Management

Answer all questions completely

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

No Plagiarism

Cite all resources used and use in-text citations

The PCNet Project (B)

Dynamically Managing Residual

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Risk

04/2005

This case was written by Christoph H. Loch, Professor of Technology and Operations Management

It is based on real events, but the names of all companies and participants have been disguised.

Any similarity with existing companies is accidental. The case is intended to be used as a basis for class discussion rather than to illustrate the effective or ineffective handling of an administrative situation.

The unexpected events that worried Jack Muller represented “residual risk”. In a project of

such complexity, no amount of planning can ever anticipate all events, no matter how

thorough; there will always be some events that are not planned for. Therefore, it is key to

build the capability of dealing with residual risk as it comes along.

The direct outcome of the 18 September meeting was a strengthening of the aggregate

oversight body (for the entire merger), not in the sense of it exerting more pressure, but in

terms of adding experience and enhancing its problem-solving and advice-giving capacity.

First, the Integration Management Committee Meeting became the Performance Monitoring

Meeting, with a dedicated manager (who followed up issues), expanded membership to add

relevant areas of expertise, and a more systematic synergy follow up.

The Risk Management Office

At the level of the IT integration, Max Schmeling had already begun to build a structure for

managing residual, unforeseen contingencies during execution. The Risk Management

Office (RMO) was put in place as a complement to the Project Management Office (PMO).

Whereas the PMO followed up on actions and on reporting, the RMO focused on responding

to deviations. It was a central control point to which all teams were required to call in at least

once a day to report on progress and problems that arose.

The RMO achieved two things. First, it represented a problem-solving resource – Metal

Resources Co. had its own technical experts present in this center, plus experts on call from

all technical areas at the main systems vendors (such as HP and IBM for PCs, Cisco for

routers, Microsoft for operating systems, SAP for R3, EDS for the network operation, etc),

and experts in culture and change management were also on call. Thus, when an unforeseen

problem occurred, the center diagnosed it with the team in question and then helped to

mobilize the expertise to bring about, or plan, a solution as quickly as possible. Second, the

rapid information exchange helped to set off alarm bells (early warnings) as well as solution

approaches, across the many parallel teams. As they were working on very similar issues at

multiple sites, a problem occurring at one site might well subsequently occur at one of the

others, and thus the transfer of solutions was efficient. The rapid communication of relevant

warnings from one team to another was dubbed “the hotwire”.

Thus, at each local deployment, a representative of the next local deployment team (in another

state or country) was present so that they could become familiar with the logistical as well as

technical issues. The Latin American deployment went very smoothly as a result of this

approach. Similarly, problems that arose in the application migration to the new platform in

Singapore were subsequently avoided throughout the Southeast Asian region.

Both the PMO and the RMO also attempted to prevent certain risks by enforcing strict

standards (thus reducing the complexity and number of things that could go wrong), such as

all of North America having to move to a single SAP system configuration (there was a

separate central control center for that project alone, which worked with all the organizational

units to produce a common standard that satisfied most of the needs). Many technical and

business software applications were standardized (such as statistical analysis packages,

geological expert systems etc.), which, in turn, reduced the number of different problems that

could occur and facilitated the sharing of solutions across teams.

The activities of the RMO enabled the organization to work with budget and schedule

variances (deviations) in a more sophisticated way, for example, by performing variance

analysis. There was significant overspending in Phase 3, because some work originally

foreseen for Phase 4 was in fact carried out at this point due to small “design changes” or

improvements in protocols and processes as the organization learned during the project. The

activities of the RMO involved providing explanations and documentation for residual risk

and the respective actions required. Thus the organization had a ‘trace’ that offered a

thorough explanation of deviations and an institutionalized effort to learn from such changes.

The following example illustrates the effect of such learning: the early PC deployments took

several man days per person as the migration team was learning and stabilizing the

components of the network, whereas later deployments required only a few hours (a reduction

of 75%) and were much more stable. Overall, the project remained slightly under budget,

although it took 6 months longer than originally planned.

Dealing With Individual Residual Risks

The problem of lost e-mails and corrupted e-mail capabilities had to be attacked at two levels.

The first level was technical: when the lost file incidents were examined, the root problem

turned out to be that Microsoft XP did not have a translator to automatically modify files. In

response, the Microsoft developers made their own in-house translator software available

which systematically eliminated the problems and improved the overall robustness of the

network. Several similar fixes contributed to overall network stabilization. The second

solution level concerned change management processes: over time, the merger team put such

processes in place (“who can change what system features, after discussing it with whom”),

and convinced employees to comply with them, which eliminated incompatibilities introduced

by local changes.

The Sri Lankan government partner eventually came on board, although at its own pace. This

contributed to a six-month delay but did not “stop the show”.

The refining manager who refused the deployment was won over with a combination of carrot

and stick. On the one hand, the IT organization conducted a security audit at his site, which

exposed serious vulnerability to external attacks and other breakdowns. This allowed the

team to show him how badly it might get for him locally (carrot) and make it clear that he

could not be permitted to pose a risk for the rest of the organization (stick).

The cajoling and convincing of the refining plant manager was then generalized to a

standardized, prepared, compelling argument that was used with operating managers who

thought they had no time for off-line activities like IT migration (Exhibit 1). The argument

again combined carrot and stick – on the one hand it explained the benefits to the operating

units themselves and emphasized that they could get help; on the other it threatened them that

their network would no longer be supported if they did not migrate. This standard argument

was, of course, complemented by personal visits and face-to-face explanations.

Overall Project Success

“You guys will have to learn how to walk, whistle and chew gum, all at the same

time.”

Martin Folz, CEO

The ITC organization did learn to “walk, whistle and chew gum at the same time”, as the

CEO demanded. They took the metaphor seriously enough to define it: walking meant to not

disrupt ongoing operations, whistling to lead the project with state-of-the-art methods, and

chewing gum stood for status reviews and dealing with residual risks. At the end, no

unexpected event was serious enough to break the project. The thorough planning, combined

with the flexibility of the RMO and the hotwire, was so powerful that the huge IT merger

became a convincing success. The total IT merger project beat its target by $20 million,

producing $230 million of synergies in the first year, and the PCNet project made a

significant contribution to this overfulfillment (partially driven by an extra $10 million in PC

discounts that came out of the proactive negotiations).

Critical to this success was the support and constancy of purpose of top management: the

CEO listened to the business case and stayed the course. No IT migration budgets were cut,

in spite of the lean economic times, and the project was able to maintain priority and focus.

Exhibit 1

Communication Document for Operating Company Compliance

The PCNet Deployment Consultant team presents……..

The Top Ten List of “Reasons why you should quickly and carefully

decommission your legacy IT environment”

10. Dual environments will make it more difficult to maintain IP compliance, particularly once Microsoft

ceases support of NT 4.0.

9. Dual environments are impacting our networks due to unnecessary traffic from the legacy

infrastructures such as file replication, Exchange Global Catalog replication, SMS inventory and

package traffic, as well as WINS and DNS traffic.

8. Increased vulnerability to security attacks and viruses as vendors start dropping maintenance

support for Win9x, NT4 and W2K, and our internal centralized efforts are no longer funded for

these environments.

7. Increased cost for support as troubleshooting by support staff becomes a lot more complex due to

having to follow separate processes and using different tools in order to support two environments.

Cost also increases due to reduced reliability and increased break/fix calls as hardware has lived

long past its planned life-cycle.

6. Legacy Master Account NT4 and AD domains will be decommissioned, leaving resource domains

with no trusts. The old PC and workstation environments will lose connectivity. There will also be

performance issues as Master Account domain controllers are removed one by one.

5. The decommissioning effort is part of Metal Resources and RBD synergy cost-savings and the

realization of these savings now becomes our responsibility.

4. The business case for the synergies will be compromised by having to support dual

infrastructures.

3. Manpower can be redirected towards strategic projects once deployment and decommissioning

efforts are completed (and we can take our vacations now!).

2. Old computing standards monthly costs will be increased by x2, x4 and x6 the longer you keep

your old hardware. Costs to maintain old infrastructure will be divided by the number of remaining

old standard users.

And the #1 Reason is …

1. The old desktop has been declared “non-standard”. Yes, it is true. The sun has set on the old

standard, with the IT design team only providing Anti-Virus updates and major security patches.


Having old standard machines at your site makes your site “Non-Standard”.

—————————————————————————————————————————————-

Here are three documents to help you in your efforts to decommission:

Decommission Legacy Systems Guide

Decommissioning Server Assets

Decommissioning Workstation Assets

*** If the thought of pulling the plug on your favorite Compaq Proliant server is giving you nightmares

and sleepless nights, then please email me back about getting the PCNet Deployment Consultant

team to offer decommissioning consulting services at your site.

31

“The PCNet Project (B) Dynamically Managing Residual Risk.” Loch, Christoph. Case No.

5272b. Published 04/2005, INSEAD, (6 pages).

Answer all questions completely

No Plagiarism

Cite all resources used and use in-text citations

Assignment 2: Risk Management Plan

Note: The assignments are a series of papers that are based on the same case. The assignments are dependent upon one another.

In this assignment, you will create a risk management plan. You have a budget of $100,000 and a timeline of six (6) months for the plan. Please refer to Figure A-1, Risk Management Plan Template, from Appendix A (shown below) of the Hillson and Simon text to create the plan.

Write an eight to ten (8-10) page Risk Management Plan Component paper in which you:

1. Prepare the Scope and Objectives of the Risk Management Process section of the Risk Management Plan based on the facts presented in the case study.

2. Determine the project size, based on the facts presented in the case study, and provide justification based on Figure 3-4, Example Project Sizing Tool (Chapter 3 of the Hillson and Simon text-shown below).

3. Select the risk tools and techniques, and complete the Risk Tools and Techniques section of the Risk Management Plan for both the qualitative and quantitative aspects of the project. Provide a rationale for the selection.

4. Develop the Risk Reviews and Reporting section of the Risk Management Plan based on the project size previously determined.

5. Define the Probability and Impacts section of the Risk Management Plan and justify the values assigned.

6. Define the Risk Thresholds section of the Risk Management Plan and justify the values assigned.

Your assignment must follow these formatting requirements:

· Be typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.

· Include a cover page containing the title of the assignment, the students name, the professors name, the course title, and the date. The cover page and the reference page are not included in the required assignment page length.

Hillson, D. (2012). Practical project risk management, 2nd Edition. [Strayer University Bookshelf]. Retrieved from https://strayer.vitalsource.com/#/books/9781567263671/

Appendix A-1

Figure 3-4

See Below

Still stressed with your coursework?
Get quality coursework help from an expert!