategic infor-
mation that could become vulnerable in the hands of suppliers. According to Scott McNealy,
co-founder and former CEO of Sun Microsystems, Inc., “What you want to handle in-house
is the stuff that gives you an edge over your competition—your core competencies. I call it
your ‘secret sauce.’ If you’re on Wall Street and you have your own program for tracking and
analyzing the market, you’ll hang onto that. At Sun, we have a complex program for testing
microprocessor designs, and we’ll keep it.”6 Project teams must think carefully about procure-
ment issues and make wise decisions based on the unique needs of their projects and organi-
zations. They must also be aware of political issues, as described in the following example.
W H A T W E N T W R O N G ?
In 2011, New York City’s mayor, Michael Bloomberg, acknowledged that City Hall had
mismanaged its major IT projects and vowed to improve their oversight. He even said that
city administrators would not oppose legislation requiring them to alert the City Council
when projects ran into serious problems. These statements were made at a Council hear-
ing called in response to reports of troubled technology projects. For example, prosecu-
tors said the $700 million price tag for the CityTime payroll system was inflated by fraud,
and the mayor demanded $600 million back from the main contractor. The automated
personnel system, Nycaps, suffered significant delays and cost overruns due to leadership
issues, increasing from an original estimate of $66 million to over $363 million.
Caswell F. Holloway, the deputy mayor for operations, testified at the hearing
that the administration had begun an overhaul of how it manages complex technol-
ogy projects. He said it would seek more use of off-the-shelf software and avoid paying
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

470
consultants by the hour when it could specify completion of key deliverables for pay-
ment. He also said the city would stop letting individual agencies negotiate their own con-
tracts and bring in the city’s Law Department and the Mayor’s Office of Contract Services
to negotiate IT contracts worth more than $5 million.
“Other speakers at the hearing said that much of what Mr. Holloway was promising
to do was already written into city policy, to little effect. Henry Garrido, research director
for District Council 37, the municipal workers’ union, said a standard clause in the city’s
IT contracts allowed the city to sue contractors for damages. ‘But the city doesn’t exer-
cise it,’ he said.”7
Outsourcing can also cause problems in other areas for companies and nations as a
whole. For example, in 2004 many people in Australia were concerned about outsourc-
ing software development. “The Australian Computer Society says sending work offshore
may lower the number of students entering IT courses, deplete the number of skilled IT
professionals, and diminish the nation’s strategic technology capability. Another issue is
security, which encompasses the protection of intellectual property, integrity of data, and
the reliability of infrastructure in offshore locations.”8 A 2015 article stated that the job
market for IT workers in Australia did improve as several companies brought jobs back to
the country. The only downside was that pay increases were declining.9
The success of many IT projects that use outside resources is often due to good proj-
ect procurement management. Project procurement management includes the processes
required to acquire goods and services for a project from outside the performing organiza-
tion. Organizations can be either the buyer or seller of products or services under a con-
tract or other agreement.
There are four main processes in project procurement management:
1. Planning procurement management involves determining what to procure
and when and how to do it. In procurement planning, one must decide what
to outsource, determine the type of contract, and describe the work for po-
tential sellers. Sellers are providers, contractors, or suppliers who provide
goods and services to other organizations. Outputs of this process include a
procurement management plan, procurement statements of work, procure-
ment documents, source selection criteria, make-or-buy decisions, change
requests, and project documents updates.
2. Conducting procurements involves obtaining seller responses, selecting sell-
ers, and awarding contracts. Outputs include selected sellers, agreements,
resource calendars, change requests, and updates to the project management
plan and other project documents.
3. Controlling procurements involves managing relationships with sellers,
monitoring contract performance, and making changes as needed. The main
outputs of this process include work performance information, change re-
quests, and updates to the project management plan, project documents, and
organizational process assets.
4. Closing procurements involves completion and settlement of each contract
or agreement, including resolution of any open items. Outputs include closed
procurements and organizational process assets updates.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Figure 12-1 summarizes these processes and outputs, showing when they occur in a
typical project.
12.2 PLANNING PROCUREMENT MANAGEMENT
Planning procurements involves identifying which project needs can best be met by us-
ing products or services outside the organization. It involves deciding whether to procure,
how to procure, what to procure, how much to procure, and when to procure. An impor-
tant output of this process is the make-or-buy decision, in which an organization decides
whether it should make certain products and perform certain services inside the organiza-
tion, or if it is better to buy those products and services from an outside organization. If
there is no need to buy products or services from outside the organization, then further
procurement management is not needed.
Inputs needed for planning procurements include the project management plan, re-
quirements documentation, the risk register, activity resource requirements, the project
schedule, activity cost estimates, the stakeholder register, enterprise environmental fac-
tors, and organizational process assets, such as types of contracts.
12.2a Types of Contracts
Contract type is an important consideration in procurement management. Different types
of contracts can be used in different situations. Three broad categories of contracts are fixed
Planning
Process: Plan procurement management
Outputs: Procurement management plan, procurement statements of work,
procurement documents, source selection criteria, make-or-buy
decisions, change requests, project documents updates
Executing
Process: Conduct procurements
Outputs: Selected sellers, agreements, resource calendars, change requests,
project management plan updates, project documents updates
Monitoring and Controlling
Process: Control procurements
Outputs: Work performance information, change requests, project
management plan updates, project documents updates,
organizational process assets updates
Closing
Process: Close procurements
Outputs: Closed procurements, organizational process assets updates
Project Start Project Finish
FIGURE 12-1
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

price or lump sum, cost reimbursable, and time and material. A single contract can actually
include all three of these categories if it makes sense for a particular procurement. For ex-
ample, you could have a contract with a seller that includes purchasing specific hardware for
a fixed price or lump sum, some services that are provided on a cost-reimbursable basis, and
other services that are provided on a time-and-material basis. Project managers and their
teams must understand and decide which approaches to use to meet their project needs. It
is also important to understand when and how to take advantage of unit pricing in contracts.
Fixed-price or lump-sum contracts involve a fixed total price for a well-defined
product or service. The buyer incurs little risk in this situation because the price is
predetermined. The sellers often pad their estimate to reduce their risk, although they
realize their price must still be competitive. For example, a company could award a
fixed-price contract to purchase 100 laser printers with a certain print resolution and
print speed to be delivered to one location within two months. In this example, the
product and delivery date are well defined. Several sellers could create fixed-price
estimates for completing the job. Fixed-price contracts may also include incentives
for meeting or exceeding selected project objectives. For example, the contract could
include an incentive fee paid if the laser printers are delivered within one month. A
firm-fixed-price (FFP) contract has the least amount of risk for the buyer, followed by
a fixed-price incentive fee (FPIF) contract. A fixed-price with economic price adjust-
ment contract (FP-EPA) includes a special provision for predefined final adjustments to
the contract price due to changes in conditions such as inflation or the cost of specific
commodities. An FP-EPA contract is intended to protect both the buyer and seller from
external conditions beyond their control.
Contracts can also include incentives to prevent or reduce cost overruns. For
example, according to the U.S. Federal Acquisition Regulation (FAR) 16.4, fixed-price
incentive fee contracts can include a Point of Total Assumption (PTA), which is the
cost at which the contractor assumes total responsibility for each additional dollar of
contract cost. Contractors do not want to reach the PTA because it hurts them finan-
cially, so they have an incentive to prevent cost overruns. The PTA is calculated with the
following formula:
PTA 5 (ceiling price ] target price) ∕ government share 1 target cost
For example, given the following information, and assuming that all dollar amounts
are in millions, the PTA will be $1.2 million:
Ceiling price 5 $1,250
Target price 5 $1,100
Target cost 5 $1,000
Government share: 75percent
PTA 5 ($1,250 ] $1,100) ∕ .75 1 $1,000 5 $1,20010
Contracts for the U.S. federal government can be very complex. Consult FAR 16.4 and
similar references for more details.
Cost-reimbursable contracts involve payment to the supplier for direct and indirect
actual costs. Recall from Chapter 7 that direct costs can be directly related to producing
a project’s products and services. Normally, these costs can be traced back to a project in
a cost-effective way. Indirect costs are not directly related to the products or services of
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

473
the project, but they are indirectly related to performing the project. Normally, these costs
cannot be traced back to the project in a cost-effective way. For example, direct costs
include the salaries for people working directly on a project and hardware or software pur-
chased for a specific project. Indirect costs include the cost of providing a work space with
electricity and an employee cafeteria. Indirect costs are often calculated as a percentage of
direct costs. Cost-reimbursable contracts often include fees, such as a profit percentage or
incentives for meeting or exceeding selected project objectives. These contracts are often
used for projects that include providing goods and services that involve new technologies.
The buyer absorbs more of the risk with cost-reimbursable contracts than with fixed-price
contracts. Three types of cost-reimbursable contracts, in order of lowest to highest risk to
the buyer, include cost plus incentive fee, cost plus fixed fee, and cost plus percentage
of costs.
With a cost plus incentive fee (CPIF) contract, the buyer pays the supplier for
allowable costs (as defined in the contract) along with a predetermined fee and
an incentive bonus. See the Media Snapshot for an example of providing finan-
cial incentives to complete an important construction project ahead of schedule.
Also, incentives are often provided to suppliers for reducing contract costs. If the
final cost is less than the expected cost, both the buyer and the supplier benefit
from the cost savings, according to a negotiated share formula. For example,
suppose that the expected cost of a project is $100,000, the fee to the supplier
is $10,000, and the share formula is 85/15, meaning that the buyer absorbs 85
percent of the uncertainty and the supplier absorbs 15 percent. If the final cost is
$80,000, the cost savings are $20,000. The supplier would be paid the final cost
and the fee plus an incentive of $3,000 (15 percent of $20,000), for a total reim-
bursement of $93,000.
M E D I A S N A P S H O T
Contract incentives can be extremely effective. On August 1, 2007, tragedy struck
Minneapolis, Minnesota, when an Interstate bridge over the Mississippi River suddenly
collapsed, killing 13 motorists and injuring 150 people. The Minnesota Department of
Transportation (MnDOT) acted quickly to find a contractor to rebuild the bridge. MnDOT
also provided a strong incentive to finish the bridge as quickly as possible, ensuring
quality and safety along the way.
Peter Sanderson, project manager for the joint venture of Flatiron-Manson, led his
team in completing the rebuilding project three months ahead of schedule, and the new
bridge opened on September 18, 2008. The contractors earned $25 million in incentive
fees on top of their $234 million contract for completing the bridge ahead of schedule.
Why did MnDOT offer such a large incentive fee for finishing the project early?
“I-35W in Minneapolis is a major transportation artery for the Twin Cities and entire
state. Each day this bridge has been closed, it has cost road users more than $400,000,”
MnDOT Commissioner Tom Sorel remarked. “Area residents, business owners, motor-
ists, workers and others have been affected by this corridor’s closure. The opening of this
bridge reconnects our community.”11
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

474
With a cost plus fixed fee (CPFF) contract, the buyer pays the supplier for al-
lowable costs (as defined in the contract) plus a fixed fee payment that is usually
based on a percentage of estimated costs. This fee does not vary, however, un-
less the scope of the contract changes. For example, suppose that the expected
cost of a project is $100,000 and the fixed fee is $10,000. If the actual cost of the
contract rises to $120,000 and the scope of the contract remains the same, the
contractor will still receive the fee of $10,000.
With a cost plus award fee (CPAF) contract, the buyer pays the supplier
for allowable costs (as defined in the contract) plus an award fee based on
the satisfaction of subjective performance criteria. A tip or gratuity that you
would give a server in a restaurant would qualify as a simple example, as long
as there is no set gratuity percentage. You still pay for the cost of your meal,
but you can decide on the tip amount based on your satisfaction with the
food, drinks, and service provided. This type of contract is not usually sub-
ject to appeals.
With a cost plus percentage of costs (CPPC) contract, the buyer pays the
supplier for allowable costs (as defined in the contract) along with a prede-
termined percentage based on total costs. From the buyer’s perspective, this
is the least desirable type of contract because the supplier has no incentive
to decrease costs. In fact, the supplier may be motivated to increase costs,
because doing so will automatically increase profits based on the percentage
of costs. This type of contract is prohibited for U.S. government use, but it is
sometimes used in private industry, particularly in the construction industry.
All of the risk is borne by the buyer.
Time and material (T&M) contracts are a hybrid of fixed-price and cost-reimbursable
contracts. For example, an independent computer consultant might have a contract with
a company based on a fee of $80 per hour for services, plus a fixed price of $10,000 for
providing specific project materials. The materials fee might also be based on approved re-
ceipts for purchasing items, with a ceiling of $10,000. The consultant would send an invoice
to the company each week or month; the invoice would list the materials fee, the number
of hours worked, and a description of the work produced. This type of contract is often
used for required services when the work cannot be specified clearly and total costs cannot
be estimated in a contract. Many contract programmers and consultants, such as those Ma-
rie’s company hired in the chapter’s opening case, prefer time and material contracts.
Unit pricing can also be used in various types of contracts to require the buyer to pay
the supplier a predetermined amount per unit of product or service. The total value of the
contract is a function of the quantities needed to complete the work. Consider an IT de-
partment that might have a unit price contract for purchasing computer hardware. If the
company purchases only one unit, the cost might be $1,000. If the company purchases 10
units, the cost might be $10,000. This type of pricing often involves volume discounts. For
example, if the company purchases between 10 and 50 units, the contracted cost might
be $900 per unit. If the company purchases more than 50 units, the cost might go down
to $800 per unit. This flexible pricing strategy is often advantageous to both the buyer and
the seller.
Any type of contract should include specific clauses that account for unique proj-
ect issues. For example, if a company uses a time and material contract for consulting
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

475
services, the contract should stipulate different hourly rates based on the level of experi-
ence of the individual contractors. The services of a junior programmer with no Bachelor’s
degree and less than three years’ experience might be billed at $40 per hour, whereas the
services of a senior programmer with a Bachelor’s degree and more than 10 years of expe-
rience might be billed at $80 per hour.
Figure 12-2 summarizes the spectrum of risk to the buyer and supplier for different
types of contracts. Buyers have the least risk with firm-fixed price contracts, because they
know exactly what they must pay the supplier. Buyers have the most risk with cost plus per-
centage of costs (CPPC) contracts because they do not know the supplier’s costs in advance,
and the suppliers may be motivated to keep increasing costs. From the supplier’s perspective,
a CPPC contract carries the least risk and a firm-fixed price contract carries the most risk.
Time and material contracts and unit-price contracts can be high- or low-risk, de-
pending on the nature of the project and other contract clauses. For example, if an organi-
zation is unclear in describing the work that needs to be done, it cannot expect a supplier
to sign a firm-fixed price contract. However, the buyer could find a consultant or group
of consultants to work on specific tasks based on a predetermined hourly rate. The buy-
ing organization could evaluate the work produced each day or week to decide if it wants
to continue using the consultants. In this case, the contract would include a termination
clause—a contract clause that allows the buyer or supplier to end the contract. Some ter-
mination clauses state that the buyer can terminate a contract for any reason and give the
supplier only 24 hours’ notice. Suppliers, by contrast, must often give a one-week notice
to terminate a contract and must have sufficient reasons for the termination. The buyer
could also include a contract clause that specifies hourly rates based on the education and
experience of consultants. These contract clauses reduce the risk incurred by the buyer
while providing flexibility for accomplishing the work.
It is important to understand why a company would want to procure goods or services
and what inputs are needed to plan purchases and acquisitions. In the opening case,
Marie’s company hired outside consultants to help complete an operating system conver-
sion project because it needed people with specialized skills for a short period of time.
This is a common occurrence in many IT projects. It can be more effective to hire skilled
consultants to perform specific tasks for a short period of time than to hire or keep em-
ployees on staff full time.
Seller risk
CPPC
Cost plus
percentage
of costs
CPFF
Cost plus
fixed fee
CPIF
Cost plus
incentive
fee
FPI
Fixed
price
incentive
FP-EPA
Fixed price
economic
price
adjustment
FFP
Firm-
fixed
price
Buyer risk
CPAF
Cost plus
award fee
lowhigh
low high
FIGURE 12-2
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

476
However, it is also important to define clearly the scope of the project, the products,
services, or results required, market conditions, and constraints and assumptions. In
Marie’s case, the scope of the project and services required were relatively clear, but her
company may not have adequately defined the market conditions or constraints and
assumptions involved in using outside consultants. Could other companies provide con-
sultants to help with similar conversion projects? Did the project team investigate the
background of the company that provided the consultants? Did the team list important
constraints and assumptions for using the consultants, such as limiting the time that the
consultants had to complete the conversion project or the minimum years of experience
for any consultant assigned to the project? It is important to answer these types of ques-
tions before signing an outsourcing agreement.
12.2b Tools and Techniques for Planning Procurement Management
Several tools and techniques are available to help project managers and their teams in
planning procurement management, including make-or-buy analysis, expert judgment,
and market research.
Make-or-Buy Analysis
Make-or-buy analysis is a general management technique used to determine whether an
organization should make a product or perform a service inside the organization or buy it
from someone else. This form of analysis involves estimating the internal costs of provid-
ing a product or service and comparing the estimate to the cost of outsourcing. Consider
a company that has 1,000 international salespeople with laptops. Using make-or-buy anal-
ysis, the company could compare the cost of providing those services using internal re-
sources to the cost of buying the same services from an outside source. If supplier quotes
were less than the company’s internal estimates, the company would have to consider
outsourcing the training and user support services. Another common make-or-buy deci-
sion, though more complex, is whether a company should develop an application itself or
purchase software from an outside source and customize it to the company’s needs.
Many organizations also use make-or-buy analysis to decide whether to purchase or
lease items for a project. For example, suppose that a project requires a piece of equipment
that has a purchase price of $12,000 and daily operating costs of $400. Suppose that you
could lease the same piece of equipment for $800 per day, including the operating costs.
You can set up an equation so that you can see when the purchase cost equals the lease
cost and determine when it makes sense financially to lease or buy the equipment. In this
example, d is the number of days you need the piece of equipment. The equation would be:
$800 /day 5 $12,000 1 $400 /day
Subtracting $400 /day from both sides, you get:
$400 /day 5 $12,000
Dividing both sides by $400, you get:
d 5 30
In other words, the purchase cost would equal the lease cost in 30 days. So, if you
need the equipment for less than 30 days, leasing would be more economical. If you need
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

477
the equipment for more than 30 days, you should purchase it. In general, leasing is
often cheaper for meeting short-term needs, but more expensive for long-term needs.
Expert Judgment
Experts both from inside and outside an organization can provide excellent advice in
planning purchases and acquisitions. Project teams often need to consult experts within
their organization as part of good business practice. Internal experts might suggest that the
company in the preceding example could not provide training and support for the 1,000 lap-
top users because the service involves so many people with different skill levels in so many
different locations. Experts in the company might also know that most of their competitors
outsource this type of work and know who the qualified outside suppliers are. It is also im-
portant to consult legal experts because contracts for outsourced work are legal agreements.
Experts outside the company, including potential suppliers themselves, can also pro-
vide expert judgment. For example, suppliers might suggest an option for salespeople to
purchase the laptops themselves at a reduced cost. This option would solve problems that
would otherwise be created during employee turnover—exiting employees would own
their laptops and new employees would purchase a laptop through the program. An inter-
nal expert might then suggest that employees receive a technology bonus to help offset
what they might view as an added expense. Expert judgment, both internal and external,
is an asset in making many procurement decisions.
Market Research
Market research is very important in planning procurements. Many potential suppliers are
often available for goods and services, so the project team must choose suppliers carefully.
Some organizations have a preferred vendor list and detailed information about them. A
wealth of information is also available online, and numerous conferences are held where
attendees can see and discuss new products.
In addition to make-or-buy decisions, change requests, and project documents up-
dates, important outputs of planning procurements are a procurement management plan,
statement of work, procurement documents such as requests for proposals or quotes, and
source selection criteria.
12.2c Procurement Management Plan
As you have learned, every project management knowledge area includes some planning.
The procurement management plan is a document that describes how the procurement
processes will be managed, from developing documentation for making outside purchases
or acquisitions to contract closure. Like other project plans, contents of the procurement
management plan will vary with project needs. The following materials can be included in
a procurement management plan:
Guidelines for types of contracts to be used in different situations
Standard procurement documents or templates to be used, if applicable
Guidelines for creating contract work breakdown structures, statements of
work, and other procurement documents
Roles and responsibilities of the project team and related departments, such
as the purchasing or legal department
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

478
Guidelines for using independent estimates to evaluate sellers
Suggestions for managing multiple providers
Processes for coordinating procurement decisions with other project areas,
such as scheduling and performance reporting
Constraints and assumptions related to purchases and acquisitions
Lead times for purchases and acquisitions
Risk mitigation strategies for purchases and acquisitions, such as insurance
contracts and bonds
Guidelines for identifying prequalified sellers and organizational lists of
preferred sellers
Procurement metrics to assist in evaluating sellers and managing contracts
12.2d Statement of Work
The statement of work (SOW) is a description of the work required for the procure-
ment. Some organizations use the term statement of work for a document that de-
scribes internal work as well. If a SOW is used to describe only the work required for
a particular contract, it is called a contract statement of work. The contract SOW is a
type of scope statement that describes the work in sufficient detail to allow prospective
suppliers to determine if they can provide the required goods and services and to deter-
mine an appropriate price. A contract SOW should be clear, concise, and as complete as
possible. It should describe all services required and include performance reporting. It is
important to use appropriate wording in a contract SOW, such as must instead of may.
For example, must means that something has to be done; may implies that a choice is
involved in doing something or not. The contract SOW should specify the products and
services required for the project, use industry terms, and refer to industry standards.
Many organizations use samples and templates to generate SOWs. Figure 12-3
provides a basic outline or template for a contract SOW that Marie’s organization
could use when hiring outside consultants or purchasing other goods or services. For
example, for the operating system conversion project, Marie’s company should specify
the manufacturer and model number for the hardware involved, the former operating
systems and new ones for the conversion, and the number of pieces of each type of
hardware involved. The contract SOW should also specify the location of the work, the
expected period of performance, specific deliverables and when they are due, applicable
standards, acceptance criteria, and special requirements. A good contract SOW gives
bidders a better understanding of the buyer’s expectations. A contract SOW should be-
come part of the official contract to ensure that the buyer gets what the supplier bid on.
12.2e Procurement Documents
Planning procurements also involves preparing the documents needed for potential sell-
ers to bid on a project and determining the evaluation criteria for the contract award. The
project team often uses standard forms and expert judgment as tools to help create rel-
evant procurement documents and evaluation criteria.
Two common examples of procurement documents include a Request for Proposal
(RFP) and a Request for Quote (RFQ). A Request for Proposal (RFP) is a document
used to solicit proposals from prospective suppliers. A proposal is a document prepared
by a seller when there are different approaches for meeting buyer needs. For example, if
an organization wants to automate its work practices or solve a business problem, it can
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

479
write and issue an RFP so suppliers can respond with proposals. Suppliers might pro-
pose various hardware, software, and networking solutions to meet the organization’s
need. Selections of winning sellers are often made on a variety of criteria, not just the
lowest price. Developing an RFP is often a time-consuming process. Organizations must
plan properly to ensure that they adequately describe what they want to procure, what
they want sellers to include in their proposals, and how they will evaluate proposals.
Although RFPs have been used for many years, outsourcing experts say the process is
becoming less appealing in several IT procurement processes. “In today’s dynamic era of
technology change, the traditional RFP simply takes too long and costs too much. By the time
the proposals come in, the business requirements have often changed.”12 Enterprise mar-
ketplaces, such as app stores that provide a collection of software and services for sale (i.e.,
Google Play, App Store, and IBM Cloud Marketplace) and other new purchasing processes will
emerge as companies collaborate with service providers to figure out better IT solutions.
A Request for Quote (RFQ) is a document used to solicit quotes or bids from pro-
spective suppliers. A bid, also called a tender or quote (short for quotation), is a document
Statement of Work (SOW)
I . Scope of Work: Describe the work to be done in detail. Specify the hardware
and software involved and the exact nature of the work.
I I . Location of Work: Describe where the work must be performed. Specify the
location of hardware and software and where the people must perform the work.
I I I . Period of Performance: Specify when the work is expected to start and end,
working hours, number of hours that can be billed per week, where the work must
be performed, and related schedule information.
I V. Deliverables Schedule: List specific deliverables, describe them in detail, and
specify when they are due.
V. Applicable Standards: Specify any company or industry-specific standards that
are relevant to performing the work.
V I . Acceptance Criteria: Describe how the buyer organization will determine if the
work is acceptable.
V I I . Special Requirements: Specify any special requirements such as hardware or
software certifications, minimum degree or experience level of personnel, travel
requirements, and so on.
FIGURE 12-3
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

480
prepared by sellers to provide pricing for standard items that the buyer has clearly
defined. Organizations often use an RFQ for solicitations that involve specific items. For
example, if a company wanted to purchase 100 personal computers with specific features,
it might issue an RFQ to potential suppliers. RFQs usually do not take nearly as long to
prepare as RFPs, nor do responses to RFQs. Selections are often based on the lowest bid.
Writing a good RFP is a critical part of project procurement management, but many
people have never had to write or respond to one. To generate a good RFP, expertise is in-
valuable. Many examples of RFPs are available within different companies, from potential
contractors, and from government agencies. Legal requirements are often involved in is-
suing RFPs and reviewing proposals, especially for government projects. It is important to
consult with experts who know the contract planning process for particular organizations.
To make sure that an RFP has enough information to provide the basis for a good proposal,
the buying organization should try to put itself in the suppliers’ shoes. Could the organiza-
tion develop a good proposal based on the information it provided in the RFP? Could it
determine detailed pricing and schedule information based on the RFP? Developing a good
RFP is difficult, as is writing a good proposal.
Figure 12-4 provides a basic outline or template for an RFP. The main sections of an
RFP usually include its statement of purpose, background information on the organization
FIGURE 12-4
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

issuing the RFP, the basic requirements for the products and services being proposed, the
hardware and software environment (which is usually important for IT-related propos-
als), a description of the RFP process, the statement of work and schedule information,
and possible appendices. A simple RFP might be three to five pages long, but an RFP for a
larger, more complicated procurement might take hundreds of pages.
Other terms used for RFQs and RFPs include invitations for bid, invitations for nego-
tiation, and initial contractor responses. Regardless of what they are called, all procure-
ment documents should be written to facilitate accurate and complete responses from
prospective sellers. Procurement documents should include background information on
the organization and project, a relevant statement of work, a schedule, a description of the
desired form of response, evaluation criteria, pricing forms, and any required contractual
provisions. The documents should also be rigorous enough to ensure consistent, compa-
rable responses, but flexible enough to allow consideration of sellers’ suggestions for better
ways to satisfy the requirements.
12.2f Source Selection Criteria
It is very important for organizations to prepare some form of evaluation criteria for
source selection, preferably before they issue a formal RFP. Organizations use criteria to
rate or score proposals, and they often assign a weight to each criterion to indicate its im-
portance. Some examples of criteria and weights include the technical approach (30 per-
cent weight), management approach (30 percent weight), past performance (20 percent
weight), and price (20 percent weight). The criteria should be specific and objective. For
example, if the buyer wants the supplier’s project manager to be a certified Project Man-
agement Professional (PMP), the procurement documents should state that requirement
clearly and follow it during the award process. Losing bidders may pursue legal recourse if
the buyer does not follow a fair and consistent evaluation process.
Organizations should heed the saying, “Let the buyer beware.” It is critical to evaluate
proposals based on more than the professionalism of the paperwork submitted. A key factor
in evaluating bids, particularly for projects involving IT, is the past performance record of
the bidder. The RFP should require bidders to list other similar projects they have worked
on and provide customer references for those projects. Reviewing performance records and
references reduces the risk of selecting a supplier with a poor track record. Suppliers should
also demonstrate their understanding of the buyer’s need, their technical and financial capa-
bilities, their management approach to the project, and their price for delivering the desired
goods and services. It is also crucial to write the contract to protect the buyer’s interests.
Some IT projects also require potential sellers to deliver a technical presentation as part
of their proposal. The proposed project manager should lead the potential seller’s presentation
team. When the outside project manager leads the proposal presentation, the organization
can build a relationship with the potential seller from the beginning. Visits to contractor sites
can also help the buyer get a better feeling for the seller’s capabilities and management style.
12.3 CONDUCTING PROCUREMENTS
After planning for procurement management, the next process involves deciding whom to
ask to do the work, sending appropriate documentation to potential sellers, obtaining pro-
posals or bids, selecting a seller, and awarding a contract. Prospective sellers do some of
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

the work in this process, normally at no cost to the buyer or project. The buying organiza-
tion is responsible for advertising the work, and for large procurements, the organization
often holds some sort of bidders’ conference to answer questions about the job. Two of the
main outputs of this process are a selected seller and procurement contract award.
Organizations can advertise to procure outside goods and services in many different
ways. Sometimes a specific supplier might be the top choice for the buyer. In this case,
the buyer gives procurement information just to that company. If the preferred supplier
responds favorably, the organizations proceed to work together. Many organizations have
formed good working relationships with certain suppliers.
In many cases, however, more than one supplier might be qualified to provide the
goods and services. Providing information to multiple sources and receiving bids from
them often takes advantage of the competitive business environment. Offshore outsourc-
ing, as you learned earlier, has increased tremendously as organizations find suitable sell-
ers around the globe. As a result of pursuing a competitive bidding strategy, the buyer can
receive better goods and services than expected at a lower price.
A bidders’ conference, also called a supplier conference or pre-bid conference, is a
meeting with prospective sellers prior to preparation of their proposals or bids. These con-
ferences help ensure that everyone has a clear, common understanding of the buyer’s de-
sired products or services. In some cases, the bidders’ conference might be held online via
a webcast or using other communications technology. Buyers will also post procurement
information on a website and post answers to frequently asked questions. Before, during,
or after the bidders’ conference, the buyer may incorporate responses to questions into
the procurement documents as amendments.
Once buyers receive proposals or bids, they can select a supplier or decide to cancel
the procurement. Selecting suppliers or sellers, often called source selection, involves
evaluating proposals or bids from sellers, choosing the best one, negotiating the contract,
and awarding the contract. It can be a long, tedious process, especially for large procure-
ments. Several stakeholders in the procurement process should be involved in selecting
the best supplier for the project. Often, teams of people are responsible for evaluating vari-
ous sections of the proposals. There might be a technical team, a management team, and
a cost team to focus on each major area. Buyers typically develop a short list of the top
three to five suppliers to reduce the work involved in selecting a source.
Experts in source selection highly recommend that buyers use formal proposal evalu-
ation sheets during source selection. Figure 12-5 provides a sample proposal evaluation
sheet that the project team might use to help create a short list of the best three to five
proposals. Notice that this example is a form of a weighted scoring model, as described in
Chapter 4, Project Integration Management. To calculate the score for a criterion, multiply
the weight of the criterion by the rating for the proposal. Add the scores to provide the
total weighted score for each proposal. The proposals with the highest weighted scores
should be included in the short list of possible sellers. Experts also recommend that tech-
nical criteria should not be given more weight than management or cost criteria. Many
organizations have suffered the consequences of paying too much attention to the techni-
cal aspects of proposals. For example, the project might cost much more than expected
or take longer to complete because the source selection team focused only on technical
aspects of proposals. Paying too much attention to these technical aspects is especially
likely to occur on IT projects. However, it is often the supplier’s management team—not
the technical team—that makes procurement successful.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

483After developing a short list of possible sellers, organizations often follow a more de-
tailed proposal evaluation process. For example, they might list more detailed criteria for
important categories, such as the management approach. They might assign points for
the potential project manager’s educational background and PMP certification, the seller’s
formal presentation if it was part of the evaluation process, top management support for
the project, and the organization’s project management methodologies. If the criteria and
evaluation are done well, the seller with the most points based on all of the criteria should
be offered the contract.
It is customary to have contract negotiations during the source selection process. Sell-
ers on the short list are often asked to prepare a best and final offer (BAFO). In addition, top
managers from both the buying and selling organizations usually meet before making final
decisions. The final output is a contract that obligates the seller to provide the specified prod-
ucts or services and obligates the buyer to pay for them. For some projects, it is also appropri-
ate to prepare a contract management plan that describes how the contract will be managed.
12.4 CONTROLLING PROCUREMENTS
Controlling procurements ensures that the seller’s performance meets contractual require-
ments. The contractual relationship is a legal relationship, which means it is subject to
state and federal contract laws. It is very important that appropriate legal and contracting
professionals be involved in writing and administering contracts.
Ideally, the project manager, a project team member, or an active user in the project
should help write and administer the contract, so that everyone understands the impor-
tance of good procurement management. The project team should also seek expert advice
when working with contractual issues. Project team members must be aware of potential
legal problems they might cause by not understanding a contract. For example, most
projects involve changes, and these changes must be handled properly for items under
contract. Without understanding the provisions of the contract, a project manager may
unknowingly authorize a contractor to do additional work at greater costs. Therefore,
change control is an important part of the contract administration process.
FIGURE 12-5
Proposal 1
Criteria Weight Rating Score
Proposal 2
Rating Score
Proposal 3, etc.
Rating Score
Technical
approach
Management
approach
Past
performance
Price
Total score
30%
30%
20%
20%
100%
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

484
It is critical that project managers and team members watch for constructive change
orders. Constructive change orders are oral or written acts or omissions by someone with
actual or apparent authority that can be construed to have the same effect as a written
change order. For example, if a member of the buyer’s project team has met with the con-
tractor on a weekly basis for three months to provide guidelines for performing work, the
team member can be viewed as an apparent authority. If the team member tells the con-
tractor to redo part of a report that has already been delivered and accepted by the project
manager, the action can be viewed as a constructive change order and the contractor can
legally bill the buyer for the additional work. Likewise, if the apparent authority tells the
contractor to skip parts of a critical review meeting in the interests of time, the omission
of that information is not the contractor’s fault.
It is important to follow other good practices related to project procurement:
Changes to any part of the project need to be reviewed, approved, and docu-
mented by the same people in the same way they approved the original part of
the plan.
Evaluation of any change should include an impact analysis. How will the
change affect the scope, time, cost, and quality of the goods or services being
provided? There must also be a baseline to understand and analyze changes.
Changes must be documented in writing. Project team members should docu-
ment all important meetings and telephone calls.
When procuring complex information systems, project managers and their
teams must stay closely involved to make sure the new system will meet
business needs and work in an operational environment. Do not assume that
everything will go well because you hired a reputable supplier. The buying
organization needs to provide expertise as well.
Have backup plans in case the new system does not work as planned.
Several tools and techniques can help in contract administration, such as a
formal contract change control system, buyer-conducted procurement per-
formance reviews, inspections and audits, performance reporting, payment
systems, claims administration, and records management systems.
12.5 CLOSING PROCUREMENTS
The final process in project procurement management is closing procurements, which
is sometimes referred to as contract closure. Contract closure involves completion
and settlement of contracts and resolution of any open items. The project team should
determine if all work required in each contract was completed correctly and satisfacto-
rily. The contract itself should include requirements for formal acceptance and closure.
The team should also update records to reflect final results and archive information for
future use.
Tools to assist in contract closure include procurement audits, negotiated settlements,
and a records management system. Procurement audits are often done during contract
closure to identify lessons learned in the entire procurement process. A records manage-
ment system provides the ability to easily organize, find, and archive procurement-related
documents. It is often an automated system, or at least partially automated, because a
large amount of information can be related to project procurement.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

485
Ideally, all procurements should end in a negotiated settlement between the buyer
and seller. If negotiation is not possible, then some type of alternate dispute resolution
such as mediation or arbitration can be used; if all else fails, litigation in courts can be
used to settle contracts.
Archiving information for future use is particularly important. Organizations should
strive to improve all of their business processes, including procurement management.
Archiving information, particularly in an automated records management system,
supports efforts to improve procurement management.
Outputs from contract closure include closed procurements and updates to organiza-
tional process assets. The buying organization often provides the seller with formal written
notice that the contract has been completed.
12.6 USING SOFTWARE TO ASSIST IN PROJECT
PROCUREMENT MANAGEMENT
Over the years, organizations have used various types of productivity software to assist in
project procurement management. For example, most organizations use word-processing
software to write proposals or contracts, spreadsheet software to create proposal evalua-
tion worksheets, databases to track suppliers, and presentation software to present pro-
curement-related information.
Many companies are now using more advanced software to assist in procurement
management. The term e-procurement often describes various procurement functions
that are now done electronically, as follows:
B E S T P R A C T I C E
In today’s fast-changing competitive environment, it isn’t enough to follow traditional
procurement best practices. Instead, find innovative ways to improve the procurement
process. Mining completely different functional areas and technologies is a great way to
discover ideas that can be used to improve procurement. “Supply market intelligence
starts from procurement being intelligent about how business requirements can be
matched intelligently to what supply markets can offer. So, the greater your diversity of
knowledge of solutions from far flung areas, the better you’ll be able to match supply
[solutions] to demand [requirements].” The following examples illustrate some ideas of
how to make procurement more intelligent:
Data scientists build predictive models to analyze big data related to finance,
marketing, etc. Why not model procurement processes?
Behavioral economists know that people do not act rationally. Why not apply
irrationality to your advantage in negotiations?
Quality control/assurance departments encourage employees to suggest quality
improvements all the time. Why not enable your workers to be on the lookout
for additional new and innovative suppliers?
Crowdsourcing solicits ideas from a large group of people. Can it apply to some
of your organization’s procurements?13
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

486
Web-based ERP (Electronic Resource Planning): Creating and approving pur-
chasing requisitions, placing purchase orders, and receiving goods and services
by using a software system based on Internet technology.
E-MRO (Maintenance, Repair, and Overhaul): The same as web-based ERP,
except that the goods and services ordered are MRO supplies that are not
related to a particular product.
E-sourcing: Identifying new suppliers for a specific category of purchasing
requirements using Internet technology.
E-tendering: Sending requests for information and prices to suppliers and
receiving the responses of suppliers using Internet technology.
E-reverse auctioning: Using Internet technology to buy goods and services
from a number of known or unknown suppliers.
E-informing: Gathering and distributing purchasing information with inter-
nal and external parties using Internet technology.
E-marketsites: Expands on web-based ERP to open up value chains. Buying
communities can access preferred suppliers’ products and services, add to
shopping carts, create requisitions, seek approval, receive purchase orders,
and process electronic invoices with integration to suppliers’ supply chains
and buyers’ financial systems.
Many websites and software tools can assist in procurement functions. For example,
most business travelers use the web to purchase airline tickets and to reserve rental cars
and hotel rooms for business trips. With the rise of applications for smartphones, shoppers
can even take pictures of barcodes on all types of products and compare prices of compet-
ing stores to confirm that they are getting the best deal. Likewise, many organizations can
purchase items online, or they can buy specialized software to help streamline their pro-
curement activities.
One type of software that is particularly useful for streamlining procurement is the
procure-to-pay suite, which provides support for indirect procurements. Unlike direct
procurement, where procurement experts in organizations acquire raw materials and
goods for production or services related to their organization’s primary business, indirect
procurement involves acquiring supplies and services required to keep the day-to-day
business functioning, such as equipment repairs, office supplies, and services related to
keeping business processes running. According to Gartner, the procurement process has
evolved from paper-intensive order processing to a strategic enterprise function. Their
qualitative analysis of the procure-to-pay suites market makes the point that because
self-service software tools are available, employees at all levels of an organization can buy
goods and services without the need for professional procurement expertise. This stream-
lines the process for indirect procurements, so that procurement experts can focus on the
more strategic direct procurements. The four main capabilities of procure-to-pay suites for
indirect procurements include:
E-purchasing functionality: Provides a self-service solution to requisition and
order goods and services through the use of catalogs, e-forms, or free-text orders
(for when users cannot find items in a structured format).
Catalog management capabilities: Includes catalog content upload, content
update evaluation tools, and catalog search tools.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

487
E-invoicing: Enables the interchange and storage of legally valid invoices in
electronic format.
Accounts Payable Invoice Automation (APIA): Allows approval and control
of incoming invoices through either automatic or manual approvals by auto-
matic workflows.
At current software suite prices, organizations with annual revenues of $800 million
or more usually realize a good return on investment from using these tools. Gartner’s re-
search identified Ariba (SAP), Coupa, Basware, and SciQuest as market leaders in 2015.14
Organizations can also take advantage of information available on the web, in industry
publications, or in various discussion groups offering advice on selecting suppliers. For exam-
ple, many organizations invest millions of dollars in enterprise project management software.
Before deciding which seller’s software to use, organizations use the Internet to find product in-
formation provided by various suppliers, prices, case studies, and current customers to assist in
making procurement decisions. Buyers can also use the Internet to hold bidders’ conferences,
as you learned earlier in this chapter, or to communicate procurement-related information.
As with any information or software tool, organizations must focus on using the informa-
tion and tools to meet project and organizational needs. Many nontechnical issues are often
involved in getting the most value out of new technologies, especially new e-procurement
software. For example, organizations must often develop partnerships and strategic alliances
with other organizations to take advantage of potential cost savings. Organizations should
practice good procurement management in selecting new software tools and managing
relationships with the chosen suppliers.
The processes of project procurement management follow a clear, logical sequence.
However, many project managers are not familiar with the issues involved in purchasing
goods and services from other organizations. If projects will benefit by procuring goods or
services, then project managers and their teams must follow good project procurement
management. As outsourcing for IT projects increases, it is important for all project
managers to have a fundamental understanding of this knowledge area.
C A S E W R A P – U P
After reading the contract for her company’s consultants carefully, Marie McBride found
a clause giving her company the right to terminate the contract with a one-week notice.
She met with her project team to get suggestions. The team still needed help completing
the system conversion project. One team member had a friend who worked for a compet-
ing consulting firm. The competing firm had experienced people available, and their fees
were lower than those in the current contract. Marie asked this team member to help her
research other consulting firms that could work on the conversion project. She then re-
quested bids from these companies. She personally interviewed people from the top three
suppliers’ management teams and checked their references for similar projects.
Marie worked with the purchasing department to terminate the original contract and
issue a new one with a new consulting firm that had a much better reputation and lower
hourly rates. This time, she made certain the contract included a statement of work, specific
deliverables, and requirements for the minimum experience level of consultants provided.
The contract also included incentive fees for completing the conversion work within a certain
time period. Marie had learned the importance of good project procurement management.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

488
Chapter Summary









Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

489
Quick Quiz

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

490
Quick Quiz Answers
Discussion Questions

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.


Exercises
IT outsourcing





Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Running Case




Key Terms
bid
constructive change orders
contract
cost plus award fee (CPAF) contract
cost plus fixed fee (CPFF) contract
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

493
cost plus incentive fee (CPIF) contract
cost plus percentage of costs (CPPC)
contract
cost-reimbursable contracts
fixed-price contract
lump-sum contract
make-or-buy decision
Point of Total Assumption (PTA)
procurement
project procurement management
proposal
Request for Proposal (RFP)
Request for Quote (RFQ)
sellers
statement of work (SOW)
termination clause
time and material (T&M) contracts
unit pricing
End Notes
3
wired.com
4 Minneapolis Star Tribune
5
CIO Journal Wall Street Journal blogs.wsj.com/cio/2014/08/08/
zulily-calls-in-house-software-a-differentiator-for-competitive-advantage/.
6 Sun
Executive Perspectives, www.sun.com/dot-com/perspectives/stop.html –
7 The New York
Times
8 The Age
9
Business Insider Australia
WIFCON.com
ConstructionEquipmentGuide.com
CIO.com
Chief Procurement Officer spendmatters.com/cpo/procurement-must
-stretch-beyond-procurement-best-practices/
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C H A P T E R 13
PROJECT STAKEHOLDER
MANAGEMENT
L E A R N I N G O B J E C T I V E S
After reading this chapter, you will be able to:


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

496
13.1 THE IMPORTANCE OF PROJECT STAKEHOLDER
MANAGEMENT
As you learned in Chapter 1, stakeholders are an important part of the project manage-
ment framework. Stakeholders request projects, approve them, reject them, support them,
and oppose them. Because stakeholder management is so important to project success,
the Project Management Institute decided to create an entire knowledge area devoted to it
as part of the Fifth Edition of the PMBOK® Guide in 2013. Many of the concepts related
to communications and human resource management also apply to stakeholder manage-
ment, but unique activities are required to perform good stakeholder management. The
purpose of project stakeholder management is to identify all people or organizations af-
fected by a project, to analyze stakeholder expectations, and to effectively engage stake-
holders in project decisions throughout the life of a project. Project managers and their
teams must have a good dialogue with stakeholders and address issues as they occur to
ensure stakeholder satisfaction.
Projects often cause changes in organizations, and some people may lose their jobs
when a project is completed. For example, a project might create a new system that
makes some jobs obsolete, or a project might result in outsourcing work to an external
O P E N I N G C A S E
Debra Hughes took the risk of becoming an independent consultant after working her
way up the corporate ladder for 10 years. Her last firm was downsizing and cut her entire
strategic IT consulting department, but the firm offered her a transfer that would require
her to travel about 80 percent of the time. With two small children, she did not want to
travel, so she jumped at the chance to work independently. One of her colleagues knew
an IT director at a local oil company, and he offered her a contract that paid three times
what she received as an employee. The problem was that the initial contract was only
for two weeks. However, after she proved her value by successfully managing the first
project, the company kept her on, giving her bigger and bigger projects to manage. Her
current project was to evaluate and then implement a project management software
solution so the new VP of Operations, Stephen, could oversee the upgrade of oil refiner-
ies in several countries. The refinery upgrades were estimated to cost over $200 million.
Debra worked with an internal analyst, Ryan, and Stephen to determine requirements
and their approach to choosing a new software solution. They needed to award a con-
tract to a supplier within two months and then integrate the new system with their other
systems, especially the accounting systems, as quickly as possible.
Unfortunately, Chien, the IT director who hired Debra and authorized her paycheck
every week, was very upset with her recommendation. He called her into his office and
started yelling at her. “How could you make this recommendation? You know it goes
against what I think is best for IT at this company. Ryan made a totally different recom-
mendation than you did. You consultants think you can come in and shake things up, not
worrying about what happens to us after you’re gone. Get out of here before I say some-
thing I shouldn’t!” Debra quietly left Chien’s office, worrying about what to do next. She
knew that her recommendation would please Stephen and be in the best interest of the
entire company, even though it was not the choice that Chien and Ryan were promoting.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

497
group to make the organization more efficient. The project managers might be viewed as
enemies by these stakeholders and other negatively affected stakeholders. By contrast,
some people may view project managers as allies if they lead a project that increases prof-
its, produces new jobs, or increases pay for certain stakeholders. In any case, project man-
agers must learn to identify, understand, and work with a variety of stakeholders.
W H A T W E N T W R O N G ?
Changing the way work is done can send a shock wave through an organization, leaving
many people afraid and even thinking about ways to stop or sabotage a project. Donald
White, founder and program manager at Defense Systems Leaders in Washington, D.C.,
described situations that can lead to project sabotage:
Buy-in blues: Top-down support and early buy-in for projects is crucial.
Allowing negativity to fester will decrease the likelihood of project success.
Deal with protesters early.
Short-term profits: Cutting costs by any means possible for immediate payoff
will sacrifice the future health of an organization and its employees. Avoid
projects that focus only on the short term.
Overachieving: Trying to do too many things at the same time introduces waste
and significantly slows down progress. Focus on the most important projects first.
Lack of respect: “Disrespect people, and they will retaliate with apathy, bore-
dom, absenteeism, make-work [performing tasks of little importance to keep
busy], outright sabotage and other maladies. Disrespect customers, and they’ll
find someone who will treat them better.”1
The four processes in project stakeholder management include the following:
1. Identifying stakeholders involves identifying everyone involved in the project
or affected by it and determining the best ways to manage relationships with
them. The main output of this process is a stakeholder register.
2. Planning stakeholder management involves determining strategies to effec-
tively engage stakeholders in project decisions and activities based on their
needs, interests, and potential impact. Outputs of this process are a stake-
holder management plan and project documents updates.
3. Managing stakeholder engagement involves communicating and working with
project stakeholders to satisfy their needs and expectations, resolving issues,
and fostering engagement in project decisions and activities. The outputs of
this process are issue logs, change requests, project management plan up-
dates, project documents updates, and organizational process assets updates.
4. Controlling stakeholder engagement involves monitoring stakeholder relation-
ships and adjusting plans and strategies for engaging stakeholders as needed.
Outputs of this process are work performance information, change requests,
project documents updates, and organizational process assets updates.
Figure 13-1 summarizes these processes and outputs, showing when they occur in a
typical project.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

498
13.2 IDENTIFYING STAKEHOLDERS
Recall from Chapter 1 that stakeholders are the people involved in project activities or af-
fected by them. The PMBOK® Guide, Fifth Edition, expands on this definition as follows:
“Project stakeholders are individuals, groups, or organizations who may affect, be affected
by, or perceive themselves to be affected by a decision, activity, or outcome of a project.”
Stakeholders can be internal to the organization or external.
Internal project stakeholders generally include the project sponsor, project team,
support staff, and internal customers for the project. Other internal stakeholders
include top management, other functional managers, and other project managers
because organizations have limited resources.
External project stakeholders include the project’s customers (if they are ex-
ternal to the organization), competitors, suppliers, and other external groups
that are potentially involved in the project or affected by it, such as govern-
ment officials and concerned citizens.
The website www.projectstakeholder.com offers an even more detailed list of poten-
tial stakeholders for a project:
Program director
Program manager
Project manager
Project manager’s family
Sponsor
Initiating
Process: Identify stakeholders
Outputs: Stakeholder register
Planning
Process: Plan stakeholder management
Outputs: Stakeholder management plan, project documents updates
Executing
Process: Manage stakeholder engagement
Outputs: Issue log, change requests, project management plan updates,
project documents updates, organizational process assets
updates
Monitoring and Controlling
Process: Control stakeholder engagement
Outputs: Work performance information, change requests, project
documents updates, organizational process assets updates
Project Start Project Finish
FIGURE 13-1 s s
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

499
Customer
Performing organization
Other employees of the organization
Labor unions
Project team members
Project management office
Governance board
Suppliers
Governmental regulatory agencies
Competitors
Potential customers with an interest in the project
Groups representing consumer, environmental, or other interests
Groups or individuals who are competing for limited resources
Groups or individuals who are pursuing goals that conflict with those of the
project2
Recall that the ultimate goal of project management is to meet or exceed stakeholder
needs and expectations for a project. To do that, you must first identify your particular
project stakeholders. Identifying some stakeholders is obvious, but others might be more
difficult to identify. For example, some competitors outside the organization or even in-
side it might be opposed to the project without the project manager’s knowledge. Stake-
holders also might change during a project due to employee turnover, partnerships, and
other events. It is important to use formal and informal communications networks to
make sure that all key stakeholders are identified.
It is also necessary to focus on stakeholders with the most direct ties to the project.
For example, if you listed every single supplier for goods and services used on a project,
you would be wasting precious time and resources. If a supplier is just providing an off-
the-shelf product, it should need little if any attention. However, if a supplier is providing a
customized product or service that is critical to the project’s success, the supplier
deserves much more attention.
A simple way to document basic information on project stakeholders is by creating
a stakeholder register. This document can take various forms and include the following
information:
Identification information: The stakeholders’ names, positions, locations, roles
in the project, and contact information
Assessment information: The stakeholders’ major requirements and expecta-
tions, potential influences, and phases of the project in which stakeholders
have the most interest
Stakeholder classification: Is the stakeholder internal or external to the
organization? Is the stakeholder a supporter of the project or resistant
to it?
Table 13-1 provides an example of part of the stakeholder register for the project
described in the chapter’s opening case. Notice that it includes only basic stakeholder
information, such as name, position, whether stakeholders are internal or external to the or-
ganization, their role on the project, and contact information. Because this document is avail-
able to other people in the organization, the project manager must be careful not to include
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

sensitive information, such as how strongly the stakeholders support the project or how much
power they have. Also notice that some stakeholders, like the project manager’s husband and
children, are not included on this list, even though they are important stakeholders to Debra!
A stakeholder analysis is a technique for analyzing information to determine which
stakeholders’ interests to focus on and how to increase stakeholder support throughout
the project. After identifying key project stakeholders, you can use different classifica-
tion models to determine an approach for managing stakeholder relationships. For ex-
ample, you can create a power/interest grid to group stakeholders based on their level of
authority (power) and their level of concern (interest) for project outcomes, as shown in
Figure 13-2. You should manage relationships very closely with stakeholders 1 and 2 in
this example because they have high interest and high power, especially stakeholder 1. You
should keep stakeholders 3 and 4 informed because they have high interest but low power.
Stakeholders 5 and 6 should be kept satisfied, perhaps by brief updates on the project,
because they have low interest but high power. You should spend the least amount of effort
by simply monitoring stakeholders 7 and 8, who both have low interest and low power.
It is also important to measure the engagement level of stakeholders throughout the
project. You can categorize stakeholders as being one of the following:
Unaware: Unaware of the project and its potential impacts on them
Resistant: Aware of the project yet resistant to change
Neutral: Aware of the project yet neither supportive nor resistant
Supportive: Aware of the project and supportive of change
Leading: Aware of the project and its potential impacts and actively engaged
in helping it succeed
The project team should take corrective action if stakeholders with high interest and
high power are also categorized as resistant or unaware. If they are unaware, setting up a
short meeting to discuss the importance of the project would be appropriate. The project
TABLE 13-1 s r
Name Position
Internal/
External Project Role Contact Information
Stephen VP of
Operations
Internal Project sponsor stephen@globaloil.com
Betsy CFO Internal Senior manager, approves
funds
betsy@globaloil.com
Chien CIO Internal Senior manager, PM’s boss chien@globaloil.com
Ryan IT analyst Internal Team member ryan@globaloil.com
Lori Director,
Accounting
Internal Senior manager lori@globaloil.com
Sanjay Director,
Refineries
Internal Senior manager of largest
refinery
sanjay@globaloil.com
Debra Consultant External Project manager debra@gmail.com
Suppliers Suppliers External Supply software suppliers@gmail.com
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

1
2
3
4
7
8
Low Interest High
High
Power
Low
High interest/high power
Manage closely
Low interest/low power
Monitor
High interest/low power
Keep informed
Low interest/high power
Keep satisfied
5
6
An Introduction to Project Management,
FIGURE 13-2
W H A T W E N T R I G H T ?
Instead of just saying “no” when your project sponsor asks for something unreasonable, it
is better to explain what is wrong with the request and then present a realistic way to solve
the problem at hand. For example, Christa Ferguson, a PMP and independent program
manager in San Francisco, described how she handled a request from a project sponsor to
deliver a new tablet device in two months when she knew she would need more time. Based
on her experience, she knew the Request for Quote for the effort alone would take almost a
month. Christa quickly researched the facts to propose a realistic delivery schedule.
manager could ask the project sponsor or another senior manager to participate in the
meeting. If stakeholders are resistant to the project, you would definitely want a senior-
level manager to talk to them directly to understand the reasons for their resistance and
develop a strategy to handle potential conflicts. Another common problem with stakehold-
ers, especially project sponsors, is that they support a project but have unreasonable ex-
pectations. It can be difficult to say “no” to them, as described in the following What Went
Right? feature.
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

13.3 PLANNING STAKEHOLDER MANAGEMENT
After identifying and analyzing stakeholders, the project manager and team should de-
velop a stakeholder management plan to help them effectively engage stakeholders and
make sure that good decisions are made throughout the life of the project. This plan may
be formal or informal, based on the needs of the project.
In addition to information found in the stakeholder register, such as stakeholder iden-
tification information, assessment information, and classification, a stakeholder manage-
ment plan can include the following:
Current and desired engagement levels: If these levels are not the same, the
project team should develop a strategy to align engagement levels.
Interrelationships between stakeholders: As you learned in earlier chap-
ters, there are many interrelationships between project activities and
stakeholders. The project manager must be in tune with the politics of the
organization.
Communication requirements: The communications management plan
should specify stakeholder requirements, and the stakeholder register can
expand on unique requests from specific people.
Potential management strategies for each stakeholder: This critical section
can contain very sensitive information.
Methods for updating the stakeholder management plan: All plans need
some process for handling changes and updates. Flexibility would be impor-
tant as stakeholders change on the project.
Because a stakeholder management plan often includes sensitive information, it
should not be part of the official project documents, which are normally available for all
stakeholders to review. In many cases, only project managers and a few other team mem-
bers should prepare the stakeholder management plan. In many cases, parts of the stake-
holder management plan are not written down, and if they are, distribution is strictly
limited.5
Table 13-2 provides an example of parts of a stakeholder management plan that
Debra could use to help manage project stakeholders in the opening case. It is important
for project managers to take the time to develop this plan, which helps them meet stake-
holder needs and expectations. In addition, as new stakeholders are added to the proj-
ect and more information is provided, the plan should be updated. For example, once a
supplier is selected for a project, specific supplier names and other information can be
added to the list.
“I created a timeline for the request for quotation and requested the companies
quoting the job to include a breakdown of the work required with a high-level schedule.
Then we could see the project was going to take at least six months to complete. By
creating a factual, data-driven picture of the situation, I didn’t have to explain anything
other than what work had to be done and how long it would take. Our sponsor reset
expectations once he learned what it took to produce the tablets.”4
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

TABLE 13-2
Name
Power/
Interest
Current
Engagement Potential Management Strategies
Stephen High/high Leading Stephen can seem intimidating due to his physical stature and
deep voice, but he has a great personality and sense of humor.
He previously led a similar refinery upgrade program at another
company and knows what he wants. Manage closely and ask for his
advice as needed. He likes short, frequent updates in person.
Chien High/
medium
Resistant Chien is a very organized yet hardheaded man. He has been
pushing corporate IT standards, and the system the PM and
sponsor (Debra and Stephen) like best goes against those
standards, even though it’s the best solution for this project and
the company as a whole. Need to convince him that this is okay
and that people still respect his work and position.
Ryan Medium/
high
Supportive Ryan has been with the company for several years and is well
respected, but he feels threatened by Debra. He also resents her
getting paid more than he does. He wants to please his boss,
Chien, first and foremost. Need to convince him that the suggested
solution is in everyone’s best interest.
Betsy High/low Neutral Very professional, logical person. Gets along well with Chien.
She has supported Debra in approving past projects with strong
business cases. Provide detailed financial justification for the
suggested solution to keep her satisfied. Also ask her to talk to
Chien on Debra’s behalf.
© Cengage Learning 2016
13.4 MANAGING STAKEHOLDER ENGAGEMENT
Project managers must understand and work with various stakeholders; therefore, they
should specifically address how to use various communications methods and their in-
terpersonal and management skills to engage stakeholders. Recall that project success is
often measured in different ways, such as meeting scope, time, and cost goals. Many prac-
titioners, however, define project success as satisfying the customer or sponsor, knowing
that it’s rare to meet scope, time, and cost goals without modifying at least one goal.
Project sponsors can usually rank scope, time, and cost goals in order of impor-
tance and provide guidelines on how to balance the triple constraint. This ranking can
be shown in an expectations management matrix, which can help clarify expectations.
For example, Table 13-3 shows part of an expectations management matrix that Debra
could use to help manage key stakeholders from the opening case. The expectations
management matrix includes a list of measures of success as well as priorities, expecta-
tions, and guidelines related to each measure. You could add other measures of success,
such as meeting quality expectations, achieving a certain customer satisfaction rating,
and meeting ROI projections after the project is completed, to meet individual project
needs. The challenge comes when key stakeholders disagree on priorities. For example,
Stephen wants a system that will meet his requirements, so scope is most important to
him. Chien wants to enforce corporate standards, so technology/standards are most im-
portant to him. Project managers must acknowledge these different priorities and make
the tough decisions about what to do. In this example, Debra believes that Stephen’s
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

priorities are most  important to the company as a whole, even though it might hurt her
relationship with Chien.
Understanding the stakeholders’ expectations can help in managing issues. If
the project manager knows that cost is not as high a priority as the schedule, it
shouldn’t be difficult to ask the project sponsor for needed funds, as long as the request
makes sense.
Issues should be documented in an issue log, a tool used to document, monitor, and
track issues that need resolution. Unresolved issues can be a major source of conflict and
result in stakeholder expectations not being met. Note that PMI lists issue logs as a tool for
stakeholder management, even though they can be used to address issues related to other
knowledge areas. For example, issues can be documented for requirements, procurement,
staffing, and other areas, but stakeholders must be informed about these issues and en-
gaged in the process of addressing them.
Table 13-4 provides a sample issue log that Debra could use to help document and
manage issues on her project. The issue log includes columns for the issue number, the
issue description, the impact of the issue on the project, the date the issue was reported,
who reported the issue, the person assigned to resolve the issue, the priority of the issue
(high, medium, or low), the due date for reporting back on the issue, the status of the is-
sue, and comments related to the issue. Some project management software includes the
ability to track issues, or a simple spreadsheet can be used. Many project managers sort
issues by priority and focus on resolving the high-priority issues first.
In addition to an issue log, other outputs of managing stakeholder engagement
include change requests and updates to the project management plan, project docu-
ments, and organizational process assets. For example, after Stephen clarified which
TABLE 13-3
Measure of
Success Priority Expectations Guidelines
Scope 1 The scope statement
clearly defines mandatory
requirements and optional
requirements.
Focus on meeting mandatory
requirements before considering
optional ones. In this case, following
corporate IT standards is optional.
Time 1 There is little give in the
project completion date. The
schedule is very realistic.
The project sponsor must be alerted
if any issues might affect meeting
schedule goals.
Cost 3 This project is crucial to the
organization. If you can clearly
justify the need for more funds,
they can be made available.
There are strict rules for project
expenditures and escalation
procedures. Cost is very important,
but it takes a back seat to meeting
schedule and then scope goals.
Technology/
standards
2 There are several potential
solutions available, but
only one that meets all
of the sponsor’s technical
requirements, especially for
accounting.
While corporate IT standards are
important, an exception makes
sense in this case.
© Cengage Learning 2016
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

requirements were mandatory for the project management system needed to upgrade
the oil refineries, it would probably affect which suppliers would meet the criteria for
potential selection. If the project included visiting potential suppliers, the schedule and
cost might be affected depending on the location of the top suppliers. In addition, Debra
might be able to use these mandatory requirements to argue for using nonstandard tech-
nology when talking to Chien. Debra would still need to address this issue carefully with
him, and she could benefit from using some of the ideas described in the following Best
Practice feature.
TABLE 13-4
Issue # Description Impact
Date
Reported
Reported
By
Assigned
To
Priority
(H/M/L)
Due
Date Status Comments
1 Need
requirements
categorized
as mandatory
and optional
Cannot
do much
without it
Feb. 4 Ryan Stephen H Feb. 8 Closed Require-
ments clearly
labeled
2 Need
shorter list
of potential
suppliers – no
more than 10
Will delay
evaluation
without it
Feb. 6 Debra Ryan H Feb.
12
Open Almost fin-
ished; needed
requirements
categorized
first
Etc.
© Cengage Learning 2016
B E S T P R A C T I C E
Project managers are often faced with challenges, especially in managing stakeholders.
Sometimes they simply cannot meet requests from important stakeholders. Sugges-
tions for handling these situations include the following:
Project managers should emphasize the importance of
their projects to the entire organization. For example, in the opening case, the
company had to upgrade several oil refineries to stay in business. IT standards
are important, but when a powerful new VP is hired and wants software with spe-
cific requirements to get an important job done, you have to consider all options.
Project managers have to be able to explain the
consequences of various decisions. Senior managers may not like a decision, but
if you present the logic behind it, they are more open to accepting it.
There are many forms of contingency plans. If
a  project manager cannot reason with an important stakeholder, a more sen-
ior person might be asked to help, for example. In extreme cases, project manag-
ers might even move on to other jobs if they feel their work is not  appreciated.
continued
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

13.5 CONTROLLING STAKEHOLDER ENGAGEMENT
You cannot control stakeholders, but you can control their level of engagement. Engage-
ment involves a dialogue in which people seek understanding and solutions to issues of
mutual concern. Many teachers are familiar with various techniques for engaging students.
It is important to set the proper tone at the start of a class or project. For example, if a
It is much better to be honest about project challenges so that
actions can be taken. One of the worst situations project managers face is tell-
ing sponsors something cannot be done after assuring them that it could.
Project managers do make a difference in leading their projects,
and part of the job is acknowledging the need for a change in course. “If you
don’t step it up and say, ‘We cannot get this done and this is the way it is,’ then
what are you there for? … If a sponsor wants a good, seasoned project manager,
that’s what you must do.”6
continued
M E D I A S N A P S H O T
Many students today like to interact via text messages. Parents and teachers have  adopted
this means of communication as well, especially with young people. Ellen  DeGeneres, a
popular comedian with her own television show, likes to poke fun at text messages in a
segment based on amusing errors caused by cell phone auto- correct  features. For exam-
ple, a father had the following text exchange with his daughter:
New MessagesMessage Edit
Send
“Your mom and I are going to divorce next month.”
“What??? Why??? Call me please!”
“I wrote Disney and this phone changed it.
We are going to Disney.”
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

In addition to watching out for auto-correct errors when messaging, users must also be
careful who they reply to and what they say in reply. The following example comes from
an actual college student who forgot about an exam. The professor called the student’s
cell phone shortly after the exam started. Her policy was to assign a grade of zero if stu-
dents did not show up without a valid excuse. The student did not answer the phone call,
but he sent the following texts:
New MessagesMessage Edit
Send
Professor: “Where are you?”
Student: “In class. Who is this?”
Student: “Who is this?”
Professor: “Did you drop MIS101? Professor Smith”
Professor: “You are missing exam 1 right now.”
Student: “Okay. Is it possible to do it during your office hours?”
Professor: “No. Now.”
Student: “No. I had to give my sister’s fiancé a ride to the veteran’s
hospital because he doesn’t have a car and my sister was at work.”
The professor was surprised when the student walked into her classroom a few
seconds later. Apparently he was down the hall working on a campus computer. Even
though he lied twice (about being in class and about taking someone to the hospital), the
professor let him take the exam and tried not to give him a hard time about his lies. The
student was on time for future exams.
teacher does nothing but lecture on the first day of class or criticizes the first student who
offers a comment, students will quickly decide that their best strategy is to keep quiet and
maybe not even attend class. On the other hand, if the teacher uses a lot of activities to
get all students to speak or use technology to participate, students will expect to be active
participants in future classes.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Just like teachers, project managers need to set the stage for engaging project stake-
holders early in the project. For example, key stakeholders should be invited to actively
participate in a kick-off meeting rather than merely attend it. The project manager should
emphasize that a dialogue is expected at the meeting, using whatever means of communi-
cation the stakeholders prefer. It is also helpful for the project manager to meet with im-
portant stakeholders before the kick-off meeting.
The project schedule should include activities and deliverables related to stakeholder
engagement. Surveys, reviews, demonstrations, sign-offs, and other items require stake-
holder engagement.
On some IT projects, important stakeholders are invited to be members of the project
teams. For example, when Northwest Airlines (now Delta) was developing a new reserva-
tion system called ResNet, it interviewed reservation agents for positions as programmers
on the project team. Northwest made sure that user needs were understood by having
them actually develop the system’s user interface. See the companion website for detailed
information about how the ResNet team engaged with users.
13.6 USING SOFTWARE TO ASSIST IN PROJECT
STAKEHOLDER MANAGEMENT
As in the other knowledge areas, software can also assist in project stakeholder manage-
ment. Productivity software like word processors, spreadsheets, and presentation software
can aid in creating various documents related to stakeholder management. Communica-
tions software like e-mail, blogs, websites, texts, and tweets can aid in stakeholder com-
munications. Collaboration tools like Google docs, wikis, and virtual meeting software can
also promote stakeholder engagement in projects.
A very popular software category today—social media—can also help engage stake-
holders. For example, many professionals use LinkedIn to connect with other profession-
als. Several project management groups are on LinkedIn and other sites where people can
share ideas about various topics. In fact, searching LinkedIn groups for the term project
management in May 2015 yielded over 7,000 results, including the following:
The Project Manager Network: With over 705,000 members, this group says it is
the “#1 Project Manager Social Media Group & Community on LinkedIn.” It was
created by ProjectManagers.net.
Project Manager Community: This group claims to be the “best group for
project management” with over 288,000 members. This community was cre-
ated by ProjectManager.com.
PMI Project, Program and Portfolio Management: With over 156,000 mem-
bers, this official PMI group claims to be #1 for career advancement.
PMO—Project Management Office: This virtual community has over 79,000
members around the globe.
Although many organizations do not promote the use of Facebook at work, sev-
eral project management software tools include functionality like Facebook’s to en-
courage relationship building on projects. For example, some tools allow people to
give each other “high fives” for a job well done. Many include photos of project team
members and other stakeholders. Users can also have conversation threads within the
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

tools. In fact, several books and articles are available about using social media to help
manage projects.
Elizabeth Harrin, Director of the Otobos Group in London, is the author of Social
Media for Project Managers. In the book, Harrin describes the pros and cons of several
social media tools, including blogs, collaboration tools, instant messaging, microblogs like
Twitter and Facebook, podcasts, RSS, social networks, vodcasts (video podcasts), webi-
nars, and wikis. In the foreword of the book, Len O’Neal, Online Content and Strategy
Manager for PMI, stated: “Making social media work on your projects can be a project in
itself … Individual, team, organizational, and cultural biases and influences can play a
significant part in how far you explore the road to project-based social media efforts and
how successful you are.”7 Harrin provides advice for when to use social media and when
not to use it.
As the saying goes, “A fool with a tool is still just a fool.” It is crucial that project man-
agers and their teams focus on controlling stakeholder management to meet their needs
and expectations, not to show off the latest technology. A lot of stakeholder engagement
requires old-fashioned techniques like talking to someone!
G L O B A L I S S U E S
Not all software implementations go well, and managing stakeholders is a major chal-
lenge. The U.K. government scrapped its £11.4 billion national healthcare IT initiative in
September 2011 after it failed to deliver the promised benefits. Unfortunately, this proj-
ect was just one in a series of high-profile failures in the U.K.
In response, the government decided to send its project managers back to school!
The government partnered with the University of Oxford and the Deloitte consulting
firm to establish the Major Projects Leadership Academy in Oxford, England. Currently,
300 people are categorized as major project leaders in the British government. The goal
of the new academy is to reduce the overreliance on expensive external consultants and
build expertise within the civil service. In the future, “no one will be able to lead a major
government project without completing the Academy.”8 Project leaders working on the
2012 Olympics and the High Speed Two railway system were the first to benefit from the
new program.
As of spring 2015, about 120 people have graduated and another 200 have enrolled.
Has it made a difference? According to Paul Chapman, EngD, the head of the academy, it
certainly has. “Three years ago, about one-third of the government’s major projects were
delivered on time and to budget.… now this is nearly two-thirds.”9 You can find more
details on the Major Projects Leadership Academy website.
The processes involved in project stakeholder management, like the other knowledge
areas, follow a clear, logical sequence. However, this may be the most difficult area to mas-
ter for many project managers. As you learned in this and previous chapters, understand-
ing a wide variety of people and getting them to work together to meet project goals is not
an easy undertaking.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

C A S E W R A P – U P
Debra let Chien cool down a while before entering his office again. She realized that
she needed his signature on an important document.
“Are you going to yell at me again?” she asked.
Chien smiled and apologized for being so upset earlier. He was very happy with
Debra’s performance and knew that she was an asset to the company. He explained
how hard it was for him to try to develop and enforce IT standards, especially when a
new VP like Stephen comes in and gets what he wants so easily.
Debra explained that the software solution she recommended was the only one
that would integrate well with the various accounting systems at refineries in other
countries. She described some of the technical details she learned after meeting with
the Director of Accounting, and Stephen knew it was essential to keep track of costs
well on such a huge project. Chien agreed that upgrading the oil refineries quickly
and cost-effectively was the top priority for the company now. He told Debra that he
trusted her objective analysis in making the best recommendation. He also told her
that it took a lot of guts to go against him and Ryan, but he knew now that it was best
for the company as a whole.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Chapter Summary
PMBOK® Guide

Quick Quiz
PMBOK® Guide
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Quick Quiz Answers
Discussion Questions

Exercises


Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

www.linkedin.com. –

Running Case
Key Terms
expectations management matrix
issue log
power/interest grid
stakeholder analysis
stakeholder register
End Notes
PM Network
www.projectstakeholder.com
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

An Introduction to Project Management, Fourth Edition
PM Network
An Introduction to Project Management, Fourth Edition
PM Network
Social Media for Project Managers
PM  Network
PM Network
www.pmi.org/Learning/PM-Network/2015/facing-government-it-project-failures.aspx.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

A P P E N D I X A
GUIDE TO
USING MICROSOFT
PROJECT 2013
Note 1: This Appendix is used with permission from Schwalbe Publishing. It was published
as a stand-alone book on May 2, 2013, and as an appendix in Kathy Schwalbe’s Healthcare
Project Management (co-authored with Dan Furlong) and Revised An Introduction to
Project Management, Fourth Edition.
Note 2: This guide was written using the free trial of Microsoft Office Project 2013 Pro-
fessional and Windows 7. Your screens may appear slightly different. You can download a
free trial of Project 2013 Professional from the Microsoft website. You can access updated
information as well as the older version of this guide based on Project 2010 at www.
intropm.com. You can purchase just this new Appendix from www.intropm.com in Kin-
dle or hard-copy format. Also note that Microsoft now provides a cloud-based tool called
Project Online, available for a monthly fee.
Introduction A.2
Project Management Software Reviews A.3
Basic Features of Project Management Software A.6
What’s New in Project 2013 A.7
Using Project 2013 A.7
Before You Begin A.7
Using the 60-day Trial of Project 2013 A.8
Overview of Project 2013 A.9
Starting Project 2013 and Getting Started A.9
Understanding the Main Screen Elements A.12
Using Project Help and the Project website A.14
Exploring Project 2013 Using an Existing File A.15
Project 2013 Views A.17
Project 2013 Reports A.19
Project 2013 Filters A.21
Creating a New File and Entering Tasks in a Work Breakdown Structure A.23
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.2 Creating a New Project File A.23
Creating a Work Breakdown Structure Hierarchy A.25
Creating Summary Tasks A.26
Numbering Tasks A.27
Saving Project Files Without a Baseline A.28
Developing the Schedule A.29
Calendars A.29
Task Durations A.31
Manual and Automatic Scheduling A.31
Duration Units and Guidelines for Entering Durations A.32
Entering Task Durations A.34
Establishing Task Dependencies A.38
Gantt Charts, Network Diagrams, and Critical Path Analysis A.43
Project Cost and Resource Management A.46
Entering Fixed and Variable Cost Estimates A.46
Entering Fixed Costs in the Cost Table A.47
Entering Resource Information and Cost Estimates A.47
Using the New Team Planner Feature A.51
Entering Baseline Plans, Actual Costs, and Actual Times A.52
Viewing Earned Value Management Data A.56
Integrating Project 2013 with Other Applications and Apps for Office A.57
Copying Information Between Applications A.57
Creating Hyperlinks to Other Files A.59
Using Project 2013 Apps A.60
Discussion Questions A.63
Exercises A.63
End Notes A.64
INTRODUCTION
There are hundreds of project management software products on the market today. Gart-
ner estimated the project and portfolio management (PPM) software market to be over
$1 billion in 2011, and it continues to grow. Unfortunately, many people who own PPM
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

A.3
Guide to Using Microsoft Project 2013
software have no idea how to use it. It is important to understand the basic concepts of
project management, such as creating a work breakdown structure, determining task de-
pendencies, and so on before making effective use of this software. Many project teams
still use spreadsheets or other familiar software to help manage projects. However, if
you can master a good project management software tool, it can really help in managing
projects. This appendix summarizes basic information on project management software
in general. It also provides a brief guide to using Microsoft Office Project 2013 Profes-
sional (often referred to as Project 2013), the latest version of the most widely used PPM
software.
PROJECT MANAGEMENT SOFTWARE REVIEWS
Figure A-1 provides a screen shot showing the top ten project management software prod-
ucts based on a June 2009 review by TopTenREVIEWS™. That was the last year that a
review was provided of non-online PPM software. Most PPM tools now offer totally online
versions, including Project 2013.
FIGURE A-1 Top ten project management software product comparisons
1TopTenREVIEWS™, “Project Management Software,” (project-management-software-review.toptenreviews.com)
(accessed June 17, 2009).
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.4
The products listed in the top ten include:
1. Microsoft Project
2. MindView
3. Project KickStart
4. RationalPlan Multi Project
5. FastTrack Schedule
6. Service Desktop Pro
7. Milestones
8. MinuteMan
9. FusionDesk Professional
10. VIP Team To Do List
Notice that Microsoft Project is number one on the list. Also notice its steep
price back in 2009 of over $500 for a single user. Remember that students can pur-
chase  Microsoft Project and other software at greatly reduced rates from sites such as
www.journeyed.com. You can also download a free trial of Project 2013 Professional
(not Project Online, which cost $45 per user per month without an annual subscription,
as of April 2013) and other software products or access them remotely via the Internet
with your school’s software license. Check with your school’s IT department for more
information.
Below are descriptions of the criteria for comparing the software products:
Collaboration: How information and issues are communicated with project
team members, including e-mail, conference calls, meetings, web-based loca-
tions, and more. Collaboration should be easy to use.
Resource Management: Project management software should manage and
control the resources needed to run a project, such as people, money, time,
and equipment.
Project Management: The process, practice, and activities needed to perform
continuous evaluation, prioritization, budgeting, and selection of investments
are key. Proper project management capabilities provide the greatest value
and contribution to the strategic interest of your company.
Ease of Use: All project management software has a learning curve, but the
best have functions that are easy to find and simple enough for anyone to use
from Day 1, Project 1.
Help/Support: Project management software should offer a comprehensive
user guide and help system. The manufacturer should provide e-mail ad-
dresses or telephone numbers for direct answers to technical questions.1
In addition to reviewing project management software in general, TopTenREVIEWS™
also compared online products in a separate category. These products require an Internet
connection for use. Figure A-2 lists the top ten results for 2013.
The top ten products listed include:
1. Clarizen
2. Genius Project
3. Daptiv
4. Tenrox
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.5
5. Celoxis
6. Project Insight
7. AtTask
8. EPM Live
9. Liquid Planner
10. Easy Projects.net
TopTenREVIEWS™ only listed online project management tools in 2013, and
their  review was done before Microsoft’s Project Online was released. Tools in this list pro-
vide the ability to create Gantt charts, numerous reports and views, project dashboards,
and integrate with Microsoft Project files. See End Note 2 or visit the websites for any
of these products and use a free trial version. Also note that there are many other tools
available.
FIGURE A-2 Top ten online project management product comparisons2
2TopTenREVIEWS™, “Best Online Project Management Comparisons,” (online-project-management-review.
toptenreviews.com/) (accessed April 7, 2013).
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.6 BASIC FEATURES OF PROJECT MANAGEMENT SOFTWARE
What makes project management software different from other software tools? Why not
just use a spreadsheet or database to help manage projects?
You can do a lot of project management planning and tracking using non-project man-
agement software. You could use a simple word processor to list tasks, resources, dates,
and so on. If you put that information into a spreadsheet, you can easily sort it, graph it,
and perform other functions. A relational database tool could provide even more manipu-
lation of data. You can use e-mail and other tools to collaborate with others.
However, project management software is designed specifically for managing projects,
so it normally includes several distinct and important features not found in other software
products:
Creating work breakdown structures, Gantt charts, and network diagrams:
A fundamental concept of project management is breaking down the scope of
the project into a work breakdown structure (WBS). The WBS is the basis for
creating the project schedule, normally shown as a Gantt chant. The Gantt chart
shows start and end dates of tasks as well as dependencies between tasks, which
are more clearly shown in a network diagram. Project management software
makes it easy to create a WBS, Gantt chart, and network diagram. These features
help the project manager and team visualize the project at various levels of detail.
Integrating scope, time, and cost data: The WBS is a key tool for summarizing
the scope of a project, and the Gantt chart summarizes the time or schedule
for a project. Project management software allows you to assign cost and other
resources to tasks on the WBS, which are tied to the schedule. This allows you
to create a cost baseline and use earned value management to track project
performance in terms of scope, time, and cost in an integrated fashion.
Setting a baseline and tracking progress: Another important concept of
project management is preparing a plan and measuring progress against the
plan. Project management software lets you track progress for each task. The
tracking Gantt chart is a nice tool for easily seeing the planned and actual
schedule, and other views and reports show progress in other areas.
Providing other advanced project management features: Project manage-
ment software often provides other advanced features, such as setting up
different types of scheduling dependencies, determining the critical path and
slack for tasks, working with multiple projects, and leveling resources. For
example, you can easily set up a task to start when its predecessor is halfway
finished. After entering task dependencies, the software should easily show
you the critical path and slack for each task. You can also set up multiple
projects in a program and perform portfolio management analysis with some
products. Many project management software products also allow you to
easily adjust resources within their slack allowances to create a smoother re-
source distribution. These advanced features unique to project management
are rarely found in other software tools.
As you can see, there are several important features that are unique to project man-
agement software that make them worth using. Next you’ll learn what’s new in Project
2013 and how to use its basic features.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

lenovo

Guide to Using Microsoft Project 2013
A.7WHAT’S NEW IN PROJECT 2013
If you are familiar with Project 2010 or an earlier version, it may be helpful to review
some of the new features in Project 2013.
Improved reports: With Project 2013, you can create professional reports
and add pictures, charts, animation, and links to clearly share project status
information. An entirely new set of pre-installed reports are available, includ-
ing burn down reports, a popular chart used for agile projects. The earned
value chart is also much easier to create.
New collaboration features: You can stay in touch with team members by
getting progress updates, asking questions, or having strategy discussions,
all without leaving Project 2013. You can hover over a name and start an IM
session, video chat, e-mail, or phone call. You must have Lync 2010 or later
installed to take advantage of this feature.
Task paths: You can now highlight any task and see its task path. All of the
task’s predecessor tasks show up in one color, and all of its successor tasks
show up in another color.
Extended dates: You can set task and project dates up to 12/31/2149.
Shared meetings: If you export Project 2013 reports, timelines, or data to
other Office programs, you can use the new sharing feature to join online
meetings, share your PowerPoint slides, Word documents, Excel spreadsheets,
and OneNote notes from any supported device, even if Office isn’t installed.
Cloud storage: You can easily save files to your own SkyDrive or to your or-
ganization’s shared site. From there you can access and share your files from
Project 2013 and other Office applications. Note that Project Online is deliv-
ered through Office 365 and used totally online.
Easy access: If you have Project Online, Windows 7 (or later), and an Inter-
net connection, you can access a full version of Project from any location,
similar to the new Office applications.
Next, you will learn some basic information about Project 2013 and explore the main
screen elements and Help facility.
USING PROJECT 2013
Before you can use Project 2013 or any project management software effectively, you
must understand the fundamental concepts of project management, such as creating
work breakdown structures (WBS), linking tasks, entering duration estimates, assigning
resources, and so on. The purpose of this text is to provide specific instructions for using
Project 2013 Professional. Consult Microsoft’s website for detailed information on other
products and other resources to help you understand project management concepts.
Before You Begin
This appendix assumes you are using Project 2013 with Windows 7 (or later) and are fa-
miliar with other Windows-based applications. Check your work by reviewing the many
screen shots included in the steps, or by using the solution files that are available for
download from the companion website or from your instructor.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.8
This appendix uses a fictitious project—Project A+—to illustrate how to use the soft-
ware. The WBS for Project A+ uses the five project management process groups as level 2
items (initiating, planning, executing, monitoring and controlling, and closing). Standard
deliverables under each of those process groups are included. Each section of the appen-
dix includes hands-on activities for you to perform.
N O T E
You need to be running Windows 7 or later to use Project 2013, a 1 Ghz or greater x86/x64 processor
with SSE2 instruction set, 1 GB RAM (32 Bit) / 2 GB RAM (64 Bit), and an up-to-date browser. Cer-
tain features require Internet connectivity. You can read more detailed system requirements and down-
load a free trial from Microsoft’s website. Students can purchase a full version from sites like www.
journeyed.com at a discount. Many colleges and universities provide the software to students either
on campus or through remote access. If you can use remote access, the main requirement is Internet
connectivity. Check with your instructor for details. You might also want to pay for monthly access to
Project Online.
N O T E
To complete some of the hands-on activities in the appendix, you will need to download files from the
companion website (www.intropm.com) to your computer. When you begin each set of steps, make
sure you are using the correct file. Save the files you create yourself in a different folder so you do not
write over the ones you download.
In addition, you will create the following files from scratch as you work through the
steps:
mywbs.mpp
myschedule.mpp
You will also use the following file to create a hyperlink:
stakeholder register
Using the 60-Day Trial of Project 2013
If you plan to download the free trial, perform the following steps:
1. Search for Microsoft’s site for downloading a free trial of Project 2013 (the
site address changes periodically) and click the Try on button under Project
Professional 2013.
2. Enter your account information. You do need a Microsoft account. It used to
be called a Windows Live account, so you may already have one if you set it
up for Xbox 360, SkyDrive, Office 2013, Office 365 or other items. If you do
not have a Microsoft account, set one up for free.
3. Install Project 2013. The installation for Project 2013 is a bit different from
past installations. Follow the instructions from Microsoft. The trial software is
run through Microsoft’s online environment, similar to Office 365.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.9
Next you will learn how to start Project 2013, review the Help facility and a template
file, and begin to plan Project A+.
Overview of Project 2013
The first step to mastering Project 2013 is to become familiar with the major screen ele-
ments and the Help facility. This section describes each of these features.
Starting Project 2013 and Getting Started
To start Project 2013:
1. Open Project 2013. There are slightly different methods for opening Project
2013 depending on your operating system. For example, in Windows 7, click
the Start button on the taskbar, and then click Project 2013 or type it in the
search bar. Alternatively, a shortcut or icon might be available on the desk-
top; in this case, double-click the icon to start the software.
2. Review the Get Started feature. Click Get Started, as shown in the upper
right section of Figure A-3.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-3 Project 2013 initial options – access Get Started
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.10
3. Start the introduction. Click Create, and then click Start, as shown in Figure A-4.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-4 Project 2013 Get Started introductory screen
4. Review the “4 simple steps” Microsoft lists for using Project 2013. Review
the first step, called Schedule your work, as shown in Figure A-5. Review the
other steps by clicking Next, as shown in Figures A-6–A-8.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-5 Schedule your work screen
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.11
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-6 Create a timeline screen
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-7 Report on progress screen
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.12
5. Explore Help features. The last screen of Getting Started, Learn More, as
shown in Figure A-9, provides links to the Project 2013 Getting Started Cen-
ter (which includes a short video on what’s new that is worth watching) and
the Project blog. The help feature (question mark in the upper right of the
screen) also includes a lot of helpful resources.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-8 Collaborate with your team screen
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-9 Learn More screen
Understanding the Main Screen Elements
To open a blank file:
1. Open a blank file. Click the File tab, New, and then click the first option,
Blank Project.
2. Examine the main screen. Review the main screen elements, as shown in
Figure A-10. Look at some of the elements of the screen.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.13
The Ribbon, tabs, and Quick Access toolbar are similar to other Office
applications.
The timeline view is displayed below the ribbon.
The default manual scheduling for new tasks is on the lower left of the
screen. You can click that option to switch to automatic scheduling.
The default view is the Gantt chart view, which shows tasks and other
information as well as a calendar display. You can access other views by
clicking the View icon on the far left side of the ribbon.
The areas where you enter information in a spreadsheet-like table are part
of the Entry table. For example, you can see entry areas for Task Name,
Duration, Start, Finish, and Predecessors.
You can make the Entry table more or less wide by using the Split bar. When
you move the mouse over the split bar, your cursor changes to the resize
pointer. Clicking and dragging the split bar to the right reveals columns for
Resource Names and Add New columns.
The first column in the Entry table is the Indicators column. The Indicators
column displays indicators or symbols related to items associated with each
task, such as task notes or hyperlinks to other files. The second column dis-
plays if a task is manually or automatically scheduled, as described later in
this appendix.
The file name displays centered at the top of the screen. When you open a
Blank Project after starting Project 2013, it opens a new file named Project1,
which is shown in the title bar. If you open a second Blank Project, the name
will be Project2, and so on, until you save and rename the file.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-10 Project 2013 main screen
Quick Access
Toolbar
Indicators
column Tabs
Ribbon
Timeline
Split bar
Manual/
automatic
scheduling
Entry
table
Gantt chart view
(default view)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.14
Using Project Help and the Project Website
To access information to help you learn how to use Project 2013:
1. Access Project Help. Click the question mark/help icon on the upper side of
the ribbon. The Project Help screen displays, as shown in Figure A-11.
Remember that this feature requires an Internet connection.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-11 Topics under Project help
2. Explore various help topics. Click the Project Help link called “What’s new
with Project 2013.” Microsoft provides short videos, steps, templates, arti-
cles, and other features to help you learn to use this powerful software. Watch
the short video, read the other information on the page, and explore links for
more help.
3. Close Project 2013. Click the Close icon (X in the upper right of the screen)
to exit Project 2013.
Many features in Project 2013 are similar to ones in other Windows programs. For
example, to collapse or expand tasks, click the appropriate symbols to the left of the task
name. To access shortcut items, right-click in either the Entry table area or the Gantt
chart. Many of the Entry table operations in Project 2013 are very similar to operations
in Excel. For example, to adjust a column width, click and drag between the column
heading titles.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.15
Next, you will get some hands-on experience by opening an existing file to explore
various screen elements. Project 2013 comes with several template files, and you can also
access templates from Microsoft Office Online or other websites.
EXPLORING PROJECT 2013 USING AN EXISTING FILE
To open a template file and adjust Project 2013 screen elements:
1. Open Project 2013 and select the Customer Service template file. Click the
Start button on the taskbar, select Project 2013, click Customer Service, and
then click Create. These screen shots were taken on April 3, 2013, so you
can enter that date if you like. Your screen should resemble Figure A-12.
(Note: If you cannot find the template, you can download it from www.
intropm.com and open it. To open an existing file, click the File tab, then
select Open, and browse to find the file.)
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-12 Customer Service template file
Note Indicator Widen Column Split Bar Timeline Notes
2. Widen the Task Name column. Move the cursor between the Task Name and
Duration columns, and then double-click to widen the Task Name column so
all of the text shows in one line.
3. Move the Split Bar. Move the Split Bar to the right so the entire Task Name
column text is visible, but not the Duration column. The default table view is
the Entry table.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.16
4. View the first Note. Move your cursor over the yellow Notes symbol in the
Indicators column for Task 1 to read it. You can insert notes by any task.
To show different WBS levels:
1. Select Outline Level 1 to display WBS level 2 tasks. Click the View tab and
then the Outline button’s list arrow, and then click Outline Level 1. Notice
that only the level 2 WBS items display in the Entry table. The black bars on
the Gantt chart represent the summary tasks. Recall that the entire project
is normally referred to as WBS level 1, and the next highest level is called
level 2.
2. Adjust the timescale. Click the Zoom out button (minus sign) on the left side
of the Zoom slider on the lower right of the screen, as shown in Figure A-13.
Notice the milestone task in row 143 indicating the project completion date.
Recall that the black diamond symbol on a Gantt chart shows milestones.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-13 Showing part of the WBS on the Gantt chart
Expand/
Collapse Symbol Outline Summary Tasks Timeline
Zoom out
Milestone
3. Expand a task. Click the expand symbol to the left of Task 2, Initial As-
sessment, to see its subtasks. Click the collapse symbol to hide its subtasks.
Experiment with expanding and collapsing other tasks and resizing other
columns.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.17
4. View all tasks. Click the Outline button and select All Subtasks to see all of
the items in the Task Name column again.
5. Remove the Timeline. Click the Timeline checkbox on the Ribbon to unselect
it. Click it again to display it.
6. Close the file without saving. Click the Close icon in the upper right of the
window, and select No when prompted to save the file.
Project 2013 Views
Project 2013 provides many ways to display or view project information. In addition to the
default Gantt chart, you can view the network diagram, calendar, and task usage views, to
name a few. These views allow you to analyze project information in different ways. The
View tab also provides access to different tables that display information in various ways.
In addition to the default Entry table view, you can access tables that focus on data related
to areas such as the Schedule, Cost, Tracking, and Earned Value.
To access and explore different views:
1. Explore the Network Diagram for the Customer Service file. Open the
Customer Service file again. Click the Network Diagram button under the
View tab, and then move the Zoom slider on the lower right of the screen all
the way to the left. Your screen should resemble Figure A-14. Critical tasks
display in red.
Network Diagram
Zoom slider
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-14 Network diagram view of Customer Service file
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.18
2. Explore the Calendar view. Click the Calendar button (under the Network
Diagram button). Notice that the screen lists tasks each day in a calendar
format.
3. Change the table view. Click the Gantt Chart button on the ribbon, click
the Tables button under the View tab, and then click Schedule. Figure A-15
shows the table view options.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-15 Table view options
4. Examine the Schedule table and other views. Select the Schedule table view
and move the Split bar to the right to review the Total Slack column. Notice
that the columns in the table to the left of the Gantt chart, as shown in Figure
A-16, now display more detailed schedule information, such as Late Start,
Late Finish, Free Slack, and Total Slack. Remember that you can widen col-
umns by double-clicking the resize pointer to the right of that column. You
can also move the split bar to reveal more or fewer columns. Experiment with
other table views, then return to the Entry table view.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.19
Project 2013 Reports
Project 2013 provides many ways to report project information as well. In addition to tra-
ditional reports, you can also prepare visual reports, with both available under the Report
tab. Note that the visual reports often require that you have other Microsoft application
software, such as Excel and Visio. Project 2013 automatically formats reports for ease of
printing.
To access and explore different reports:
1. Explore the Reports feature. Click the Report tab to see the variety of reports
available in Project 2013.
2. View the Project Overview report. Click Dashboards, and then click Project
Overview. Review the report and new options on the ribbon, as shown in
Figure A-17.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-16 Schedule table view
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.20
3. Open the Resource Overview report. Click the Report tab again, click
Resources, and then click Resource Overview. Review the report, as shown
in Figure A-18.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-17 Project Overview report
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-18 Resource Overview report
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.21
4. Examine the report and experiment with others. Click the Report tab, click
In Progress, and then click Critical Tasks to display the Critical Tasks report,
as shown in Figure A-19. Examine other reports.
5. Return to the Gantt chart. Click the View tab, and then click Gantt Chart to
return to the Gantt chart view. You can close the file without saving it if you
wish to take a break.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-19 Critical tasks report
Project 2013 Filters
Project 2013 uses a relational database to filter, sort, store, and display information. Filter-
ing project information is very useful. For example, if a project includes thousands
of tasks, you might want to view only summary or milestone tasks to get a high-level view
of the project by using the Milestones or Summary Tasks filter from the Filter list. You can
select a filter that shows only tasks on the critical path if that is what you want to see.
Other filters include Completed Tasks, Late/Overbudget Tasks, and Date Range, which
displays tasks based on dates you provide. As shown earlier, you can also click the Show
button on the toolbar to display different levels in the WBS quickly.
To explore Project 2013 filters:
1. Access filters. Click the View tab, if necessary, and make sure the Customer
Service file is in the Gantt Chart: Table Entry view. Click the Filter list arrow
(under the Data group), as shown in Figure A-20. The default filter is No Fil-
ter, which shows all tasks.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.22
2. Filter to show milestones. Click Milestones in the list of filters. Notice that
the Gantt chart only shows the summary tasks and milestones for the proj-
ect. Your screen should resemble Figure A-21. Recall that milestones are sig-
nificant events.
3. Show critical tasks. Select No Filter from the Filter list box to reveal all the
tasks in the WBS again. Click the Filter list arrow, and then click Critical.
Now only the critical tasks appear in the WBS. Experiment with other filters.
4. Close the file. When you are finished reviewing the Customer Service file,
click Close from the File tab or click the Close button. Click No when asked
if you want to save changes.
5. Exit Project 2013. Click the Close button for Project 2013.
Now that you are familiar with the main screen elements, views, reports, and filters,
you will learn how to use Project 2013 to create a new file.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-20 Using a filter
Filter list arrow
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.23
CREATING A NEW FILE AND ENTERING TASKS IN A WORK
BREAKDOWN STRUCTURE
To create a new Project 2013 file, you must first name the project, enter the start date,
and then enter the tasks. The list of tasks and their hierarchy is the work breakdown
structure (WBS). The file you create could be used for a class project which lasts approxi-
mately three months. It uses the project management process groups to reinforce use of
several project management deliverables described in this text. You could modify this file
to meet your specific needs.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-21 Milestones filter applied
N O T E
In this section, you will go through several steps to create a new Project 2013 file named mywbs.mpp.
If you want to download the completed file to check your work or continue to the next section, a copy
of mywbs.mpp is available on the companion website at www.intropm.com. Try to complete an entire
section of this appendix (entering tasks in a work breakdown structure, developing the schedule, and
so on) in one sitting to create the complete file.
Creating a New Project File
To create a new project file:
1. Create a blank project. Open Project 2013 and click Blank Project. A blank
project file opens with a default filename of Project1, Project2, and so on.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.24
(If Project 2013 is already open and you want to open a new file, click the
File tab, select New, and then Blank Project.)
2. Open the Project Information dialog box. Click the Project tab, and then
click Project Information to display the Project Information dialog box, as
shown in Figure A-22. This dialog box enables you to set dates for the project,
select the calendar to use, and view project statistics. The project start date
will default to the current date. Note that in Figure A-22 the file was created
on 4/3/13 and a Start date of 9/9/13 was entered.
N O T E
All dates are entered in month/day/year or American format. You can change the date format by se-
lecting Options from the File tab. Click the date format you want to use in the Date Format box under
the General settings. You can also customize the Ribbon, change default currencies in the display, and
so on under Project Options.
Start date
text box Current date
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-22 Project information dialog box
3. Enter the project start date. In the Start date text box, enter 9/9/13. Setting
your project start date to 9/9/13 will ensure that your work matches the re-
sults that appear in this appendix. Leave the Current date and other informa-
tion at the default settings. Click OK or press Enter.
4. Enter advanced project properties. Click the File tab, and then click Info. Click
Project Information on the right side of the screen, and then click Advanced
Properties. Enter Project A+ for the title, if you want to change the title. You
can also enter a subject, author, and other information as desired. Click the
left arrow at the top left of the screen to go back to the previous screen.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.25Creating a Work Breakdown Structure Hierarchy
As mentioned earlier, a work breakdown structure (WBS) is a fundamental part of project
management. Developing a good WBS takes time, and it will make entering tasks into the
Entry table easier if you develop the WBS first. For this example, you will use the proj-
ect management process groups as the level 2 items and add some key deliverables and
milestones under each one. You will use the information in Figure A-23 to enter tasks.
Note that Microsoft Project uses the term tasks instead of deliverables or activities or mile-
stones, so it is also used in this appendix.
Order | Task Name Order | Task Name
1. Initiating 16. Deliverable 2
2. Stakeholder identification 17. Deliverable 3
3. Stakeholder register completed 18. Deliverable 1 completed
4. Stakeholder management strategy completed 19. Deliverable 2 completed
5. Project charter 20. Deliverable 3 completed
6. Project charter completed 21. Monitoring and Controlling
7. Kickoff meeting 22. Actual hours tracking
8. Kickoff meeting completed 23. Project documents updates
9. Planning 24. Progress report 1
10. Schedule 25. Progress report 2
11. Gantt chart completed 26. Team review meetings
12. Scope statement 27. Closing
13. Initial scope statement completed 28. Final project report
14. Executing 29. Final project presentation
15. Deliverable 1 30. Project completed
Schwalbe Publishing 2013.
FIGURE A-23 Task list for Project A+
To develop a WBS for the project:
1. Enter task names. Enter the 30 items in Figure A-23 into the Task Name
column in the order shown. To not have the text wrap, click the Format Tab,
click Column Settings, and then click Wrap Text to turn it off. Do not worry
about durations or any other information at this time. Type the name of each
item into the Task Name column of the Entry table, beginning with the first
row. Press Enter or the down arrow key on your keyboard to move to the
next row.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.26
2. Adjust the Task Name column width as needed. To make all the text display
in the Task Name column, move the cursor over the right-column gridline
in the Task Name column heading until you see the resize pointer, and then
click the left mouse button and drag the line to the right to make the column
wider, or double-click to adjust the column width automatically.
This WBS separates tasks according to the project management process groups of
initiating, planning, executing, controlling, and closing. These categories will be the level
2 items in the WBS for this project. (Remember the whole project is level 1.) It is a good
idea to include all of these process groups because there are important deliverables that
must be done under each of them. Recall that the WBS should include all of the work re-
quired for the project. In the Project A+ WBS, the WBS will be purposefully left at a high
level (level 3). You will create these levels, or the WBS hierarchy, next when you create
summary tasks. For a real project, you would usually break the WBS into even more levels
and then enter activities to provide more details to describe all the work involved in the
project. For example, each deliverable would probably have several levels, activities, and
milestones under it. You can review other Project 2013 template files or other sources for
more information.
Creating Summary Tasks
After entering the items listed in Figure A-23 into the Entry table, the next step is to show
the WBS levels by creating summary tasks. The summary tasks in this example are Tasks
1 (initiating), 9 (planning), 14 (executing), 21 (monitoring and controlling), and 27 (clos-
ing). You create summary tasks by highlighting and indenting their respective subtasks.
To create the summary tasks:
1. Select lower level or subtasks. Highlight Tasks 2 through 8 by clicking the
cell for Task 2 and dragging the mouse through the cells to Task 8.
2. Indent subtasks. Click the Indent Task button on the Ribbon under the
Schedule group of the Task tab (or press Alt + Shift + right arrow) so your
screen resembles Figure A-24. After the subtasks (Tasks 2 through 8) are in-
dented, notice that Task 1 automatically becomes boldface, which indicates
that it is a summary task. A collapse symbol appears to the left of the new
summary task name. Clicking the collapse symbol (filled triangle sign) will
collapse the summary task and hide the subtasks beneath it. When subtasks
are hidden, an expand symbol (unfilled triangle sign) appears to the left of the
summary task name. Clicking the expand symbol will expand the summary
task. Also, notice that the symbol for the summary task on the Gantt chart
has changed from a blue to a black line with arrows indicating the start and
H E L P
If you accidentally skip a row, highlight the task row, right-click, and select Insert Task. To edit a task
entry, click the text for that task, and either type over the old text or edit the existing text. Entering tasks
in Project 2013 and editing the information is similar to entering and editing data in an Excel spread-
sheet. You can also easily copy and paste text from Excel or Word into Project, such as the list of tasks.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.27
end dates. The Task Mode has also changed to make this task Automatically
scheduled. You’ll learn more about this feature later. For now, focus on enter-
ing and indenting the tasks to create the WBS.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-24 Indenting tasks to create the WBS hierarchy
Expand or collapse
symbols by
Summary tasks Indent task
Summary task
symbol
3. Create other summary tasks and subtasks. Create subtasks and summary
tasks for the other process groups by following the same steps. Indent Tasks
10 through 13 to make Task 9 a summary task. Indent Tasks 15 through 20
to make Task 14 a summary task. Indent Tasks 22 through 26 to make Task
21 a summary task. Indent Tasks 28 through 30 to make Task 27 a summary
task. Widen the Task Name column to see all of your text, as needed.
Numbering Tasks
To display automatic numbering of tasks using the standard tabular numbering system for
a WBS:
1. Show outline numbers. Click the Format tab, and then click the Outline
Number checkbox under the Show/Hide group. Project 2013 adds the appro-
priate WBS numbering to the task names.
2. Show project summary task. Click the Project Summary Task checkbox just
below the Outline Number checkbox. Scroll to the top of the file to see that
a new task, Project A+, the title of the project, has been added under row 0.
Your file should resemble Figure A-25.
T I P
To change a task from a subtask to a summary task or to change its level in the WBS, you can “out-
dent” the task. To outdent the task, click the cell of the task or tasks you want to change, and then click
the Outdent Task button (the button just to the left of the Indent Task button). You can also press Alt +
Shift + Right Arrow to indent tasks and Alt + Shift + Left Arrow to outdent tasks.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.28
Saving Project Files Without a Baseline
An important part of project management is tracking performance against a baseline, or
approved plan. It is important to wait until you are ready to save your file with a baseline
because Project 2013 will show changes against a baseline. Since you are still developing
your project file for the Project A+ project, you want to save the file without a baseline,
which is the default way to save a file. Later in this appendix, you will save the file with
a baseline. You will then enter actual information to compare planned and actual perfor-
mance data.
To save a file without a baseline:
1. Save your file. Click the File tab and then click Save, or click the Save button
on the Quick Access toolbar.
2. Enter a filename. In the Save dialog box, type mywbs in the File name text
box. Browse to the location in which you want to save the file, and then click
Save. Remember that you can move the Split bar to show more or fewer
columns.
3. Close Project 2013. Click the Close icon to exit Project 2013.
Outline
numbers
Project summary
task
Outline number and
project summary
check boxes
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-25 Adding automatic outline numbers and a project summary task
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.29
DEVELOPING THE SCHEDULE
Many people use Project 2013 for its scheduling features. The first step in using these fea-
tures, after inputting the WBS for the project, is to change calendars, if needed, and then
enter durations for tasks or specific dates when tasks will occur. You must also enter task
dependencies in order for schedules to adjust automatically and to do critical path analy-
sis. After entering durations and task dependencies, you can view the network diagram,
critical path, and slack information.
Calendars
The standard Project 2013 calendar assumes that working hours are Monday through Fri-
day, from 8:00 a.m. to 5:00 p.m., with an hour for lunch from noon until 1:00 p.m. In ad-
dition to the standard calendar, Project 2013 also includes a 24 Hours calendar and Night
Shift calendar. The 24 Hours calendar assumes resources can work any hour and any day
of the week. The Night Shift calendar assumes working hours are Monday through Satur-
day, from 12:00 a.m. to 3:00 a.m., 4:00 a.m. 8 a.m., and 11 p.m. to 12 a.m. You can create
a different base calendar to meet your unique project requirements.
To create a new base calendar:
1. Open a new file and access the Change Working Time dialog box. With
Project 2013 open, click the Project tab, and then click the Change Working
Time button under the Properties group. The Change Working Time dialog
box opens, as shown in Figure A-26.
2. Name the new base calendar. In the Change Working Time dialog box, click
Create New Calendar. The Create New Base Calendar dialog box opens. Click
the Create new base calendar radio button, type Fiscal as the name of the
new calendar in the Name text box, and then click OK.
3. Change the fiscal year start. In the Change Working Time dialog box, click
Options at the bottom of the screen. Change the fiscal year to start in Octo-
ber instead of January. Review other options in this screen, and then click
OK twice.
H E L P
If you want to download the Project 2013 file mywbs.mpp to check your work or continue to the next
section, a copy is available on the companion website at www.intropm.com.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.30
You can use this new calendar for the whole project, or you can assign it to specific
resources on the project.
To assign the new calendar to the whole project:
1. Open the Project Information dialog box. Click the Project tab, and then
click the Change Working Time button.
2. Select a new calendar. Click the For calendar list arrow to display a list of
available calendars. Select your new calendar named Fiscal from this list, and
then click OK.
To assign a specific calendar to a specific resource:
1. Assign a new calendar. Click the View tab, and then click the Resource
Sheet button under the Resource Views group. Type Adam in the Resource
Name column, press Enter, and then select the word Adam.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-26 Change Working Time dialog box
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.31
2. Select the calendar. Click the cell under the Base column that says Standard
on the right part of the screen for Adam. Click the list arrow to display the
options, and then select Fiscal as shown in Figure A-27.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-27 Changing calendars for specific resources
3. Block off vacation time. Double-click the resource name Adam to display
the Resource Information dialog box, and then click the Change Working
Time button, located on the General tab in the Resource Information dialog
box. You can block off vacation time for people by selecting the appropriate
days on the calendar and marking them as nonworking days. Click OK to
accept your changes, and then click OK to close the Resource Information
dialog box.
4. Close the file without saving it. Click the Close box, and then click No when
you are prompted to save the file.
Task Durations
Recall that duration includes the actual amount of time spent working on an activity plus
elapsed time. Duration does not equal effort. For example, you might have an activity that
you estimate will take one person 40 hours of effort to complete, but you allow two weeks
on a calendar for its duration. You can simply enter 2w (for two weeks) in the Duration
column for that activity (called a task in Project 2013).
Manual and Automatic Scheduling
If you have used earlier versions of Project, you probably noticed that when you entered
an item in the Task Name column, it was automatically assigned a duration of one day,
and Start and Finish dates were also automatically entered. This is still the case in Project
2013 if you use automatic scheduling for a task. If you use manual scheduling, no dura-
tions or dates are automatically entered. The other big change with manual scheduling
is that summary task durations are not automatically calculated based on their subtasks
when they are set up as manually scheduled tasks. Figure A-28 illustrates these differ-
ences. Notice that the Manual subtask 1 had no information entered for its duration, start,
or finish dates. Also note that the duration for Manual summary task 1’s duration is not
dependent on the durations of its subtasks. For the automatic summary task, its duration
is dependent on its summary tasks, and information is entered for all of the durations,
start, and end dates. You can switch between automatic and manual scheduling for tasks
in the same file, as desired, by changing the Task Mode.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.32
When you move your cursor over the Task Mode column (shown in the far left in Fig-
ure A-28) Project 2013 displays the following information:
A task can be either Manually Scheduled or Automatically Scheduled.
Manually Scheduled tasks have user-defined Start, Finish, and Duration val-
ues. Project will never change their dates, but may warn you if there are po-
tential issues with the entered values.
Automatically Scheduled tasks have Start, Finish, and Duration values cal-
culated by Project based on dependencies, constraints, calendars, and other
factors.
Project Help provides the following example of using both manual and automatic
scheduling. You set up a preliminary project plan that’s still in the proposal stage. You
have a vague idea of major milestone dates but not much detail on other dates in vari-
ous phases of the project. You build tasks and milestones using the Manually Scheduled
task mode. The proposal is accepted and the tasks and deliverable dates become more
defined. You continue to manually schedule those tasks and dates for a while, but as
certain phases become well-defined, you decide to switch the tasks in those phases to
the Automatically Scheduled task mode. By letting Project 2013 handle the complexi-
ties of scheduling, you can focus your attention on those phases that are still under
development.
Duration Units and Guidelines for Entering Durations
To indicate the length of a task’s duration, you normally type both a number and an ap-
propriate duration symbol. If you type only a number, Project 2013 automatically enters
days as the duration unit. Duration unit symbols include:
d = days (default)
w = weeks
m = minutes
h = hours
mo or mon = months
ed = elapsed days
ew = elapsed weeks
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-28 Manual versus automatic scheduling
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.33
For example, to enter two weeks for a task’s duration, type 2w in the Duration col-
umn. (You can also type wk, wks, week, or weeks, instead of just w.) To enter four days for
a task’s duration, type 4 or 4d in the Duration column. You can also enter elapsed times
in the Duration column. For example, 3ed means three elapsed days, and 2ew means two
elapsed weeks.
You would use an elapsed duration for a task like “Allow cement to dry.” The cement
will dry in exactly the same amount of time regardless of whether it is a workday, a week-
end, or a holiday. Project’s default calendar does not assume that work is done on week-
ends. You will learn to change the calendar later in this appendix.
It is important to follow a few important rules when entering durations:
To mark a task as a milestone, enter 0 for the duration. You can also mark tasks
that have a non-zero duration as milestones by checking the “Mark task as mile-
stone” option in the Task Information dialog box on the Advanced tab. You sim-
ply double-click a task to access this dialog box. The milestone symbol for those
tasks will appear at their start date.
You can enter the exact start and finish dates for activities instead of entering
durations in the automatic scheduling mode. To enter start and finish dates,
move the split bar to the right to reveal the Start and Finish columns. You
normally only enter start and finish dates in this mode when those dates are
certain.
If you want task dates to adjust according to any other task dates, do not en-
ter exact start and finish dates. Instead, enter durations and then establish
dependencies to related tasks.
To enter recurring tasks, such as weekly meetings, select Recurring Task
from the Task button under the Task tab, Insert group. Enter the task name,
the duration, and when the task occurs. Project 2013 will automatically in-
sert appropriate subtasks based on the length of the project and the number
of tasks required for the recurring task.
Project 2013 uses a default calendar with standard workdays and hours.
Remember to change the default calendar if needed, as shown earlier.
Next, you will set task durations in the file that you created and saved in the previous
section. If you did not create the file named mywbs.mpp, you can download it from the
companion website.
Use the information in Figure A-29 to enter durations. The Project 2013 row number
is shown to the left of each task name in the table.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.34
Entering Task Durations
To enter task durations:
1. Enter the duration for Task 2. Open the mywbs file, and move the split bar to
the right, if needed, to reveal the Duration, Start, and Finish columns. Click
the Duration column for row 2, Stakeholder identification, type 1w, and
then press Enter. Notice that the duration for the first task, Initiating, also
changed since it is a summary task and is an Automatically scheduled task,
Task Row Task Name Duration
2 Stakeholder identification 1w
3 Stakeholder register completed 0
4 Stakeholder management strategy completed 0
5 Project charter 1w
6 Project charter completed 0
7 Kickoff meeting 3d
8 Kickoff meeting completed 0
10 Project schedule 5d
11 Gantt chart completed 0
12 Scope statement 8d
13 Initial scope statement completed 0
15 Deliverable 1 3w
16 Deliverable 2 5w
17 Deliverable 3 6w
18 Deliverable 1 completed 0
19 Deliverable 2 completed 0
20 Deliverable 3 completed 0
24 Progress report 1 0
25 Progress report 2 0
28 Final project report 4d
29 Final presentation 4d
30 Project completed 0
Schwalbe Publishing 2013.
FIGURE A-29 Task durations
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.35
as shown in the Task Mode column. When you created summary tasks earlier,
Project changed their scheduling mode to Automatic. Also notice that the
Start and Finish date for Task 2 remain blank, since that task is a Manually
scheduled task.
2. Enter the duration for Task 3. In the Duration column for row 3, Stakeholder
register completed, type 0, and then press Enter. Remember that a task with
zero duration is a milestone. Notice the milestone or diamond symbol next to
the date 9/9 that appears on the Gantt chart, as shown in Figure A-30.
Adjust the Task Name column width to see all of the text, and use the Zoom
slider on the bottom right of the screen to change the length of the Gantt
chart bars.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-30 Entering task durations
3. Make all tasks Automatically scheduled tasks. To save time because you do
want most of the tasks to be automatically scheduled, select all of the
tasks by clicking the Task Name column heading, and then click the Auto
Schedule button under the Task tab, Tasks group. Most of the durations
change to 1.
4. Enter remaining task durations. Continue to enter the durations using the in-
formation in Figure A-29 or Figure A-31. Do not enter durations for tasks not
listed in the figure. Notice that the Planning Wizard dialog box displays when
you make the same entry several times in a row, such as after task 20.
Click OK to close the dialog box. You can adjust the column widths and
Zoom, if desired.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.36
5. Insert a recurring task above Task 26, Team meetings. Click Team review
meetings (Task 26) in the Task Name column to select that task. Click the
Task tab, and click the Task button drop-down box under the Insert group,
and then click Recurring Task. The Recurring Task Information dialog box
opens.
6. Enter task and duration information for the recurring task. Type Team
review meetings as the task title in the Task Name text box. Type 15min in
the Duration text box. Select the Weekly radio button under Recurrence
pattern. Make sure that 1 is entered in the Recur every list box. Select the
Thursday check box. In the Range of recurrence section, type 9/12/13 in the
Start text box (or select it with the drop-down calendar), click the End by
radio button, and then type 12/5/13 in the End by text box (or select it in
the calendar), as shown in Figure A-32. The new recurring task will appear
above Task 26, Team review meetings, when you are finished. Delete task
40, Team review meetings, by right clicking anywhere in row 40 and select-
ing Delete Task.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-31 Entering more durations
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.37
7. View the new summary task and its subtasks. Click OK. Project 2013 in-
serts a new Team review meetings subtask in the Task Name column. To col-
lapse the recurring task, click the collapse symbol. Move your cursor over the
Recurring Task symbol in the Indicator column for row 26 to read the note
about it occurring 13 times. Notice that the recurring task appears on the ap-
propriate dates on the Gantt chart.
8. Adjust the columns displayed and the timescale. Move the split bar so that
only the Task Name and Duration columns are visible. If needed, increase
the Duration column’s width so all of the text is visible. Click the Zoom Out
button on the Zoom slider in the lower right of the screen to display all of the
symbols in the Gantt chart. Your screen should resemble Figure A-33.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-32 Recurring task information dialog box
T I P
You can also enter a number of occurrences instead of an End by date for a recurring task. You might
need to adjust the End by date after you enter all of your task durations and dependencies. Remem-
ber, the date on your computer determines the date listed as Today in the calendar.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.38
9. Save your file and name it. Click File on the Menu bar, and then click Save
As. Enter myschedule as the filename, and then save the file to the desired
location on your computer or network. Notice that all of the tasks still begin
on 9/9/13. This will change when you add task dependencies. Keep this file
open for the next set of steps.
Establishing Task Dependencies
To use Project 2013 to adjust schedules automatically and perform critical path analysis,
you must determine the dependencies or relationships among tasks. There are several
different methods for creating task dependencies: using the Link Tasks button, using the
Predecessors column of the Entry table or the Predecessors tab in the Task Information
dialog box, or clicking and dragging the Gantt chart symbols for tasks with dependencies.
You will use the first two methods in the following steps.
To create dependencies using the Link Tasks button, highlight tasks that are related
and then click the Link Tasks button under the Task tab, Schedule group. For example, to
create a finish-to-start (FS) dependency between Task 1 and Task 2, click any cell in row
1, drag down to row 2, and then click the Link Tasks button. The default type of link is
finish-to-start. In the Project A+ file, you will also set up some other types of dependencies
and use the lag option to set up overlaps between dependent tasks.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-33 All task durations and recurring task entered
T I P
To select adjacent tasks, click and drag the mouse to highlight them. You can also click the first task,
hold down the Shift key, and then click the last task. To select nonadjacent tasks, hold down the Con-
trol (Ctrl) key as you click tasks in order of their dependencies.
When you use the Predecessors column of the Entry table to create dependencies, you
must manually enter the information. To create dependencies manually, type the task row
number of the preceding task in the Predecessors column of the Entry table. For example,
Task 3 has Task 2 as a predecessor, which can be entered in the Predecessors column,
meaning that Task 3 cannot start until Task 2 is finished. To see the Predecessors column
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.39
of the Entry table, move the split bar to the right. You can also double-click on the
task, click the Predecessors tab in the Task Information dialog box, and enter the
predecessors there.
Next, you will enter the predecessors for tasks as indicated. You will create some de-
pendencies by manually typing the predecessors in the Predecessors column, some by
using the Link Tasks button, and the remaining dependencies by using whichever method
you prefer.
To link tasks or establish dependencies for Project A1:
1. Display the Predecessors column in the Entry table. Move the split bar to
the right to reveal the full Predecessors column in the myschedule.mpp file
you saved in the previous section. Widen the Task Name or other columns, if
needed.
2. Highlight the cell where you want to enter a predecessor, and then type the
task number for its predecessor task. Click the Predecessors cell for Task 3,
Stakeholder register completed, type 2, and press Enter. Notice that as you
enter task dependencies, the Gantt chart changes to reflect the new schedule.
Also notice that several cells become highlighted, showing the Visual Change
Highlights feature of Project 2013.
3. Enter predecessors for Task 4 and view the Task Path. Click the Predeces-
sors cell for Task 4, type 2, and press Enter. Click the Format tab, and then
click the Task Path button under the Bar Styles group. Experiment with
the options to highlight Predecessor, Driving Predecessors, Successors, and
Driven Successors, and then click Remove Highlighting.
4. Establish dependencies using the Link Tasks button. To link Tasks 5
and 6, click the task name for Task 5 in the Task Name column and drag
down through Task 6. Then, in the Task tab, click the Link Tasks button
(looks like a chain link) under the Schedule group. Notice that the result is
the same as typing 5 in the Predecessors column for Task 6, as shown in
Figure A-34.
Link task icon Predecessors Changes in Gantt Chart
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-34 Entering predecessor
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.40
5. Enter dependencies and lag time using the Task Information dialog box.
Double-click the Task Name for task 5, Project charter, and then click the
Predecessors tab in the Task Information dialog box. Click the cell under
Task Name, and then click the Task Name down arrow and select Stake-
holder identification. Click the Type drop-down arrow to see the various
types of dependencies. For this task, you will keep the default type of finish-
to-start. Click the Lag drop-down arrow, then type -50% and press Enter.
(Lag means there is a gap between tasks, and lead or negative lag means
there is an overlap). Your screen should resemble Figure A-35. Click OK to
close the dialog box. Notice that the Predecessor column for task 5 displays
2FS-50%, meaning there is a finish-to-start relationship with task 2 and a
lag of -50%, meaning the task can start when task 2 is 50% completed.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-35 Entering predecessor information using the task information dialog box
6. Enter remaining dependencies. Link the other tasks by either manually
entering the predecessors into the Predecessors column, by using the Link
Tasks button, or using the Task Information dialog box. Use the information
in Figure A-36 to make your entries, being careful to leave some of the pre-
decessors blank, as shown. If you have entered all data correctly, the project
should end on 12/6, or December 6, 2013.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.41
7. Adjust several dates. You know that you have to deliver the two progress re-
ports on specific dates. Click the Start dates for Tasks 24 and 25 and change
those dates to October 10 and November 7. Also change the Finish dates for
tasks 22 and 23 to December 4 to make those dates more realistic. Project
Schwalbe Publishing 2013.
FIGURE A-36 Predecessor information for Project A
Task Row Task Name Predecessors
3 Stakeholder register completed 2
4 Stakeholder management strategy completed 2
5 Project charter 2FS-50%
6 Project charter completed 5
7 Kickoff meeting 2,6
8 Kickoff meeting completed 6,7
9 Planning
10 Schedule 5,12FS-50%
11 Gantt chart completed 10
12 Scope statement 5
13 Initial scope statement completed 12
14 Executing
15 Deliverable 1 12
16 Deliverable 2 18
17 Deliverable 3 18
18 Deliverable 1 completed 15
19 Deliverable 2 completed 16
20 Deliverable 3 completed 17
21 Monitoring and Controlling
22 Actual hours tracking 2
23 Project documents updates 3
24-40 Progress Report 1 through Closing
41 Final project report 18,19,20
42 Final presentation 18,19,20
43 Project completed 41,42
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.42
2013 will display a yellow warning symbol to remind you that you are chang-
ing default dates, which is fine in these examples.
8. Review the file. If needed, click the Zoom Out button on the Zoom slider to
adjust the timescale so all of the information shows on your screen. When
you finish, your screen should resemble Figure A-37. Double-check your
screen to make sure you entered the dependencies correctly.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-37 Project A+ file with durations and dependencies entered
9. Preview and save your file. Click the File tab, and then select Print to pre-
view and print your file. Click Page Setup, and then click the option to Fit
to 1 so it will print on one page, as shown in Figure A-38. Be careful before
printing any Project 2013 files so you do not waste a lot of paper. When you
are finished, click Save to save your file again. Keep the file open for the next
set of steps.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.43
Gantt Charts, Network Diagrams, and Critical Path Analysis
Project 2013 shows a Gantt chart as the default view to the right of the Entry table. As
described earlier in this text, network diagrams are often used to show task dependen-
cies. This section explains important information about Gantt charts and network dia-
grams and describes how to make critical path information more visible in the Gantt
Chart view.
Because you have already created task dependencies, you can now find the critical
path for Project A+. You can view the critical tasks by changing the color of those items in
the Gantt Chart view. Tasks on the critical path will automatically be red in the Network
Diagram view. You can also view critical path information in the Schedule table or by us-
ing the Critical Tasks report.
To make the text for the critical path tasks appear in red on the Gantt chart:
1. Change the critical tasks format. Using the myschedule.mpp file you previ-
ously saved, click the Format tab, and then click the Critical Tasks check
box in the Bar Styles group, as shown in Figure A-39. Notice that the critical
tasks display in red in the Gantt chart. You can also quickly change the Gantt
Chart Style by clicking one of those options.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-38 Project A+ set up to print on one page
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.44
2. View the network diagram. Click the View tab, and then click the Network
Diagram button under the Task Views group. Click the Zoom Out button on
the Zoom slider several times and watch the view change. Figure A-40 shows
all of the tasks in the Project A+ network diagram. Note that milestone tasks,
such as Stakeholder management strategy completed, the fourth box on the
top, appear as pointed rectangular boxes, while other tasks appear as rect-
angles. Move your cursor over that box to see it in a larger view. Notice that
tasks on the critical path automatically appear in red. A dashed line on a net-
work diagram represents a page break. You often need to change some of the
default settings for the Network Diagram view before printing it. As you can
see, network diagrams can be messy, so you might prefer to highlight critical
tasks on the Gantt chart as you did earlier for easier viewing.
Critical tasks check box
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-39 Formatting critical tasks
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-40 Network diagram view
3. View the schedule table. Click the Gantt Chart button under the View tab
to return to Gantt Chart view. Right-click the Select All button to the left of
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.45
the Task Mode column heading and select Schedule. Alternatively, you can
click the View tab and click the Tables button under the Data group
and then select Schedule. The Schedule table replaces the Entry table
to the left of the Gantt Chart. Your screen should resemble Figure A-41.
This view shows the start and finish (meaning the early start and early fin-
ish) and late start and late finish dates for each task, as well as free and total
slack. Right-click the Select All button and select Entry to return to the En-
try table view.
Select All
button Schedule table
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-41 Schedule table view
4. Open the Project Overview report. Click the Report tab, and click the Dash-
boards button under the View Reports group, and then click Project Over-
view to open the Overview Reports, as shown in Figure A-42. Note that the
report shows the milestones due and % complete. Examine other reports, as
desired.
5. Close the report and save your file. When you are finished examining the
reports, click the Save button on the Quick Access toolbar to save your final
myschedule.mpp file, showing the Entry table and Gantt chart view. Close
Project 2013 if you are not continuing to the next section.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.46
Next you will explore some of the cost and resource management features of Project 2013.
PROJECT COST AND RESOURCE MANAGEMENT
Many people do not use Project 2013 for cost or resource management. Some organiza-
tions have more established cost management software products and procedures in place,
and many people simply do not know how to use the cost or resource management fea-
tures of Project 2013. However, these features make it possible to integrate total project
information more easily. This section offers brief instructions for entering fixed and vari-
able cost estimates, assigning resources to tasks, viewing resource histograms, and enter-
ing actual cost and schedule information after establishing a baseline plan. It also explains
how to use Project 2013 for earned value management. More details on these features are
available in Project Help, online tutorials, or other texts. See other chapters of this text for
information on some of these concepts.
Entering Fixed and Variable Cost Estimates
You can enter costs as fixed or variable. Fixed costs include costs like a specific quantity
of materials or costs for consultants hired at a fixed cost. Variable costs vary based on the
amount of materials or hours people work. On many projects, human resource costs are
the largest percentage of total project costs.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-42 Project Overview report
H E L P
If you want to download the Project 2013 file myschedule.mpp to check your work or continue to the
next section, a copy is available on the companion website at www.intropm.com.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.47
Entering Fixed Costs in the Cost Table
The Cost table allows you to easily enter fixed costs related to each task. You will enter a
fixed cost of $200 related to Task 15, Deliverable 1.
To enter a fixed cost:
1. Display the Cost Table view. Open your Project 2013 file myschedule.mpp,
if necessary. Right-click the Select All button to the left of the Task Mode
column heading and select Cost. The Cost table replaces the Entry table to
the left of the Gantt chart. Widen the Task Name column and then move the
Split bar to the right, as needed, until you see the entire Cost table.
2. Enter a fixed cost. In the Fixed Cost column for Task 15, Deliverable 1, type
200 and press Enter. Notice that the Total Cost and Remaining Cost columns
reflect this entry, and changes are made to the summary task, Executing, as
well. Your screen should resemble Figure A-43.
Entering Resource Information and Cost Estimates
Several methods are available for entering resource information in Project 2013. The Re-
source Sheet allows you to enter the resource name, initials, resource group, maximum
units, standard rate, overtime rate, cost/use, accrual method, base calendar, and code.
Once you have established resources in the Resource Sheet, you can assign those re-
sources to tasks in the Entry table with the list arrow that appears when you click a cell in
the Resource Names column. The Resource Names column is the last column of the Entry
table. You can also use other methods for assigning resources, such as using the Assign
Resources button or using the split window, which is the recommended approach to have
the most control over how resources are assigned because Project 2013 makes several as-
sumptions about resources assignments that might mess up your schedule or costs. Next,
Select all
button
Fixed Cost column
of cost table
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-43 Entering a fixed cost
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.48
you will enter information for three people working on Project A+ and assign them to a
few tasks using various methods.
To enter basic information about each person into the Resource Sheet and assign
them to tasks using the Entry table and toolbar:
1. Display the Resource Sheet view. Click the View tab, and then click the Re-
source Sheet button under the Resource Views group.
2. Enter resource information. Enter the information from Figure A-44 into the
Resource Sheet. The three resources names are Kathy, Dan, and Scott. The
Std. Rate and Ovt. Rate for Kathy is 40, and the Std. and Ovt. Rates for Dan
and Scott are 30. Type the information as shown and press the Tab key to
move to the next field. When you type the standard and overtime rates, you
can just type the number, such as 40, and Project 2013 will automatically en-
ter $40.00/hr. The standard and overtime rates entered are based on hourly
rates. You can also enter annual salaries by typing the annual salary number
followed by /y for “per year.” Your screen should resemble Figure A-44 when
you are finished entering the resource data.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-44 Resource sheet view with resource data entered
T I P
If you know that some people will be available for a project only part time, enter their percentage of
availability in the Max Units column of the Resource Sheet. Project 2013 will then automatically assign
those people based on their maximum units. For example, if someone can work only 50% of his or her
time on a project throughout most of the project, enter 50% in the Max Units column for that person.
When you enter that person as a resource for a task, his or her default number of hours will be 50%
of a standard eight-hour workday, or four hours per day. You can also enter the number of hours each
person is scheduled to work, as shown later.
3. Assign resources to tasks. From the View tab, select the Gantt Chart button
under the Task Views group, and then click the Select All button and switch
back to the Entry table. Move the Split bar to reveal the Resource Names
column, if needed.
4. Assign Kathy to task 2, Stakeholder identification. Click in the Resource
Names cell for row 2. Click the list arrow, click the checkbox next to Kathy,
and then press Enter or click on another cell. Notice that the resource
choices are the names you just entered in the Resource Sheet. Also notice
that after you select a resource by checking the appropriate checkbox, his
or her name appears on the Gantt chart, as shown in Figure A-45. To assign
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.49
more than one resource to a task using the list arrow, simply select another
checkbox. Note that Project 2013 will assume that each resource is assigned
full-time to tasks using this method since the task is in automatically sched-
ule mode. Also note that you can use filter by Resource Names to only show
tasks assigned to specific resources after you enter the resources.
Filter Resource Names
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-45 Resource assigned using the entry table
5. Assign two resources to a task. Click in the Resource Names cell for row 5
(Project charter). Click the list arrow, then click the checkbox next to Dan
and Kathy, and then press Enter. Notice that both resource names appear
in the Resource Names column and on the Gantt chart for this task, and the
task duration remains at 1 week.
6. Change the resource assignments. Click in the Resource Names cell for Task
2, Stakeholder identification, click the list arrow, and add Dan as another
resource. Notice that when you change an original resource assignment, Proj-
ect prompts you for how you want to handle the change, as shown in Figure
A-46. Click the Exclamation point symbol to read your options. In past ver-
sions of Project, resource additions would change schedules automatically
unless the user entered them a certain way. Now you have much more con-
trol of what happens to your schedule and costs. In this case, we do want to
accept the default of keeping the duration constant.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-46 Options when additional resources are added to tasks
7. Review the cost table. Right-click the Select All button to the left of the Task
Mode column heading and select Cost. Notice that costs have been added to
the tasks where you added resources. Project assumes that people are as-
signed full-time to tasks. It is showing a cost of $2,800 each for Task 2 and
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.50
Task 5. In the next section, you will see how to control resources entries even
more. First, right-click the Select All button to the left of the Task Mode col-
umn heading and select Entry to return to the Entry table.
To control resource and work assignments using the Resource details window:
1. Open the Resource Form. Notice the red symbols in the Indicator columns
for rows/tasks 2 and 5. Move your cursor over the symbol to read the message
about resources being overallocated. Click the Task Name for row 2, Stake-
holder identification, click the Resource tab, and then click the Details but-
ton under the Properties group. A Resource Form is displayed at the bottom
of the screen, as shown in Figure A-47. Project 2013 assumes every task is
assigned full-time, so since Kathy is scheduled on two tasks on the same day,
it says she is overallocated.
Task mode
indicator Change # work hours
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-47 Changing Work hours for tasks
T I P
You can right-click on the lower screen to review see additional forms/views. You can click the Select All
button at the top right of the screen to view different tables at the top of the screen. You want to make
sure that resource and work hour assignments do not adjust your schedules in ways you did not intend.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.51
2. Make tasks 2 and 5 manually scheduled. Right-click the Select All button
and switch to the Entry table. Click the drop-down in the Task Mode column
for Tasks 2 and 5 to make them manually scheduled. When you assigned re-
sources, Project 2013 assumed they were working full-time or 40 hours per
week on each task. Because these two tasks have days that overlap, there is
an overallocation. You do not expect each resource to work that many hours,
so you can change them by using the Resource Form.
3. Change the number of Work hours. Select Task 2, Stakeholder identification
in the top window, and then click the Work column in the Resource Form
window for Kathy in the lower part of your screen. Type 10h, press Enter,
and again type 10h and press Enter for the next task, Task 5, Project charter,
and then click the OK button. Click Next to see Dan’s Resource Form, as
shown in Figure A-47.
4. Enter additional work hours and review the Gantt chart. Change Dan’s
work hours to 10h for Tasks 2 and 5 as well. Notice in the Gantt chart that
the duration for Tasks 2 and 5 are still one week. The overallocation indicator
should now disappear because the number of hours has been reduced from
the default of 8 hours per day, or 40 hours for a 5-day task. To remove the Re-
source Form, click Details on the Ribbon under the Resource tab.
5. Examine the new cost information. Right-click the Select All button, and
then click Cost to view the Cost table. Tasks 2 and 5 each show only $700 for
Total Cost.
6. Close the file without saving it. Close the file, but do not save the changes
you made.
Using the Team Planner Feature
Another way to assign resources and reduce overallocations is by using the Team Planner fea-
ture. Assume you have two people assigned to work on a project, Brian and Cindy, as shown
in Figure A-48. Notice that Brian is assigned to work on both Task 1 and Task 2 full-time the
first week. Therefore, Brian is overallocated. Cindy is scheduled to work on Task 3 full-time
the second week, and Task 4, also scheduled for the second week, is not assigned yet.
Overallocation
indicator
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-48 Overallocated resource
You can click the Team Planner view under the View tab to see a screen similar to the
top section of Figure A-49. Notice that Brian has both Tasks 1 and 2 assigned to him at the
same time. These tasks and Brian’s name display in red to show the overallocation. Cindy
is assigned Task 3 the following week, and Task 4 is unassigned. By simply clicking and
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.52
dragging Task 4 straight up so it is under Brian in Week 2 and Task 2 straight down so it is
under Cindy in Week 1, you can reassign those tasks and remove Brian’s overallocation, as
shown in the bottom section of Figure A-49. Many people will appreciate the simplicity of
this feature, first introduced in Project 2010!
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-49 Adjusting resource assignments using the Team Planner feature
Entering Baseline Plans, Actual Costs, and Actual Times
After entering information in the Task Name column, establishing task durations and de-
pendencies, and assigning costs and resources, you are ready to establish a baseline plan.
By comparing the information in your baseline plan to actual progress during the course
of the project, you can identify and solve problems. After the project ends, you can use
the baseline and actual information to plan similar, future projects more accurately. To
use Project 2013 to help control projects and view earned value information, you must es-
tablish a baseline plan, enter actual costs, and enter actual durations. In the next series of
steps you will use a new file called tracking.mpp that you downloaded from the companion
website (www.intropm.com).
To save a file as a baseline and enter actual information:
1. Open the file called tracking.mpp. The file should be showing the Cost table
view. Notice that this short project was planned to start on January 7, 2013
and end on February 13 of the same year, have three resources assigned to it,
and cost $11,200. Click the Project tab, click the Set Baseline button under
the Schedule group, and click Set Baseline, as shown in Figure A-50.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.53
2. Save the file as a baseline. Examine the Set Baseline dialog box. Click the
drop-down arrow to see that you can set up to ten baselines. Accept the de-
fault to save the entire project. Click OK. Notice that the Baseline column
changes to blue.
3. Display the Tracking table. Click the Task tab, right-click the Select All but-
ton and then click Tracking to view the tracking table. Move the split bar to
the right to reveal all of the columns in the table, if needed. Move your cursor
over each tracking button on the Ribbon in the top line of the Schedule group
to see what it does. Your screen should resemble Figure A-51.
4. Mark Tasks 2 through 4 as 100% complete. Click the Task Name for Task
2, Subtask 1 under Main task 1, and drag down through Task 4 to highlight
those tasks. Click the 100% Complete button on the Ribbon. The columns
with dates, durations, and cost information should now contain data instead
of the default values, such as NA or 0. The % Comp. column should display
100%. Adjust column widths if needed. Your screen should resemble Figure
A-52. Notice that the Gantt chart bars for those three tasks now have a black
line through them.
Select All button Set baseline
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-50 Saving a baseline
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.54
5. Enter actual completion dates for Task 6. Click the Task Name for Task 6,
Subtask 1 under Main Task 2, click the Mark on Track drop-down, and then
click Update Tasks. The Update Tasks dialog box opens. For Task 6, enter the
Actual Start date as 1/28/13 (the same as the Current Start date) and the Ac-
tual Finish date as 2/11/13 (ten days later than the Current Finish date), as
shown in Figure A-53. Click OK. Notice how the information in the tracking
sheet has changed.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-51 Using the tracking table and tracking buttons
Tracking table Tracking buttons
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-52 Tracking table information
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.55
6. View the Tracking Gantt chart. Click the drop-down arrow on the far left of
the screen next to the Gantt chart, and then click Tracking Gantt to quickly
switch to that view. Move the split bar and adjust column widths as needed.
Use the horizontal scroll bar in the Gantt chart window to the right (move
the slider to the left) to see symbols on the Tracking Gantt chart. Use the
Zoom slider on the lower right of the screen to adjust the timescale so you
can see all of the symbols. Your screen should resemble Figure A-54. The
blue bar for Task 6 shows the actual time you just entered. Notice that the
delay in this one task on the critical path has caused the planned completion
date for the entire project to slip (now Feb 25 versus Feb 13). Also notice
the Indicator column to the far left. The check marks show that tasks are
completed.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-53 Update Tasks dialog box
Completion indicator Tracking Gantt chart
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-54 Tracking Gantt chart view
7. Save your file as a new file named myactuals.mpp. Click File on the Menu
bar, and then click Save As. Name the file myactuals, and then click Save.
Notice the additional information available on the Tracking Gantt chart. Completed
tasks have 100% next to their symbols on the Tracking Gantt chart. Tasks that have not
started yet display 0%. Tasks in progress, such as Task 5, show the percentage of the work
completed (35% in this example). The project summary task bar indicates that the entire
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.56
project is 57% complete. Viewing the Tracking Gantt chart allows you to easily see your
schedule progress against the baseline plan. After you have entered some actuals, you can
review earned value information for the initiating tasks of this project.
VIEWING EARNED VALUE MANAGEMENT DATA
Earned value management is an important project management technique for measuring
project performance. Because you have entered actual information, you can now view
earned value information in Project 2013. You can also view an earned value report using
the visual reports feature.
To view earned value information:
1. View the Earned Value table. Using the myactuals file you just saved (or
downloaded from the companion website), right-click the Select All button,
select More Tables, and double-click Earned Value. Move the split bar to
the right to reveal all of the columns, as shown in Figure A-55. Note that the
Earned Value table includes columns for each earned value acronym, such
as PV, EV, AC, SV, CV, etc. Also note that the EAC (Estimate at Completion)
is higher than the BAC (Budget at Completion) for Task 6 (and its summary
task, Task 5), where the task took longer than planned to complete. Task 0
shows a VAC (Variance at Completion) of ($3,360.00), meaning the project is
projected to cost $3,360 more than planned at completion. Remember that
not all of the actual information has been entered yet. Also note that the date
on your computer must be set later than the date of a completed task for the
data to calculate properly.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-55 Earned value table
2. View the earned value chart. Click the Report tab, and then click Costs un-
der the View Reports group, and then click Earned Value Report, as shown
in Figure A-56. You can experiment with different report options or click the
link to learn more about earned value, as desired.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.57
3. Close Project 2013 without saving the file. Click the File tab, click Close,
and select No when prompted to save the file. You can also exit Project 2013
and take a break, if desired.
Next you will use a few more features of Project 2013 to help tie your Project to other
applications.
INTEGRATING PROJECT 2013 WITH OTHER APPLICATIONS AND
APPS FOR OFFICE
Project 2013 provides several features to make it easy to integrate with other applications.
For example, you can copy data between Project 2013 and other applications (including
the timeline), or you might want to create hyperlinks to project documents created in
Word, Excel, PowerPoint, or other applications from within your project files. You can also
purchase and add new apps to Project 2013 from Microsoft’s Office Store.
Copying Information Between Applications
Most people are familiar with copying information between Office applications. For ex-
ample, you can highlight a column of data in Excel, select Copy, and then select Paste in
Project 2013 or other applications. You can also create a new Project 2013 file from an ex-
isting Excel file by select New from Excel Workbook. It is also easy to copy a timeline from
Project 2013 into another application.
To copy a timeline from Project 2013:
1. Open another Project 2013 template file. Start Project 2013, and open a tem-
plate file, such as Residential Construction, as shown in Figure A-57. Notice
the timeline near the top of the screen.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-56 Earned value report
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.58
2. Make changes to the Timeline. Move your cursor over the second item on the
Timeline called Site Work. Right-click Site Work, and select Remove from
Timeline.
3. Open the Insert Hyperlink dialog box. Click Task 4, right-click Apply for
Permits, and then click Add to Timeline. (Note that this milestone could be
worded better to indicate that it has no duration, such as Permit Applications
Submitted). Make other adjustments to the Timeline, as desired.
4. Copy the Timeline into PowerPoint. Click anywhere on the Timeline, and
then click the Copy Timeline button in the Copy group on the Ribbon, as
shown in Figure A-58, and select For Presentation.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-57 Residential construction template
Copy Timeline
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-58 Copy Timeline
5. Copy the Timeline into PowerPoint. Open PowerPoint, change the slide
layout, add a title to the slide, and change the theme, as desired, and then
right-click and select Paste picture. Your screen should resemble Figure A-59,
showing the Project 2013 Timeline in your presentation.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.59
Creating Hyperlinks to Other Files
Some people like to use their Project 2013 file as a main source of information for many
different project documents. To do this, you can simply insert a hyperlink to other docu-
ment files. For example, you can create a hyperlink to the file with the stakeholder regis-
ter you listed as a milestone in your Task Name column earlier.
To insert a hyperlink within a Project 2013 file:
1. Open the myschedule.mpp file. Use the file you saved earlier or download it
from the companion website. The Entry table and Gantt Chart view should
display.
2. Select the task in which you want to insert a hyperlink. Click the Task Name
for Task 3, Stakeholder register completed.
3. Open the Insert Hyperlink dialog box. Right-click in that cell, then click
Hyperlink. The Insert Hyperlink dialog box opens, as shown in Figure A-60.
You will have different folders visible based on your computer’s directory
structure.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-59 Timeline copied into PowerPoint
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.60
4. Double-click the filename of the hyperlink file. Change the Look in: informa-
tion until you find where you have saved the files you downloaded for this
appendix. Double-click the Word file named stakeholder register, and then
click OK. A Hyperlink button appears in the Indicators column to the left of
the Task Name for Task 3. Move your cursor over the hyperlink button until
the mouse pointer changes to the Hand symbol to reveal the name of the hy-
perlinked file. If you click on it, the file will open.
Using Project 2013 Apps
Microsoft has an Office Store where you can download special apps for Project 2013. New
apps are added often.
To explore Project 2013 apps:
1. Access the Office Store. With Project 2013 open, click the Project tab, then
click the Apps for Office button on the left of the Ribbon under the Apps
group. The Apps for Office dialog box opens, as shown in Figure A-61.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-60 Insert hyperlink dialog box
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.61
2. Explore the Office Store. Click the Office Store button. Your screen should
resemble Figure A-62, which shows the apps available on April 6, 2013. Read
information about various apps, and add them as desired.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-61 Apps for Office dialog box
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.62
You have really just touched the surface of Project 2013’s powerful features, but you
probably know more than most people who have this software! There are several books
with more detailed information on using Project 2013 that you can use to learn even
more, or you can experiment with the software and Help feature to understand it more.
Created using Microsoft Project, used with permission from Microsoft.
FIGURE A-62 New Apps for Project on the Office Store (April, 2013)
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Guide to Using Microsoft Project 2013
A.63Discussion Questions
1. What are some unique features of project management software?
2. What are the new features of Project 2013?
3. How do you create a WBS in Project 2013?
4. How do you enter task durations and establish dependencies between tasks?
5. How can you make sure that resource assignments do not mess up your schedule?
6. How can you use the Team Planner to assign resources and reduce overallocations?
7. How do you establish a baseline in Project 2013 and enter actual information?
8. What type of information do you see in the Earned Value table?
9. How can you copy a Timeline from Project into other applications and access other applica-
tion files from within Project 2013?
10. Where can you access apps created for Project 2013?
Exercises
1. To make sure you understand the information in this appendix, perform the steps yourself.
Print out the following screens or send them to your instructor, as directed:
a. The adjusted Customer Service file as shown in Figure A-13.
b. The Schedule table view for the Customer Service file, similar to Figure A-16.
c. The Customer Service file filtered to show only milestones, similar to Figure A-21.
d. The mywbs file with automatic outline numbers and a project summary task, similar to
Figure A-25.
e. Create a new Project file called generic-wbs that shows the WBS for a generic project.
Make the main categories phase 1, phase 2, phase 3, and phase 4. Include at least
four tasks and one milestone under each of these main categories, using meaningful,
fictitious names for them. Enter 0 for the duration of the milestones, but do not enter
any durations for the other tasks. Be sure to indent tasks and show the outline numbers
before printing or submitting the file. Note: If you are doing a project for your class, you
can use data for that project instead.
2. Continue performing the steps in this appendix, starting with the section called Developing
the Schedule. Print out the following screens or send them to your instructor, as directed:
a. The myschedule file with durations and dependencies entered, similar to Figure A-38.
b. The earned value table, similar to Figure A-55.
c. Continue performing the steps, even if you do not have to print out more screens. Write
a one-to-two page paper describing the capabilities of Project 2013 and your opinion of
this software. What do you like and dislike about it?
3. Use some of the information in the body of the text (or find a sample WBS and Gantt chart
on your own). Enter the WBS into Project 2013 to practice your Project 2013 skills.
a. Review one of the sample WBSs. Indent tasks and use the automatic numbering fea-
ture. Print out or submit your file.
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Appendix A
A.64
b. Use the information in Chapter 6 under the section called Developing the Project
Schedule to create the Gantt chart for Project X. Also create the network diagram for
Project X. Make sure both will print out on one page each, then print or submit them to
your instructor. Assume the start date was 6/9/09, or June 9, 2009, to make your results
match the screen shots in Chapter 6. (Or use a similar project you find elsewhere).
c. Make up actual information for Project X (or a similar project). Assume some tasks are
completed as planned, some take more time, and some take less time. View and then
print out or submit the tracking Gantt chart.
4. If you are doing a team project as part of your class or for a project at work, use Project
2013 to create a detailed file describing the work you plan to do for the project.
a. Create a detailed WBS, including several milestones, estimate task durations, link
tasks, add tasks to the timeline, and enter resources and costs, assign resources, and
so on. Save your file as a baseline and print it out send it to your instructor, as desired.
b. Track your progress on your team project by entering actual cost and schedule informa-
tion. Create a new baseline file if there have been a lot of changes. View earned value
information when you are halfway through the project or course. Continue tracking your
progress until the project or course is finished. Print or submit your Gantt chart, Project
Summary report, Earned Value table, and relevant information to your instructor.
c. Write a two- to three-page report describing your experience. What did you learn about
Project 2013 from this exercise? How do you think Project 2013 helps in managing a
project? You may also want to interview people who use Project 2013 for their experi-
ences and suggestions.
Endnotes
1 TopTenREVIEWS™, “Project Management Software,” (project-management-software-
review.toptenreviews.com) (accessed June 17, 2009).
2 TopTenREVIEWS™, “Best Online Project Management Comparisons,” (online-project-
management-review.toptenreviews.com/) (accessed April 7, 2013).
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

5 whys A technique in which you repeatedly
ask the question “Why?” to help peel away
the layers of symptoms that can lead to the
root cause of a problem
acceptance decisions Decisions that deter-
mine if the products or services produced
as part of the project will be accepted or
rejected
activity An element of work normally found
on the WBS that has an expected duration,
cost, and resource requirements; also called
a task
activity attributes Information about each
activity, such as predecessors, successors,
logical relationships, leads and lags, resource
requirements, constraints, imposed dates,
and assumptions related to the activity
activity list A tabulation of activities to be
included on a project schedule
activity-on-arrow (AOA) A network
diagramming technique in which activities
are represented by arrows and connected at
points called nodes to illustrate the sequence
of activities; also called arrow diagramming
method (ADM)
actual cost (AC) The total of direct and
indirect costs incurred in accomplishing
work on an activity during a given period
adaptive software development (ASD) A
software development approach used when
requirements cannot be clearly expressed
early in the life cycle
agile Quick and coordinated in movement;
a method based on iterative and incremental
development, in which requirements and
solutions evolve through collaboration
agile methods An approach to managing
projects that includes a workflow comprised
of short iterations and incremental delivery
of software
agile software development A method for soft-
ware development that uses new approaches,
focusing on close collaboration between
programming teams and business experts
analogous estimates A cost-estimating
technique that uses the actual cost of a
previous, similar project as the basis for
estimating the cost of the current project;
also calledtop-down estimates
analogy approach Creating a WBS by using
a similar project’s WBS as a starting point
appraisal cost The cost of evaluating
processes and their outputs to ensure that a
project is error-free or within an acceptable
error range
arrow diagramming method (ADM) A
network diagramming technique in which
activities are represented by arrows and
connected at points called nodes to illustrate
the sequence of activities; also called
activity-on-arrow (AOA)
artifact A useful object created by people
backward pass A project network
diagramming technique that determines
the late start and late finish dates for each
activity
balanced scorecard A strategic planning and
management system that helps organizations
align business activities to strategy, improve
communications, and monitor performance
against strategic goals
baseline The approved project management
plan plus approved changes
baseline dates The planned schedule dates
for activities in a Tracking Gantt chart
benchmarking A technique used to generate
ideas for quality improvements by compar-
ing specific project practices or product
characteristics to those of other projects or
products within or outside the performing
organization
benchmarking Generating ideas by com-
paring specific project practices or product
characteristics to those of other projects or
products inside or outside the performing
organization
best practice An optimal way recognized by
industry to achieve a stated goal or objective
GLOSSARY
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.2
bid A document prepared by sellers to
provide pricing for standard items that
the buyer has clearly defined; also called a
tender or quote (short for quotation)
blogs Journals on the web that allow users
to write entries, create links, and upload
pictures, while readers can post comments to
journal entries
bottom-up approach Creating a WBS by
having team members identify as many
specific tasks related to the project as
possible and then grouping them into
higher-level categories
bottom-up estimates A cost-estimating
technique based on estimating individual
work items and summing them to get a
project total
brainstorming A technique by which a group
attempts to generate ideas or find a solution
for a specific problem by amassing ideas
spontaneously and without judgment
budget at completion (BAC) The original
total budget for a project
budgetary estimate A cost estimate used to
allocate money into an organization’s budget
buffer Additional time to complete a task; a
buffer is added to an estimate to account for
various factors
burndown chart A chart that shows the
cumulative work remaining in a sprint on a
day-by-day basis
burst A single node followed by two or more
activities on a network diagram
Capability Maturity Model Integration
(CMMI) A process improvement approach
that provides organizations with the essential
elements of effective processes
capitalization rate The rate used in
discounting future cash flow; also called the
discount rate or opportunity cost of capital
cash flow Benefits minus costs or income
minus expenses
cash flow analysis A method for determining
the estimated annual costs and benefits for a
project
cause-and-effect diagram A diagram that
traces complaints about quality problems
back to the responsible production opera-
tions to help find the root cause; also known
as a fishbone diagram or Ishikawa diagram
champion A senior manager who acts as a
key proponent for a project
change control board (CCB) A formal
group of people responsible for approving or
rejecting changes on a project
change control system A formal, docu-
mented process that describes when and how
official project documents may be changed
checksheet A technique used to collect and
analyze data; sometimes called a tally sheet
or checklist
closing processes Formalizing acceptance
of the project or project phase and ending it
efficiently
coercive power Using punishment, threats,
or other negative approaches to get people to
do things they do not want to do
collaborating mode A conflict-handling
mode in which decision makers incorporate
different viewpoints and insights to develop
consensus and commitment
communications management plan A docu-
ment that guides project communications
compromise mode Using a give-and-take
approach to resolve conflicts; bargaining and
searching for solutions that bring some degree
of satisfaction to all the parties in a dispute
configuration management A process that
ensures that the descriptions of a project’s
products are correct and complete
conformance Delivering products that meet
requirements and fitness for use
conformance to requirements Project
processes and products that meet written
specifications
confrontation mode Facing a conflict
directly using a problem-solving approach
that allows affected parties to work through
their disagreements
constructive change orders Oral or written
acts or omissions by someone with actual
or apparent authority that can be construed
to have the same effect as a written change
order
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.3
contingency allowances Provisions held by
the project sponsor or organization to reduce
the risk of cost or schedule overruns to an
acceptable level; also called contingency
reserves
contingency plans Predefined actions that
the project team will take if an identified risk
event occurs
contingency reserves Dollar amounts
included in a cost estimate to allow for fu-
ture situations that may be partially planned
for (sometimes called known unknowns)
and that are included in the project cost
baseline
contingency reserves Provisions held by the
project sponsor or organization to reduce
the risk of cost or schedule overruns to an
acceptable level; also called contingency
allowances
contract A mutually binding agreement
that obligates the seller to provide specified
products or services and obligates the buyer
to pay for them
control chart A graphic display of data that
illustrates the results of a process over time
cost baseline A time-phased budget that
project managers use to measure and
monitor cost performance
cost of capital The return available by
investing capital elsewhere
cost of nonconformance Taking
responsibility for failures or not meeting
quality expectations
cost of quality The cost of conformance plus
the cost of nonconformance
cost performance index (CPI) The ratio of
earned value to actual cost; can be used to
estimate the projected cost to complete the
project
cost plus award fee (CPAF) contract A con-
tract in which the buyer pays the supplier for
allowable costs (as defined in the contract)
plus an award fee based on the satisfaction of
subjective performance criteria
cost plus fixed fee (CPFF) contract A con-
tract in which the buyer pays the supplier for
allowable costs (as defined in the contract)
plus a fixed fee payment that is usually based
on a percentage of estimated costs
cost plus incentive fee (CPIF) contract A
contract in which the buyer pays the
supplier for allowable costs (as defined in the
contract) along with a predetermined fee and
an incentive bonus
cost plus percentage of costs (CPPC)
contract A contract in which the buyer pays
the supplier for allowable costs (as defined
in the contract) along with a predetermined
percentage based on total costs
cost variance (CV) The earned value minus
the actual cost
cost-reimbursable contracts Contracts that
involve payment to the supplier for direct
and indirect actual costs
crashing A technique for making cost and
schedule trade-offs to obtain the greatest
amount of schedule compression for the least
incremental cost
critical chain scheduling A method of
scheduling that takes limited resources into
account when creating a project schedule
and includes buffers to protect the project
completion date
critical path method (CPM) or critical
path analysis A project network diagram-
ming technique used to predict total project
duration
critical path The series of activities in a
network diagram that determines the
earliest completion of the project; it is
the longest path through the network
diagram and has the least amount of slack
or float
daily Scrum A short meeting in which the
team shares progress and challenges
decision tree A diagramming analysis
technique used to help select the best
course of action when future outcomes are
uncertain
decomposition Subdividing project deliver-
ables into smaller pieces
defect Any instance in which the product
or service fails to meet customer
requirements
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.4
definitive estimate A cost estimate that pro-
vides an accurate estimate of project costs
deliverable A product or service, such as a
technical report, a training session, a piece
of hardware, or a segment of software
code, produced or provided as part of a
project
Delphi technique An approach used
to derive a consensus among a panel of
experts to make predictions about future
developments
dependency The sequencing of project
activities or tasks; also called a relationship
deputy project managers People who fill in
for project managers in their absence and
assist them as needed
design of experiments A quality technique
that helps identify which variables have the
most influence on the overall outcome of a
process
direct costs Costs that can be directly
related to creating the products and services
of the project
directives New requirements imposed by
management, government, or some external
influence
discount factor A multiplier for each year
based on the discount rate and year
discount rate The rate used in discounting
future cash flow; also called the capitalization
rate or opportunity cost of capital
discretionary dependencies The sequenc-
ing of project activities or tasks defined
by the project team and used with care
because they may limit later scheduling
options
DMAIC (Define, Measure, Analyze,
Improve, Control) A systematic, closed-loop
process for continued improvement that is
scientific and fact based
dummy activities Activities with no duration
and no resources used to show a logical
relationship between two activities in the
arrow diagramming method of project
network diagrams
duration The actual amount of time worked
on an activity plus elapsed time
early finish date The earliest possible time
an activity can finish based on the project
network logic
early start date The earliest possible time
an activity can start based on the project
network logic
earned value (EV) An estimate of the value
of the physical work actually completed
earned value management (EVM) A project
performance measurement technique that
integrates scope, time, and cost data
effort The number of workdays or work
hours required to complete a task
emotional intelligence Knowing and
managing one’s own emotions and
understanding the emotions of others for
improved performance
empathic listening Listening with the intent
to understand
enterprise project management
software Software that integrates informa-
tion from multiple projects to show the sta-
tus of active, approved, and future projects
across an entire organization; also called
portfolio project management software
estimate at completion (EAC) An estimate
of what it will cost to complete the project
based on performance to date
ethics A set of principles that guides
decision making based on personal values of
what is considered right and wrong
executing processes Coordinating people
and other resources to carry out the project
plans and create the products, services, or
results of the project or project phase
executive steering committee A group of
senior executives from various parts of the
organization who regularly review important
corporate projects and issues
expectations management matrix A tool that
helps clarify expectations and lists project
measures of success as well as priorities,
expectations, and guidelines related to each
measure
expected monetary value (EMV) The
product of a risk event probability and the
risk event’s monetary value
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.5
expert power Using one’s personal knowl-
edge and expertise to get people to change
their behavior
external dependencies The sequencing of
project activities or tasks that involve rela-
tionships between project and non-project
activities
external failure cost A cost related to all
errors that are not detected and corrected
before delivery to the customer
extrinsic motivation An approach that
causes people to do something for a reward
or to avoid a penalty
fallback plans Plans developed for risks that
have a high impact on meeting project objec-
tives and implemented if attempts to reduce
the risk are not effective
fast tracking A schedule compression tech-
nique in which you do activities in parallel
that you would normally do in sequence
features The special characteristics that
appeal to users
feeding buffers Time added before tasks on
the critical chain if they are preceded by
other tasks that are not on the critical path
finish-to-finish dependency A relationship
on a project network diagram in which the
“from” activity must be finished before the
“to” activity can be finished
finish-to-start dependency A relationship
on a project network diagram in which the
“from” activity must be finished before the
“to” activity can be started
fishbone diagram A diagram that traces
complaints about quality problems back to
the responsible production operations to help
find the root cause; also known as a cause-
and-effect diagram or Ishikawa diagram
fitness for use A product that can be used as
it was intended
fixed-price contract A contract with a fixed
total price for a well-defined product or
service; also called a lump-sum contract
float The amount of time a project activity
may be delayed without delaying a succeed-
ing activity or the project finish date; also
called slack
flowchart A graphic display of the logic and
flow of processes that helps you analyze how
problems occur and how processes can be
improved
flowcharts Diagrams that show how
various elements of a system relate to each
other
forcing mode Using a win/lose approach to
conflict resolution to get one’s way
forecasts Predictions of future project status
and progress based on past information and
trends
forward pass A network diagramming tech-
nique that determines the early start and
early finish dates for each activity
free slack (free float) The amount of time
an activity can be delayed without delaying
the early start of any immediately following
activities
function points A means of measuring
software size in terms that are meaningful to
end users
functional organizational structure An
organizational structure that groups people
by functional areas such as IT, manufactur-
ing, engineering, and human resources
functionality The degree to which a system
performs its intended function
Gantt chart A standard format for displaying
project schedule information by listing proj-
ect activities and their corresponding start
and finish dates in a calendar format; some-
times referred to as bar charts
Google Docs Online applications offered by
Google that allow users to create, share, and
edit documents, spreadsheets, and presenta-
tions online
groupthink Conformance to the values or
ethical standards of a group
hierarchy of needs A pyramid structure
illustrating Maslow’s theory that people’s
behaviors are guided or motivated by a
sequence of needs
histogram A bar graph of a distribution of
variables
human resources (HR) frame A frame that
focuses on producing harmony between the
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.6
needs of the organization and the needs of
people
indirect costs Costs that are not directly
related to the products or services of the
project, but are indirectly related to perform-
ing the project
influence diagram A diagram that represents
decision problems by displaying essential
elements, including decisions, uncertainties,
and objectives, and how they influence each
other
initiating processes Defining and authorizing
a project or project phase
intangible costs or benefits Costs or benefits
that are difficult to measure in monetary
terms
integrated change control Identifying, evalu-
ating, and managing changes throughout the
project life cycle
integration testing Testing that occurs
between unit and system testing to test
functionally grouped components and ensure
that a subset or subsets of the entire system
work together
interface management Identifying and man-
aging the points of interaction between vari-
ous elements of a project
internal failure cost A cost incurred to cor-
rect an identified defect before the customer
receives the product
internal rate of return (IRR) The discount
rate that results in an NPV of zero for a
project
interviewing A fact-finding technique that
is normally done face to face, but can also
occur through phone calls, e-mail, or instant
messaging
intrinsic motivation An approach that
causes people to participate in an activity for
their own enjoyment
Ishikawa diagram A diagram that traces
complaints about quality problems back to
the responsible production operations to
help find the root cause; also known as a
cause-and-effect diagram or fishbone diagram
ISO 9000 A quality system standard devel-
oped by the International Organization for
Standardization (ISO) that includes a three-
part, continuous cycle of planning, controlling,
and documenting quality in an organization
issue log A tool used to document, monitor,
and track issues that need resolution
IT governance The authority and control
for key IT activities in organizations, includ-
ing IT infrastructure, IT use, and project
management
Joint Application Design (JAD) Using
highly organized and intensive workshops
to bring together project stakeholders—the
sponsor, users, business analysts, program-
mers, and so on—to jointly define and design
information systems
kaizen The Japanese word for improve-
ment or change for the better; an approach
used for continuously improving quality in
organizations
kanban a just-in-time method of inventory
control that can be modified used in con-
junction with Scrum
kick-off meeting A meeting held at the
beginning of a project so that stakeholders
can meet each other, review the goals of the
project, and discuss future plans
kill point A management review that should
occur after each project phase to determine
if projects should be continued, redirected,
or terminated; also called a phase exit
known risks Risks that the project team
has identified and analyzed and that can be
managed proactively
known unknowns Dollar amounts included
in a cost estimate to allow for future situ-
ations that may be partially planned for
(sometimes called contingency reserves) and
that are included in the project cost baseline
late finish date The latest possible time an
activity can be completed without delaying
the project finish date
late start date The latest possible time an
activity may begin without delaying the
project finish date
leader A person who focuses on long-term
goals and big-picture objectives while inspir-
ing people to reach those goals
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.7
lean An approach for improving quality that
involves evaluating processes to maximize
customer value while minimizing waste
learning curve theory A theory that when
many items are produced repetitively, the
unit cost of those items normally decreases
in a regular pattern as more units are
produced
legitimate power Getting people to do things
based on a position of authority
lessons-learned report Reflective statements
written by project managers and their team
members to document important informa-
tion they have learned from working on a
project
life cycle costing The total cost of
ownership, or development plus support
costs, for a project
lump-sum contract A contract with a fixed
total price for a well-defined product or
service; also called a fixed-price contract
maintainability The ease of performing
maintenance on a product
make-or-buy decision An organization’s
decision to make certain products and
perform certain services inside the orga-
nization or to buy them from an outside
organization
Malcolm Baldrige National Quality
Award An award started in 1987 to
recognize companies that have achieved
a level of world-class competition through
quality management
management reserves Dollar amounts
included in a cost estimate to allow for future
situations that are unpredictable (sometimes
called unknown unknowns)
manager A person who deals with the
day-to-day details of meeting specific goals
mandatory dependencies The sequencing of
project activities or tasks that are inherent
in the nature of the work being done on the
project
matrix organizational structure An orga-
nizational structure in which employees
are assigned both to functional and project
managers
maturity model A framework for helping
organizations improve their processes and
systems
mean The average value of a population
measurement and test equipment costs
The capital cost of equipment used to
perform prevention and appraisal
activities
merge Two or more nodes that precede a
single node on a network diagram
methodology A description of how things
should be done
metric A standard of measurement
milestone A significant event that normally
has no duration on a project; serves as a
marker to help in identifying necessary
activities, setting schedule goals, and moni-
toring progress
mind mapping A technique that uses
branches radiating from a core idea to
structure thoughts and ideas
mirroring Matching certain behaviors of
another person
monitoring and controlling processes
Regularly measuring and monitoring progress
to ensure that the project team meets the
project objectives
Monte Carlo analysis A risk quantification
technique that simulates a model’s outcome
many times to provide a statistical distribu-
tion of the calculated results
multitasking Working on more than one task
at a time
Murphy’s Law The principle that if
something can go wrong, it will
Myers-Briggs Type Indicator (MBTI) A
popular tool for determining personality
preferences
net present value (NPV) analysis A method
of calculating the expected net monetary
gain or loss from a project by discounting all
expected future cash inflows and outflows to
the present point in time
network diagram A schematic display of the
logical relationships or sequencing of project
activities
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.8
node The starting and ending point of an
activity on an activity-on-arrow diagram
normal distribution A bell-shaped curve
that is symmetrical about the mean of the
population
offshoring Outsourcing from another
country
opportunities Chances to improve an
organization
opportunity cost of capital The rate used in
discounting future cash flow; also called the
capitalization rate or discount rate
organizational breakdown structure
(OBS) A specific type of organizational chart
that shows which organizational units are
responsible for particular work items
organizational culture A set of shared as-
sumptions, values, and behaviors that
characterize the functioning of an organization
organizational process assets Formal and
informal plans, policies, procedures, guide-
lines, information systems, financial systems,
management systems, lessons learned, and
historical information that can influence a
project’s success
outsourcing An organization’s acquisition of
goods and services from an outside source
overallocation A state in which not enough
resources are available to perform the
assigned work during a given time period
overrun The additional percentage or dol-
lar amount by which actual costs exceed
estimates
parametric estimating A cost-estimating
technique that uses project characteristics
(parameters) in a mathematical model to es-
timate project costs
Pareto analysis Identifying the vital few
contributors that account for most quality
problems in a system
Pareto chart A histogram that helps identify
and prioritize problem areas
Parkinson’s Law The principle that work
expands to fill the time allowed
payback period The amount of time needed
to recoup the total dollars invested in a
project, in terms of net cash inflows
performance How well a product or service
performs the customer’s intended use
PERT weighted average (Optimistic time +
4 * most likely time + pessimistic time)/6
phase exit A management review that should
occur after each project phase to determine
if projects should be continued, redirected,
or terminated; also called a kill point
planned value (PV) The portion of the
approved total cost estimate planned to be
spent on an activity during a given period
planning processes Devising and maintain-
ing a workable scheme to ensure that the
project addresses the organization’s needs
Point of Total Assumption (PTA) The
cost at which the contractor assumes total
responsibility for each additional dollar of
contract cost in a fixed-price incentive fee
contract
political frame A frame that addresses
organizational and personal politics
politics Competition between groups or
individuals for power and leadership
power The ability to influence behavior
to get people to do things they would not
otherwise do
power/interest grid A tool used to group
stakeholders based on their level of authority
(power) and their level of concern (interest)
for project outcomes
precedence diagramming method (PDM) A
network diagramming technique in which
boxes represent activities
predictive life cycle A software development
approach used when the scope of the project
can be articulated clearly and the schedule
and cost can be predicted accurately
prevention cost The cost of planning and
executing a project so that it is error-free or
within an acceptable error range
probabilistic time estimates Duration esti-
mates based on using optimistic, most likely,
and pessimistic estimates of activity dura-
tions instead of using one specific or discrete
estimate
probability/impact matrix or chart A matrix
or chart that shows the relative probability
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.9
of a risk occurring and the relative impact of
the risk
problems Undesirable situations that pre-
vent an organization from achieving its goals
process A series of actions directed toward a
particular result
process adjustments Adjustments made to
correct or prevent further quality problems
based on quality control measurements
procurement Acquiring goods and services
from an outside source
product backlog A single list of features
prioritized by business value
product owner The person responsible for
the business value of the project and for
deciding what work to do and in what order
when using a Scrum method
profit margin The ratio of profits to
revenues
profits Revenues minus expenses
program A group of related projects, sub-
programs, and program activities managed
in a coordinated way to obtain benefits and
control not available from managing them
individually
Program Evaluation and Review Technique
(PERT) A project network analysis tech-
nique used to estimate project duration when
there is a high degree of uncertainty about
the individual activity duration estimates
program manager A person who provides
leadership and direction for the project man-
agers heading the projects within a program
progress reports Reports that describe what
the project team has accomplished during a
certain period of time
project A temporary endeavor undertaken to
create a unique product, service, or result
project acquisition The last two phases in a
project (implementation and close-out) that
focus on delivering the actual work
project and portfolio management soft-
ware Software that integrates information
from multiple projects to show the status of
active, approved, and future projects across
an entire organization; also called enterprise
project management software
project archives A complete set of organized
project records that provide an accurate his-
tory of the project
project buffer Time added before the proj-
ect’s due date
project charter A document that formally
recognizes the existence of a project and
provides direction on the project’s objectives
and management
project cost management The processes
required to ensure that the project is com-
pleted within the approved budget
project feasibility The first two phases in
a project (concept and development) that
focus on planning
project integration management Processes
that coordinate all project management
knowledge areas throughout a project’s
life, including developing the project
charter, developing the preliminary project
scope statement, developing the project
management plan, directing and managing
the project, monitoring and controlling the
project, providing integrated change control,
and closing the project
project life cycle A collection of project
phases, such as concept, development, im-
plementation, and close-out
project management The application of
knowledge, skills, tools, and techniques
to project activities to meet project
requirements
Project Management Institute (PMI) An
international professional society for project
managers
project management knowledge areas
Project integration management, scope,
time, cost, quality, human resource,
communications, risk, procurement, and
stakeholder management
Project Management Office (PMO) An orga-
nizational group responsible for coordinating
the project management functions through-
out an organization
project management plan A document
used to coordinate all project planning
documents and guide project execution and
control
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.10
project management process groups The
progression of project activities from
initiation to planning, executing, monitoring
and controlling, and closing
Project Management Professional
(PMP) Certification provided by PMI that re-
quires documenting project experience and
education, agreeing to follow the PMI code of
ethics, and passing a comprehensive exam
project management tools and tech-
niques Methods available to assist project
managers and their teams; some popular
time-management tools include Gantt charts,
network diagrams, and critical path analysis
project manager The person responsible for
working with the project sponsor, the project
team, and the other people involved to meet
project goals
project organizational structure An orga-
nizational structure that groups people by
major projects
project portfolio management or portfolio
management When organizations group and
manage projects as a portfolio of investments
that contribute to the entire enterprise’s
success
project procurement management The pro-
cesses required to acquire goods and services
for a project from outside the performing
organization
project quality management Ensuring that a
project will satisfy the needs for which it was
undertaken
project scope management The processes
involved in defining and controlling what
work is or is not included in a project
project scope statement A document that
includes at least a description of the project,
including its overall objectives and justifi-
cation, detailed descriptions of all project
deliverables, and the characteristics and
requirements of products and services pro-
duced as part of the project
project sponsor The person who provides
the direction and funding for a project
project time management The processes
required to ensure timely completion of a
project
PRojects IN Controlled Environments
(PRINCE2) A project management method-
ology developed in the United Kingdom that
defines 45 separate subprocesses and orga-
nizes these into eight process groups
proposal A document prepared by sellers
when there are different approaches for
meeting buyer needs
prototyping Developing a working replica of
the system or some aspect of it to help define
user requirements
quality The totality of characteristics of
an entity that bear on its ability to satisfy
stated or implied needs or the degree to
which a set of inherent characteristics fulfill
requirements
quality assurance Periodic evaluation of
overall project performance to ensure that
the project will satisfy the relevant quality
standards
quality audit A structured review of spe-
cific quality management activities that
helps identify lessons learned and that can
improve performance on current or future
projects
quality circles Groups of nonsupervisors and
work leaders in a single company department
who volunteer to conduct group studies on
how to improve the effectiveness of work in
their department
quality control Monitoring specific project
results to ensure that they comply with the
relevant quality standards and identifying
ways to improve overall quality
RACI charts Charts that show Responsibil-
ity, Accountability, Consultation, and In-
formed roles for project stakeholders
rapport A relation of harmony, conformity,
accord, or affinity
rate of performance (RP) The ratio of actual
work completed to the percentage of work
planned to have been completed at any given
time during the life of the project or activity
Rational Unified Process (RUP) framework
An iterative software development process
that focuses on team productivity and
delivers software best practices to all team
members
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.11
referent power Getting others to do things
based on a person’s own charisma
relationship The sequencing of project
activities or tasks; also called a dependency
reliability The ability of a product or ser-
vice to perform as expected under normal
conditions
Request for Proposal (RFP) A document
used to solicit proposals from prospective
suppliers
Request for Quote (RFQ) A document used
to solicit quotes or bids from prospective
suppliers
required rate of return The minimum
acceptable rate of return on an investment
requirement A condition or capability that
must be met by the project or that must be
present in the product, service, or result
to satisfy an agreement or other formally
imposed specification
requirements management plan A plan that
describes how project requirements will be
analyzed, documented, and managed
requirements traceability matrix (RTM) A
table that lists requirements, their various
attributes, and the status of the requirements
to ensure that all are addressed
reserves Dollar amounts included in a cost
estimate to mitigate cost risk by allowing for
future situations that are difficult to predict
residual risks Risks that remain after
all of the response strategies have been
implemented
resource breakdown structure A hierarchi-
cal structure that identifies the project’s re-
sources by category and type
resource histogram A column chart that
shows the number of resources assigned to a
project over time
resource leveling A technique for resolving
resource conflicts by delaying tasks
resource loading The amount of individual
resources an existing schedule requires dur-
ing specific time periods
resources People, equipment, and materials
responsibility assignment matrix (RAM) A
matrix that maps the work of a project, as
described in the WBS, to the people respon-
sible for performing the work, as described in
the organizational breakdown structure (OBS)
return on investment (ROI) A method for
determining the financial value of a project;
the ROI is the result of subtracting the proj-
ect costs from the benefits and then dividing
by the costs
reward power Using incentives to induce
people to do things
rework Action taken to bring rejected
items into compliance with product require-
ments, specifications, or other stakeholder
expectations
risk An uncertainty that can have a negative
or positive effect on meeting project
objectives
risk acceptance Accepting the consequences
if a risk occurs
risk appetite The degree of uncertainty an
entity is willing to take on in anticipation of
a reward
risk avoidance Eliminating a specific threat
or risk, usually by eliminating its causes
risk breakdown structure A hierarchy of
potential risk categories for a project
risk enhancement Changing the size of an
opportunity by identifying and maximizing
key drivers of the positive risk
risk events Specific uncertain events that
may occur to the detriment or enhancement
of the project
risk exploitation Doing whatever you can to
make sure a positive risk happens
risk factors Numbers that represent the
overall risk of specific events, given their
probability of occurring and the consequence
to the project if they do occur
risk management plan A plan that docu-
ments the procedures for managing risk
throughout a project
risk mitigation Reducing the impact of a
risk event by reducing the probability of its
occurrence
risk owner The person who will take respon-
sibility for a risk and its associated response
strategies and tasks
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.12
risk register A document that contains re-
sults of various risk management processes,
often displayed in a table or spreadsheet
format
risk sharing Allocating ownership of a risk to
another party
risk tolerance The maximum acceptable
deviation an entity is willing to accept
on a project or business objectives as the
potential impact
risk transference Shifting the consequence
of a risk and responsibility for its manage-
ment to a third party
risk utility The amount of satisfaction or
pleasure received from a potential payoff
risk-averse Having a low tolerance for risk
risk-neutral A balance between risk and
payoff
risk-seeking Having a high tolerance for risk
Robust Design methods Methods that focus
on eliminating defects by substituting scien-
tific inquiry for trial-and-error methods
rough order of magnitude (ROM) estimate
A cost estimate prepared very early in the
life of a project to provide a rough idea of
what a project will cost
run chart A chart that displays the history
and pattern of variation of a process over
time
scatter diagram A diagram that helps to
show if there is a relationship between two
variables; sometimes called XY charts
schedule baseline The approved planned
schedule for the project
schedule performance index (SPI) The ratio
of earned value to planned value; can be used
to estimate the projected time to complete a
project
schedule variance (SV) The earned value
minus the planned value
scope All the work involved in creating the
products of the project and the processes
used to create them
scope baseline The approved project scope
statement and its associated WBS and WBS
dictionary
scope creep The tendency for project scope
to keep getting bigger
scope validation Formal acceptance of the
completed project deliverables
Scrum team or development team A cross-
functional team of five to nine people who
organize themselves and the work to produce
the desired results for each sprint
Scrum The leading agile development
methodology for completing projects with a
complex, innovative scope of work
ScrumMaster A person who ensures that
the team is productive, facilitates the daily
Scrum, enables close cooperation across all
roles and functions, and removes barriers
that prevent the team from being effective
secondary risks Risks that are a direct result
of implementing a risk response
sellers Contractors, suppliers, or providers
who provide goods and services to other
organizations
sensitivity analysis A technique used to
show the effects of changing one or more
variables on an outcome
seven run rule If seven data points in a row
on a quality control chart are all below the
mean, above the mean, or are all increasing
or decreasing, then the process needs to be
examined for nonrandom problems
SharePoint portal A tool that allows users to
create custom websites to access documents
and applications stored on shared devices
six 9s of quality A measure of quality con-
trol equal to 1 fault in 1 million opportunities
Six Sigma A comprehensive and flexible sys-
tem for achieving, sustaining, and maximiz-
ing business success that is uniquely driven
by close understanding of customer needs,
disciplined use of facts, data, and statistical
analysis, and diligent attention to manag-
ing, improving, and reinventing business
processes
Six Sigma methodologies Define, Measure,
Analyze, Improve, and Control (DMAIC) is
used to improve an existing business process,
and Define, Measure, Analyze, Design,
and Verify (DMADV) is used to create new
product or process designs
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.13
slack The amount of time a project activity
may be delayed without delaying a succeed-
ing activity or the project finish date; also
called float
slipped milestone A milestone activity that
is completed later than planned
SMART criteria Guidelines to help define
milestones that are specific, measurable,
assignable, realistic, and time-framed
smoothing mode Deemphasizing or avoiding
areas of differences and emphasizing areas of
agreement
software defect Anything that must be
changed before delivery of the program
Software Quality Function Deployment
(SQFD) model A maturity model that
focuses on defining user requirements and
planning software projects
sprint A set period of time, normally two to
four weeks, during which specific work must
be completed and made ready for review
when using Scrum methods
sprint backlog The highest-priority items
from the product backlog to be completed in
a sprint
staffing management plan A document that
describes when and how people will be added
to a project team and taken off it
stakeholder analysis A technique for
analyzing information to determine which
stakeholders’ interests to focus on and how
to increase stakeholder support throughout
the project
stakeholder register A document that
includes details about identified project
stakeholders
stakeholder register A document that
includes details related to the identified
project stakeholders
stakeholders People involved in or affected
by project activities
standard Best practices for what should be
done
standard deviation A measure of how much
variation exists in a distribution of data
start-to-finish dependency A relationship
on a project network diagram in which the
“from” activity cannot start before the “to”
activity is finished
start-to-start dependency A relationship
on a project network diagram in which the
“from” activity cannot start until the “to”
activity starts
statement of work (SOW) A description of
the work required for procurement
statistical sampling Choosing part of a
population of interest for inspection
status reports Reports that describe where a
project stands at a specific point in time
strategic planning Determining long-term
objectives by analyzing the strengths and
weaknesses of an organization, studying
opportunities and threats in the business
environment, predicting future trends, and
projecting the need for new products and
services
structural frame A frame that deals with
how the organization is structured (usually
depicted in an organizational chart) and
focuses on different groups’ roles and respon-
sibilities to meet the goals and policies set by
top management
subproject managers People responsible for
managing the subprojects of a larger project
sunk cost Money that has been spent in the
past
SWOT analysis Analyzing Strengths, Weak-
nesses, Opportunities, and Threats; used to
aid in strategic planning
symbolic frame A frame that focuses on
the symbols, meanings, and culture of an
organization
synergy An approach in which the whole is
greater than the sum of the parts
system outputs The screens and reports the
system generates
system testing Testing the entire system
as one entity to ensure that it is working
properly
systems Sets of interacting components
working within an environment to fulfill
some purpose
systems analysis A problem-solving
approach that requires defining the scope of
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.14
the system to be studied, and then dividing
it into component parts for identifying and
evaluating its problems, opportunities,
constraints, and needs
systems approach A holistic and analytical
approach to solving complex problems that
includes using a systems philosophy, systems
analysis, and systems management
systems development life cycle (SDLC) A
framework for describing the phases involved
in developing and maintaining information
systems
systems management Addressing the busi-
ness, technological, and organizational issues
associated with creating, maintaining, and
modifying a system
systems philosophy An overall model for
thinking about things as systems
systems thinking A holistic view of an
organization to effectively handle complex
situations
tangible costs or benefits Costs or benefits
that can be easily measured in dollars
task An element of work normally found on
the WBS that has an expected duration, cost,
and resource requirements; also called an
activity
team development Building individual and
group skills to enhance project performance
termination clause A contract clause that
allows the buyer or supplier to end the
contract
Theory of Constraints (TOC) A
management philosophy that any complex
system at any point in time often has only
one aspect or constraint that limits the
ability to achieve more of the system’s goal
three-point estimate An estimate that
includes an optimistic, most likely, and
pessimistic estimate
time and material (T&M) contracts A
hybrid of fixed-price and cost-reimbursable
contracts
Top Ten Risk Item Tracking A qualitative
risk analysis tool for identifying risks
and maintaining an awareness of risks
throughout the life of a project
top-down approach Creating a WBS by
starting with the largest items of the project
and breaking them into subordinate items
top-down estimates A cost-estimating
technique that uses the actual cost of a
previous, similar project as the basis for
estimating the cost of the current project;
also called analogous estimates
total slack (total float) The amount of time
an activity may be delayed from its early
start without delaying the planned project
finish date
Tracking Gantt chart A Gantt chart that
compares planned and actual project
schedule information
triggers Indications for actual risk events
triple constraint Balancing scope, time, and
cost goals
Tuckman model A model that describes
five stages of team development: forming,
storming, norming, performing, and
adjourning
unit pricing An approach in which the buyer
pays the supplier a predetermined amount
per unit of service, and the total value of
the contract is a function of the quantities
needed to complete the work
unit test A test of each individual
component (often a program) to ensure that
it is as defect-free as possible
unknown risks Risks that cannot be
managed proactively because they have not
been identified and analyzed
unknown unknowns Dollar amounts
included in a cost estimate to allow for future
situations that are unpredictable (sometimes
called management reserves)
use case modeling A process for identifying
and modeling business events, who initiated
them, and how the system should respond to
them
user acceptance testing An independent test
performed by end users prior to accepting
the delivered system
user stories Short descriptions written by
customers of what they need a system to do
for them
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Glossary
G.15
variance The difference between planned
and actual performance
virtual team A group of people who work
together despite time and space boundaries
using communication technologies
watch list A list of risks that have low
priority but are still identified as potential
risks
WBS dictionary A document that includes
detailed information about each WBS item
weighted scoring model A technique
that provides a systematic process for
selecting projects based on numerous
criteria
wiki A website that enables anyone who
accesses it to contribute or modify content
withdrawal mode Retreating or withdrawing
from an actual or potential disagreement
work breakdown structure (WBS) A deliver-
able-oriented grouping of the work involved
in a project that defines its total scope
work package A task at the lowest level of
the WBS
workarounds Unplanned responses to risk
events when no contingency plans are in
place
yield The number of units handled correctly
through the development process
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

INDEX
Note: Page numbers followed by f refer to
figures; page numbers in color and/or bold
refer to key terms.
5 whys, 308
The 7 Habits of Highly Effective People
(Covey), 355, 393
14 Points for Management, 322–323
21st Century Insurance Group, 206
60-day trial of project 2013, A8–A9
2014 Winter Olympic Games in Sochi, 223
A
AACE. See Association for the
Advancement of Cost Engineering
(AACE) International
Abbot, Mike, 54
AC. See actual cost (AC)
Accenture, 265
acceptance decisions, 307
Achor, Shawn, 237
ACP. See Agile Certified Practitioner (ACP)
acquisition, project, 57
activities, 223, 225–228
activity attributes, 226
activity list, 226
activity-on-arrow (AOA) approach,
229–230
actual cost (AC), 283
adaptive software development (ASD) life
cycle model, 61
Addeman, Frank, 240
Adelaide desalination project, 111
ADM. See arrow diagramming method
(ADM)
Agile Certified Practitioner (ACP), 71
agile community, 189
agile management, 248
agile movement, 306
agile projects, reduce schedule risk on, 451
agile software development, 62, 69–72,
87–88
Agile Unified Process (AUP), 87
Air Force, 200
Alexander, Alvin, 280
Alperovitch, Dmitri, 328
analogous estimates, 273–274
analogy approach, 200–201
Anderson, David J, 306
Andy Mattes, 346
AOA approach. See activity-on-arrow
(AOA) approach
Apple, 67
appraisal cost, 327–328
Arbon, Jason, 189
arrow diagramming method (ADM),
229–230
artifacts, 119
ASD. See adaptive software development
(ASD) life cycle model
Association for the Advancement of Cost
Engineering (AACE) International,
273
AUP. See Agile Unified Process (AUP)
automobiles, impressive technology for,
326
Avraham Y. Goldratt Institute, 246
B
BAC. See budget at completion (BAC)
backward pass, 241
BAFO. See best and final offer (BAFO)
balanced scorecard, 154
Baldrige, Malcolm, 325
bar graphs, 311
baseline, 166, 282, A28, A52–A56
baseline dates, 238
Belbin, Meredith, 68
benchmarking, 189, 306–307
best and final offer (BAFO), 483
best practices, 20, 111, 145, 332, 365
bidders’ conference, 482, 487
bids, 479
Blizzard, 63
blogs, 415
Bloomberg, Michael, 469
bottom-up approach, 201
bottom-up estimates, 274
Bowen, Daniel, 207
brainstorming, 439
Brooks, Frederick, 392
budgetary estimate, 272
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.2
budget at completion (BAC), 285
budgeting, 281–282
buffers, 245
Bullock, Fraser, 167
Burke, Eric, 19
burndown chart, 119
bursts, 230
business analysts, jobs for, 187
business area analysis, 143–146
Butrick, Robert, 20
C
Capability Maturity Model Integration
(CMMI), 331
capitalization rate, 148
CAPM certification, 33
carbon neutral practice, 268–269
careers, 2, 317–318
Carollo, Jeff, 189
CASE. See Computer Aided Software
Engineering (CASE)
cash flow, 148
cash flow analysis, 269–270
cause-and-effect diagrams, 308–309
CCB. See change control board (CCB)
Centers for Medicare & Medicaid Services
(CMS), 53
Certification of Competency in Business
Analysis (CCBA®) certification, 187
certifications
Agile Certified Practitioner (ACP), 71
Certified Associate in Project Management
(CAPM), 33
PMI Risk Management Professional, 426
Certified Associate in Project Management
(CAPM) certification, 33
Certified Business Analysis Professional
(CBAP®) certification, 187
Certified Professional for Requirements
Engineering (CPRE), 187
champions, 54
change control board (CCB), 169–170
change control system, 169–172
change requests, 168. See also integrated
change control
CHAOS report, 3–4, 16–17
CHAOS study, 14
Chapman, Paul, 509
checklists, 440
checksheets, 310–311
Chemical Bank, 301
Chief Information Officer (CIO), 55–56
Chief Project Officer (CPO), 56
Ciber, Inc., 151
CIO (Chief Information Officer), 55–56
closing processes, 81, 85–86, 114–117,
126, 172, 484–485
cloud computing, 173
cloud storage, 173
CMMI. See Capability Maturity Model
Integration (CMMI)
coercive power, 354
collaborating mode, 377
collaboration, 402–403
Collins, James, 317
Collins, Susan, 16
communication, 171, 405–406. See also
project communication management
communication channels, 396–397
communications management plan, 398
compromise mode, 376
Computer Aided Software Engineering
(CASE), 61, 160, 209
computer viruses, 328–329
Computing Technology Industry Associa-
tion (CompTIA), 33, 347
configuration management, 170
conformance to requirements, 302, 327
confrontation mode, 376
constructive change orders, 484
contingency allowances, 434
contingency plans, 434
contingency reserves, 270, 434
Continuing Certification Requirements
(CCR) program, 359
contracts, 469, 471–476
control charts, 309–310
cost, defined, 265
Cost Estimating in an Agile Development
Environment (2015), 280
cost management. See project cost
management
cost of capital, 148
cost of quality, 327–329
cost performance index (CPI), 284
cost plus award fee (CPAF) contracts,
474, 475f
cost plus fixed fee (CPFF) contracts,
474, 475f
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.3
cost plus incentive fee (CPIF) contracts,
473, 475f
cost plus percentage of costs (CPPC)
contracts, 474, 475, 475f
cost-reimbursable contracts, 472–473
cost variance (CV), 284
course management software, 409
Covey, Stephen, 355–357, 393
CPAF contracts. See cost plus award fee
(CPAF) contracts
CPFF contracts See cost plus fixed fee
(CPFF) contracts
CPI. See cost performance index (CPI)
CPIF. See cost plus incentive fee (CPIF)
contracts
CPM. See critical path method (CPM)
CPO. See Chief Project Officer (CPO)
CPPC. See cost plus percentage of costs
(CPPC) contracts
crashing, 243
critical chain scheduling, 243–247
critical path, 29, 238–239
calculating, 239–240
importance of updating critical path
data, 243
to shorten project schedule, 242–243
critical path method (CPM), 238–239, 453,
A43–A46
to make schedule trade-offs, 240–242
CRM. See Customer Relationship
Management (CRM)
Crosby, Philip B., 323–324
Crowe, Andy, 82, 210
Crystal, 87
cultural differences, 329–330
Customer Relationship Management
(CRM), 56
customer testimonials, 251
CV. See cost variance (CV)
D
daily Scrum, 119
decision trees, 447–448
decomposition, 194
defect, 319
Defense Systems Leaders, 497
definitive estimates, 272
deliverables, 57, 184
Dell, Michael, 268–269
Delphi technique, 439
Delta Air Lines, 467
DeMarco, Tom, 274, 328, 329
Demers, Clement, 111
Deming, W. Edwards, 322
Department of Defense (DOD), 161, 200
dependencies, 228
deputy project managers, 360
design of experiments, 304
development team, 118
diagramming techniques, 440
direct costs, 269–270
directives, 147
discount factor, 149
discount rate, 148
DISC Profile, 374–375
discretionary dependencies, 228
DMADV, 88
DMAIC, 88, 315
DOD guidelines. See Department of
Defense (DOD)
Doran Jones Inc., 467
DSDM. See Dynamic Systems Development
Method (DSDM)
dummy activities, 232
durations, 233–234
Dynamic Systems Development Method
(DSDM), 87
E
EAC. See estimate at completion (EAC)
early finish date, 241
early start date, 241
earned value (EV), 283
earned value management (EVM), 282–288
data, A56–A57
e-cigarette chargers, 328
effectiveness, 355–357
effort, 233
electric cars, 326
Eli Lilly, 451
e-mail, 395, 407, 408–410
e-mail addresses, hacking, 301
emotional intelligence, 357–358
Emotional Intelligence (Goleman), 357–358
Emotional Intelligence for Project
Managers: The People Skills You
Need to Achieve Outstanding Results
(Mersino), 357
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.4
empathic listening, 356
employment rates, 2–3, 344–345
EMV. See expected monetary value (EMV)
Enterprise Applications Consulting, 206
enterprise project management software,
21
Epic, 89
EPM. See Microsoft Office Enterprise
Project Management (EPM) Solution
e-procurement, 485–486
ESI International, Inc., 333
estimate at completion (EAC), 285
ethics, 34–35
EV. See earned value (EV)
EVM. See earned value management
(EVM)
executing processes, 81, 85–86, 107–111,
124
executive steering committee, 63
expectations management matrix, 503–504
expected monetary value (EMV), 447–448
expert judgment, 477
expert power, 355
external dependencies, 228
external failure cost, 328
extrinsic motivation, 349
F
fallback plans, 434
Farmland Industries, Inc., 210
fast tracking, 243
FBI. See Federal Bureau of Investigation
(FBI)
feasibility, project, 57
features, 304
Federal Bureau of Investigation (FBI),
227–228
feeding buffers, 245
Feigenbaum, Armand V., 325
Ferguson, Christa, 501
FFP. See firm-fixed-price (FFP) contracts
financial analyses, project selection,
147–152
NPV, 147–150
payback period, 151–152
ROI, 150–151
Financial Stability Forum (FSF), 429
finish-to-finish dependency, 231
finish-to-start dependency, 231
FireChat app, 401
firm-fixed-price (FFP) contracts, 472, 475f
fishbone diagrams, 308
fitness for use, 302
fixed-price contracts, 472
fixed-price incentive fee (FPIF) contracts,
472, 475f
fixed-price with economic price adjust-
ment (FP-EPA) contracts, 472, 475f
Flatiron-Manson, 473
Fleming, Quentin, 286
float, 239
flowcharts, 313, 440
Forbes, 53
forcing mode, 377
Ford Motor Company, 322
forecasts, 404
formal communication, 394–395
forward pass, 241
FoxMeyer Drug, 205
FP-EPA. See fixed-price with economic
price adjustment (FP-EPA) contracts
FPIF. See fixed-price incentive fee (FPIF)
contracts
Frames of Mind: The Theory of Multiple
Intelligences (Gardner), 357
free float, 240–241
free slack, 240–241
Friang, Luke, 468
Friedman, Thomas L., 65
functionality, 304
functional organizational structure,
49, 50
Function Point Analysis (FPA) techniques,
280
function points, 277
G
Gantt charts, 13, 28, 234–236, A43–A46
adding milestones to, 236–237
for software launch project, 236f
tracking Gantt chart, 237–238
Gantt, Henry, 28
Gardner, Howard, 357
Gartner, Inc., 5–6, 154
Gates, Bill, 300, 372
General Motors, 300, 451, 468
Germanwings crash (2015), 436
globalization, 65–66
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.5
Goldratt, Eliyahu M., 243–244
Goleman, Daniel, 357–358
Google, 189, 345, 365
Google Docs, 408–409, 410
Gottron, Joe, 63
Grant Thornton, 140
Greenbaum, Joshua, 206
group communication, 392–394
groupthink, 377
guidelines, 161–162, 200
Guide to Business Analysis Body of
Knowledge (BABOK® Guide), 187
Gumpert, Peter, 390, 398, 400, 412, 416
H
The Happiness Advantage (Achor), 237
Harrin, Elizabeth, 509
healthcare clinic, scheduling work, 246
Healthcare Project Management
(Schwalbe), A1
HEART (guest experience), 56
Herzberg, Frederick, 350–351
Hewlett-Packard, 325, 468
hierarchy of needs, 349–350
Hillson, David, 428, 430
Hilton Worldwide, 56
histograms, 311
The Hobbit, 84
Holloway, Caswell F., 469–470
Hollstadt, Rachel, 56
Hoover, Dan, 151
How Google Tests Software (Whittaker),
189
The Huffington Post, 346
human resource management. See project
human resource management
human resources (HR) frame, 47–48
Huntington Bancshares, Inc., 63
Hurley, Kevin, 140
I
Ibbs, William, 426–427
IBM, 89, 378, 484
IEEE. See Institute of Electrical and
Electronics Engineers (IEEE)
incremental build life cycle model, 61
indirect costs, 270
influence and power, 353–355
influence diagrams, 440
informal communication, 394–395
initial contractor responses, 481
initiating processes, 81, 85–86, 93–98,
121–122
Institute for International Finance (IIF),
429
Institute of Electrical and Electronics
Engineers (IEEE), 161–162
intangible costs or benefits, 269
integrated change control, 168–172
integration management. See project
integration management
integration testing, 320
interactive communication, 401
interface management, 140
internal failure cost, 328
internal logical files (ILFs), 280
internal rate of return (IRR), 144, 151
Internal Revenue Service (IRS), 83
International Institute of Business Analysis
(IIBA)®, 187
International Organization for
Standardization (ISO), 325–326
International Project Management
Association (IPMA), 33
International Requirements Engineering
Board (IREB), 187
interviewing, 439
intrinsic motivation, 349
invitations for bid, 481
IPMA. See International Project
Management Association (IPMA)
IRR. See internal rate of return (IRR)
Ishikawa diagrams, 308–309
Ishikawa, Kaoru, 324
ISO 9000, 325–326
issue logs, 504
IT companies, best practices, 145
IT governance, 55
IT Governance Institute (ITGI), 55
IT projects
agile software development,
62, 69–72
diverse technologies in, 65
globalization and, 65–66
nature of, 64
outsourcing, 66–67
team member characteristics,
64–65
virtual teams, 67–69
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.6 J
Jackson, Peter, 84
Jobs, Steve, 352
Johnson, Jim, 63
Joint Application Design (JAD), 88, 209
Judge, Timothy, 51
Juran, Joseph, 317, 323, 326
K
kaizen, 306
kanban, 71
Kanban (Anderson), 306
kanban boards, 408–410
kanban, core properties, 306
Kanter, Rosabeth Moss, 20
Kaplan, Robert, 154
Keirsey, David, 372
Keirsey Temperament Sorter, 372
Kenya Red Cross, 154
kick-off meetings, 14, 97–98
Kidder, Tracy, 356
kill points, 62
Kivestu, Peeter, 165, 210
KLCI Research Group, 427
knowledge areas, 11–12
known risks, 431
known unknowns, 270
Knutson, Joan, 240
KPMG International, 66, 436
Kwak, Young H., 426–427
L
Lansley, Andrew, 265
late finish date, 241
late start date, 241
leadership, 358–359
leadership styles, 56, 358
Leadership: Theory and Practice
(Northouse), 358
leaders vs. managers, 26–27
lean, 306
learning curve theory, 270
legitimate power, 354
Lehman, Matthew, 167
Lencioni, Patrick, 378
lessons-learned reports, 13, 412
life cycle costing, 267, 268
Lister, Timothy, 329
lump-sum contracts, 472
M
maintainability, 305
Major Projects Leadership Academy, 509
make-or-buy decisions, 471,
476–477
Malcolm Baldrige National Quality Award,
325
management reserves, 270, 434
managers vs. leaders, 26–27
mandatory dependencies, 228
Manifesto for Agile Software Development,
69–70
market research, 477
Marston, William Moulton, 374
Maslow, Abraham, 349–350
matrix organizational structure, 50
maturity models, 330–333, 426–428
MBTI. See Myers-Briggs Type Indicator
(MBTI)
McClelland, David, 352
McDonald’s Restaurants, 205–206
McDonnell Aircraft Company, 200
McDonough, Denis, 53
McGregor, Douglas, 352–353
mean, 318–319
measurement and test equipment costs,
328
meetings, 406–408
Mehrabian, Albert, 394
merges, 230
Mersino, Anthony C., 357
mesh-networking, 401
methodologies, 86–89
metrics, 303
Metzen, Chris, 63
Meyer, Marissa, 346
Microsoft, 251
Microsoft Excel, 451
Microsoft Office Enterprise Project
Management (EPM) Solution, 416
Microsoft Project 2013 software, 29, 161,
250–252, 379
before you begin, A7–A8
calendars, A29–A31
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.7
cost and resource management,
A46–A56
creating new file, A23–A24
creating summary tasks, A26–A27
creating WBS hierarchy, A25–A26
critical path analysis, A43–A46
developing schedule, A29–A46
entering task durations, A31–A38
establishing task dependencies,
A38–A43
exercises, A63–A64
features, A6–A7
filters, A21–A23
Gantt charts, A43–A46
integrating with applications and apps
for office, A57–A62
network diagrams, A43–A46
numbering tasks, A27–A28
overview, A9–A15
project cost management, A46–A56
project resource management, A46–A56
reports, A19–A21
reviews, A3–A5
saving files without baseline, A28
using, A7–A15
using 60-day trial of, A8–A9
using existing file to explore, A15–A23
viewing EVM data, A56–A57
views, A17–A19
Microsoft Solution Framework (MSF), 445
milestones, 226, 236–237
mind mapping, 142–143, 201–203
Minnesota Department of Transportation
(MnDOT), 473
mirroring, 357
Money magazine, 406
monitoring and controlling processes, 81,
85–86, 111–114, 124–126, 166–168,
307–308
Monte Carlo analysis, 449–451, 455
Monte Carlo simulation, 451
Morhaime, Mike, 63
motivation, 349–353
Motorola, Inc., 319, 327
Mott, Randy, 468
multitasking, 244
Murphy’s Law, 245
Myers-Briggs Type Indicator (MBTI),
371–372
myki, 207
N
NASA International Space Station
Program, 18
National Health Service, 265
National Programme for Health IT, 265
National University Hospital in Singapore,
246–247
natural disasters, 400
net present value (NPV), 144, 147–150
network diagrams, 229–232, A43–A46
New Line Cinema, 84
new product development (NPD), 403
nodes, 229–230
normal distribution, 318
Northouse, Peter, 358
Northrop Grumman, 206
Northwest Airlines, 165, 208, 210, 273, 307
Norton, David, 154
NPD. See new product development (NPD)
NPV. See net present value (NPV)
NTT East, 400–401
O
Obama, Barack, 53–54
Obama Trauma Team, 54
OBS. See organizational breakdown
structure (OBS)
OECD. See Organisation for Economic
Co-operation and Development
(OECD)
offshoring, 66–67
Olympic Games, 167, 223
O’Neal, Len, 509
OPM3. See Organizational Project
Management Maturity Model (OPM3)
Oppenheimer, Robert, 28
opportunities, 147
opportunity cost of capital, 148
Organisation for Economic Co-operation
and Development (OECD), 170
organizational breakdown structure (OBS),
362
organizational charts, 360–362
organizational culture, 51–52
organizational influences on quality, 329
organizational process assets, 155
Organizational Project Management
Maturity Model (OPM3), 19, 331–333
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.8
organizations
benefits realization processes, 268
culture, 51–52
human resources (HR) frame, 47–48
political frame, 47–48
requirements management, 194
structural frame, 47, 49–51
symbolic frame, 47–48
training and certification programs for
business analysts, 187
world-class, 280
Ouchi, William, 358
outsourcing, 66–67, 466–470
overallocation, 366
overruns, 264–265
P
parametric estimating, 274
Pareto charts/analysis, 311–312
Parkinson’s Law, 245
payback period, 151–152
PDM. See precedence diagramming
method (PDM)
Pell, Philip A., 83
performance, 305
performance reporting, 403–404
Per Scholas, 467
personality measures, 370–375
PERT. See Program Evaluation and Review
Technique (PERT)
PERT weighted average, 247
phase exits, 62
physician’s office or clinic, scheduling
work, 246
Pink, Daniel, 351
planned value (PV), 283
planning processes
case studies, 98–107, 122–124
communications management, 398–399
cost management, 270–271
integration management, 141–143
knowledge areas, 85–86
process groups, 81, 85–86
procurement management, 471–481
quality management, 304–305
risk management, 433–434
rolling wave, 226
scope management, 186–187
stakeholder management, 502
strategic, 141–143
time management, 225–226
PMBOK Guide, 23, 50, 71, 87, 98
PMI. See Project Management Institute
(PMI)
PMI Professional in Business Analysis
(PMI-PBA)®, 187
PMI Risk Management Professional
(PMI-RMP)SM credential, 426
PMI Talent Triangle, 359
PMO. See Project Management Office
(PMO)
PMP. See Project Management Professional
(PMP)
podcasts, 415
Point of Total Assumption (PTA), 472
political frame, 47–48
politics, 48
Porras, Jerry, 317
Porter, Michael, 145
portfolio management, 18–22, 288–289
power, 354–355
power/interest grid, 500
Practice Standard for Work Breakdown
Structures, 195, 200
pre-bid conference, 482
precedence diagramming method (PDM),
230–232
predictive life cycle, 60
prevention cost, 327
PriceWaterhouseCoopers (PWC), 89
Primal Leadership (Goleman), 358
PRINCE2/PRINCE2 Practitioner
certification, 87
probabilistic time estimates, 247
probability/impact matrix/chart,
443–444
problems, 146–147
process, 81
process adjustments, 308
process groups. See project management
process groups
Procter & Gamble, 451
procurement, 466
procurement management. See project
procurement management
procurement process, improving, 485
product backlog, 119
product life cycles, 59–62
product owner, 118
profit margin, 267
profits, 267
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.9
Program Evaluation and Review Technique
(PERT), 247–248
program managers, 18
programs, 17
progress reports, 14, 404
project acquisition, 57
project and portfolio management (PPM)
software, 21–22, A2–A3
project archives, 413
project buffers, 245
project charter, 155–158
project communication management
controlling communications, 404–405
importance of, 390–392
improving communications, 405–414
keys to good communication, 392–397
managing communications, 399–404
planning, 398–399
software for, 414–417
project cost management
budgeting, 281–282
controlling costs, 282–289
definition and overview, 266
estimating costs, 271–280
importance of, 264–266
Microsoft Project 2013 and, A46–A56
planning, 270–271
principles of, 266–270
software for, 289–290
project feasibility, 57
project human resource management
definition and overview, 347–348
human resource plan, 359–364
importance of, 344–347
Microsoft Project 2013 and, A46–A56
psychosocial issues, 348–359
software for, 379–380
team acquisition, 364–369
team development, 369–375
team management, 375–379
project integration management
aligning IT with business strategy,
144–145
closing, 172
definition and overview, 138–141
directing and managing project work,
162–166
integrated change control and, 168–172
monitoring and controlling project work,
166–168
project charter, 155–158
project management plan, 158–162
selection of projects, 146–157
software and, 172–174
strategic planning and, 141–145
project life cycle, 57–59
project management. See also IT projects
defined, 9–10
demand for and advantages of, 1–4
ethics and, 34–35
history of, 28–32
knowledge areas, 11–12
methodologies, 86–89
planning (See also planning processes)
portfolio management and, 18–22
project attributes and, 6–7
project managers and, 7, 22–27
software, 35–36
software tools, 173
stakeholders, 10–11
success/failure of, 15–17
tools and techniques, 12–15
triple constraint and, 7–9
Project Management Institute (PMI), 19,
32–33, 88
2015 report by, 268
Project Management Office (PMO),
30–31
project management plan, 158–162
project management process groups
closing, 81, 85–86, 114–117, 126, 172,
484–485
executing, 81, 85–86, 107–111, 124
initiating, 81, 85–86, 93–98,
120–122
knowledge areas, 85–86
monitoring and controlling, 81, 85–86,
111–114, 124–126, 166–168, 307–308
overview, 81–84
planning, 81, 85–86
pre-initiation, 89–93, 120–122
templates, 126–128
tools and techniques, 12–15, 308–322,
476–477
Project Management Professional (PMP),
3, 33–34, 56
Project Management Professional (PMP)
certification
increase in, 3
need for, 56
project managers, 7, 22–27
project organizational structure, 50
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.10
project procurement management
closing procurements, 484–485
conducting procurements, 481–483
controlling procurements, 483–484
importance of, 466–470
planning, 471–481
software and, 485–487
project quality management
controlling quality, 307–308
definition and overview, 302–303
importance of, 300–302
improving, 326–333
modern quality management,
322–326
planning, 304–305
quality assurance, 306–307
software for, 333
project risk management, 436
contracts and, 471–476
controlling risks, 454–455
identifying risks, 438–442
importance of, 426–433
planning, 433–434
qualitative risk analysis,
442–447
quantitative risk analysis,
447–452
software for, 455–456
sources of risk, 434–438
projects
attributes of, 6–7
constraints, 7–9
defined, 4
examples of, 4–6
project scope management
collecting requirements, 188–191
controlling scope, 207–210
defining scope, 191–194
overview, 184–185
planning, 186–187
software and, 210–211
validating scope, 205–207
work breakdown structure, 194–205
project scope statements, 191
project selection
balanced scorecard, 154
business area analysis and, 143–144
categorizing IT projects, 146–147
financial analyses and, 147–152
focus on broad organizational needs,
146
Projects in Controlled Environments
(PRINCE2), 87
project sponsors, 7
project stakeholder management
controlling stakeholder engagement,
506–508
focusing on needs, 52–54
identifying stakeholders, 498–502
importance of, 496–498
managing stakeholder engagement,
503–506
planning, 502–503
register of, 94, 499, 500
software for, 508–509
project time management, 248
controlling the schedule, 248–250
defining activities, 225–228
estimating duration, 233–234
overview, 222–225
planning schedules, 225
resource estimation, 232–233
schedule development, 234–248
schedule importance, 222–225
sequencing activities, 228–232
software for, 250–252
prototyping, 209
prototyping life cycle model, 61
PTA. See Point of Total Assumption
(PTA)
pull communication, 401
Pulse of the Profession®: Capturing the
Value of Project Management 2015,
164
purchasing, 466
push communication, 401
PV. See planned value (PV)
Q
quadruple constraint, 9
quality, 302
quality assurance, 306–307
quality audits, 307
quality circles, 324
quality control, 307–308
Quality Control Handbook (Juran), 323
quality management. See project quality
management
Quartier International de Montréal (QIM),
111
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.11R
RACI charts, 363
RAD. See Rapid Application Development
(RAD) model
RAM. See responsibility assignment matrix
(RAM)
Rapid Application Development (RAD)
model, 61, 88
rapport, 357
rate of performance (RP), 283
Rational Unified Process (RUP) framework,
88
Reachi device, 401
referent power, 355
relationships, 228
reliability, 305
Request for Proposal (RFP), 361, 478–481
Request for Quote (RFQ), 479–481
requirements, 186, 209–210
requirements analyses, 13
requirements management plans, 187
requirements management, report on, 194
requirements traceability matrix (RTM),
191
reserves, 270
residual risks, 454
resource breakdown structures, 233
resource histograms, 363, 366, A46
resource leveling, 367–369
resource loading, 366–367
resources, 224, 232–233, A46–A56
responsibility assignment matrix (RAM),
362–363
return on investment (ROI), 150–151, 268
reward power, 355
rework, 307
RFP. See Request for Proposal (RFP)
RFQ. See Request for Quote (RFQ)
risk, 429
risk acceptance, 453, 454
risk appetite, 430
risk-averse, 431
risk avoidance, 452–453
risk breakdown structure, 437
risk enhancement, 454
risk events, 440
risk exploitation, 453–454
risk factors, 444
risk information technologies and services
(RITS), 429
risk management. See project risk
management
Risk Management Guide for DOD
Acquisition, 438
risk management plans, 433–434
risk mitigation, 453
risk-neutral, 431
risk owner, 442
risk registers, 440
risk-seeking, 431
risk sharing, 454
risk tolerance, 430
risk transference, 453
risk utility, 431
Robbins, Stephen P., 51
Robust Design methods, 324–325
ROI. See return on investment (ROI)
rolling wave planning, 226
Ross, Douglas, 356
Ross, Jeanne, 55
rough order of magnitude (ROM) estimate,
272
Rowley, Mark, 140
RP. See rate of performance (RP)
RSA Animate, 351
RTM. See requirements traceability matrix
(RTM)
run charts, 313, 314
RUP. See Rational Unified Process (RUP)
framework
S
salaries, 3
Salt Lake Organizing Committee (SLOC),
167
Sanderson, Peter, 473
Satisfaction and Loyalty Tracking (SALT)
customer analytics, 56
scatter diagrams, 310, 311
schedule baseline, 237–238
schedule performance index (SPI), 284
schedules. See project time
management
schedule variance (SV), 284
Schlumberger, 289
Schwalbe, Kathy, A1
scope, 184, 191–194, 205–211
scope baseline, 194
scope creep, 205
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.12
scope management. See project scope
management
scope statements, 13
scope validation, 206
Scrum, 70–71, 118–121
ScrumMaster, 118
Scrum team, 118
SDLC. See systems development life cycle
(SDLC)
secondary risks, 454
SEI. See Software Engineering Institute
(SEI)
selection of projects. See project selection
sensitivity analysis, 451–452
Sentinel project, 248
Sentinel system, 227–228
Seven Basic Tools of Quality, 308–322
seven run rule, 309–310
SharePoint portal, 408
Shat-R-Shield, 154
simulation, 449–451
six 9s of quality, 320
Six Sigma methodologies, 88, 315–320
skills gap, 347
Skjødt, Pernille, 401
slack, 239
slipped milestones, 238
SMART criteria, 236–237
smoothing mode, 377
social media blunders, 406
Social Media for Project Managers
(Harrin), 509
social networking, 509
Social Styles Profile, 373–374
software. See also Microsoft Project 2013
software
agile software development, 69–72,
87–88
Computer Aided Software Engineering
(CASE), 209
course management software, 409
defects, 321
historical perspectives, 28–32
overview, 25–36
project and portfolio management
software, 21–22
for project communication management,
414–417
for project cost management, 289–290
for project human resource
management, 379–380
project integration management and,
172–174
and project procurement management,
485–487
for project quality management, 333
for project risk management, 455–456
project scope management and,
210–211
for project stakeholder management,
508–509
for project time management, 250–252
SDLCs and, 60–62
tools and techniques, 13–14
Software Engineering Institute (SEI),
330–331
Software Quality Function Deployment
(SQFD) model, 330
source selection, 482
SOW. See statement of work (SOW)
SPI. See schedule performance index (SPI)
spiral life cycle model, 60
sprint, 118
sprint backlog, 119
SQFD. See Software Quality Function De-
ployment (SQFD) model
staffing management plans, 363
stakeholder analysis, 500, 503
stakeholder management. See project
stakeholder management
stakeholder register, 94, 499, 500
stakeholders, 10–11
standard deviation, 318
standards, 86
Standish Group, 3–4, 14, 63, 434, 435
start-to-finish dependency, 231
start-to-start dependency, 231
Startup Box, 467
statement of work (SOW), 478
statistical sampling, 314–315
status reports, 404
Stougaard, Ida, 401
strategic and business management, 359
strategic planning, 141–143
strategy, improving ability to execute, 164
stratification, 313
structural frame, 47
subproject managers, 360
success/failure, 15–17
sunk cost, 270
supplier conference, 482
suppliers, 466
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.13
Surrey Integrated Reporting Enterprise
Network (Siren) project, 140
SV. See schedule variance (SV)
SWOT analysis, 142–143, 440
symbolic frame, 47, 48
synergy, 355
system outputs, 304
systems, 45
systems analysis, 45
systems approach, 45
systems development life cycle
(SDLC), 60
systems management, 45, 46–47
systems philosophy, 45
systems thinking, 45
system testing, 320, 322
T
Taguchi, Genichi, 324
Talent Triangle, PMI, 359
tangible costs or benefits, 269
task, 223
task dependencies, A38–A43
task durations, A31–A38
TAT. See Thematic Apperception Test
(TAT)
team-building, 371
team development, 369–375
technical project management, 359
telecommuting, 346
templates, 126–128, 411–414, A15–A16,
A57–A58
termination clause, 475
Tesla Motors Inc., 468
testing, 320–322
text messages, 506–507
Thamhain, H. J., 353
Thematic Apperception Test (TAT), 352
Theory of Constraints (TOC), 243–245,
247
Theory X, 352–353
Theory Z, 352–353
three-point estimate, 234
time and material (T&M) contracts, 474,
475
time management. See project time
management
Titanic factor, 446–447
Tiwari, Sudhir, 88
T&M contracts. See time and material
(T&M) contracts
TOC. See Theory of Constraints (TOC)
tools and techniques, 12–15, 308–322,
476–477
top-down approach, 201
top-down estimates, 273
Top Ten Risk Item Tracking, 444–446
total float, 241
total quality control (TQC), 325
total slack, 241
TQC. See total quality control (TQC)
tracking Gantt charts, 237–238
training, 370–371
triggers, 441
triple constraint, 7–9, 226
Tuckman, Bruce, 370
Tuckman model, 370
U
United States Department of Justice, 301
unit pricing, 474
unit tests, 320
unknown risks, 431
unknown unknowns, 270
Urban Development Center (UDC) for soft-
ware testing projects, 467
urban onshoring, 467
Urmson, Chris, 326
use case modeling, 209
user acceptance testing, 320
user input, 208–209
user stories, 123
V
variance analysis, 208
Victoria, Australia, 207
virtual teams, 67–69
W
Walmart, 467
Walton, Jane, 289
Ward, J. Leroy, 69
watch lists, 446
waterfall life cycle model, 60
Water, Sydney, 55
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Index
I.14
WBS. See work breakdown structure
(WBS)
WBS dictionary, 203–205
webcasts, 415
weighted scoring model, 152–154
Weill, Peter, 55
White, Donald, 497
Whittaker, James, 189
wikis, 408–409, 410
Wilemon, D. L., 353–354
Williams, David J., 227
wireless broadband, 170
withdrawal mode, 377
workarounds, 455
work breakdown structure (WBS), 13, 57,
160, 194–205, 453, A23–A28
work from home, 346
working relationships, 430
work packages, 196
workplace factors on quality, 329
work, rules to focus on, 237
Y
Yahoo, 346
yield, 319
YouTube, 415
Z
zero defects, 323–324
Zients, Jeff, 53
Zulily, 468
Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Copyright 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.

Brief Contents
Table of Contents
Preface
Ch 1: Introduction to Project Management
1.1 Introduction
1.2 What is a Project?
1.3 What is Project Management?
1.4 Program and Project Portfolio Management
1.5 The Role of the Project Manager
1.6 The Project Management Profession
Chapter Summary
Ch 2: The Project Management and Information Technology Context
2.1 A Systems View of Project Management
2.2 Understanding Organizations
2.3 Focusing on Stakeholder Needs
2.4 Project Phases and the Project Life Cycle
2.5 The Context of Information Technology Projects
2.6 Recent Trends Affecting Information Technology Project Management
Chapter Summary
Ch 3: The Project Management Process Groups: A Case Study
3.1 Project Management Process Groups
3.2 Mapping the Process Groups to the Knowledge Areas
3.3 Developing an IT Project Management Methodology
3.4 Case Study 1: JWD Consulting’s Project Management Intranet Site Project (Predictive Approach)
3.5 Case Study 2: JWD Consulting’s Project Management Intranet Site Project (Agile Approach)
3.6 Templates by Process Group
Chapter Summary
Ch 4: Project Integration Management
4.1 What is Project Integration Management?
4.2 Strategic Planning and Project Selection
4.3 Methods for Selecting Projects
4.4 Developing a Project Charter
4.5 Developing a Project Management Plan
4.6 Directing and Managing Project Work
4.7 Monitoring and Controlling Project Work
4.8 Performing Integrated Change Control
4.9 Closing Projects or Phases
4.10 Using Software to Assist in Project Integration Management
Chapter Summary
Ch 5: Project Scope Management
5.1 What is Project Scope Management?
5.2 Planning Scope Management
5.3 Collecting Requirements
5.4 Defining Scope
5.5 Creating the Work Breakdown Structure
5.6 Validating Scope
5.7 Controlling Scope
5.8 Using Software to Assist in Project Scope Management
Chapter Summary
Ch 6: Project Time Management
6.1 The Importance of Project Schedules
6.2 Planning Schedule Management
6.3 Defining Activities
6.4 Sequencing Activities
6.5 Estimating Activity Resources
6.6 Estimating Activity Durations
6.7 Developing the Schedule
6.8 Controlling the Schedule
6.9 Using Software to Assist in Project Time Management
Chapter Summary
Ch 7: Project Cost Management
7.1 The Importance of Project Cost Management
7.2 Basic Principles of Cost Management
7.3 Planning Cost Management
7.4 Estimating Costs
7.5 Determining the Budget
7.6 Controlling Costs
7.7 Using Project Management Software to Assist in Project Cost Management
Chapter Summary
Ch 8: Project Quality Management
8.1 The Importance of Project Quality Management
8.2 What is Project Quality Management?
8.3 Planning Quality Management
8.4 Performing Quality Assurance
8.5 Controlling Quality
8.6 Tools and Techniques for Quality Control
8.7 Modern Quality Management
8.8 Improving IT Project Quality
8.9 Using Software to Assist in Project Quality Management
Chapter Summary
Ch 9: Project Human Resource Management
9.1 The Importance of Human Resource Management
9.2 What is Project Human Resource Management?
9.3 Keys to Managing and Leading People
9.4 Developing the Human Resource Plan
9.5 Acquiring the Project Team
9.6 Developing the Project Team
9.7 Managing the Project Team
9.8 Using Software to Assist in Human Resource Management
Chapter Summary
Ch 10: Project Communications Management
10.1 The Importance of Project Communications Management
10.2 Keys to Good Communications
10.3 Planning Communications Management
10.4 Managing Communications
10.5 Controlling Communications
10.6 Suggestions for Improving Project Communications
10.7 Using Software to Assist in Project Communications
Chapter Summary
Ch 11: Project Risk Management
11.1 The Importance of Project Risk Management
11.2 Planning Risk Management
11.3 Common Sources of Risk on IT Projects
11.4 Identifying Risks
11.5 Performing Qualitative Risk Analysis
11.6 Performing Quantitative Risk Analysis
11.7 Planning Risk Responses
11.8 Controlling Risks
11.9 Using Software to Assist in Project Risk Management
Chapter Summary
Ch 12: Project Procurement Management
12.1 The Importance of Project Procurement Management
12.2 Planning Procurement Management
12.3 Conducting Procurements
12.4 Controlling Procurements
12.5 Closing Procurements
12.6 Using Software to Assist in Project Procurement Management
Chapter Summary
Ch 13: Project Stakeholder Management
13.1 The Importance of Project Stakeholder Management
13.2 Identifying Stakeholders
13.3 Planning Stakeholder Management
13.4 Managing Stakeholder Engagement
13.5 Controlling Stakeholder Engagement
13.6 Using Software to Assist in Project Stakeholder Management
Chapter Summary
Appendix A: Guide to Using Microsoft Project 2013
Glossary
Index

Still stressed with your coursework?
Get quality coursework help from an expert!