Question 1: A network consists of the activities in the following list. Times are given in weeks.
Activity
Preceding
Time
A
—
8
B
—
3
C
A
7
D
A, B
3
E
C
4
F
D
6
a. Draw the network diagram.
b. Calculate the ES, EF, LS, LF, and Slack for each activity.
Task
Early Start
Early Finish
Late Start
Late Finish
Slack
A
B
C
D
E
F
c. What is project completion time?
Question 2: A partially solved PERT problem is detailed in the table below. Times are given in weeks.
Activity
Preceding
Optimistic
Time
Probable
Time
Pessimistic
Time
Expected
Time
Variance
A
—
7
9
14
1.361
B
A
2
2
8
0
C
A
8
12
16
0
D
A
3
5
10
1.361
E
B
4
6
8
0
F
B
6
8
10
0
G
C, F
2
3
4
0
H
D
2
2
8
1.000
I
H
6
8
16
2.778
J
G, I
4
6
14
2.778
K
E, J
2
2
5
0.250
a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above.
b. Which activities form the critical path?
c. What is the estimated time of the critical path?
d. What are the project variance and the project standard deviation?
e. What is the probability of completion of the project before week 40?