Question 1
In _______, people experience greater learning and growth, and their knowledge and skills are transferred from project to project.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 2
Calculate the earliest start for Task B if its predecessor, Task A, finishes on
day 3
and the duration of Task B is 2 days.
Answer
day 5
day 3
day 1
Cannot be calculated based upon information given.
1 points
Question 3
The latest finish time for a specific activity must be
the same as
or
earlier than
the earliest of all the latest start times of all the activities emerging directly from that specific activity.
Answer True False
1 points
Question 4
A ______________ plan must be developed that identifies and assesses potential risks, determines the likelihood of occurrence and potential impacts of risks, and delineates responses for dealing with risks
Answer
risk development
risk management
risk mitigation
risk avoidance
1 points
Question 5
The _________ sets the tone for the project.
Answer
project kickoff meeting
project progress meeting
project status meeting
project design meeting
1 points
Question 6
Projects are constrained only by the scope, schedule, and budget.
Answer True False
1 points
Question 7
A disadvantage of a functional organizational structure is that there is a lack of
customer
focus.
Answer True False
1 points
Question 8
__________ also facilitates information flow.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 9
If resources are to be considered in planning, it is necessary to
Answer
when each is taking vacation time or time off.
know the name of each resource on the project.
list all the projects to which the resources have been assigned.
indicate the amounts and types of resources needed to perform each activity.
1 points
Question 10
________________ establish the foundation for successful funding.
Answer
Research and records
Relationships
Public documents
Financial investments
1 points
Question 11
It is good practice to have the person who will be responsible for the costs associated with the work make the cost estimates.
Answer True False
1 points
Question 12
The project purpose should
Answer
summarize the need and justification for the project.
state what is expected to be accomplished.
state the major end products or items expected to be produced.
be concise and create a vision for the end result of the project.
1 points
Question 13
The win ratio is the percentage of the number of proposals a contractor won out of the total number of proposals the contractor submitted to various customers over a particular time period.
Answer True False
1 points
Question 14
Before a
project team
meeting, the _______ should determine whether a meeting is really necessary, the purpose of the meeting, and who needs to participate in the meeting.
Answer
the project team.
the team member that identified a problem.
the
project manager
.
the customer.
1 points
Question 15
Half of making communication effective is
Answer
listening.
responding.
understanding.
talking.
1 points
Question 16
A risk is an uncertain event that, if it occurs, can jeopardize accomplishing
the project objective.
Answer True False
1 points
Question 17
With knowledge of potential risks, the contractor can include contingency or management reserve amounts in the bid price.
Answer True False
1 points
Question 18
The heart of communication is not words, but
Answer
listening.
responding.
understanding.
talking.
1 points
Question 19
The project budget includes costs for each activity plus other project costs such as administrative costs and overhead costs.
Answer True False
1 points
Question 20
A project charter summarizes
Answer
the project objective.
the detailed description of the project.
the key conditions and parameters of the project.
the funding and contracting of the project.
1 points
Question 21
_________is typically used in businesses that primarily sell and produce standard products. For example, a company that manufactures and sells video recorders.
Answer
An autonomous project organizational structure
A functional organizational structure
A matrix organizational structure
A project management office
1 points
Question 22
In the ______ stage of team development, individuals do a lot of questioning in the
forming
stage: What is our purpose? Who are the other team members? What are they like?
Answer
forming
norming
storming
performing
1 points
Question 23
mc010-1 Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question.If the tasks were placed in a serial relationship with Task 1 first and the others in numerical order, on what day would Task 3 be done?
Answer
day 18
day 3
day 10
day 9
1 points
Question 24
In the _______ stage of team development, a feeling of camaraderie emerges.
Answer
forming
norming
storming
performing
1 points
Question 25
Calculate the latest finish for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.
Answer
day 9
day 10
day 12
Cannot be calculated based upon information given.
1 points
Question 26
During the _____, the project team or contractor should ensure that copies of appropriate project documentation are properly organized, filed, and archived so that
they can be readily retrieved for future use.
Answer
evaluating the project phase
.
controlling the project phase
.
performing the project phase
.
closing the project phase
.
1 points
Question 27
Listening is more than just letting the other person talk. It must be
Answer
a passive, not an active, process.
an impatient, not a patient, process.
an reactive, not a proactive, process.
an active, not a passive, process.
1 points
Question 28
Companies with _______are in the projects business; they do not produce standard products.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 29
A project organization can take several steps to create and sustain a supportive and positive climate for
diversity.
These include all the following except
Answer
develop a written policy regarding diversity.
provide training about diversity in the workplace.
include diversity as a primary meeting agenda item.
have team meetings for members to get to know each other and value each other’s differences.
1 points
Question 30
Socialization among team members supports
Answer
team dissention.
knowing too much about each other.
team building.
not getting work done because too much social time.
1 points
Question 31
The ________ agenda contains the Closing comments to reinforce the expectations and the roles and allow tem members to ask questions, make comments, and get to know each other.
Answer
project kickoff meeting
project progress meeting
project status meeting
project design meeting
1 points
Question 32
In the _______ stage of team development, work performance accelerates and productivity increases.
Answer
forming
norming
storming
performing
1 points
Question 33
In the _______ phase of team development, relationships have become settled.
Answer
forming
norming
storming
performing
1 points
Question 34
A potential conflict on projects is Cost where conflict often arises over
Answer
how much the work should cost.
how the work should be done.
at what level of quality the work should be done.
how much work should be done.
1 points
Question 35
In _________, there is little opportunity for members of different project teams to share knowledge or technical expertise, because each project team tends to be isolated.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 36
With respect to the project schedule, changes can result in any of the following except
Answer
the addition or deletion of activities.
the initial planning and sequencing of activities.
changes to estimated durations for specific activities.
a new required completion time for the project.
1 points
Question 37
Risks may change as the project progresses and should be reflected in
Answer
the Risk Assessment Matrix.
the action trigger point.
the risk response plan.
the risk management strategy.
1 points
Question 38
It is fair to meet with potential contractors and provide information about the potential project while developing the RFP.
Answer True False
1 points
Question 39
Corrective action must be take for a project when
Answer
actual progress to the planned progress shows the progress is ahead of schedule.
the technical specifications have been met.
the actual costs of the activities is less than the funds received for the work completed.
the actual progress is less than the planned progress.
1 points
Question 40
Some RFPs mention the type of contract the customer intends to use.
Answer True False
1 points
Question 41
During project closing, the project team or contractor should ensure that copies of appropriate project documentation are properly organized, filed, and archived so that
Answer
they can be stored easily.
they can be readily retrieved for future use.
the files are ready for audit.
the project sponsor could review them.
1 points
Question 42
A financial related activity that must be performed during the closing phase is assuring that
Answer
total budgeted costs are calculated.
the quarterly payments are invoiced.
the personnel responsible for financial work is identified.
all payments have been collected from the customer.
1 points
Question 43
All of the following are barriers to effective listening except
Answer
pretending to listen.
patience.
bias and closed-mindedness.
jumping to conclusions.
1 points
Question 44
Total slack for the project is the difference between
Answer
LF time of last activity and the project required completion time.
EF time of last activity and the project required completion time.
ES time of last activity and the project required completion time.
LS time of last activity and the project required completion time.
1 points
Question 45
The statement, “Network diagrams illustrate the technical constraints among activities,” means the activities are constrained because
Answer
each of the activities are independent from the other activities.
one activity cannot be started until the predecessors are finished.
the activities use different resources to be completed.
some activities use the same resources that may not be available.
1 points
Question 46
The project title should
Answer
summarize the need and justification for the project.
state what is expected to be accomplished.
state the major end products or items expected to be produced.
be concise and create a vision for the end result of the project.
1 points
Question 47
In the ________ stage of team development, the project manager still needs to be directive, but less directive than in the forming stage.
Answer
forming
norming
storming
performing
1 points
Question 48
________ involves determining the likelihood that the risk event will occur and the degree of impact the event will have on the project objective.
Answer
Priority alignment
Responding to a risk
Assessing each risk
Risk planning
1 points
Question 49
The greatest constraint for a project is the
Answer
cash flow for the organization
the schedule for the project.
availability of the right resources at the right time.
the level of quality to be produced.
1 points
Question 50
A consistent time base, such as hours or days or weeks, should be used for all the estimated durations of activities in a
network diagram
.
Answer True False
1 points
Question 51
Risks are prioritized based on
Answer
the likelihood of occurrence and degree of impact.
the order they are identified.
the gut feeling of the project team.
the priorities set in a different project.
1 points
Question 52
The __________ approach to handling conflict can result in resentment and deterioration of the work climate.
Answer
Collaborating, Confronting, or Problem Solving
Avoiding or Withdrawing
Competing or Forcing
Accommodating or Smoothing
1 points
Question 53
In __________,
project team members
can inform the project manager and the functional manager.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 54
The
project scope document
should include a list of
deliverables
and associated
acceptance criteria
.
Answer True False
1 points
Question 55
Quantitative benefits of a project are the intangible benefits of completing a project such as employee morale.
Answer True False
1 points
Question 56
Waiting for unfavorable events to occur and then reacting to them
Answer
is part of a well designed response plan.
reflects much planning and consideration of consequences.
is a cost saving measure by not planning.
can result in panic and costly responses.
1 points
Question 57
Having the contractor or project team review the
statement of work
with the sponsor or customer provides an opportunity to make sure everything that the customer expects is included.
Answer True False
1 points
Question 58
The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. How much slack does the project have now that Task A is finished?
Answer
Negative
5 days slack.
Positive
5 days slack.
Positive 16 days slack.
Positive 3 days slack.
1 points
Question 59
Resource-limited scheduling is a method for
Answer
developing a schedule that attempts to minimize the fluctuations in requirements for resources.
making sure all the resources do the same amount of work.
making sure every task has the same number of resources.
developing the shortest schedule when the number or amount of available resources is fixed and cannot be exceeded.
1 points
Question 60
__________ can be cost-inefficient both for individual projects and for the company. Each project must pay the salaries of its dedicated project team, even during parts of the project when they are not busy.
Answer
An autonomous project organizational structure
A functional organizational structure
A matrix organizational structure
A project management office
1 points
Question 61
In ________, the project manager is responsible for the project results, while the functional managers are responsible for providing the resources needed to achieve the results.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 62
The project organization should establish a __________ that includes an easily accessible repository that encourages project managers and teams to retrieve lessons learned and information from previous projects.
Answer
document storage routine
file structure
knowledge base system
revision process
1 points
Question 63
Travel costs in the project costs estimate are for
Answer
travel (other than local travel) required during the project.
all travel by the organization.
travel costs for local meetings.
travel for conferences that may not be related to the project.
1 points
Question 64
The acceptance criteria deals with the scope of the project, outlining the tasks or work elements the customer wants the contractor or project team to perform.
Answer True False
1 points
Question 65
Cost estimates should be unreasonable and excessive.
Answer True False
1 points
Question 66
Project management is a proactive approach to controlling a project to ensure that the project objective is accomplished, even when things do not go according to plan.
Answer True False
1 points
Question 67
Resource-limited scheduling will not extend the project completion time if necessary in order to keep within the resource limits.
Answer True False
1 points
Question 68
The project manager needs to set the tone for encouraging open and timely discussion of risks among the project team.
Answer True False
1 points
Question 69
Every project has a starting date and an ending date.
Answer True False
1 points
Question 70
The cost of developing a proposal should be added in as a direct expense in the budget for a proposal.
Answer True False
1 points
Question 71
Clear, ambiguous acceptance criteria for all deliverables are important because they are the basis for verifying that the project scope has been completed in accordance with the customer’s requirements and expectations.
Answer True False
1 points
Question 72
The key to managing cash flow is to ensure that cash comes in faster than it goes out.
Answer True False
1 points
Question 73
Why are activities drawn in a serial relationship in a network diagram?
Answer
The activities use different resources.
The activities are independent of each other.
From a technical standpoint, the activities must be performed in that sequence.
The order of completion doesn’t matter.
1 points
Question 74
In the _______ phase of team development, the project team has accepted its operating environment.
Answer
forming
norming
storming
performing
1 points
Question 75
A resource requirements plan illustrates
Answer
who is responsible for which activities.
the amount of labor expenses for the project.
the expected utilization of resources by time period during the time span of the project.
the budget for material and cost resources.
1 points
Question 76
In ________ provides the project and customer focus of the project structure, but it retains the functional expertise of the functional structure.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 77
In the _______stage of team development, the team is highly committed and eager to achieve the project objective.
Answer
forming
norming
storming
performing
1 points
Question 78
The work package includes all of the specific work activities that need to be performed to produce the deliverable associated with that work package.
Answer True False
1 points
Question 79
The win ratio approach gives
Answer
equal weight to proposals with larger dollar amounts.
more weight to proposals with larger dollar amounts.
equal weight to all proposals.
less weight to proposals with larger dollar amounts.
1 points
Question 80
Although the __________ approach may make a conflict situation livable, it does not resolve the issue.
Answer
Collaborating, Confronting, or Problem Solving
Avoiding or Withdrawing
Competing or Forcing
Accommodating or Smoothing
1 points
Question 81
A bidders meeting may be held to
Answer
clarify the RFP and answer any questions from potential bidders.
provide additional information only to those that attend the meeting.
provide an unfair advantage to those at the meeting.
solicit feedback on the clarity of the RFP to change the project requirements.
1 points
Question 82
There _____ to develop the skills necessary to be an effective project manager.
Answer
are various ways
are limited ways
is only one way
are no ways
1 points
Question 83
__________ is customer focused.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 84
The purpose of team meetings is to discuss openly such questions as the following except
Answer
How are we working as a team?
What barriers are impeding teamwork (such as procedures, resources, priorities, or communications)?
What can we do to overcome these barriers and improve our teamwork?
How is the project progressing?
1 points
Question 85
If actual progress falls behind planned progress or unexpected events occur, the project manager
Answer
watches to see what happens.
takes immediate action.
alerts the sponsor and asks for more funds.
has an immediate meeting with the project
stakeholders
.
1 points
Question 86
At the start of the project, procedures need to be established regarding how changes will be
Answer
initiated.
documented and authorized.
compensated.
presented.
1 points
Question 87
Costs related to ___________ are for outsourced work when the project teams or contractors do not have the expertise or resources to do certain project tasks.
Answer
benefactors and
suppliers
stakeholders
reserve and withholding
subcontractors
and consultants
1 points
Question 88
The total dollar value approach is the ratio of the total dollar value of proposals that the contractor won as a percentage of the total dollar value of all the proposals the contractor submitted to various customers during a specific time period.
Answer True False
1 points
Question 89
Meeting the acceptance criteria listed in the project charter means the customer is satisfied.
Answer True False
1 points
Question 90
In _________, the project team has full control over the resources, including authority over how the work gets done and by whom.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 91
The project objective requires completing the project work scope on time and within budget.
Answer True False
1 points
Question 92
An RFP must provide a statement of work.
Answer True False
1 points
Question 93
The __________ approach emphasizes the search for areas of agreement within the conflict and minimizes the value of addressing differences.
Answer
Collaborating, Confronting, or Problem Solving
Avoiding or Withdrawing
Competing or Forcing
Accommodating or Smoothing
1 points
Question 94
Cumulative actual cost (CAC) should be calculated to compare to the cumulative budgeted cost (CBC).
Answer True False
1 points
Question 95
In the __________ approach, topics that may cause hurt feelings are not discussed.
Answer
Collaborating, Confronting, or Problem Solving
Avoiding or Withdrawing
Competing or Forcing
Accommodating or Smoothing
1 points
Question 96
The project manager should _________ for smaller projects.
Answer
assemble members as needed
acquire the entire team
determine who is needed an hope they are available
get extra people than planned
1 points
Question 97
Contractors should get to know people in customer organizations
Answer
by talking all about themselves so the customers know them.
by limiting contacts to once or twice a year for business.
on a business level only.
on personal and business levels.
1 points
Question 98
________ assist with the complexity of generating a resource-leveled schedule and resource requirements graphs and tables.
Answer
Project management information systems
Formulas and techniques
Trial and error techniques
Calendaring systems
1 points
Question 99
Successful projects should end with some type of
Answer
recognition and celebration.
criticism review.
list of all the problems in the project.
letter to all the stakeholders about what went wrong.
1 points
Question 100
Latest start time is calculated by
Answer
subtracting the activity’s estimated duration from the activity’s succeeding activity’s latest finish time: LS = LF succeeding activity – Estimated Duration.
adding the activity’s estimated duration to the predecessor of the activity’s latest start time: LS = LS predecessor + Estimated Duration.
subtracting the activity’s estimated duration from the activity’s latest finish time: LS = LF– Estimated Duration.
adding the activity’s estimated duration to the activity’s latest finish time: LS = LF+ Estimated Duration.
1 points
Question 101
In _________, a full-time project manager has complete project and administrative authority over the project team.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 102
The customer will pay the contractor a bonus if the project is completed ahead of schedule or exceeds other customer performance requirements.
Answer True False
1 points
Question 103
The agreed-upon project scope document establishes the baseline for any changes that may be made to the scope during the performance of the project.
Answer True False
1 points
Question 104
All branches of the WBS have to be broken down to the same level.
Answer True False
1 points
Question 105
The project manager clearly defines the project objective and reaches agreement with the______ on this objective.
Answer
customer
stakeholders
suppliers
project team
1 points
Question 106
A project has an unlimited time frame.
Answer True False
1 points
Question 107
The project quality plan should state which tools and techniques to use and when.
Answer True False
1 points
Question 108
Which of following would allow for level resources on the project?
Answer
mc017-1
mc017-2
mc017-3
mc017-4
1 points
Question 109
__________ reduces duplication and overlap of activities.
Answer
An autonomous project organizational structure
A functional organizational structure
A matrix organizational structure
A project management office
1 points
Question 110
The estimated resources required for an activity will influence the estimated duration to perform the activity.
Answer True False
1 points
Question 111
The ________ should prepare a written report of project performance including lessons learned and recommendations.
Answer
stakeholders
customer
project manager
CEO of the contractor’s organization
1 points
Question 112
The __________ may need to describe certain inspection techniques, testing procedures, or specific testing equipment or facilities that must be used.
Answer
statement of work
customer requirement
deliverables
acceptance criteria
1 points
Question 113
The network diagram can be created using a graphic chart format or as an indentured list.
Answer True False
1 points
Question 114
The project manager should schedule the post-project evaluation meeting with the customer or sponsor for a time when the customer is in a position to
Answer
pay all the expenses of the project to the contractor.
really determine whether the project met expectations and achieved the anticipated benefits.
solicit proposals for a new RFP.
begin planning for future projects or opportunities for the contractor.
1 points
Question 115
Labor costs in the project costs estimate are the estimated costs for the various types or classifications of ___________ and are based on the estimated work time (not necessarily the same as the activity estimated duration) and the dollar labor rate for each.
Answer
people who are expected to work on the project
people, even if they are not directly assigned to the project
overhead and direct expenses
subcontractors
1 points
Question 116
In the _______ stage of team development, team members now begin to test the limits and flexibility of the project manager and the ground rules.
Answer
forming
norming
storming
performing
1 points
Question 117
The deliverables in the project scope document will be used as the basis for creating a more detailed WBS in the next step of the planning process.
Answer True False
1 points
Question 118
In the _______stage of team development, communication is open.
Answer
forming
norming
storming
performing
1 points
Question 119
In the _______ stage of team development, the group begins to establish an identity and attempts to define and plan the tasks that need to be done. Little actual work is accomplished.
Answer
forming
norming
storming
performing
1 points
Question 120
Materials costs in the project costs estimate are the estimated costs of materials that the project team or contractor
Answer
want to have in supply in the office.
needs even if not for this particular project.
needs to purchase for the project.
might want to use on the project.
1 points
Question 121
_______ body language can be a frown, crossed arms, slouching, fidgeting, gazing or looking away, doodling, or yawning.
Answer
Neutral
Negative
Critical
Positive
1 points
Question 122
Addressing risks
proactively
will increase the chances of accomplishing the project objective.
Answer True False
1 points
Question 123
In _________, all the resources needed to accomplish each project are assigned full-time to work on that project.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 124
________ provides for effective utilization of company resources.
Answer
An autonomous project organizational structure
A functional organizational structure
A matrix organizational structure
A project management office
1 points
Question 125
In _______, the project manager also needs to take the time to regularly update the other functional managers in the company on the status of the project and thank them for the support of their people assigned to the task force.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 126
The process of closing the project involves various actions, including
Answer
assigning Staff to activities..
examining and estimating costs associated with Staff.
recognizing and evaluating Staff.
having Staff get to know each other.
1 points
Question 127
At the beginning of the project, it may not be possible to estimate the costs for all activities with a level of confidence regarding their accuracy. This is especially true for
Answer
projects with a short term.
longer-term projects.
projects that are similar to ones completed by the organization before.
projects with activities that are serially related.
1 points
Question 128
It is unfair to receive a noncompetitive contract with a customer that was thinking about developing an RFP.
Answer True False
1 points
Question 129
The project manager reviews the plan with the customer to gain endorsement and then sets up a project management information system for
Answer
recording the plan.
solidifying the agreement of the plan.
comparing actual progress to planned progress.
using technology to appear competent.
1 points
Question 130
Verifying that all payments have been made to any subcontractors, consultants, vendors, or suppliers for any purchased materials or services is completed during the
Answer
evaluating the project phase.
controlling the project phase.
performing the project phase.
closing the project phase.
1 points
Question 131
A final ________ when the contractor has completed the detailed specifications, drawings, screen and report formats, and such. The purpose of this final design review meeting is to gain approval from the customer.
Answer
project status review meetings
problem-solving meetings
design review meetings
post-project evaluation meetings
1 points
Question 132
A request for proposal is required for projects that are completed by an external contractor to an organization.
Answer True False
1 points
Question 133
A project has a sponsor or customer.
Answer True False
1 points
Question 134
_______ involves empowering the project team to achieve the project objective and empowering each team member to accomplish the expected results for his or her area of responsibility.
Answer
Consignment
Facilitation
Authorization
Delegation
1 points
Question 135
It is the responsibility of the________ to make sure that the customer is satisfied that the work scope is completed in a quality manner, within budget, and on time.
Answer
project manager
stakeholders
project team members
project authority
1 points
Question 136
The goals of the diversity policy might be to create a work environment where all the following are true except
Answer
The right of all team members to participate and contribute is respected.
Differences are respected and valued.
All team members flourish.
There will be acceptance for breach of respect or intolerant behavior.
1 points
Question 137
_________ allows efficient utilization of resources by having individuals from various functions assigned to work on specific projects.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 138
Based on analysis of actual cost it is possible to forecast what the total costs will be at the completion of the project or work package.
Answer True False
1 points
Question 139
Resources are identified and selected in the
Answer
initiating phase.
planning phase.
performing phase.
closing phase.
1 points
Question 140
The ____________ may include a high-level WBS in a graphic chart format or as an indentured list of the work elements and associated deliverables.
Answer
statement of work
project scope document
network diagram
work breakdown structure
1 points
Question 141
A potential conflict on projects is Organizational Issues where organizational issues can cause conflict. There may be disagreement over all the following except
Answer
the need for certain procedures established by the project manager.
ambiguous project communication.
from failure to make timely decisions.
payment schedules from the customer.
1 points
Question 142
During the______, review and evaluate performance of the project and identify what can be done to improve performance on future projects.
Answer
evaluating the project phase
controlling the project phase
performing the project phase
closing the project phase
1 points
Question 143
Risks_____ should be given higher priority because if the risk occurs, it would have a greater impact on the schedule than if it was associated with activities on a path that has a large positive value of total slack.
Answer
that occur first in the project
that affect the most costly activities
on the critical path
that affect the activities near the end of the project
1 points
Question 144
The earliest start time for a specific activity must be _________ the latest of all the earliest finish times of all the activities leading directly into that specific activity.
Answer
earlier than
the same as
the same as or
later than
later than
1 points
Question 145
The RFP must include the customer requirements and the name of the sponsor’s designee
Answer True False
1 points
Question 146
Addressing risks ________ will increase the chances of accomplishing the project objective.
Answer
reactively
inactively
hyperactively
proactively
1 points
Question 147
In _______, employees work on multiple projects at any given time.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Question 148
The one thing that you can be sure will happen during a project is
Answer
change.
the project plan will remain.
the scope of the project will not creep.
decisions will stand.
1 points
Question 149
Do not identify or refer to team members by drawing attention to their
Answer
diversity.
experiences.
good work on the project.
personal information shared with the team.
1 points
Question 150
In _______, the project manager does not have complete authority over the project team, because administratively the members still work for their respective functional managers.
Answer
an autonomous project organizational structure
a functional organizational structure
a matrix organizational structure
a project management office
1 points
Save and Submit