Please see attached.
(crashing/shortening/etc.)
Project Management Exercise.
The instructions for Part 2 are as follows:
1. Access your MS Project file submitted (See attached .mpp file). Now, shorten this project so that the concert can take place as planned (September 4th).
2. Identify the tasks you will shorten to achieve this goal and adjust the durations of these activities so that the “finish time” indicates the concert can take place as scheduled. This is your “After” or “Crashed” entry screen.
3.
This will be your “After” Network Diagram
Tips:
1. Find the tasks on the critical path(s).
2. Crash the least expensive task(s) on the critical path(s).
MUSIC FEST TABLE.
Activity
Description
Predecessors
Normal Time
in Days
Normal Time
Cost
Task can be
shortened to
Total Cost of
Shortened Time
1
Finalize sites & facility contracts
28
$10,000
2
Select concert promoter
1
14
$7,500
3
Hire Production Manager
2
21
$5,000
4
Design Promotional Website
2
25
$15,000
5
Finalize TV right
2
60
$8,000
50
$12,000
6
Hire Director
2
28
$7,500
7
Plan for TV camera placement
6
13
$7,250
8
Target Headline entertainers
2
45
$12,500
41
$18,000
9
Target Support entertainers
8
43
$11,000
10
Travel accommodations for talent
9
4
$6,000
3
$8,000
11
Set venue capacity
3
3
$2,000
12
Sign Ticket Master Contract
2,4,11
17
$6,000
13
On-site ticketing
12
6
$1,500
5
$4,000
14
Lease sound and staging equipment
3
8
$5,500
15
Passes & stage credentials
7,16,18
4
$2,500
2
$3,000
16
Travel accommodations for staff
21,23
4
$4,000
17
Hire Sponsor Coordinator
2
21
$5,900
18
Finalize sponsors
17
35
$9,000
32
$12,000
19
Define & place signage for sponsors
5,17,24
8
$3,000
20
Sign Concession Contracts
2,11
32
$8,000
21
Hire Operations Manager
2
48
$5,500
43
$10,000
22
Develop site plan
21
31
$9,000
28
$9,000
23
Hire Security Director
2
20
$4,200
24
Hire Support Staff
21,23
17
$3,600
25
Develop police/fire security plan
23
55
$10,000
50
$15,000
26
Develop Traffic Plan
10,13,20,23
20
$9,500
18
$10,350
27
Determine Reqmts for Power, Facilities
22
30
$6,200
26
$7,200
28
Secure Merchandise sales
2
25
$6,100
29
Secure Online merchandise sales
28
20
$4,700
30
Install Power/plumbing/AC/Toilet Svcs
27
6
$9,500
31
Construct Stage
3,14,22,27,30
2
$7,000
32
Test Sound/Lighting
15,30,31
2
$3,000
1
$4,500
33
Ready for Concert
19,25,26,29,32
1